20.104 construction of steelwork

Upload: william-chong

Post on 06-Jul-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 20.104 Construction of Steelwork

    1/52

    PETRON S

    TECHNIC L ST ND RDS

    DESIGN AND ENGINEERING PRACTICE

    TECHNICAL SPECIFICATION

    CONSTRUCTION OF STRUCTUR L

    STEELWORK

    PTS 20 104

    APRIL 1989

    PETRON S

  • 8/17/2019 20.104 Construction of Steelwork

    2/52

    PREF CE

    PETRONAS Technical Standards (PTS) publications reflect the views, at the time of publication,

    of

    PETRONAS OPUs/Divisions.

    They are based

    on

    the experience acquired during the involvement with the design, construction,

    operation

    and

    maintenance

    of

    processing units and facilities. Where appropriate they are based

    on, or reference

    is

    made to, national and intemational standards and codes

    of

    practice.

    The objective is

    to

    set the recommended standard for good technical practice to be applied by

    PETRONAS OPUs

    in

    oil and gas production facilities, refineries, gas processing plants, chemical

    plants, marketing facilities or any other such facility, and thereby to achieve maximum technical

    and economic benefit from standardisation.

    The information set forth in these publications is provided

    to

    users for their consideration and

    decision to implement. This is of particular importance where PTS may not cover every

    requirement or diversity

    of

    condition at each locality. The system of PTS

    is

    expected to

    be

    sufficiently flexible to allow individual operating units to adapt the information set forth n

    PTS

    to

    their own environment and requirements.

    When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for the

    quality

    of

    work and the attainment

    of

    the required design and engineering standards.

    n

    particular, for those requirements not specifically covered, the Principal will expect them to follow

    those design

    and

    engineering practices which will achieve the same level of integrity as reflected

    in the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his

    own responsibility, consult the Principal or Its technical advisor.

    The right to use

    PTS

    rests with three categories

    of

    users :

    1 PETRONAS and Its affiliates.

    2) Other parties who are authorised

    to

    use

    PTS

    subject to appropriate contractual

    arrangements.

    3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with

    users referred to under 1) and 2) which requires that tenders for projects,

    materials supplied or - generally - work performed

    on

    behalf

    of

    the said users

    comply with the relevant standards.

    Subject to any particular terms and conditions as may be set forth in specific agreements with

    users, PETRONAS disclaims any liability

    of

    whatsoever nature for any damage (Including Injury

    or

    death) suffered by any company

    or

    person whomsoever as a result

    of

    or in connection with the

    use, application or implementation of any PTS, combination of PTS or any part thereof. The

    benefit

    of

    this disclaimer shall Inure

    n

    all respects to PETRONAS and/or any company affiliated

    to PETRONAS that may Issue PTS

    or

    require the use

    of

    PTS.

    Without prejudice to any specific terms n respect

    of

    confidentiality under relevant contractual

    arrangements,

    PTS

    shall not, without the prior written consent

    of

    PETRONAS, be disclosed by

    users to any company or person whomsoever and the PTS shall be used exclusively for the

    purpose they have been provided to the user. They shall be returned after use, Including any

    copies which shall only

    be

    made by users with the express prior written consent

    of

    PETRONAS.

    The copyright of

    PTS

    vests

    n

    PETRONAS. Users shall arrange for PTS to be held

    n

    safe

    custody and PETRONAS may

    t

    any time require Infonnatlon satisfactory to PETRONAS

    n

    order

    to ascertain how users Implement this requirement.

  • 8/17/2019 20.104 Construction of Steelwork

    3/52

    T BLE OF

    CONTENTS

    1.0 GENERAL

    1 1 Scope

    1.2 Performance

    f

    Work

    1.3 Errors

    And

    Omissions

    1.4 Referenced Documents

    1.5 Documentation

    1.6 Glossary

    1.7 Abbreviations

    2.0 MATERIALS

    2 1 General

    2 2

    Weldable Structural Steel

    And

    Steel Products

    3.0 WELDING

    3 1 General

    4.0 WELDING CONSUMABLE

    4 1

    Types Of Electrodes Wires

    And

    Fluxes

    4.2 Conditions And Storage

    4.3 Heating

    And

    Baking Requirements

    5 0

    QUALIFICATION OF WELDING PROCEDURE

    5 1 General

    5 2

    Parameters

    In

    Welding Procedure Specification

    5 3

    Welding Procedure Qualification Test

    5.4 Essential Variables In Qualification Of Welding Procedures

    5 5

    Procedure Qualification Record

    5 6 ~ ~ o Permitted Welding Processes

    5 7

    Testing Requirements For Procedural Qualification Test

    5 8

    Acceptance Criteria

    5 9 Retest

    6.0 QUALIFICATION OF WELDERS AND WELDING OPERATORS

    6 1 General

    6 2

    Qualification Test For SMAW with Covered Eiectrodes

    7.0 PRODUCTION WELDING

    7 1

    General

    7 2 Welding Sequence

    7.3 Weld Preparations

  • 8/17/2019 20.104 Construction of Steelwork

    4/52

    7.4 Weld Execution

    7.5 Preheating And Interpass Temperatures

    7.6 Stress Relieving - Post Weld Heat Treatment

    8.0 FABRICATION

    8 1

    General

    8.2 Material Preparation

    8.3 Forming Of Tubular And Cones

    8.4 Spacing of Seams And Splices

    8.5 Laying-Out Alignment And Fit-up

    8.6 Temporary And Non-Structural Attachments And Cut-Outs

    8.7 Finishing Of Surfaces

    8.8 Repair And Remedial Procedures

    8.9 Ancillaries And Temporary Works

    9.0 TOLERANCES

    9 1

    General

    9.2 Local Tolerances For Structural Components And Sub-Assemblies

    9.3 Global Tolerances For The Completed Structure

    9.4 Miscellaneous Structural Tolerances

    9.5 Launchways

    10.0 INSPECTION AND TESTING

    10 1

    General

    10.2 Personnel

    10.3 Testing Of Welds

    10 4 NOT Reporting Requirements

    11.0 PLACING DRAWINGS

    12.0 AS-BUILT DRAWINGS

  • 8/17/2019 20.104 Construction of Steelwork

    5/52

    1 0 GENERAL

    1 1

    Scope

    a This specification shall govern the material specifications, shop and field welding

    fabrication and inspection requirements of all structural steel for the Works,

    i.e.

    i

    Platform support structures

    Uackets,

    piles etc)

    ii) The deck, whether constructed of plate girders, box girders or tubular frames,

    and

    all associated support structures in or

    on the

    deck, access

    and

    protection

    steelwork e.g stairways, walkways

    and

    handrails,

    and

    bridges

    iii) Deck to substructure connection

    iv) Structural steel

    in

    or on

    the

    substructure, such as J-tubes, subsea pipeline

    bridges, manifold jackets

    and

    supports for e.g piping, process equipment,

    electrical equipment, instrumentation equipment, etc

    v) Jetties

    vi) Steel skirt to foundation if any)

    b

    The

    Contractor shall supply

    all

    steel, materials, labour, tools, equipment and services

    and

    perform or arrange

    all

    tests specified or necessary unless speCifically directed

    otherwise

    in

    the contract)

    to

    ensure that the requirements of this SpeCification are

    fulfilled and to ensure proper functioning of components.

    c

    Where it is necessary for certain structural steel components to be installed offshore,

    compliance with

    all

    the requirements of this Specification shall also mean that such

    component shall be trial assembled onshore to ensure subsequent correct fit, whenever

    directed by the Company.

    d

    The

    Contractor shall satisfy himself

    as

    to the details of the scope and requirements

    in

    the contract and shall be deemed to have included for the above stated and all that

    follows

    in

    this section

    o

    the SpeCification.

    e

    This

    SpeCification

    covers the material selection and welding of mild steels

    with

    yield

    strengths of less than or equal

    to

    52,000

    psi as

    defined in the relevant material

    speCification.

    1 2 Performance

    f

    Work

    a

    The Contractor shall have in charge of the

    work,

    at

    all

    times, a thoroughly competent

    superintendent and a fully qualified welding engineer, who are experienced

    in

    this

    category of steelwork construction and its fabrication. The Contractor shall deSignate a

    competent representative with whom

    the

    company and/or its representative may

    communicate at all times.

    b The Contractor shall employ only qualified craftsmen to perform all aspects of the work

    including testing. Any workman considered unsuitable by the Company shall be

    removed from the Works without delay and shall not be re-employed on the Works.

    c

    The Company shall be advised at least two days before commencement of any work by

    the Contractor and his sub-contractors.

    d

    The Contractor shall demonstrate to the Company that he

    is

    capable of producing work

    to the required standard, with particular respect to his sub-contractors he may wish to

    employ. This may be achieved by producing documented past and current types of

    work the Contractor/subcontractor has been engaged on.

    1 3 Errors

    And

    Omissions

    The Contractor shall be responsible for all errors and omissions

    in

    the detailing, layout and

    fabrication of the Works. It is the obligation of the Contractor to check the Contract

    Documents including

    the

    Contract Drawings immediately upon award of the Contract

    and to

    notify the Company immediately o any errors or omissions discovered.

