19623402 scheduling and sequencing by johnson rule

Upload: muthuvasavs88

Post on 04-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    1/18

    SCHEDULING & SEQUENCING

    BY JOHNSONS RULE

    GROUP MEMBERS

    Rajendra kumar

    Pratik

    Puneet

    Pintu

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    2/18

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    3/18

    DEFINATION

    Establishing the timing of the use of

    equipment, facilities and human activities in an

    organization

    Effective scheduling can produce:-

    1) Cost savings

    2) Increases in productivity

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    4/18

    Scheduling Difficulties

    Variability in

    Setup times

    Processing times

    Interruptions

    Changes in the set of jobs

    No method for identifying optimal schedule

    Scheduling is not an exact science

    Ongoing task for a manager

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    5/18

    Minimizing Scheduling Difficulties

    Set realistic due dates

    Focus on bottleneck operations

    Consider lot dividing of large jobs

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    6/18

    SEQUENCING

    JOHNSONSRULE

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    7/18

    SEQUENCING

    Sequencing: Determine the order in which jobs

    at a work center will be processed.

    Workstation: An area where one person works,

    usually with special equipment, on aspecialized job.

    Priority rules: Simple hierarchy

    used to select the order inwhich jobs will be processed.

    Job time: Time needed for

    setup and processing of a job.

    Everything is

    #1 Priority

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    8/18

    Priority Rules

    FCFS - first come, first served

    LTR - Least time required

    LAR/LORLeast activity required/Fewestoperations required

    EDD - earliest due date

    CRS - critical ratio schedulingTop Priority

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    9/18

    JOHNSONS RULE

    Technique for minimizing completion time for

    a group of jobs to be processed on twomachines or at two work centers.

    Minimizes total idle time

    Several conditions must be satisfied

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    10/18

    Johnsons Rule Conditions

    Job time must be known and constant Job times must be independent of

    sequence

    Jobs must follow same two-step sequence

    Job priorities cannot be used

    All units must be completed at the firstwork center before moving to second

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    11/18

    Example Of Johnsons Rule (Two Machines)

    Job No. Time on M1 Time on M2 MC1 MC2 Sequence

    St. Time End Time St. Time End Time

    A 15 11 0 15 15 26 C

    B 17 10 15 32 32 42 G

    C 9 13 32 41 42 55 D

    D 12 15 41 53 55 70 HE 14 14 53 67 70 84 E

    F 12 10 67 79 84 94 I

    G 12 14 79 91 94 108 JH 13 15 91 104 108 123 A

    I 15 14 104 119 123 137 B

    J 13 13 119 132 137 150 F

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    12/18

    Sequence MC1 MC2

    (By Johnson's Rule) St. Time End Time St. Time End Time

    C 0 9 9 22G 9 21 22 36

    D 21 33 36 51

    H 33 46 51 66E 46 60 66 80

    I 60 75 80 94

    J 75 88 94 107

    A 88 103 107 118

    B 103 120 120 130

    F 120 132 132 140

    So we can say that by

    using Johnsons rule

    of scheduling Time

    saved in this case is :-

    150 140 = 10

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    13/18

    Johnsons Rule for Three Machines

    Condition:-Largest time on M2should be less

    thanor equalto smallest time on M1or M2or

    both.

    If condition satisfied then we calculate:-

    R1 = M1 + M2

    R2 = M2 + M3

    This whole can be understand by the help of

    following example:-

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    14/18

    Job No. Time on M1 Time on M2 Time on M3 MC1 MC2

    St. Time End Time St. Time End Time

    A 16 12 11 0 16 16 28

    B 15 11 12 16 31 31 42

    C 12 10 13 31 43 43 53

    D 13 9 15 43 56 56 65E 14 11 17 56 70 70 81

    F 15 10 16 70 85 85 95

    G 13 9 14 85 98 98 107H 12 12 17 98 110 110 122

    TOTAL 84 115

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    15/18

    MC3

    St. Time End Time

    28 39

    42 54

    54 67

    67 82

    82 99

    99 115

    115 129

    129 146

    R1 R2 SEQUENCE

    M1+M2 M2+M3 (BY JOHNSON'S RULE)

    28 23 C

    26 23 G

    22 23 D

    22 24 H

    25 28 F

    25 26 E

    22 23 A24 29 B

    Idle time on

    Machine-2 is:-

    122 84 = 38

    Idle time on

    machine-3 is:-

    146 115 = 31

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    16/18

    SEQUENCE MC1 MC2 MC3

    (BY JOHNSON'S RULE) St. Time End Time St. Time End Time St. Time End Time

    C 0 12 12 22 22 35

    G 12 25 25 34 35 49

    D 25 38 38 47 49 64H 38 50 50 62 64 81

    F 50 65 65 75 81 97

    E 65 79 79 90 97 114

    A 79 95 95 107 114 125

    B 95 110 110 121 125 137

    Total time saved by

    Using Johnsons rule

    Is:-

    146 137 = 06

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    17/18

    CONCLUSION

    Thus we can say that by using Johnsons rulewe can do more better sequencing of machines

    and can save the time of production.

  • 8/13/2019 19623402 Scheduling and Sequencing by Johnson Rule

    18/18