Download - 2010-01-22
• Poured housekeeping pads on the 4th floor.
• Air Handling Units were delivered to the site.
• Generator was delivered and placed on the equipment yard.
• The CMU parapet wall at the HQ has started.
• Started the lintel angle on the HQ.
• Framing and forming the upper roof at the VC is complete.
• Installing pans, reinforcing, and MEP rough-in on the upper roof.
• Placed concrete pans at stair 2 on Tuesday 1/19/10.
• AHU’s will be put on the HQ beginning of next week.
• The upper roof on the VC will be placed on Friday 1/29/10.
• Start stairs at the VC later next week.
• MEP above ceiling rough-in and interior partition framing are continu-
ing up the HQ.
Texas A&M University Agriculture Headquarters
Week ly Repo r t : 1 / 1 8 / 10 - 1 / 22 / 10
Overview of VC Generator for the Equipment Yard
North View of Jobsite
Parapet Wall at HQ