  • 8/17/2019 20.104 Construction of Steelwork

    6/52

    1.4 Referenced Documents

    1.4.1 Base Specifications

    a

    Materials

    The BS 4360 has been selected as the basis for materials. All materials shall meet the

    requirements o this Code

    and

    the requirements mentioned

    in

    this Specification Chapter

    2.0.

    b Welding

    All welding, temporary or permanent, shall meet the requirements

    o

    the latest edition

    o

    AWS 01.1 Structural Welding Code-Steel

    as

    modified by this specification.

    c

    Inspection

    All inspection requirements shall meet AWS 01. 1. and the codes mentioned therein

    describing the techniques and as modified

    in

    this Specification

    in

    Chapter 10.0.

    1.4.2 Standards. Rules And Codes

    a

    Unless otherwise specifically indicated, the following standards, rules and codes shall

    be the guides governing the works. These shall be considered complimentary to and

    providing further detailed. requirements and recommendations to those stated in this

    Specification and shall be complied with. Where, however, the requirements

    o

    this

    Specification are

    in

    conflict with or expand the above requirements, this Specification

    shall prevail.

    b All the standards, rules and codes stated below are to be the latest editions at the

    commencement o the contract.

    i) American Petroleum Institute (API)

    API 5L - Specification For Line Pipe.

    API RP 2A - Recommended Practice For Planning, Designing And Constructing

    Fixed Offshore Platforms

    API 2B - Specification For Fabricated Structural Steel Pipe.

    API 2H - Specification For Carbon Manganese Steel Plate For Offshore Platform

    Tubular Joints.

    ii) American Institute

    o

    Steel Construction (AISC)

    Code

    o

    Standard Practice For Steel Building And Bridges Specification For The

    Design, Fabrication And Erection

    o

    Structural Steel For Buildings.

    iii)

    American Welding Society (AWS)

    AWS 01.1 - Structural Welding Code-Steel

    AWS A.2.4 - Symbols For Welding And Non Destructive Testing

    AWS A.3.0 - Welding Terms And Definitions

    AWS A.5.1 - Specification For Carbon Steel Covered Arc Welding Electrodes

    AWS A.5.5 - Specification For Low Alloy Steel Covered Arc Welding Electrodes

    AWS A.5.17 - Specification For Bare Carbon Steel Electrodes For Submerged

    Arc Welding

    AWS A.5.18 - Specification For Carbon Steel Filler Metals For Gas Shielded Arc

    Welding

  • 8/17/2019 20.104 Construction of Steelwork

    7/52

    iv) American Society For Testing And Materials ASTM)

    ASTM

    A6

    - Specification For General Requirements For Delivery of Rolled

    Steel Plates, Shapes, Sheet Piles

    And

    Bars For Structural Use

    ASTM A36 - Specification For Structural Steels

    v) British Standards BS)

    BS

    4360 - Weldable Structural Steels

    BS 4 Pt1 Specification For Structural Steel Sections:

    Pt1

    :

    Hot

    Rolled

    Sections

    BS 4848

    Pt2

    - Specification For Hot Rolled Structural Steel Sections: Pt2

    Hollow Sections

    BS 5135 Metal Arc Welding of Carbon

    And

    Carbon Manganese Steel

    BS 638 Arc Welding Plant Equipment

    And

    Accessories

    BS

    3971

    Image Quality Indicators For Radiography And Recommended

    Use

    vi) Det Norske Veritas DNV)

    Rules For The Design, Construction

    And

    Inspection For Fixed Offshore

    Platforms.

    vii) Deutsches Institute for Normung DIN)

    DIN

    17100 - Steels For General Structural Purposes.

    viii) International Institute of Welding IIW)

    Collection of Reference Radiographs of Welds In Steel

    IIW-36-39 - Recommended Practice For The Radiographic Inspection of

    Circumferential Fusion Welded Butt Joints In Steel Pipes Up To

    50mm Wall Thickness

    ix) National Association of Corrosion Engineers NACE)

    • Std RP-01-76 - Recommended Practice For Control of Corrosion

    On

    Steel,

    Fixed Offshore Platforms Associated With Petroleum Production

    x

    Japanese Industrial Standard JIS)

    JIS G3106 SM41-B - Rolled Steels For Welded Structures

  • 8/17/2019 20.104 Construction of Steelwork

    8/52

    1 5 ocumentation

    1.5.1 Prior

    To

    Fabrication

    Prior

    to

    commencement of any part of

    the

    fabrication, the Contractor shall submit the

    following documentation for approval by the Company.

    a

    Mill certificate for Contractor supplied materials.

    b

    Fabrication procedures, welding sequence and erection

    sequence. This is

    to

    include

    the welding procedure specification to be applied, sequence of plates to be welded, and

    number and location of welders at each stage

    o

    assembly.

    c Fabrication drawings including plate seam arrangement drawings, plate cutting

    drawings and

    weld

    details.

    d Drawings and calculations of temporary works, inclusive of support points, jacking

    points and sling points, approved

    by

    a qualified engineer.

    e List

    o

    proposed welding consumable and their areas of application including detailed

    control procedures for consumable handling, baking, storage

    and issue.

    f Welding procedures, repair welding procedures with their supporting procedure

    qualification records and including weld maps.

    g Certificates

    o

    welders, welding operators and tackers qualified

    in

    accordance with this

    Specification complete with list of welder identification numbers and photographs.

    h Key plan showing

    an

    unambiguous member identification and weld marking scheme.

    i

    Inspection procedures and detailed report sheets for non-destructive testing and

    inspection. This

    shall

    include separate sheets for Visual, Radiography, Ultrasonic, Dye

    Penetrant, Magnetic Particle, Painting

    and

    Coating.

    j) Identification and control procedures for materials.

    k Procedures for control of tolerances during fabrication and procedure for distortion

    rectification.

    I Detail procedures for welding equipment maintenance

    and

    calibration.

    m Qualification certificates for all inspection personnel.

    n) Summary sheets for NDT test reports for each joint which are

    to be

    kept up

    to

    date as

    the work progresses.

    1.5.2 puring Fabrication

    As the work progresses, the following shall be required :

    a As built dimensional survey records which shall be updated continually.

    b Where traceability is required, plans marked to relate certificate references for

    all

    materials to its final position

    in the

    structure.

    c

    NDT test reports original only) including radiographs and key plans marked showing

    final identification numbering, test report numbers and the results.

    d Production mechanical test reports, post weld heat treatment charts, leak reports and

    all charts for all items tested.

    e As

    built drawings and Specifications which shall show

    in

    detail the manner in which the

    facility was constructed and shall reflect all changes, additions, corrections or revisions

    made during the course of construction. The objective being to build up a full

    documented history of

    the

    Construction Work.

  • 8/17/2019 20.104 Construction of Steelwork

    9/52

    1 6 Glossary

    1 7

    Company - Shall mean PETRONAS

    Contractor - The party which entered into contract with the Company for the execution of

    activities as mentioned in a written agreement.

    Shall - The word shall is to

    be

    understood

    s

    mandatory to comply with the requirements of

    this specification.

    Should - The word should is to be understood as strongly recommended to comply with the

    requirements

    o

    this specification.

    Abbreviations

    API

    ASNT

    ASTM

    AWS

    BS

    CSR

    CAR

    CSWIP

    DPI

    DIN

    GTAW

    GMAW

    JIS

    MSF

    NDT

    PQR

    PWHT

    RT

    SAW

    SMAW

    SSB/SSPC

    WPS

    UT

    American Petroleum Institute

    American Society For Non-clestructive Testing

    American Society For Testing and Materials

    American Welding Society

    British Standard

    Company Site Representative

    Company Authorised Representative

    Certification Scheme For Welding Inspection Personnel

    Dye Penetrant Inspection

    Deutsches Institute for Normung

    Gas Tungsten Arc Welding

    Gas Metallic Arc Welding

    Japanese Industrial Standard

    Main Structural Frame

    Non Destructive Testing

    Procedure Qualification Record

    Post Weld Heat Treatment

    Radiographic Testing

    Submerged Arc Welding

    Shielded Metallic Arc Welding

    Sarawak Shell Berhad/Sabah Shell Petroleum Company

    Welding Procedure SpeCification

    Ultrasonic Testing

  • 8/17/2019 20.104 Construction of Steelwork

    10/52

    2 0

    MATERIALS

    2.1.1

    General

    a The purpose of this chapter is

    to

    specify the composition, properties, dimensions,

    tolerances, manufacturing process, handling, etc,

    o

    all materials which will

    be

    incorporated, both permanently and temporarily as either structural members or

    structural appurtenances, into the offshore platform.

    b

    Company inspection personnel shall

    be

    permitted free access

    to

    the Manufacturer s

    works for the inspection of any process necessary for the manufacture of these

    materials.

    c If a material not described in this chapter is required, it shall be brought to

    the

    attention

    of the Company which will decide which Specification shall apply.

