140808 p49 method statement for demolition rev.1

18
METHOD STATEMENT FOR RECOVERY PLAN OF P49 Rev.1 July 24, 2014 Rev. Draft by Submission Date Eng. Approval 0 Miyamoto Suzuki/Hasegawa 28 June2014   1 Miyamoto Suzuki/Hasegawa 24 July 2014           KAJIMA – WASKITA KAWA JOINT OPERATION Document No. MS_RPP49 Rev 1

Upload: fajarizme

Post on 08-Nov-2015

254 views

Category:

Documents


8 download

DESCRIPTION

Sequence of work for concrete structure demolition

TRANSCRIPT

  • METHOD STATEMENT FOR

    RECOVERY PLAN OF P49

    Rev.1 July 24, 2014

    Rev. Draft by Submission Date Eng. Approval

    0 MiyamotoSuzuki/Hasegawa 28June2014

    1 MiyamotoSuzuki/Hasegawa 24July2014

    KAJIMA WASKITA

    KAWA JOINT OPERATION

    Document No. MS_RPP49

    Rev 1

  • KAWA Joint Operation

    TABLE OF CONTENTS

    A. Method Statement for Recovery Plan

    1. Work Location ...................................................................... 1

    2. Equipment List ...................................................................... 1

    3. Work Schedule ...................................................................... 2

    4. Shop Drawing ...................................................................... 2

    5. Current Condition ...................................................................... 3

    6. Activity Flow ....................................................................... 4

    7. Activity Description ..................................................................... 5

    8. Organization Chart ...................................................................... 16

    9. Safety Plan ...................................................................... 16

    10. Traffic Management..................................................................... 16

    B. Attachment

    1. Approved Shop Drawing

    2. Traffic Route and Working Space

    3. Working Stage for Pier Head and Column

    4. Site Arrangement for 250 ton Crane Activity and Catalogue of 250 ton Crane

    5. Position of Coring and Cutting

    6. Location of Crush Yard and Transportation Route

    7. Risk Assessment

    8. Study of Structural Stability during Demolition of Pier Head

    9. Detailed Wire Sawing Activity on Pier Head and Column

    10. Procedure of Demolition of Column & Footing and Pile Head Treatment

  • KAWA Joint Operation

    1

    METHOD STATEMENT FOR RECOVERY PLAN FOR P49

    1. WorkLocation

    This method statement describes detail explanation of Recovery work for Pier-49.

    Figure1. Work Location

    2. EquipmentListTable of Equipments Usage

    ITEM WORK DESCRIPTION MACHINE NO.OF UNITS

    1 Mobilization Crawler Crane 250 Ton 2 nos

    2 Working Stage Mobile Crane 50 Ton 1 nos

    3 Coring and Cutting

    Wire Saw(DSM-101A)

    Expected Productivity 6m2/day

    (*1)See image of Equipment 2 sets

    Generator (100kVA) 1 set

    Coring Machine 2 sets

    4 Transportation

    (to Crush Yard)

    Trailer (40ton class)

    Carrying Capacity 60ton 2 sets

    5 Crushing Work (Site) Excavator (0.8m3 class)

    with crusher attachment 2 sets

    Giant Breaker 2 sets

    Water jet 1 set

    Excavator (0.8m3 class) 1 nos

    Dump Truck (10 ton) 1 nos

    6 Crushing Work (Crush Yard) Crawler Crane 250 Ton 1 nos

    Excavator (0.8m3 class)

    with crusher attachment 1 set

    Water jet 1 set

  • KAWA Joint Operation

    2

    Sprinkler Truck 8kl 1 nos

    7 Transportation

    (for disposal) Dump Truck (10 ton) 2 nos

    Excavator (0.8m3 class) 1 nos

    8 Shoring for Earth Work Vibration Hammer 1 set

    Note: The number of equipment can be changed following the site condition

    (*1)ImageofWireSawEquipment

    3. WorkScheduleWorking Schedule for Recovery of P49

    Approval of Diversion & Demolition MethodImport of Material & Equipment for Demolition Work

    Temporary Backf illing at P50(L) 14Diversion Work 7Installation of Support & Scffolding 10Pier Head Wire Sawing 2 37 332m2Dismantle of Support & Scaffolf ing 10Diversion Work 7Installation of Scaffo lding 2Pier Wire Sawing 2 9 76m2Dismantle of Scaffolf ing 2Pier BH+GB 1 3 27m3SP+Excavation 21Footing BH+GB 2 26 567m3Re-constructionOriginal Schedule :Amendment 2) 165

    Sub-Total 313

    Jul Aug2015

    Ju l Aug Sep Oct Nov Dec Jan Feb MarDiscriptionDemolition

    Method Gr.

