SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
NATIONAL1 Drafting of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
2 Reactivation of DepED CO TWG DepED-HNC
3 Writeshop on the Finalization of SBFP MOA &
TOR
DSWD
4 Legal Review of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
5 Consultation Workshop on SBFP with DepED
& DSWD Regional Personnel
DepED-HNC
6 Finalization and approval of the ff:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
7 Planning Workshop of Regional & Division
SBFP Implementers
DepED-HNC with TWG
8 Issuance of DepED Memo to circulate the
Implementing Guidelines
DepED-CO
9 Submission of Final List of Schools &
Beneficiaries
• from HNC to DSWD CO DepED-HNC
10 Submission of Physical & Financial Report fr
DepEd CO to DSWD CO
DepED-CO
11 Monitoring of regions, divisions, & schools DepED-HNC with TWG
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
Page 1
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
12 Consolidation & submission of Terminal
Report
• from DepED HNC to DSWD CO DepED-HNC
13 Conduct of Program Implementation Review DSWD/DepED CO
Page 2
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
REGIONAL
1 Creation of Regional TWG (DepED, DSWD,
NNC, LGUs)
DepED RO
2 Drafting of Regional MOA DSWD-FO/DepED RO
3 Submission to DSWD FO of Regional WFP DepED RO
4 Signing of Regional MOA DSWD-FO/DepED RO
5 Transfer of funds from DSWD RO to DepED
RO
DSWD-FO/DepED RO
6 Transfer of funds from DepED RO to DepED
DO
DepED RO
7 Division Orientation among SBFP School
Implementers
DepED RO & DO with
RTWG
8 Submission of Final List of Schools &
Beneficiaries
DepED RO
• from RO to DepED HNC, cc: DSWD RO
9 Submission of Physical & Financial Reports DepED RO
• from RO to DepED HNC, cc: DSWD RO
10 Submission of Liquidation Report to DSWD RO DepED RO
• First Partial Liquidation
• Full Liquidation
11 Monitoring of divisions & schools RTWG
12 Consolidation & submission of Terminal
Report
• from RO to DepED HNC, cc: DSWD RO DepED RO
13 Conduct ofRegional Program Implementation
Review
DSWD-FO/DepED RO
Page 3
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
DIVISION
1 Creation of Municiapl/City Level Local Alliance
by the Municipal/City TWG
M/C-TWG
• Preparatory Meetings
• Actual Meeting with Partners
• Mapping of Schools to be covered by
DSWD-DepED funds and other stakeholders
2 Submission to DepEd RO of Division WFP, List
of Schools to be covered by DepEd-DSWD
funds and those to be covered by partners
DepED DO
3 Request of NCA fr DBM
• 1st tranche DepED DO
4 Finalization of the number of beneficiaries
based on actual weighing & determination the
budget allocation per school
DepED DO
5 Issuance of checks to SH
• 1st tranche DepED DO
• 2nd tranche DepED DO
6 Submission of Final List of Schools &
Beneficiaries • from DO to RO DepED DO
7 Processing & Auditing of Liquidation Reports
from Schools
DepED DO - Acctng &
COA8 Submission of Physical & Financial Reports DepED DO
• from DO to RO
Page 4
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
9 Submission of Liquidation Report to DepED
RO
DepED DO
• First Partial Liquidation
• Full Liquidation
10 Monitoring of schools M/C-TWG
11 Consolidation & submission of Terminal
Report • from DO to RO DepED DO
Page 5
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
SCHOOLS
1 Weighing & Identification of beneficiaries Feeding Coordinator &
health personnel
2 Creation of SBFP Core Group & BAC SH
3 Submission of the following to the DO:
• Final list of schools & of names of
beneficiaries
SH & Core Group
• Cycle Menu SH & Core Group
• Work & Financial Plan SH & Core Group
• Project Procurement & Managment Plan SH & Core Group
4 Conduct of Community Assembly SH & Core Group
5 Health & Nutritional Assessment &
Deworming
Feeding Coordinator &
health personnel
6 Preparation of RFQ & conduct of procurement
process
Core Group & BAC
7 Actual Feeding Core Group