    2.1.2 Transportation. Storage and Handling of Materials

    a The Contractor shall ensure adequate protection to all steelwork during any loading and

    transportation activities by providing adequate timber bearers during transport.

    b The Contractor shall provide nylon or similar lifting slings during handling or lifting

    operations; wire ropes

    or

    chain slings will not be permitted.

    c The

    steelwork shall

    be

    stored

    above ground

    on

    pallets, timber

    blocks

    or other similar

    supports, be kept above the level of any standing water and be kept free from dirt,

    grease, paint sprays, etc. and shall

    be

    protected from harmful environments.

    d Damage to any part of the steelwork either before, during or after erection shall

    immediately be brought

    to

    the notice of the Company.

    e Particular care shall be taken in storage and handling of parts which have

    been

    metal

    sprayed, galvanised, painted, etc., and should the coating be

    damaged,

    it shall

    be

    restored by an approved method at

    the

    cost of the Contractor, and be compatible with

    the particular coating.

    2.1.3 Used Materials

    Temporary bracing, erection

    aids, scaffoldings

    and

    materials and equipment for testing shall

    be

    fumished by the Contractor

    and

    shall

    be

    safe,

    serviceable

    and

    adequate,

    but need

    not

    be

    new.

  • 8/17/2019 20.104 Construction of Steelwork

    11/52

    2.1.4 Classification of Structural Steels

    For the purpose of this Specification, structural steel

    is

    classified by the following groups.

    a) TYPE I

    STEEL

    Primary Structural Steel- High Strength

    Primary structural steel - high strength, is steel with a yield strength of 5 ksi

    and

    over

    used

    in

    members essential to the overall integrity of the structure and for other

    structural members of importance

    to

    the operational safety of the structure.

    b) TYPE II STEEL : Primary Structural Steel - High Strength With Through Thickness

    Properties

    Primary structural steel - high strength with through thickness properties,

    is

    steel with

    yield strength of

    5 ksi

    and over

    and

    used in members essential to the overall integrity

    of the structure, where stress concentrations are high and where the stresses

    in

    the

    thickness direction may lead to lamella tearing.

    c) TYPE III STEEL: Primary Structural Steel- Mild Steel

    Primary structural steel - mild steel, is steel with a yield strength between 36 ksi and 5

    ksi

    and used in members essential to the overall integrity of the structure and for other

    structural members of importance to the operational safety of the structure.

    d) TYPE IV STEEL : Primary Structural Steel - Mild Steel With Through Thickness

    Properties

    Primary structural steel - mild steel with through thickness properties

    is

    steel with yield

    strength between 36

    ksi

    and 5

    ksi

    and used in members essential to the overall

    integrity of the structure, where stress concentrations are high and where the stresses

    in the thickness direction may lead to lamella tearing.

    e) TYPE V STEEL : Secondary Structural Steel

    Secondary structural steel is steel used in members not essential to the overall integrity

    of the structure and/or the operational safety.

  • 8/17/2019 20.104 Construction of Steelwork

    12/52

    2.2

    Weldable Structural Steel And Steel Products

    2.2.1 General Provisions

    All structural steel for use in offshore structures shall meet the requirements of BS 4360

    Specification For Weldable Structural Steel .

    a The types

    of

    structural steel, including the

    BS

    4360 grade identification which shall

    be

    used are:-

     

    BS Grade Description

    HS 50A,B,C,D,EE High Strength Steel

    II

    HS TTP 50A,B,C,D,EE High Strength Steel With Improved

    Through Thickness Properties

    III

    MS

    43A,B,C,D,EE

    Mild Steel

    IV

    MSTTP 43A,B,C,D,EE Mild Steel With Improved Through

    Thickness Properties

    V

    SEC 40A,B,C,D Secondary Steel

    43A,B,C

    For through thickness properties, reference is made to BS 4360 clause B29.

    The

    suffix

    Z25 shall apply.

    b All

    structural steel shall

    be

    fully killed and fine grained. Acid and Bessemer Steel

    making processes are not acceptable. Rimming steel shall not

    be

    used.

    c Through thickness properties materials shall

    be

    used when the Contract Drawings

    require them. They shall always

    be

    calcium treated. The steel producer may propose

    additional processing to reduce

    the

    occurrence of elongated Inclusions and laminations

    as appropriate for the speCified requirements. These may include for example, reduced

    sulfur, vacuum degassing and rare-earth-metal treatment. The additional processing

    and the casting method, ingot or continuous, shall be clearly defined and will become

    part of the basis of purchase.

    d) All Contractor supplied steel shall be new stock, free from mill scales, rust, grease or

    dirt and free from deformation.

    2.2.2 Altemative Specifications

    The following material specifications are considered acceptable as

    an

    altemative to the BS

    4360 grades specified in paragraph 2.2.1 above provided that

    i the carbon content is always 0.23% maximum

    ii) the maximum carbon equivalent (CE) is 0.45% (the applicable expression for C.E. is

    defined in BS 4360 clause B.6)

    iii) all additional requirements defined in 2.2.1 are met.

    Mild Steel High Strength Steel

    API 5L Grade B JIS

    G3101

    Class 4 SS55

    API5LX4

    ASTMA36

    DIN

    17100 RSt 37-2

    DIN 17100 St 42-2

    JIS G3106 SM41-B

    API Grade X52

    DIN

    17100 St 52-3

  • 8/17/2019 20.104 Construction of Steelwork

    13/52

  • 8/17/2019 20.104 Construction of Steelwork

    14/52

    2.2.4.2 Contents Of Certificates

    a) All material certificates should state the following:

    Name

    o

    manufacturer and factory symbol

    Purchaser order number and date

    o

    revision

    Certificate number and date of issue

    Material specification in full

    Dimensions

    Quantity and/or weight

    Charge number - batch number or heat-lot number

    Specified chemical, mechanical and physical properties (or reference standards)

    Actual chemical, mechanical and physical properties

    When applicable, NOT methods and results

    When applicable, heat treatment procedure, furnace charge number of heat

    treatment records

    Supplementary or additional requirements

    b

    In

    addition, the independent third party inspection certificates (DIN 50049.3.IC) shall

    state:

    That identification

    o

    the material has been verified by the certification authority

    That

    all

    tests were witnessed by the independent third party inspection agency

    Agency or inspectors identification symbol

    Certificate number and date

    o

    Issue

    2.2.5 Material Identification

    Material marking

    o

    all Contractor supplied primary structural steel shall be white paint

    stencilled letters on black paint background. In addition,

    all

    materials shall be colour coded

    with one

    red

    and one yellow painted band.

    Plate material shall be die stamped with the plate number and heat number by the plate

    manufacturer using low stress dot matrix type die stamps.

    Materials

    in

    the Contractors yard shall be clearly identified with piece and item number

    painted on the steel.

    2.2.6 Bolts. Nuts And Washers

    All bolts and nuts shall be the ISO metric thread series. Bolts shall be ASTM A 193 Grade B7

    and nuts shall be ASTM A 194 Grade

    2H.

    Alternatively, bolts to ASTM A325 and A490 may be used provided approval

    Is

    obtained from

    the Company.

    Round washers shall conform to American Standard B27

    -2

    Type B or equivalent, for use with

    ISO metric bolts. The diameter of the washer hole shall be 1.5

    mm

    greater than the bolt size

    for bolts larger than 25 mm.

    2.2.7 Pile Packer And Pile Gripper Assemblies

    Pile packer and pile gripper assemblies shall be as shown in the Drawings and shall be

    manufactured by a manufacturer approved by the Company. The assemblies shall be

    handled, installed and tested in strict accordance with the manufacturer s Instruction.

  • 8/17/2019 20.104 Construction of Steelwork

    15/52

    2.2.8 Gratings

    2.2.8.1 General

    All materials shall be fabricated from secondary steel (type SEC .

    Alternatively, ultra violet light resistant glass reinforced epoxy grating with fire retardants may

    be

    used after approval of the Company has been obtained. The colour of the grating shall be

    black or dark grey.

    2.2.8.2 Open Steel Stair Treads and Floor Panel (See 8.9.3)

    a Stair grating panel shall be of serrated pattern. Floor grating panel should either

    be

    smooth or serrated pattern type. The cross bars of section 6 mm x 6 mm shall be

    twisted, load bearing bars

    and end

    plates shall

    be

    constructed

    as

    detailed Table

    2.

    The

    load bearing bars may be constructed from cold drawn flat bars or I-bars.

    b) On the rung of

    the

    steel ladders and stairs anti-slip ladder

    rung

    covers of the type

    Safemate industrial grade or equivalent

    as

    approved by the Company shall

    be

    installed.

    2.2.8.3 Galvanizing

    All steel grating shall be hot dip galvanised with a minimum thickness according to BS 729 or

    ASTM A-123. Where it

    is

    impossible to galvanize a complete unit which must be joined by

    welding after galvanizing,

    the

    welds shall

    be

    painted in accordance with

    PTS

    30.48.00.31-P

    2.2.8.4 Installation

    All galvanised gratings shall

    be

    installed after galvanizing

    to

    check

    the

    fit.