    P49

    Apr May JunDuration

    (Calender day) Q'ty2014

    Normal Working Hour: 8:0017:00

    (Overtime work will be considered depend on safety condition & progress)

    4. ShopDrawingsApprovedshopdrawingofthestructureisattachedinAttachment1.

    Expected Productivity of Wire Sawing

    6m2/day/set

  • KAWA Joint Operation

    3

    5. CurrentConditionThecurrentconditionofP49andstressingstatusofthepierheadareshownasbelow;

    Photo1.CurrentConditionofP49

    Figure2.CurrentConditionofTendonatP49PierHead

  • KAWA Joint Operation

    4

    6. ActivityFlowTheactivityflowsisasfollow;

    1. TrafficDiversion

    6.CuttingPierHeadConcretebyWireSaw

    2.PreparationofWorkingYard

    3.InstallationofWorkingStageforPierHead

    4.Mobilizationof2nosof250tonCranes

    5.CoreBoringWorkonPierHead

    7.TransportationofPierHeadConcretetoCrushYard

    8.DismantlementofWorkingStageforPierHead

    9.InstallationofWorkingStageforColumn

    11.CuttingColumnConcretebyWireSaw

    10.CoreBoringWorkonColumn

    12.TransportationofColumnConcretetoCrushYard

    13.DismantlementofWorkingStageforPierHead&Demobilizationof2nosof250tonCranes

    14.DemolitionofColumnConcretebyGiantBreaker

    15.EarthWorkforexposureofFooting

    16.DemolitionofFootingConcretebyGiantBreaker

    17.BreakingConcreteinCrushYard

    17.BreakingConcreteinCrushYard

    ReConstruction

  • KAWA Joint Operation

    5

    7. ActivityDescription7.1TrafficDiversion

    Inordertoconstructthediversionroad,preparationworkshallberequiredasfollows. 1.Backfilling&rigidpavementaroundP50L.2.AdditionalwideningaroundP49.3.Protectionofundergroundutilities.4.Preventionmeasuresagainsttheresidents&shops,ifany.

    AnoutlineoftherouteisshowninFigure3.Detailedplansuchashorizontalalignment,typicalcrosssections,protectionofundergroundutilitiesareshowninAttachment2.

    Figure3.TrafficDiversionPlan

    7.2PreparationofWorkingYard

    After the trafficdiversion,workingareawillbepreparedby relocationofmaterialsandcompactionoftheyardforheavyliftingworkandtransportation.Ordinaryfenceswillbeinstalledaroundtheworkingarea.

  • KAWA Joint Operation

    6

    7.3InstallationofWorkingStageforPierHead Aworkingstageforthepierheadwillbe installedafterpreparationofworkingyard.Anoutlineoftheworkingstage isshown inFigure.4andshopdrawing isattached inAttachment3.

    Figure4.WorkingStageforPierHead

    7.4Mobilizationof2numberof250tonCranes

    2numbersof250toncranewillbemobilizedduring/afterinstallationoftheworkingstage.AcatalogueincludingworkcapacityofthecraneisattachedinAttachment4.

    7.5CoreBoringWorkonPierHeadThereare2typesofcoringdiameterthatwillbeusedfor installingofwiresawandattaching lifting tools.Verticalboredholes,diameter75mm,willbeutilized forwiresawcutting.Ontheotherhand,horizontalboredholes,diameter50mm,willbeusedfor liftingof concreteblocks thatmustbehoistedbefore cuttinguntilunloading onground.AquantitytableoftheworkisshowninFigure6.2groupsofcoringmemberswillworkonthepierhead.Awatertankwillbepreparedbeforecommencementofthecoringforsupplyingwaterduringcoringofconcrete. Detailcoringpositionsareshown inAttachment5andFigure7.PhotoandsketchoftheactivityareshowninFigure8.

