2010 doe vehicle technologies program review … › sites › prod › files › 2014 › 03 ›...
TRANSCRIPT
2010 DOE Vehicle Technologies Program Review Presentation
Bi-directional dc-dc ConverterIncluding Vehicle System Study to determine
Optimum Battery and DC Link Voltages
By: Dr. Abas GoodarziUS Hybrid Corporation
June 10, 2010Project ID #APE021
This presentation does not contain any proprietary, confidential, or otherwise restricted information
2
• Start: September 2007 • End: September 2010 • 80% Complete
Barriers addressed• Reduce the cost of battery for EV and PHEV
for commercialization• Efficiency of the converter• Power Density, Size of Converter for vehicle
packaging (volume and Weight)
• Total project funding– DOE $1,113,691– Contractor: $ 668,732
• Funding for FY09 $ 360,139• Funding for FY10 $ 160,272
Timeline
Budget
Barriers
Overview
• High inlet and ambient temperatures ( >105°C) • High efficiency ( > 95 %, originally 90%) • High power density (20 – 50 W/in3, achieved
54W/in3) • Low cost ( ≤ $75 /kW)
Project Target Performance
• PHEV requires high power density battery/energy storage for hybrid operation and high energy density battery for EV mode range.
• Battery Technologies to maximize power density and energy density simultaneously, are not commercially feasible.
• The use of bi-directional dc-dc converter allow use of multiple energy storage, and the flexible dc-link voltages can enhance the system efficiency and reduce component sizing.
The Challenge
Design a bi-directional dc-dc converter and fabricate a 8kW POC unit to demonstrate the following;• High inlet and ambient temperatures ( > 105 °C) • High efficiency ( > 95 %, originally 90%) • High power density (20 – 50 W/in3, achieved 54W/in3) • Low cost ( ≤ $75 /kW)
The Objective
4
Month/Year Milestone or Go/No-Go Decision
OCT 08
Determine the optimum vehicle system design.
Determine the cost saving for dual battery system
Determine the range increase for dual battery system
May 09
Determine the cost saving for dual battery system
Determine the range increase for dual battery system
Determine the power density of bi-directional dc-dc converter
Oct-09Determine Efficiency of the bi-directional dc-dc converter
Determine the cost of bi-directional dc-dc converter
Milestones
• Multi phase bi-directional dc-dc converter topology with High bandwidth control.
• Custom power module and packaging to allow high temperature operation.
• Integrated sensors to reduce size and cost.
• Enhanced custom magnetic to increase switching frequency and efficiency.
Approach/Strategy
Major Accomplishments
1. Developed a vehicle level simulation modeling, with dual battery system and the dc-dc converter for characterizing vehicle drive cycles for various vehicle system configuration and drive cycles and vehicle platforms (Economy, Compact, Sedan and SUV)
2. Developed an FEA parametric model and analysis techniques to characterize the magnetic and thermal behavior of the dc-dc converter critical components.
3. Developed a vehicle level power and energy management.
4. Developed and implemented converter level modeling to determine the operation trade off and control system.
5. The dynamic and static behavior of the dc-dc converters were validated with actual unit, including the converter system control.
6. Demonstrated High efficiency (meeting and exceeding the target > 95 %).
7. Custom Silicon packaging with 1200V NPT fast IGBT and 1200V SIC diode with high coolant temperature of 105 °C.
8. Has been able to demonstrate high power density of 54 W/in3,(Enhanced the EMI Filter), exceeding the program target of (20 – 50 W/in3).
9. Demonstrated low cost (≤ $62.5 /kW) for quantities of 10k/year, based on actual BOM and suppliers cost data with automated testing.
10.The dual battery system provides 14% increase in range, while
11.Reducing the weight by 13% and
12.Reducing the total cost by 5%, not including the life extension of the battery.
Major Accomplishments Cont.