    At the discretion of the Company,

    the

    grating on any part of

    the

    structure may have

    to

    be

    removed prior to load out.

    In

    this case, the Contractor shall mark the grating prior

    to

    removal

    and prepare a placing drawing

    in

    accordance with Section 11 of this specification.

    2.2.9 Deck Plate

    The use of chequer plates shall be avoided where possible and only be installed when

    indicated on the contract drawings. They shall be of the type where no slippery surfaces will

    be

    created due

    to

    standing water or oily products.

    For deck plates

    in

    a working area e.g. drill floors or walkways, heavy duty anti-slip surfaces

    shall be installed of the type Safemate or equivalent as approved by the Company. These

    anti-slip surfaces shall be bolted on.

    2.2.10 Timber

    a Timber for the

    mud

    mat shall

    be

    of a medium hardwood, keruing or equivalent, with

    an air dry density of approximately 740 kg/cu.m (46 Ib/cu.ft). The required allowable

    static bending strength of the timber shall be 11 MPa (1.6 ksi) determined in

    accordance with ASTM 0143-52.

    b) Launch runner timber shall be a hardwood, (Selangan Batu) or equivalent, with an air

    dry density of approximately 960 kg/cu.m (60 Ib/cu.ft). The required allowable

    compressive strength (parallel

    to

    the fibre) o the timber shall

    be 13 MPa

    (1.9 ksi)

    in

    accordance with ASTM 143-52.

    c) Timber of drilling decks shall be as b) above.

  • 8/17/2019 20.104 Construction of Steelwork

    16/52

    3.0 WELDING

    3.1

    General

    a Welding

    All

    welding, temporary or permanent, shall meet the requirements of the latest

    edition of AWS 01.1 Structural Welding Code-Steel ,

    as

    modified by this specification.

    b

    The following sections of AWS 01.1 are not applicable:-

    10.1-10.6,10.8-10.11,4.6,4.7,4.9-4.11,4.14-4.20. Section 8 and 9 of AWS

    01 1

    are

    only applicable when specifically referenced in AWS 01.1 sections 1-6. Where

    alternative provisions apply in AWS 01.1, those of section 10 shall apply for tubulars

    and section 9 shall apply for plates, girders and sections, with the exception of the non

    destructive testing acceptance criteria which shall

    be as

    per

    AWS

    01.1. section 10.

    c All welding shall be carried out by qualified welders and welding operators using

    qualified welding procedures in accordance with this specification.

    4.0 WELDING CONSUMABLE

    4.1

    Types

    Of

    Electrodes, Wires And Fluxes

    4.1.1 General

    a) The electrodes, wires and fluxes used

    in

    fabrication shall

    be

    selected to produce welds

    with mechanical properties equivalent

    to

    those required for the base metal or as

    specified by the Company.

    b)

    When

    steels of different strengths are joined,

    the

    tensile properties of the weld metal

    shall

    be

    matched

    to

    the lower strength steel.

    4.1.2 Covered Electrodes

    a

    All covered electrodes for welding of structural steels shall

    be

    low hydrogen electrodes.

    The hydrogen content shall not exceed 10 ml per 100 grams of deposited weld metal.

    b) Electrodes shall

    be

    selected from a list of approved types of electrodes, such a list

    to

    be

    submitted

    to

    the Company for approval prior

    to

    selection being made.

    c) Electrodes shall only be used under conditions,

    in

    positions, and using the welding

    parameters recommended by the manufacturer.

    4.1.3 Wire And Flux For Submerged Arc Welding

    Wire and flux shall be carefully selected and the flux shall be of the fully basic type. The

    storage

    and use

    of wire and flux shall be

    as

    recommended

    by

    the manufacturer. The flux

    supplier shall define the range

    of

    chemical composition of wire

    to be

    used for his particular

    flux.

    No

    low-alloy wires shall be accepted. The proposed wire and flux shall

    be

    submitted for

    approval by the Company.

    4.1.4 Wire For

    Gas

    Metal Arc Welding

    The gas metal-arc process may only be used on mild steel in enclosed shop fabrication

    conditions, and provided that the filler wire selected is such that the welds produced have

    the same mechanical properties as the base metal.

  • 8/17/2019 20.104 Construction of Steelwork

    17/52

    4 2 Conditions nd Storage

    a Electrodes shall be supplied in hermetically sealed cartons and stored in a dry storage

    room where the minimum temperature is 20 Centigrade. All manual type electrodes

    shall be properly identifiable see AWS A5.1 and 5.5)

    up

    to the time of usage, each

    electrode being distinguishable by colour code marking. If colours are destroyed

    by

    baking, handling or other causes, the electrodes shall not

    be

    used. Batch numbers shall

    be recorded.

    b) Low hydrogen electrodes shall not be stored in heated cabinets containing electrodes

    of other types,

    such as

    rutile or organic type electrodes.

    c Wire spools for automatic and semi-automatic processes shall be stored in cabinets

    with supplier wrapping not removed and remain clearly identifiable up to the time of

    usage. Unidentifiable wire shall not be used.

    d) Flux shall

    be

    supplied and stored in accordance with paragraph 4.1.3.

    e Each batch of flux and wire shall be labelled with the information from the supply

    container. The labels with batch number shall be recorded for reference.

    f All unidentifiable, damaged, wet, rusty or otherwise contaminated consumable shall be

    scrapped.

    g) A consumable handling, storage and issuing procedure shall be submitted to the

    Company for approval prior to the start of any fabrication.

    4 3 Heating nd Baking Requirements

    a All low hydrogen electrodes shall

    be

    baked at 270°C

    to

    330

    °C

    for one hour prior

    to

    use.

    b

    On completion of baking, the electrodes shall be transferred to a holding oven at 150

    °C.

    When later removed from the holding oven, the electrodes shall be transferred to

    heated quivers or containers at

    75°C

    and used within 8 hours.

    c Electrodes not used within 8 hours or for some reason exposed to adverse atmospheric

    conditions shall be reba ked for one hour and then transferred to the holding oven for

    later

    use.

    Electrodes shall

    be

    rebaked only once.

    d) Flux for submerged arc welding shall be issued

    as

    required for immediate use. They

    shall be held

    in

    a heated silo at 70°C

  • 8/17/2019 20.104 Construction of Steelwork

    18/52

  • 8/17/2019 20.104 Construction of Steelwork

    19/52

    5.3 Welding Procedure Qualificat ion Test

    a) Welding Procedure Qualification tests shall

    be

    carried out at the cost of the Contractor,

    to verify the WPSs and shall simulate,

    as

    far

    as

    is practicable, the conditions and

    materials

    to be

    used for production welding. Limitations imposed by

    the

    essential

    variables of the procedure qualification shall

    be

    adhered

    to

    in production welding.

    b) Changes

    in

    any of the essential variables (See 5.4) will call for a new qualification

    test.

    c)

    Changes

    in

    one or more of the non-essential variables will not call for a new

    qualification test, but a new WPS is required.

    d) A qualified procedure is valid for materials

    and

    thicknesses

    in

    accordance with

    paragraph

    5.5.1 and

    Tables

    5.10.1 and

    5.10.3 of

    AWS D1.1

    e) Qualification of a fillet weld by a groove weld is not acceptable.

    5.4 Essential Variables In Qualification

    f

    Welding Procedures

    Any changes

    in

    the essential variables listed

    in

    AWS

    D1.1

    para 5.5.2 and/or the following

    shall require the submission of a new WPS and a complete qualification of the procedure.

    i)

    A change in base metal type or grade outside

    the

    range defined in 2.2.1 above.

    ii) A change in welding process from that qualified

    to

    any other welding process or

    combination of welding processes.

    iii) A change

    in

    the welding groove or a change

    in the

    root

    gap

    outside

    of

    the allowable

    tolerances.

    iv) A change of consumable trade name, group, grade, classification or source of origin.

    v) A change in wire/flux combination.

    vi) An increase of electrode diameter by more than 1.0 mm over that used in the procedure

    qualification.

    vii) A change

    in

    shielding gas composition of any constituent of more than 5 of the total

    flow.

    viii) The omission or inclusion of backing strips These shall

    be

    avoided wherever possible.

    ix) A change from multipass

    to

    single pass or vice versa.

    x) A change

    in

    type of current or the polarity.

    xi) The omission or inclusion of back gouging.

    xii) A deviation in the preheat and/or post-weld heat treatment procedure.

    5.5 Procedure Qualification Record

    The specific facts from the WPS and test results from the welding procedure qualification test

    shall

    be

    recorded

    in

    the procedure qualification record (PQR). The PQR shall be submitted

    to

    the Company for approval before any production welding is commenced. Test results from

    previous jobs or contracts may be acceptable but only at the discretion of the Company.

    The form used for the WPS and PQR shall be such as described

    in

    AWS D1.1. However, the

    parameters stated in

    5.2

    above shall

    be

    recorded. Other alternatives are acceptable and on

    request,

    the

    Company s forms can be made available.