8 Monitoring of weight Core Group
9 Submission of Physical & Financial Reports SH & Core Group
• from Schools to DO
10 Submission of Liquidation Report to DO SH & Core Group
• First Partial Liquidation
• Full Liquidation
Page 6
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
May June July AugustAprilACTIVITIES OFFICE RESPONSIBLE
January February March
11 Preparation of Terminal Report SH & Core Group
12 Submission of Terminal Report to the DO thru
the District Office
SH & Core Group
Feeding Days:
July 13
August (less 2 days NAD/NHD) 20
September 22
October (less 1 week for Sem Break) 18
November 20
December 14
January 13
February 120 11
120
20
22
18
20
14
15
Page 7
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
NATIONAL1 Drafting of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
2 Reactivation of DepED CO TWG DepED-HNC
3 Writeshop on the Finalization of SBFP MOA &
TOR
DSWD
4 Legal Review of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
5 Consultation Workshop on SBFP with DepED
& DSWD Regional Personnel
DepED-HNC
6 Finalization and approval of the ff:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
7 Planning Workshop of Regional & Division
SBFP Implementers
DepED-HNC with TWG
8 Issuance of DepED Memo to circulate the
Implementing Guidelines
DepED-CO
9 Submission of Final List of Schools &
Beneficiaries
• from HNC to DSWD CO DepED-HNC
10 Submission of Physical & Financial Report fr
DepEd CO to DSWD CO
DepED-CO
11 Monitoring of regions, divisions, & schools DepED-HNC with TWG
ACTIVITIES OFFICE RESPONSIBLEW1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Done
Done
Done
Done
Done
Done
Done
REMARKSSeptember October November December January February March
Page 8
ACTIVITIES OFFICE RESPONSIBLE
12 Consolidation & submission of Terminal
Report
• from DepED HNC to DSWD CO DepED-HNC
13 Conduct of Program Implementation Review DSWD/DepED CO
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 9
ACTIVITIES OFFICE RESPONSIBLE
REGIONAL
1 Creation of Regional TWG (DepED, DSWD,
NNC, LGUs)
DepED RO
2 Drafting of Regional MOA DSWD-FO/DepED RO
3 Submission to DSWD FO of Regional WFP DepED RO
4 Signing of Regional MOA DSWD-FO/DepED RO
5 Transfer of funds from DSWD RO to DepED
RO
DSWD-FO/DepED RO
6 Transfer of funds from DepED RO to DepED
DO
DepED RO
7 Division Orientation among SBFP School
Implementers
DepED RO & DO with
RTWG
8 Submission of Final List of Schools &
Beneficiaries
DepED RO
• from RO to DepED HNC, cc: DSWD RO
9 Submission of Physical & Financial Reports DepED RO
• from RO to DepED HNC, cc: DSWD RO
10 Submission of Liquidation Report to DSWD RO DepED RO
• First Partial Liquidation
• Full Liquidation
11 Monitoring of divisions & schools RTWG
12 Consolidation & submission of Terminal
Report
• from RO to DepED HNC, cc: DSWD RO DepED RO
13 Conduct ofRegional Program Implementation
Review
DSWD-FO/DepED RO
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 10
ACTIVITIES OFFICE RESPONSIBLE
DIVISION
1 Creation of Municiapl/City Level Local Alliance
by the Municipal/City TWG
M/C-TWG
• Preparatory Meetings
• Actual Meeting with Partners
• Mapping of Schools to be covered by
DSWD-DepED funds and other stakeholders
2 Submission to DepEd RO of Division WFP, List
of Schools to be covered by DepEd-DSWD
funds and those to be covered by partners
DepED DO
3 Request of NCA fr DBM
• 1st tranche DepED DO
4 Finalization of the number of beneficiaries
based on actual weighing & determination the
budget allocation per school
DepED DO
5 Issuance of checks to SH
• 1st tranche DepED DO
• 2nd tranche DepED DO
6 Submission of Final List of Schools &
Beneficiaries • from DO to RO DepED DO
7 Processing & Auditing of Liquidation Reports
from Schools
DepED DO - Acctng &
COA8 Submission of Physical & Financial Reports DepED DO
• from DO to RO
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 11
ACTIVITIES OFFICE RESPONSIBLE
9 Submission of Liquidation Report to DepED
