1 World Class Plant Performance with NLS O&M Ferdinand A. Pecson Ph. D, MBA, BS ME Cemtech Dubai, 5-8 March 2011 2 Company Profile NLSupervision A/S specializes in offering everything needed for the successful commissioning of a cement plant and its subsequent management, operation and maintenance. NLSupervision Egypt currently has O&M contracts with Arabian Cement Company located in Suez Governorate and Wadi El-Nile Cement Company located in Bene Suef Governorate. • Outside Egypt, NL Supervision A/S has contracts in four other countries: Iran, Libya, Angola and Tunisia NLSupervision Company A/S Høffdingsvej 34 DK-2500 Valby Denmark Tel.: +45 3618 3780 Fax: +45 3645 6415 Cemtech Dubai, 5-8 March 2011

Upload: mohd-ali

Post on 20-Nov-2015

10 views

Category:

Documents


4 download

DESCRIPTION

16.30 Ferdinand Pecson, NLSupervision

TRANSCRIPT

  • 1

    World Class Plant Performance with NLS O&M

    Ferdinand A. Pecson Ph. D, MBA, BS ME

    Cemtech Dubai, 5-8 March 2011

    2

    Company Profile

    NLSupervision A/S specializes in offering everything needed for the successful commissioning of a cement plant and its subsequent management, operation and maintenance.

    NLSupervision Egypt currently has O&M contracts with Arabian Cement Company located in Suez Governorate and Wadi El-Nile Cement Company located in Bene Suef Governorate.

    Outside Egypt, NL Supervision A/Shas contracts in four other countries: Iran, Libya, Angola and Tunisia

    NLSupervision Company A/SHffdingsvej 34DK-2500 ValbyDenmarkTel.: +45 3618 3780Fax: +45 3645 6415

    Cemtech Dubai, 5-8 March 2011

  • 2

    3

    Our Value Proposition to Our Customers

    Maximize your return on your investment by achieving rapid ramp-up from commissioning and guaranteeing high plant availability and high levels of production throughout the life of the project.

    Support your goal of being a dependable provider of excellent quality cement to your customers

    Help you be an attractive business partner for users of cement by operating your cement plant according to international standards for Quality (ISO 9001), Environment (ISO 14001) and Safety (OSHAS 18001)

    Enable you to focus your resources on revenue generation

    Help you sustain high levels of productivity and performance even after the O&M contract, by providing your plant with state-of-the art systems and a highly competent organization.

    Cemtech Dubai, 5-8 March 2011

    4

    Our Mission: Sustained Excellent Performance

    Cemtech Dubai, 5-8 March 2011

  • 3

    5

    The Five Key Drivers of Our Success

    Customer Focus

    Excellence in Operation & Maintenance

    Passion for Safety

    Engaged Employees

    Care for the Environment

    Cemtech Dubai, 5-8 March 2011

    6

    Delivering Results by Being Close to our Customer

    Philosophy of Our customers

    success is our success

    Daily Coordination Meetings at

    Plant Level

    Quarterly Planning of

    Production

    Planning shutdowns according

    to customer needs

    Joint Iftar Parties

    Cemtech Dubai, 5-8 March 2011

  • 4

    7

    Reputation

    Senior Management

    Immediate Superior

    Co-operation

    Daily Work

    Remuneration

    Development

    Action areas Result areas

    Perception Behaviour

    Satisfaction

    Motivation

    Satisfaction & Motivation Loyalty

    Retention

    Commitment

    Delivering Results by Engaging our People

    Employees continued to run Ramliya Plant all throughout the Egypt Crisis!

    Cemtech Dubai, 5-8 March 2011

    8

    Delivering Results through State-of-the Art O&M Systems

    O&M Organization

    Training/Coaching

    Preventive Maintenance

    Production & Maintenance

    Planning

    Quality of Execution

    Measures of Performance

    Failure Reporting & Root-cause

    analysis

    Communi-cation

    Continuous Improve-

    ment

    Thermoteknix VisIR 3:32:01 PM 2/16/2007 e : 1.00 Bg : 25.0C-20.0

    160.0

    38.9

    94.7Celsius

    45.0

    50.0

    55.0

    60.0

    65.0

    70.0

    75.0

    80.0

    85.0

    90.0

    WINDING JUNCTION100.3

    WINDING JUNCTION95.1

    Cemtech Dubai, 5-8 March 2011

  • 5

    9

    Delivering Results through Continuous Improvement

    Raw Mill Situation

    Quartz content of materials on grinding table is up to 23% compared with just 7% in raw materials High load of large particles on the separator due to high gas velocity in the nozzle ring and in the transition zone between mill and separator High wear at outlet duct & cyclones

    Improvements

    Switched to sintercast roller segments Increased nozzle ring area Raised lower housing of separator by 2 m Installed densit lining at outlet duct & cyclones

    Cemtech Dubai, 5-8 March 2011

    10

    Delivering Results through Continuous Improvement

    Kiln Situation

    High wear of refractory of tertiary air damper Alkali attack on kiln nose ring area Process control by Operator

    Improvements

    Switched to silicon carbide castable for the tertiary air damper, nose ring and area between nose ring and retainer ring Installed Process Control Expert (PXP)

    Cemtech Dubai, 5-8 March 2011

  • 6

    11

    Delivering Results through Continuous Improvement

    Cooler Situation

    Cross-bar cooler designed for 6000 tpd

    Recurring red rivers

    Improvements

    Upgraded cross-bar cooler to seagull design, which increased kiln output to 6700 tpd

    Cemtech Dubai, 5-8 March 2011

    Before upgrade

    After upgrade

    12

    Delivering Results through NLS Copenhagen Technical Support

    Performance Diagnostic

    Center

    Spare Parts Support

    Bottleneck assessment

    Efficiency improvements

    Mechanical Inspections

    Technical Training

    Research &Development

    Cemtech Dubai, 5-8 March 2011

  • 7

    13

    Delivering Results by Preparing Future Cement Engineers

    Partnership with Helwan

    University

    Total of 40 Engineering

    Students in the First Year

    Theoretical and Practical

    Cement Technology

    Training

    Cemtech Dubai, 5-8 March 2011

    14

    Delivering Results, SAFELY

    Building a Culture of Safety

    Focus on hazards control

    Work Safety Guidelines

    OHSAS 18001 Certification

    5S Implementation together

    with Arabian Cement

    Cemtech Dubai, 5-8 March 2011

  • 8

    15

    Delivering Results, by having FUN!

    Cemtech Dubai, 5-8 March 2011

    16

    Actual Results

    2,009 2,010 Kiln Average Production Rate, % of design capacity

    103% 106%

    Kiln Net Availability, % 92% 92%Kiln MTBF, hrs 301 256Safety LTIFR 6.9 2.81

    Cemtech Dubai, 5-8 March 2011

  • 9

    17

    We signed a second contract with NL Supervision because they deliver their commitments and can be depended on to support us even in difficult times. They are strongly focused on solving bottleneck issues, improving plant productivity and ensuring long-term plant reliability.

    Arabian Cement aspires to be the clinker and cement producer of reference; we see NL Supervision as the partner who can support us with that aspiration.

    Jose Maria MagrinaCEOArabian Cement Company

    What Our Customer Has to Say

    Cemtech Dubai, 5-8 March 2011