  • KAWA Joint Operation

    7

    Figure6.QuantityTableforCoringWork

    Figure7.PositionsofCuttingandCoring

    Figure8.PhotoandSketchforCoringWork

  • KAWA Joint Operation

    8

    7.6CuttingPierHeadConcretebyWireSawAftercoringconcrete,liftingtoolsandawiresawwillbeinstalled inhorizontalholesand vertical holes, respectively. Before commencement of cutting, a concrete blockwhichwillberemovedmustbehoistedasmuchasaselfloadoftheconcreteblockby250toncrane.Safetyfacilities,suchasaspecialprotectionboardandsheetforawiresaw mentioned in Figure10 must be installed properly before start of the work. Inaddition,protectionboardsforPCtendon,whichisshownonFigure4andAttachment3,willbeinstalledproperlybehindanchoragesoftendonattheedgeofthepierheadin order to protect a sudden spring out of strands and wedges during cutting ofconcreteofthepierhead.Thesequenceofcutting,thatstructuralstabilityhasbeenconsideredinAttachment8,the site arrangementwith working capacity of 250 ton crane and sketches of wiresawing method are shown in Figure7, 9 and 10, respectively. See more detailedsketchesofwiresawingmethodinAttachment9.

    Figure9.Sitearrangementwithworkingcapacityof250toncrane

  • KAWA Joint Operation

    9

    Figure10.Sketchesofwiresawingmethod

    Section View of Cutting Lifting Gears

  • KAWA Joint Operation

    10

    7.7TransportationofPierHeadConcretetoCrushYard The transportation route and loading shape of a block concrete on a trailer areshown inFigure11andAttachment6.Ablockconcretewillbetransportedbytrailersfromsitetothecrashyard(MarundaPCUStockYard).Itisconfirmedonadrawingthatthereareenoughspacesfortrailerstoturnatallcornersontheroute.Flagmenwouldbeassignedatgatesofyardsandcornersinordertoavoidtrafficcongestionsonpublicroadduetothistransportation.

    Figure11.Transportationrouteandloadingshapeofablockconcrete

    7.8DismantlementofWorkingStageforPierHead

    Theworkingstageforpierheadwillbedismantledwith250toncranes.Materialsoftheworkingstagewillbetransportedtostorageyardimmediatelyafterdismantlementinordertokeepworkspacesfornextstepsofdemolitionwork.

  • KAWA Joint Operation

    11

    7.9InstallationofWorkingStageforColumn

    Theworking stage for the columnwill be installed just after removal of aworkingstageforpierhead.Thisworkingstagewillbeoccupiedbycoreboringworkandblockconcretecuttingforthecolumn.

    Figure12.WorkingStageforColumn

    7.10CoreBoringWorkonColumn

    A groupof coringmemberswillworkon theColumn.Water tankwillbepreparedbeforecommencementofthecoringforsupplyingwaterduringcoringofconcrete. DetailcoringpositionsareshowninAttachment5andFigure7.

  • KAWA Joint Operation

    12

    7.11CuttingColumnConcretebyWireSawSafetyfacilities,suchasaprotectionboardandsheetmentioned inFigure13willbeinstalledproperly.Thesequenceofcutting,thesitearrangementwithworkingcapacityof250toncraneandsketchesofwiresawingmethodareshowninFigure7,9and10,respectively.

    Figure13.Safetyfacilitiesonwiresawingatcolumn

    7.12TransportationofColumnConcretetoCrushYardThetransportationrouteandloadingshapeofablockconcreteonatrailerareshowninFigure11.Ablockconcretewillbetransportedbytrailersfromsitetothecrashyard.It isconfirmedonadrawingthatthereareenoughspacesfortrailerstoturnatsomecornersontheroute.

    7.13DismantlementofWorkingStageforColumn&Demobilizationof2nosof250tonCrane

    The working stage for Column will be dismantled by manpower. Materials of theworkingstagewillbetransportedtostorageyard immediatelyafterdismantlement inordertokeepworkspacesfornextstepsofdemolitionwork.Simultaneously,250toncraneswillbedemobilizedorrelocated.