    5.6 Non Permitted Welding Processes

    High heat input welding processes such as electrogas, electroslag or high power density

    welding will not normally

    be

    permitted.

  • 8/17/2019 20.104 Construction of Steelwork

    20/52

    5.7 Testing Requirements For Procedural Qualification Test

    5.7.1 Non Destructive Testing

    Each test specimen shall

    be

    non-destructively tested for soundness using the following

    methods:

    a) Visual inspection.

    b)

    Radiography for butt welds.

    c) Ultrasonic inspection for thick walled butt welds and T-K-Y connections.

    d) Magnetic particle or dye penetrant inspection.

    5.7.2 Destructive Testing

    5.7.2.1 Tensile

    And

    Bend Test

    a) Complete Penetration Groove Welds:

    The type and number of specimens that must be taken to qualify a welding procedure

    are as shown in Table 5.10.1 of AWS 01.1.

    b) Partial Penetration Groove Welds:

    The type and number

    o

    specimens that must

    be

    taken

    to

    qualify a welding procedure

    are

    as shown in Table 5.10.2 of AWS 01.1.

    c) Fillet Welds:

    The

    type

    and number of specimens that must be taken to qualify a welding procedure

    are as shown in Table 5.10.3 of AWS 01.1.

    5.7.2.2 Macroetch Cross-Section Test Specimen

    Macroetch tests are required for all welds. For plate welds, one piece shall be selected. For

    tubular welds, one test piece in the 6 O clock and one test piece in the 9 O clock position shall

    be selected.

    For T-K-Y connections, a macroetch test piece shall

    be

    selected from the 3, 6 and 12 O clock

    positions. For fillet welds, refer to AWS 01.1

    Fig

    5.1 0.3A.

    5.7.2.3 Hardness Test

    A hardness survey shall

    be

    carried out

    on

    one of the macroetch cross-section test specimens.

    5.7.2.4 Impact Test

    This shall

    be

    required if ambient temperature at the fabrication yard

    is

    likely

    to

    fall below

    20

    °C. See

    also para 2.2.3 above)

    5.8 Acceptance Criteria

    5.8.1

    Visual Inspection

    The weld shall be inspected in accordance with 10.17.1 of AWS 01.1

    5.8.2 Radiographic Inspection

    The

    weld

    shall be Inspected in accordance with 10.18 and 10.17.3 of AWS 01.1

    5.8.3 Ultrasonic Inspection

    The weld shall be inspected in accordance with 10.19 and 10.17.4 of AWS 01.1.

    5.8.4 Magnetic Particle/Dye Penetrant Inspection

    Inspection shall

    be

    evaluated on the basis o the requirements for visual inspection above.

    5.8.5 Tensile Test

    The tensile strength shall not be less than the minimum of the specified tensile strength of the

    base metal used.

    5.8.6 Bend Test

    The specimen shall

    be

    Inspected

    In

    accordance with 5.12.2 of AWS 01.1

  • 8/17/2019 20.104 Construction of Steelwork

    21/52

    5.8.7 Macroetch Test

    The specimen shall be inspected in accordance with 5.12.3 of AWS D1.1

    5.8.8 Hardness Test

    The maximum hardness allowed shall

    be

    325 Hv

    10.

    5.8.9 Impact Test

    Impact requirements shall be as per 2.2.3 of this Specification.

    5 9 etest

    5.9.1

    When

    Retest

    Is

    Not Allowed

    Unacceptable defects evaluated by visual, MPI, DPI, radiographic, ultrasonic and macroetch

    testing shall be cause for rejection. A new test weld shall be required.

    5.9.2 When Retest Is Allowed

    When one of the following mechanical test specimens fail

    to

    meet the required acceptance

    criteria, two additional specimens shall

    be

    prepared for retesting. The location of the

    two

    additional specimens shall reflect the location of the failed specimen. If one or both of the

    retest specimens fail, then this shall be cause for rejection. A new test weld shall be required.

    a) Tensile test

    b

    Bend test

    c Impact test when applicable)

    d) Hardness test

  • 8/17/2019 20.104 Construction of Steelwork

    22/52

    6 0 QU LIFIC TION OF WELDERS ND WELDING OPER TORS

    6 1

    General

    6.1.1 Qualifications Required

    Welders and welding operators shall

    be

    qualified in accordance with the requirements of

    WS

    01.1 and this Specification. Only qualified welders shall

    be

    employed during the fabrication

    including tack welding structural welding

    and

    repair welding of any structural steel part. They

    shall only perform welding for positions and processes for which they are qualified. Backing

    materials

    shall

    not be used during testing. The Contractor shall ensure that welders of any

    sub-contractor or of any otherwise nominated contractor are qualified in accordance with this

    Specification. The purpose of a welder qualification test is

    to

    verify that the welder can apply a

    qualified welding procedure making welds of satisfactory quality.

    6.1.2 Witness nd Approval

    f

    Test Before Welding

    ll

    welders and welding operators tests shall

    be

    witnessed

    and

    approved by the Company

    before the welder or welding operator is permitted

    to

    work on the structure. The decision by

    the Company regarding qualification of any welder or welding operator shall

    be

    final.

    Evidence of previous qualification tests may

    be

    accepted solely at the discretion of the

    Company Representatives.

    6.1.3 Provisions Of Equipment And Costs

    f

    Test

    The Contractor shall provide equipment for the welder qualification tests

    and

    shall bear

    all

    costs for

    the

    non-destructive testing the cutting

    and

    machining of test specimens

    and

    mechanical testing. of specimens.

    6.1.4 Welder Identification System

    n identification system shall be worked out for welders

    and

    welding operators. The system

    which shall include a numbering and identification card index shall

    be

    established and agreed

    with the Company. Whilst

    on

    the Works the welder/welding operator shall always

    be

    identifiable by a badge bearing his name his photograph and his identification number.

    Welders

    and

    welding operators not wearing their badges will

    be

    dismissed

    from

    the Works

    by

    the Company Representatives.

    In

    the event that a welder leaves the Works his mark shall not

    be assigned to another welder employed on the Works.

    6.1.5 Marking Of Welds

    Each qualified welder and welding operator shall

    be

    supplied with

    an

    identification marker.

    The welder shall clearly mark the plate or pipe adjacent

    to

    his weld using soft die stamps with

    the identification mark assigned to him in his qualification certificate. Tack welding of

    components need not be marked.

    6.1.6 Applicability Of Qualifications

    The Contractor shall ensure that qualified welders and welding operators are employed during

    fabrication only on welding the type process and positions of weld for which their qualification

    test so qualifies them.

    6.1.7 Base Material

    As far as

    is

    practicable welders and welding operators shall

    be

    qualified

    on

    the same material

    to be

    used for fabrication. Similar types of materials may

    be

    substituted at the discretion of the

    Company provided that it can clearly

    be

    demonstrated that the weldability

    is

    equivalent to the

    material intended for use in the fabrication. Refer also to para 2.2.1.

    6 1 8

    If the test joint does not meet the requirements the welder or welding operator may at the

    discretion of the Company carry out a new test joint of the same type as the one rejected.

    Failing of both these tests shall result in the welder or welding operator not being employed

    further

    on

    the work. The welder shall only be considered for requalification after 14 days

    provided proof is given of proper training of the welder over that period.

  • 8/17/2019 20.104 Construction of Steelwork

    23/52

    6.1.9 Welder Qualification Record

    A record of the welders qualification test, including a reference to the corresponding

    WPS

    number, the essential variables according to

    AWS

    01.1 para 5.1.2, and the test results, shall

    be issued for

    each

    welder or welding operator for

    each

    test they pass.

    6.1.10 Period Of Effectiveness

    a)

    Welders

    and

    welding operators who will perform welds

    in

    the process/position

    combinations for which they were previously qualified need not requalify for those

    combinations if both

    o

    the following requirements are met

    i) The Contractor can show that the welder s performance has been monitored

    and proven satisfactory since

    the

    qualification test.

    ii) The welder certificate has been endorsed by a Company recognised Certifying

    Authority at a date less than six months before construction starts.

    b) Ouring construction, the Contractor shall provide evidence indicated in a) above to the

    Company so that the welder certificates can

    be

    re-endorsed within six months of the

    previous endorsement date. Any certificate not endorsed every six months shall

    be

    considered invalid.

    c)

    A qualified welder or welding operator may, at

    the

    discretion of the Company,

    be

    required

    to

    requalify if inspection reveals that

    an

    unacceptable number of repairs are

    necessary.

    6.2 Qualification Test For SM W With Covered Electrodes

    6.2.1

    Welding Test And Position

    Welders shall be qualified

    in

    the 6GR position as shown in Figure 5.21A of AWS 01.1 This

    will qualify him to perform groove or fillet welds in

    all

    positions

    on

    both pipes and plates

    including groove welds for T-K-Y connections. Other types of tests may

    be

    allowed at the

    discretion of the Company.

    6.2.2 Inspection

    And

    Test

    Each

    test weld shall

    be

    subjected

    to the

    following inspection and tests:

    a)

    Visual inspection

    b) 100 Ultrasonic test

    c)

    100

    Radiographic testing where possible

    d) Bend

    tests.