Vehicle level modeling with Dual Battery and Bidirectional dc-dc Operation
8
High Power DensityHigh Energy Density
200-300 VDC 200-500 VDC
2.1 kWhPower Battery
8kW Bi-directionalDC-DC Converter
10 & 20 kWhEnergy Battery
10 kWh 20 kWh
9
0 50 100 150 200 250 300220
240
260
280
300
320
340
360
distance (mile)
EV
Bat
tery
Vol
tage
V1V2
0 20 40 60 80 100 120 140220
240
260
280
300
320
340
360
distance (mile)
EV
Bat
tery
Vol
tage
V1V2
Vehicle level performance (Voltage)
Single and Dual Battery Load Comparison
0 10 20 30 40 50 60 70 80 90 100 1100
2
4
6
8
10
12
14
Distance (mile)
Prm
s & P
ave (k
W)
P(HEV)rms
P(HEV)ave
0 10 20 30 40 50 60 70 80 90 100 1100
2
4
6
8
10
12
14
Distance (mile)
P(HEV)rms
P(EV)rmsP(HEV)ave
P(EV)ave
Battery rms and average power for single and dual battery system with Bi-directional dc-dc converter with optimum control strategy
Dual batteryPower battery has high rms and zero average and Energy
battery has only average current)
Single battery(high rms and average current)
State of Charge (SOC) & Energy
11
0 20 40 60 80 1000
10
20
30
40
50
60
70
80
90
100
Distance (mile)
SO
C (%
)
State of Charge (SOC)
EV (12.5 kWh)HEV (12.5 kWh)Single Battery (12.5 kWh)HEV (22.5 kWh)EV (22.5 kWh)Single Battery (22.5 kWh)
0 20 40 60 80 1000
2
4
6
8
10
12
14
16
18
20
Distance (mile)
Ene
rgy
(kW
hr)
Energy Used
Single Battery (22.5 kWh)Single Battery (12.5 kWh)EV (22.5 kWh)HEV (22.5 kWh)EV (12.5 kWh)HEV (12.5 kWh)
Dual Battery and bi-directional dc-dc converter range improvement over single battery
Weight and cost reduction and the range increase for the dual battery
12
The cost and weight reduction and range extension of the dual battery system.
Packaging
13
• Demonstrated High efficiency (meeting and exceeding the target > 95 %).• Custom Silicon packaging with 1200V NPT fast IGBT and 1200V SIC diode with
high inlet and ambient temp of 105 °C.• Demonstrates high power density of 54 W/in3, (target 20 – 50 W/in3).• Demonstrated the low cost (≤ $62.5 /kW) for quantities of 10k/year (target $75/kW).
Bi-directional dc-dc performance.
14
Converter Efficiency vs. Input Power
87%
88%
89%
90%
91%
92%
93%
94%
95%
96%
97%
0 1000 2000 3000 4000 5000 6000Power (W)
Effi
cien
cy %
3-Φ-Fixed1-Φ2-Φ3-Φ
105C Cooling
IGBT and SIC diode power converter operating at 50 kHz, Vin=250V and Vout=350V.
Converter dynamic Step load response.Vin=250V, Vout(hv)=350V, step load response
with resistive load (5kW).
V-hv, 1V/div, ac coupled.
I-in, 10A/div
,
15
The 2010 proposed work:
I. To design, develop and complete performance validations of the production intent prototype high power density power 8 kW bidirectional dc/dc boost converter. Vin=150V-300V, Vout=300V-500V and meets a DOE cost target of $75/kW
II. To demonstrate a power-conversion efficiency of 95% or more at a junction temperature of 130-150 °C corresponding to an inlet coolant temperature of 105 °C
III. To realize a power density of at least 1kW/l and a specific power of at least 0.8 kW/kg by operating the multi-phase converter at a modular switching frequency of 150 kHz.
IV. FMEA analysis and reportV. Production Planning.
16
Beyond FY10
The project is anticipated to go beyond FY10, by US Hybrid with following anticipated work and applications. • FY11
– Build Pilot production for PHEV, subject to customer demand. – Build pre-production units for Fuel cell industry.
• FY12– Build production for PHEV, subject to customer demand. – Build Production Units for Smart Grid.– Build production units for Fuel cell industry.
17
Summary
• The dual battery system for PHEV has proven to increase the rangeby 14% and reduce the weight by 13%, and the cost by 5%.
• The bidirectional dc-dc convert technology has met and exceededthe program requirements, following are a summary;
• Demonstrated High efficiency (meeting and exceeding the target >95 %).
• Custom Silicon packaging with 1200V NPT fast IGBT and 1200VSIC diode with high inlet and ambient temp of 105 C.
• Demonstrates high power density of 54 W/in3, (target 20 – 50W/in3).
• Demonstrated the low cost (≤ $62.5 /kW) for quantities of 10k/year(target $75/kW).
18
FY10 Time Line
2009
Oct Nov Dec
2010
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Go No/Go Decision Point: Soft tooling vs. investment tooling and Automated end of line test equipment design and fabrication depends on customer purchase commitment.
Challenges/Barriers: Vehicle level system Validation Partner.
Vehicle Interface, FMEA and MTBF Cont.
BDC Soft Tooling
Validation Data
System level Performance Validation
BOM and Cost
analysis
Custom Components Fabrication
Components Validation
Vehicle System Review with
customer
Delay of FY09 scheduleDesign Functional Validation, EMI/EMC
Production Planning PPAP, APQP