    SectionViewofCutting LiftingGears

  • KAWA Joint Operation

    13

    7.14DemolitionofColumnConcretebyGiantBreakerThe columnwill be demolished by cutting and liftingmethod until about 2m highfromcurrentgroundelevation.Thecolumnheightlessthan2mwillbedestroyedbyagiantbreaker.Concretedebrisandrebarwillbeseparatedandsentouttofinaldisposalyardandscrapyard,whichwillbedecidedandinformedbeforecommencementofthetransportation, directly using dump trucks. See more detailed sketches of columndemolitioninAttachment10.

    Figure14.DemolitionofColumnConcretebyGiantBreaker

    7.15EarthWorkforExposureofFooting

    Sheet piles and its support members will be installed around a footing. Afterinstallationofearthshoring,excavationforexposureofthefootingwillbecommenced.

    Figure15.EarthWorkforExposureofFooting

  • KAWA Joint Operation

    14

    7.16DemolitionofFootingwithPileHeadbyGiantBreaker After exposure of the footing, itwill be demolished by a giant breaker. Concretedebrisandrebarwillbeseparatedandsentouttofinaldisposalyardandscrapyard,which will be decided and informed before commencement of the transportation,directlyusingdumptrucks.Pileswillbecutabout100mmbelowtopoftheelevationofleanconcrete.SeemoredetailedsketchesoffootingdemolitioninAttachment10.

    Figure16.DemolitionofFootingbyGiantBreaker

  • KAWA Joint Operation

    15

    7.17BreakingConcreteinCrushYard Transportedconcreteblockwillbeunloadedby250toncraneinthecrushyard.Theconcreteblockwillbedemolishedbyagiantbreakerwhichcanbe installedaspecialattachment fordemolition.Duringdemolition,waterwillbe sprinkled followingHSEregulation in order to avoid dust from demolishing concrete. Rebar in the concreteblockwillbe separated and scrapped.Concretedebriswillbe sent todisposal area,whichwillbedecidedand informedbeforecommencementofthetransportationbutshouldbeneartothecrushyard.

    Braker

    Excavator

    Dump truck

    Rebar

    Waterjet

    Attachement

    Trailer

    Figure17.BreakingConcreteinCrushYard

    7.18ReConstructionWork

    Afterdemolitionoffooting,furtheranalysiswouldbenecessaryforevaluationofthepiles. The detail of treatment of piles and the modification of footing may beconsideredwithresultsoffurthertestsandanalysis.However,thecolumnandthepierheadwill be reconstructed at the same location following original design.Detailedconstruction methods have been approved which will be applied during itsreconstruction.

  • KAWA Joint Operation

    16

    8. OrganizationChart(DemolitionWork)

    FUJIMORI081398554217 081931072529

    CHIEFENGINEERINGANDESITKRISNA M.FAJARDANIEL

    QCMANAGER

    081281968313

    081331523500

    HSEMANAGER

    GENERALSUPERINTENDENTFUKUDA

    BAMBANGBUDIMULYONO MIYAMOTO

    DEPUTYGENERALSUPERINTENDENTSUTOPO

    CHIEFHSEMANAGER CHIEFCONSTRUCTIONMANAGER ENG./COMMERCIAL/CONTRACTMANAGEROKADA

    MANAGERSAITO

    081294991440 081282212840 08119447342

    CONSTRUCTIONMANAGERSUZUKITobeassigned

    ConcreteCutting&Coring

    CONSTRUCTIONMANAGER

    JOSVDemolitionbyGiantBreaker

    HASEGAWA

    JOSV(JAPANESE)

    082113094761

    08111849422

    Figure18.OrganizationChart9. SafetyPlan

    Safety activities must be conducted in accordance with Risk Assessment. The Risk

    Assessments for below mentioned activities are shown in Attachment 7.

    a. Common Work b. Wire Sawing Work

    10. TrafficManagementBased on proposed traffic management plan, Contractor will keep roads in good condition at

    all times, and will carry out repair and reinstatement work. We will co-operate with the

    pertinent agencies regarding traffic control and all details will be subject to maintaining

    traffic safety and the avoidance of traffic delay.

    In order to facilitate traffic through the work area, it will be installed and maintained at

    prescribed points on the work area and at the approaches to the work: rubber cone, warning

    and guide signs, temporary barriers and fences and other facilities as required. During

    construction period, the traffic management will be implemented according to the stages of

    work progress following construction stages. If the location is adjacent to existing traffic or

    pedestrian path, Safety fence with MCB will be provided. Traffic management will be

    discussed with related parties in the timely manner.