    See

    para 5.26 of AWS 01.1

    6.2.3 Qualitv Requirements

    Quality requirements are as defined by AWS 01.1 chapter 6 Part C.

    6.3 Qualification Test For S W

    6.3.1

    General

    Welding operators shall be qualified

    in the

    flat position

    and

    where this is done on pipes, the

    pipe shall be mechanically rotated.

    6.3.2 Welding Procedure

    A multipass technique shall be used.

    6.3.3 Inspection And Test

    Each

    test weld shall be subjected to the following inspection and tests:

    a)

    Visual inspection

    b)

    100

    Ultrasonic test

    c)

    100

    Radiographic test

    d) Bend tests. See para 5.26

    o

    AWS 01.1

    6.3.4 Qualitv Requirements

    Quality criteria are

    as

    defined by AWS 01.1, Chapter 6 Part

    C.

  • 8/17/2019 20.104 Construction of Steelwork

    24/52

    7 0

    PRODU TION WELDING

    7.1 General

    a Preparation and welding of structural members shall be in accordance with the

    appropriate qualified welding procedure specifications. Manual electrodes, wires and

    flux shall be of the same type and manufacture as those used in the procedure

    qualification tests.

    b Welding equipment shall conform

    to

    the appropriate sections of BS 638. Any equipment

    found not

    to

    comply with these requirements shall

    be

    replaced.

    c Welding current and voltage shall be the same as the test values, or within the range

    specified in the welding procedure.

    d)

    No

    welding shall

    be

    done until

    as

    much of the structure

    as

    will be stiffened thereby has

    been properly aligned.

    7 2

    Welding Sequence

    The Contractor shall develop welding sequences to control warping, creeping and the build-

    up of excessive internal stresses

    in

    the

    structure. The sequences shall be submitted to the

    Company for approval before the assembly of any components. The Contractor shall furnish

    the necessary supervision to ensure that the planned sequences are followed.

    Sequences shall include:

    a Welding procedure speCification to be applied.

    b Sequence of plates

    to be

    welded.

    c Any differences from the specified welding procedures, such as areas of preheating,

    reinforcements, etc.

    d) Post weld heat treatment, heating and cooling rates.

    e Number and location of welders at each stage of assembly.

    f Tack welds and spacers used in the assembly of components.

    7 3

    Weld Preparations

    7.3.1

    Alignment

    a

    At Splices butt welding)

    The offset at butt joints shall not exceed

    T 10

    where T is the thickness of

    the

    thinner

    material) or 6mm, whichever is less. The offset in longitudinal seams shall not exceed

    T 10 or 3mm, whichever is less. All offsets greater than 2mm shall be given a 1:4

    transition.

    b) At Welded Intersections

    The utmost attention shall be paid to good alignment of the structural parts on opposite

    sides of the through member.

    7.3.2 Surface Cleaning Before Welding

    Surfaces

    to be

    welded shall

    be

    free from loose scales, slag, rust, grease, paint

    and

    any other

    foreign material.

    7.3.3 Edge Preparation

    Preparation of weld edges by gas cutting shall, wherever practicable, be done with a

    mechanically guided torch. Edges shall be left free of slag and the cut surface shall be ground

    to a smooth uniform surface by removing approximately 0.5 mm of metal. After grinding, the

    weld edges shall be visually examined

    to

    ensure freedom from defects.

    7.3.4 Cleaning During And After Welding

    Upon completion o each welding pass, the weld shall

    be

    cleaned of spatter, slag and flux

    deposits. After welding is complete, adjacent surfaces shalf be thoroughly cleaned of all

    spatter and deposits.

  • 8/17/2019 20.104 Construction of Steelwork

    25/52

    7 4

    eld

    Execution

    7.4.1 Welding Position And Progression

    a) SMAW Welding

    Electrodes shall only

    be

    used in the position recommended by the manufacturer. Weld

    progression in vertical joints shall utilise the uphill method. For the 1

    G, 2G,

    1F

    and 2F

    positions, the maximum size of electrode allowed

    is

    6.4mm. For any other position, the

    maximum size of electrode shall

    be

    5.0mm. The capping passes shall always

    be

    done

    with a 4.0mm maximum electrode.

    b) SAW Welding

    This shall

    be

    done in the flat position and in the case that it is done on pipe, the pipe

    shall

    be

    mechanically rotated.

    7.4.2 Size Of Welds

    a) To obtain optimum toughness, a small bead multipass technique shall

    be

    used. The

    weave width for SMAW, i.e. maximum oscillation of the electrode, shall not exceed two

    and

    a half times the electrode diameter or 12mm whichever is the least.

    b

    The width of SAW beads shall not exceed six times the electrode diameter

    and

    the

    welding speed shall

    be

    375

    mm

    per minute minimum.

    c Fillet welds shall

    be

    completed in three or more runs except for seal welds which may

    be done in one run. Two

    run

    fillet welds are not permitted.

    d) The Company shall have the right

    to

    limit the thickness of each weld bead or pass

    when this exceeds those given in the weld procedure qualification test.

    7.4.3 Intermittent Welding

    Stitch welding i.e. partial seal welds shall not

    be

    allowed.

    7.4.4 Seal Welds

    Where stress bearing welds are required

    by

    contract drawings

    to

    extend only partially around

    a member, including plates joining another member, a seal weld of 4mm minimum fillet shall

    be

    applied continuously to the remainder, but note should

    be

    taken that a hardness of HV

    325

    maximum shall not

    be

    exceeded.

    7.4.5 Tack Welds

    Bridge tacking is the preferred method

    to

    avoid the tack becoming part of the final weld.

    If another method is selected, tack welding shall

    be

    performed with the same qualified

    welding procedure as will

    be

    used for structural welds. These tack welds shall

    be

    ground

    (feathered)

    and

    checked before actual welding commences. Tack welds are

    to be

    a minimum

    of approximately 50 mm long and spaced so that shrinkage forces cannot cause cracking.

    i See 7.5.2 (c) for preheat requirements .

    .4.V

    Butt Welds

    .....

    - a) Design of the groove and performance of welding shall be in accordance with the

    approved WEB However, in general, the groove shall

    be

    bevelled

    to

    give

    an

    included

    angle of not less than 60 degrees

    and

    shall

    be

    of the V or X type (single bevel or double

    bevel). The root openmg shall not

    be

    less than 2mm and not greater than 5 mm

    and

    the

    root face, if any, shall not

    be

    greater than 2

    mm.

    b

    Where access to both sides is possible, double bevel groove welds shall

    be

    used

    to

    minimise welding stresses

    and

    shrinkage effects.

    When different thicknesses are

    to be

    butt welded, a 1:4 taper shall

    be

    provided

    on

    the

    thicker member starting at the toe of the weld cap.

    At any joint, no butt weld shall

    be

    located such that

    an

    incoming member will result in a

    weld overlapping the butt weld.

  • 8/17/2019 20.104 Construction of Steelwork

    26/52

    7.4.7 Plate and Tubular. T or Y Joints

    Design of the groove

    and

    performance of welding shall be in accordance with the approved

    WPS.

    However, in general, Table

    10.13.1A

    of AWS 01.1 shall

    be used as

    a guide for all T-K-Y

    connections. The bevel shall preferably

    be

    feather edged and the root opening shall be 3 -

    5mm

    or according to

    an

    approved procedure.

    Welding of minor members shall

    be

    a full penetration type weld and

    where

    fabrication method

    permits, welding from both sides shall

    be

    carried out.

    7.4.8 Weld Compatibility

    All weld joints shall develop the mechanical properties specified for the steel being welded.

    Where different grades of steel

    are

    joined, the weld metal shall

    be

    matched

    to

    the lower

    strength steel. The procedure shall

    be

    such

    as

    to safeguard the mechanical properties of the

    higher strength member.

    7.4.9 Weld Finish

    Welds shall be left

    as

    welded

    and

    not

    be

    doctored with a torch or by any mechanical means

    to

    change their appearance. Any grinding or other mechanical dressing shall only

    be

    permitted after inspection and authorisation by the Company.

    7.4.10 Weld Interruption

    Welding o each weld shall be a continuous operation, with the exception of manually welded

    root runs for submerged arc welding.

    In

    the case that welding must

    be

    discontinued, this shall

    not take place before at least half of the final weld thickness is achieved. The maximum time

    that a production weld will remain part welded is two days. The maximum number of heat

    cycles that will be used in a production

    weld

    shall be two. Slow cooling of the weld area shall

    be

    ensured. Before continuation of welding, the weld shall

    be

    inspected for cracks visually

    and

    by MPI.

    7.4.11

    Weather Protection

    Shelters shall be provided at

    all

    times

    to

    give protection to the weld areas

    from

    wind, rain and

    moisture. No welding shall be carried out when the weld surface is wet or the work area is

    exposed to high winds.

    Precautions required :-

    a) The weld surfaces shall

    be

    thoroughly dried by preheating not above 300 ·C).

