Download - 2010-01-22

Transcript
Page 1: 2010-01-22

• Poured housekeeping pads on the 4th floor.

• Air Handling Units were delivered to the site.

• Generator was delivered and placed on the equipment yard.

• The CMU parapet wall at the HQ has started.

• Started the lintel angle on the HQ.

• Framing and forming the upper roof at the VC is complete.

• Installing pans, reinforcing, and MEP rough-in on the upper roof.

• Placed concrete pans at stair 2 on Tuesday 1/19/10.

• AHU’s will be put on the HQ beginning of next week.

• The upper roof on the VC will be placed on Friday 1/29/10.

• Start stairs at the VC later next week.

• MEP above ceiling rough-in and interior partition framing are continu-

ing up the HQ.

Texas A&M University Agriculture Headquarters

Week ly Repo r t : 1 / 1 8 / 10 - 1 / 22 / 10

Overview of VC Generator for the Equipment Yard

North View of Jobsite

Parapet Wall at HQ

Top Related