Poured housekeeping pads on the 4th floor. Air Handling Units were delivered to the site. Generator was delivered and placed on the equipment yard. The CMU parapet wall at the HQ has started. Started the lintel angle on the HQ. Framing and forming the upper roof at the VC is complete. Installing pans, reinforcing, and MEP rough-in on the upper roof. Placed concrete pans at stair 2 on Tuesday 1/19/10. AHU’s will be put on the HQ beginning of next week. The upper roof on the VC will be placed on Friday 1/29/10. Start stairs at the VC later next week. MEP above ceiling rough-in and interior partition framing are continu- ing up the HQ. Texas A&M University Agriculture Headquarters Weekly Report: 1/18/10-1/22/10 Overview of VC Generator for the Equipment Yard North View of Jobsite Parapet Wall at HQ

Upload: texas-am-agrilife

Post on 13-Mar-2016

212 views

Category:

Documents


0 download

DESCRIPTION

• The CMU parapet wall at the HQ has started. • Framing and forming the upper roof at the VC is complete. • Poured housekeeping pads on the 4th floor. • Installing pans, reinforcing, and MEP rough-in on the upper roof. • The upper roof on the VC will be placed on Friday 1/29/10. • AHU’s will be put on the HQ beginning of next week. • Placed concrete pans at stair 2 on Tuesday 1/19/10. • Air Handling Units were delivered to the site. • Started the lintel angle on the HQ.

TRANSCRIPT

Page 1: 2010-01-22

• Poured housekeeping pads on the 4th floor.

• Air Handling Units were delivered to the site.

• Generator was delivered and placed on the equipment yard.

• The CMU parapet wall at the HQ has started.

• Started the lintel angle on the HQ.

• Framing and forming the upper roof at the VC is complete.

• Installing pans, reinforcing, and MEP rough-in on the upper roof.

• Placed concrete pans at stair 2 on Tuesday 1/19/10.

• AHU’s will be put on the HQ beginning of next week.

• The upper roof on the VC will be placed on Friday 1/29/10.

• Start stairs at the VC later next week.

• MEP above ceiling rough-in and interior partition framing are continu-

ing up the HQ.

Texas A&M University Agriculture Headquarters

Week ly Repo r t : 1 / 1 8 / 10 - 1 / 22 / 10

Overview of VC Generator for the Equipment Yard

North View of Jobsite

Parapet Wall at HQ