    Temperature control shall

    be

    carried out.

    b Special precautions made to provide conditions maintaining a satisfactory surrounding

    temperature and freedom from the effects of winds, all subject

    to

    the approval of the

    Company.

    c If any fabrication is

    to be

    carried out in the vicinity of eqUipment already installed in

    connection with the Work, then, before such fabrication work commences, the

    Contractor shall provide adequate protection to prevent any damage from weld spatter,

    flame cutting droplets and the like. Such protection shall be subject

    to

    the approval of

    the Company.

    7.4.12 Peening

    The peening

    o

    welds is not permitted.

    7.4.13 Arc

    Strikes

    Arcs shall be struck only on fusion faces and contact o the electrodes or the non-insulated

    parts of the electrode holder with the assembly shall be avoided. Places where any stray arcs

    have accidentally occurred shall

    be

    subject to repair or rejection at the discretion of the

    Company.

    Where permission to repair arc strikes mechanically has been given, the procedure shall

    Include, but not necessarily be limited to, the mechanical removal of the defective material,

    blending o the excavation, checking by MPI and confirmation that the thickness o the

    repaired material

    Is

    within permitted tolerances.

  • 8/17/2019 20.104 Construction of Steelwork

    27/52

    7.5 Preheating And Interpass Temperatures

    7.5.1 General

    a Preheating shall

    be

    carried out

    by

    electrical resistance induction equipment or with gas

    burners specifically made and shaped for this type of operation. Torches for flame

    cutting or gouging shall not be used.

    b

    The preheating temperature shall

    be

    established to a distance of at least 75mm

    on

    either side of the weld line and throughout the wall thickness prior to welding and be

    maintained over

    the

    full length of

    the

    weld joint until the weld is completed unless

    specifically agreed otherwise

    by the

    Company.

    c

    The weld area shall

    be

    protected

    from

    draughts

    and

    lagging shall

    be

    provided on

    adjacent areas, if necessary, to maintain the required temperature of preheating during

    welding.

    d The temperature measurement for preheating may be by thermocouples or temperature

    sensitive crayons, or a combination of both as may be appropriate for the type of joint

    being heated and the method of heating.

    e

    At all joints where preheating is required, the joint shall be subjected to temperature

    checks by the Company before welding commences.

    f

    During welding particularly where preheat has been used

    and

    for high heat input

    processes, care shall

    be

    exercised

    to

    control the interpass temperature and

    in no

    event

    should it exceed 300°C or as indicated in the

    WPS.

    The interpass temperature shall be

    monitored by means of thermo sticks or another approved method.

    7.5.2 Temperature Requirements

    a

    Preheat temperatures shall be as indicated in the approved

    WPS.

    b Preheat temperatures for lifting lugs or padeyes shall be 150°C minimum.

    c For tack welding where the tack becomes part of the main weld, the preheat

    temperature shall be 5 °C higher

    than

    specified

    on

    the WPS with a maximum of 300

    °C.

    7.6 Stress Relieving Post Weld Heat Treatment

    7.6.1

    General

    a

    The Contractor shall inform the Company prior to any PWHT operation so that the

    proposed format can be reviewed and inspected as a prerequisite for Company

    approval to proceed with the PWHT operation.

    b PWHT of nodes shall

    be

    carried out following complete assembly of

    the

    node.

    c The requirements for PWHT shall be determined from the thickness of the thickest

    component of

    the

    welded assembly. For tapered sections, the thickness at the weld

    shall be taken as the base metal thickness.

    d Assemblies with different maximum thickness but not exceeding a ratio of 2:1) may be

    post-weld heat treated

    in the

    same furnace charge

    in

    accordance with the heat

    treatment requirements for the thickest assembly in the charge.

    e Following PWHT,

    the

    temperature charts shall

    be

    marked with a clear identification

    and

    shall be retained for the quality control dossier. A copy shall be forwarded to the

    Company.

    7.6.2 Requirements For PWHT

    PWHT is required when any of the following conditions apply:

    a PWHT is indicated on drawings.

    b PWHT is indicated

    in the

    WPS.

    c The base metal thickness exceeds 65 mm.

  • 8/17/2019 20.104 Construction of Steelwork

    28/52

    7.6.3 Temperature Requirements

    a) When PWHT is required the following temperature ranges shall apply:

    i) 540 - 580 ·C for as-rolled

    and

    controlled-rolled steel.

    ii) 580 - 620 ·C for normalized steel.

    The soaking time shall be 1 hour per 25 mm of the maximum thickness occurring in the

    assembly

    to be

    heat treated.

    b) For furnace heat treatment, the fumace temperature at the time the assembly enters

    the furnace shall not exceed 300 ·C.

    c) The rate of heating shall not exceed 220 ·C/hour.

    During the heating period, there shall not

    be

    a greater variation

    in

    temperature

    throughout the portion of the assembly being heat treated than:

    i) 150°C within any 4500 mm interval of length and

    ii) 50°C

    between inside and outside surfaces.

    d) Cooling

    to

    400°C shall be at a rate not exceeding 275 °C/hour.

    Below

    400°C

    the fabrication may be cooled to ambient temperature in still air.

    7.6.4 Method

    a) Post-weld heat treatment shall

    be

    done in a suitable furnace or using proper induction

    or electrical resistance equipment.

    b) Where it is impracticable to heat the whole assembly in a furnace,

    the

    Contractor shall

    propose, in writing,

    an

    adequate method of PWHT for the approval of the Company.

    This procedure shall include the following information:

    The number, dimensions, locations and method of attachment of heating elements

    The location, type and thickness of insulation.

    Thermocouple types and their calibration procedures.

    Method of attachment of thermocouples, locations and number.

    • Types of temperature recorder

    and

    the calibration procedures.

    • Standard information

    to be

    recorded on the chart.

    c) The procedure for PWRT shall comply with the following:

    An assembly may be heat treated in sections in an enclosed fumace, providing the

    overlap is at least 5 SQRT Rt) R is the internal radius and t is the base metal

    thickness) with a maximum of 1500mm. Where this method

    is

    used, the portion outside

    the furnace shall be insulated so that the longitudinal temperature gradient is such that

    the distance between the peak and half peak temperature is not less than 2.5 with a

    minimum of 750

    mm.

    Circumferential seams in tubulars may

    be

    heat treated locally by electrically heating a

    shielded band around the entire circumference. The width of the heated band shall not

    be less than 5 , the weld being in the centre. For plate the width of the band shall

    be

    20t. Sufficient insulation shall

    be

    fitted

    to

    ensure that the temperature at the edge of the

    heated band

    Is

    not less than half the peak temperature. The ends of the tubulars shall

    be covered to avoid draughts inside the tubular.

    In

    addition, the adjacent portion of the tubular outside the heated zone shall

    be

    thermally insulated such that the temperature gradient is in accordance with the above.

    A minimum total insulated band width of 10 for tubulars, or 40t for plate,

    is

    recommended for the purpose of meeting this requirement.

    Welded attachments may

    be

    locally heat treated by electrically heating a shielded

    circumferential band around the entire surface.

    In

    such cases, the above requirements

    for circumferential seams in tubulars shall apply with the exception that the width of the

    circumferential band 2.5 Rt minimum or 750mm for plate) shall be measured from the

    edge of the weld which connects the attachments to the main fabrication.

    In cases where these requirements cannot be strictly applied, modifications may be

    agreed between the Contractor and the Company.

  • 8/17/2019 20.104 Construction of Steelwork

    29/52

    8.0 FABRICATION

    8.1 General

    8.1.1 Erection Loads and Stability

    a)

    During site assembly,

    the

    Contractor shall take account of

    all

    temporary erection loads

    imposed on the structure

    from

    supports, jacking

    and

    slinging at each stage of the

    structure assembly.

    b) At each stage of the structure assembly, the Contractor shall take account of the local

    or overall stability from self weight and environmental loads; inclusive of scaffolding,

    staging, welding shelters

    and

    temporary works. The Contractor shall ensure that

    all

    stresses induced in

    the

    structure during fabrication and load out are within acceptable

    limits.

    c) The Contractor shall take due consideration of the effect of wind induced vortex

    shedding on

    the

    structure or parts of the structure during construction.

    d) The Contractor shall demonstrate

    to

    the satisfaction of the Company that he has

    considered all relevant erection

    and

    temporary loads.

    e) The Contractor shall produce a procedure for each erection or transport activity where

    the item under consideration exceeds

    50

    tonnes

    in

    weight,

    and

    at other times when

    requested

    by the

    Company. The procedure shall cover

    all

    aspects detailed in this

    Clause and shall satisfy the requirements of the Malaysian Factory and Machinery Act

    and the SSB/SSPC Safety Manual.

    8.1.2 Material Identification

    a) All components shall

    be

    clearly marked in accordance with the approved scheme for

    the identification of members, welds and welders. (See 2.2.5, 6.1.5).

    b) The Contractor shall maintain full identification of primary structural steel throughout

    fabrication and

    the

    Contractor s reference number shall

    be

    die-stamped, using round

    nosed dies or

    by

    paint marking, on cut sections of plate, sections

    and

    tubulars, in a

    manner

    to be

    approved by the Company.