RO
DepED DO
• First Partial Liquidation
• Full Liquidation
10 Monitoring of schools M/C-TWG
11 Consolidation & submission of Terminal
Report • from DO to RO DepED DO
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 12
ACTIVITIES OFFICE RESPONSIBLE
SCHOOLS
1 Weighing & Identification of beneficiaries Feeding Coordinator &
health personnel
2 Creation of SBFP Core Group & BAC SH
3 Submission of the following to the DO:
• Final list of schools & of names of
beneficiaries
SH & Core Group
• Cycle Menu SH & Core Group
• Work & Financial Plan SH & Core Group
• Project Procurement & Managment Plan SH & Core Group
4 Conduct of Community Assembly SH & Core Group
5 Health & Nutritional Assessment &
Deworming
Feeding Coordinator &
health personnel
6 Preparation of RFQ & conduct of procurement
process
Core Group & BAC
7 Actual Feeding Core Group
8 Monitoring of weight Core Group
9 Submission of Physical & Financial Reports SH & Core Group
• from Schools to DO
10 Submission of Liquidation Report to DO SH & Core Group
• First Partial Liquidation
• Full Liquidation
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 13
ACTIVITIES OFFICE RESPONSIBLE
11 Preparation of Terminal Report SH & Core Group
12 Submission of Terminal Report to the DO thru
the District Office
SH & Core Group
Feeding Days:
July 13
August (less 2 days NAD/NHD) 20
September 22
October (less 1 week for Sem Break) 18
November 20
December 14
January 13
February 120
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 14
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
NATIONAL1 Drafting of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
2 Reactivation of DepED CO TWG DepED-HNC
3 Writeshop on the Finalization of SBFP MOA &
TOR
DSWD
4 Legal Review of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
5 Consultation Workshop on SBFP with DepED
& DSWD Regional Personnel
DepED-HNC
6 Finalization and approval of the ff:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
7 Planning Workshop of Regional & Division
SBFP Implementers
DepED-HNC with TWG
8 Issuance of DepED Memo to circulate the
Implementing Guidelines
DepED-CO
9 Submission of Final List of Schools &
Beneficiaries
• from HNC to DSWD CO DepED-HNC
10 Submission of Physical & Financial Report fr
DepEd CO to DSWD CO
DepED-CO
11 Monitoring of regions, divisions, & schools DepED-HNC with TWG
12 Consolidation & submission of Terminal
Report
• from DepED HNC to DSWD CO DepED-HNC
13 Conduct of Program Implementation Review DSWD/DepED CO
AprilACTIVITIES OFFICE RESPONSIBLE
January February March May June July August
Page 15
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
AprilACTIVITIES OFFICE RESPONSIBLE
January February March May June July August
Feeding Days:
July 13
August 20
September 22
October (less 1 week for Sem Break) 18
November 20
December 14
January 13
February 120 11
120
20
22
18
20
14
15
Page 16
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
NATIONAL1 Drafting of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
2 Reactivation of DepED CO TWG DepED-HNC
3 Writeshop on the Finalization of SBFP MOA &
TOR
DSWD
4 Legal Review of the following:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
5 Consultation Workshop on SBFP with DepED
& DSWD Regional Personnel
DepED-HNC
6 Finalization and approval of the ff:
• Terms of Reference (TOR) DSWD/DepED CO
• Memorandum of Agreement (MOA) DSWD/DepED CO
• Implementing Guidelines DSWD/DepED CO
• Regional MOA DSWD/DepED CO
7 Planning Workshop of Regional & Division
SBFP Implementers
DepED-HNC with TWG
8 Issuance of DepED Memo to circulate the
Implementing Guidelines
DepED-CO
9 Submission of Final List of Schools &
Beneficiaries
• from HNC to DSWD CO DepED-HNC
10 Submission of Physical & Financial Report fr
DepEd CO to DSWD CO
DepED-CO
11 Monitoring of regions, divisions, & schools DepED-HNC with TWG
12 Consolidation & submission of Terminal
Report
• from DepED HNC to DSWD CO DepED-HNC
13 Conduct of Program Implementation Review DSWD/DepED CO
ACTIVITIES OFFICE RESPONSIBLEW1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Done
Done
Done
Done
Done
Done
Done
REMARKSSeptember October November December January February March
Page 17
ACTIVITIES OFFICE RESPONSIBLE
Feeding Days:
July 13
August 20
September 22
October (less 1 week for Sem Break) 18
November 20
December 14
January 13
February 120
W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4REMARKS
September October November December January February March
Page 18
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5
REGIONAL
1 Creation of Regional TWG (DepED, DSWD,
NNC, LGUs)
DepED RO
2 Drafting of Regional MOA DSWD-FO/DepED RO
3 Submission to DSWD FO of Regional WFP DepED RO
4 Signing of Regional MOA DSWD-FO/DepED RO
5 Transfer of funds from DSWD RO to DepED
RO
DSWD-FO/DepED RO
6 Transfer of funds from DepED RO to DepED
DO
DepED RO
7 Division Orientation among SBFP School
Implementers
DepED RO & DO with
RTWG
8 Submission of Final List of Schools &
Beneficiaries
DepED RO
• from RO to DepED HNC, cc: DSWD RO
9 Submission of Physical & Financial Reports DepED RO
• from RO to DepED HNC, cc: DSWD RO
10 Submission of Liquidation Report to DSWD RO DepED RO
• First Partial Liquidation
• Full Liquidation
11 Monitoring of divisions & schools RTWG
12 Consolidation & submission of Terminal
Report
• from RO to DepED HNC, cc: DSWD RO DepED RO
13 Conduct ofRegional Program Implementation
Review
DSWD-FO/DepED RO
AprilACTIVITIES OFFICE RESPONSIBLE
January February March May June July
Page 19
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
REGIONAL
1 Creation of Regional TWG (DepED, DSWD,
NNC, LGUs)
DepED RO
2 Drafting of Regional MOA DSWD-FO/DepED RO
3 Submission to DSWD FO of Regional WFP DepED RO
4 Signing of Regional MOA DSWD-FO/DepED RO
5 Transfer of funds from DSWD RO to DepED
RO
DSWD-FO/DepED RO
6 Transfer of funds from DepED RO to DepED
DO
DepED RO
7 Division Orientation among SBFP School
Implementers
DepED RO & DO with
RTWG
8 Submission of Final List of Schools &
Beneficiaries
DepED RO
• from RO to DepED HNC, cc: DSWD RO
9 Submission of Physical & Financial Reports DepED RO
• from RO to DepED HNC, cc: DSWD RO
10 Submission of Liquidation Report to DSWD RO DepED RO
• First Partial Liquidation
• Full Liquidation
11 Monitoring of divisions & schools RTWG
12 Consolidation & submission of Terminal
Report
• from RO to DepED HNC, cc: DSWD RO DepED RO
13 Conduct ofRegional Program Implementation
Review
DSWD-FO/DepED RO
ACTIVITIES OFFICE RESPONSIBLEW1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
REMARKSAugust September October November December January February March
Page 20
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
DIVISION
1 Creation of Municiapl/City Level Local Alliance
by the Municipal/City TWG
M/C-TWG
• Preparatory Meetings
• Actual Meeting with Partners
• Mapping of Schools to be covered by
DSWD-DepED funds and other stakeholders
2 Submission to DepEd RO of Division WFP, List
of Schools to be covered by DepEd-DSWD
funds and those to be covered by partners
DepED DO
3 Request of NCA fr DBM
• 1st tranche DepED DO
4 Finalization of the number of beneficiaries
based on actual weighing & determination the
budget allocation per school
DepED DO
5 Issuance of checks to SH
• 1st tranche DepED DO
• 2nd tranche DepED DO
6 Submission of Final List of Schools &
Beneficiaries • from DO to RO DepED DO
7 Processing & Auditing of Liquidation Reports
from Schools
DepED DO - Acctng &
COA8 Submission of Physical & Financial Reports DepED DO
• from DO to RO
9 Submission of Liquidation Report to DepED
RO
DepED DO
• First Partial Liquidation
• Full Liquidation
10 Monitoring of schools M/C-TWG
11 Consolidation & submission of Terminal
Report • from DO to RO DepED DO
AprilACTIVITIES OFFICE RESPONSIBLE
January February March May June July August
Page 21
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
DIVISION
1 Creation of Municiapl/City Level Local Alliance
by the Municipal/City TWG
M/C-TWG
• Preparatory Meetings
• Actual Meeting with Partners
• Mapping of Schools to be covered by
DSWD-DepED funds and other stakeholders
2 Submission to DepEd RO of Division WFP, List
of Schools to be covered by DepEd-DSWD
funds and those to be covered by partners
DepED DO
3 Request of NCA fr DBM
• 1st tranche DepED DO
4 Finalization of the number of beneficiaries
based on actual weighing & determination the
budget allocation per school
DepED DO
5 Issuance of checks to SH
• 1st tranche DepED DO
• 2nd tranche DepED DO
6 Submission of Final List of Schools &
Beneficiaries • from DO to RO DepED DO
7 Processing & Auditing of Liquidation Reports
from Schools
DepED DO - Acctng &
COA8 Submission of Physical & Financial Reports DepED DO
• from DO to RO
9 Submission of Liquidation Report to DepED
RO
DepED DO
• First Partial Liquidation
• Full Liquidation
10 Monitoring of schools M/C-TWG
11 Consolidation & submission of Terminal
Report • from DO to RO DepED DO
ACTIVITIES OFFICE RESPONSIBLEW1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
REMARKSSeptember October November December January February March
Page 22
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4
SCHOOLS
1 Weighing & Identification of beneficiaries Feeding Coordinator &
health personnel
2 Creation of SBFP Core Group & BAC SH
3 Submission of the following to the DO:
• Final list of schools & of names of
beneficiaries
SH & Core Group
• Cycle Menu SH & Core Group
• Work & Financial Plan SH & Core Group
• Project Procurement & Managment Plan SH & Core Group
4 Conduct of Community Assembly SH & Core Group
5 Health & Nutritional Assessment &
Deworming
Feeding Coordinator &
health personnel
6 Preparation of RFQ & conduct of procurement
process
Core Group & BAC
7 Actual Feeding Core Group
8 Monitoring of weight Core Group
9 Submission of Physical & Financial Reports SH & Core Group
• from Schools to DO
10 Submission of Liquidation Report to DO SH & Core Group
• First Partial Liquidation
• Full Liquidation
11 Preparation of Terminal Report SH & Core Group
12 Submission of Terminal Report to the DO thru
the District Office
SH & Core Group
Feeding Days:
July 13
August 20
September 22
October (less 1 week for Sem Break) 18
November 20
December 14
January 13
February 120
AprilACTIVITIES OFFICE RESPONSIBLE
January February March May June July August
11
120
20
22
18
20
14
15
Page 23
SCHOOL-BASED FEEDING PROGRAM (SBFP) GANTT CHART OF ACTIVITIES FOR CY 2014 TO 1ST QUARTER OF 2015 (BY LEVEL)
SCHOOLS
1 Weighing & Identification of beneficiaries Feeding Coordinator &
health personnel
2 Creation of SBFP Core Group & BAC SH
3 Submission of the following to the DO:
• Final list of schools & of names of
beneficiaries
SH & Core Group
• Cycle Menu SH & Core Group
• Work & Financial Plan SH & Core Group
• Project Procurement & Managment Plan SH & Core Group
4 Conduct of Community Assembly SH & Core Group
5 Health & Nutritional Assessment &
Deworming
Feeding Coordinator &
health personnel
6 Preparation of RFQ & conduct of procurement
process
Core Group & BAC
7 Actual Feeding Core Group
8 Monitoring of weight Core Group
9 Submission of Physical & Financial Reports SH & Core Group
• from Schools to DO
10 Submission of Liquidation Report to DO SH & Core Group
• First Partial Liquidation
• Full Liquidation
11 Preparation of Terminal Report SH & Core Group
12 Submission of Terminal Report to the DO thru
the District Office
SH & Core Group
Feeding Days:
July 13
August 20
September 22
October (less 1 week for Sem Break) 18
November 20
December 14
January 13
February 120
ACTIVITIES OFFICE RESPONSIBLEW1 W2 W3 W4 W1 W2 W3 W4 W5 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
REMARKSSeptember October November December January February March
Page 24