    8.2

    Material Preparation

    8.2.1 Straightening

    All rolled plates, bars and sections shall be flattened and straightened and made free from

    twist, without damage, before marking and cutting. The limit on the amount of strain induced

    by cold working shall

    be

    3 .

    8.2.2 Cutting And Edge Preparation

    The plate shall

    be

    cut

    to

    size

    by

    thermal cutting or machining in accordance with approved

    procedures except that for plates less than 15 mm thick, cold shearing may

    be

    used provided,

    that the sheared edge is dressed back by machining or grinding for a distance of not less than

    1.5mm. All cut edges shall be prepared to the satisfaction of the Company.

    The hardness of flame cut edges shall be limited to 325 HV10 maximum either by controlled

    speed flame cutting, by preheat, or by grinding back or machining after cutting.

    The cut edges shall

    be 100

    visually examined for laminations, cracks,

    and

    other defects. If

    such defects are detected,

    the

    extent shall be established. A repair procedure shall

    be

    agreed

    with the Company. At the discretion of the Company, the material component may be

    rejected.

    Any bevelled edge that has been damaged shall be restored to the minimum tolerances.

    Where such restoration involves welding, only welding procedures approved by the Company

    shall be used.

    8.3

    Forming

    Of

    Tubular And Cones

    f

    the Contractor decides

    to

    produce structural tubulars and cones, the end products shall

    meet the requirements of

    BS

    4360

    and

    procedures for forming and welding shall

    be

    approved

    by the Company. Only

    one

    longitudinal seam is allowed for tubulars. Cones shall be formed

    with a minimum number of longitudinal seams.

  • 8/17/2019 20.104 Construction of Steelwork

    30/52

    8 4 Spacing

    f

    Seams nd Splices

    8.4.1 Nodes

    Circumferential seams shall in principle not

    be

    allowed.

    If,

    however, they cannot

    be

    avoided

    the distance between circumferential seams in node barrels shall not

    be

    less than 2.5 metres.

    Circumferential seams shall not

    be

    permitted in the node stubs or cones.

    Longitudinal seams of the

    node

    barrels shall

    be

    offset

    by

    more than

    90

    0

    Longitudinal seams in stab in assemblies shall not be located closer than 150

    mm

    to

    longitudinal stiffeners.

    Longitudinal seams of node barrels shall not

    be

    positioned within

    75 mm

    of the brace/stub

    to

    barrel weld or within the perimeter of the brace/stub

    to

    barrel welds.

    Where the foregoing requirements cannot

    be

    met as a result of the complexity of the node

    then the locations of weld seams shall

    be

    agreed in advance of fabrication with the Company.

    The longitudinal seam weld of the stub shall not be within 200 mm on both sides of the centre

    of the toe

    and

    heel of stUb. See Figure 6.

    8.4.2 Other Tubular Structure And Piling Assembly

    No two circumferential seams shall

    be

    located closer together than 1m or the pipe diameter,

    whichever is less. There shall

    be

    no

    more than two circumferential welds in any three metres

    length. Longitudinal seams shall, wherever practicable be 9 ° radially offset.

    In

    general the number of seams in any tubular shall

    be

    kept

    to

    a minimum; they shall

    be

    either

    as indicated

    on

    the contract drawings or the restrictions outlined above shall apply.

    8.4.3 Stiffeners

    a) Where required, transverse splices shall

    be

    located not closer than 120

    0

    intervals

    around the ring stiffener flange or web. Web seams shall not

    be

    located closer than

    150mm

    to

    the node barrel or tubular circumferential seams unless noted otherwise in

    the Contract drawings.

    b

    Stiffeners shall

    be

    fitted accurately and neatly between the flanges of beams,

    and

    where tight fits are required

    to

    transmit bearing, the ends of the stiffeners shall be milled

    or ground, as detailed on the Contract drawings, to secure an even bearing against the

    flange faces, or shall

    be

    bevelled and fully butt welded to the flange. Cope holes shall

    be

    used only when indicated on the design drawings (see 8.5.4).

    8.4.4 Splices

    8.4.4.1 General

    a) Splices shall be kept to a minimum by making individual sections as

    l rge

    as possible

    consistent with the size of the plate supplied and the Contractor's approved assembly

    sequence.

    b) Splices shall be arranged

    to

    minimise overhead welding. Spliced materials of different

    widths and thicknesses shall have smooth transitions as specified

    in 7.3.1

    .

    c Lapped jOints are not permitted.

    d) Unless speCified otherwise on the drawings, when two or more members Intersect or

    overlap at a

    jOint,

    the order

    In

    which each member comes Into the joint will

    be

    determined by wall thickness and/or diameter. The member with the thickest wall will be

    the continuous or through member, and the sequence for framing the remaining

    members shall

    be

    based

    on

    the order of decreasing wall thickness.

    8.4.4.2 Beams

    Segments of beams with the same cross-section may

    be

    spliced. The use of the beam shall

    determine the location

    and

    frequency of spliCing.

    In

    cantilever beams there shall be no splice

    located closer

    to

    the

    pOint

    of support than one-half the cantilevered length. For beams

    employed in any span between supports, there shall be no splice in the middle one-fourth of

    the span. Splices shall not

    be

    located closer together than twice the depth of the beams, or

    900 mm, whichever is larger.

  • 8/17/2019 20.104 Construction of Steelwork

    31/52

    8.4.5 Camber

    When members are required

    to be

    cambered, the amount shall

    be

    specified and shown on

    the Construction drawings, and the means of achieving the correct amount of camber shall be

    agreed with the Company.

    8.5 Laying-out Alignment nd Fit-up

    8.5.1

    Laying-out

    a At all stages during fabrication, the Contractor shall ensure correct positioning,

    alignment and levels

    in

    accordance with the required datums.

    b) During layout

    and

    assembly of each node, the Contractor shall permanently mark

    and

    identify all wrap lines, working

    pOints

    and centre lines.

    c) Overloading, damage or any permanent deformation of any of the structural

    components at any stage of the erection shall be rectified in accordance with a

    procedure approved by the Company.

    d)

    No

    structural welding shall commence until the members

    to be

    joined have been

    properly aligned and braced

    to

    prevent distortion.

    8.5.2 Alignment

    And

    Fit-up For Welding

    And

    Tack Welding

    a

    Whenever practicable, clamps, holding devices or other setting

    up

    fixtures shall

    be

    used

    in

    assembling parts of the structure

    to

    avoid temporary welded attachments or

    tack welding.

    In

    fit-up where clamps cannot

    be

    used, temporary spacer strips shall

    be

    used to ensure the correct root gap prior to tack welding.

    b) Ring stiffeners, stiffeners

    and

    diaphragms shall be close fitted

    to the

    shape of the

    surface

    to

    which they are attached either by machining or by flame cutting

    and

    grinding.

    c) At intersections, the utmost attention shall be paid to good alignment of the structural

    parts where members meet

    on

    opposite sides of a through member. As-built

    dimensions shall

    be used to

    align such plates

    and

    not theoretical dimensions.

    d) Where powered manipulations are used

    in

    conjunction with Mechanised Welding

    Machines for the production of circumferential seams

    in

    tubulars, the tubular shall be

    set to turn at a constant angular velocity to ensure uniform deposit of weld metal.

    8.5.3 Temporarv Attachment Welds

    Temporary weld attachments

    and

    their removal shall meet the requirements of Clause 8.6

    below.

    8.5.4 Cope Holes

    Cope holes for

    ring

    stiffeners, stiffeners and diaphragms shall

    be

    permitted

    to

    a maximum

    radius of 50 mm. The cut edges of the cope holes shall be ground smooth to remove all

    notches, prior

    to

    fit-up of

    the

    member s). The fillet portions of all welds are

    to

    be returned

    through the cope hole.

    Cope holes shall be used only with the permission of the Company

    and

    may have

    to be

    filled

    to an approved method.

  • 8/17/2019 20.104 Construction of Steelwork

    32/52

    8.6 Temporary nd Non-structural Attachments nd Cut-outs

    8.6.1 Welding

    Temporary and non-structural attachments shall be fitted to the shape of the surface to which

    they are attached, and welding shall be to a qualified and approved procedure by qualified

    welders. Temporary or non-structural attachments shall not be welded within 75mm of any

    other structural weld measured from weld toe to weld toe.

    Locations and fixing details of

    all

    temporary attachments are subject to the prior approval of

    the Company.

    8.6.2 Removal

    The removal of temporary attachments shall be either by thermal cutting or by grinding. If

    thermal cutting is employed, the attachments shall be cut off at a minimum distance

    of

    5mm

    from the surface

    of

    the material and then ground flush. Following removal, the area

    of

    the

    attachment weld shall be subjected to 100 magnetic particle inspection.

    Temporary attachments shall not be removed by hammering, or by any other technique which

    may cause mechanical damage to the surface of the steel forming the main structure.

    Following removal, any damaged area shall be ground to merge smoothly with the original

    surface, and the surface is to be magnetic particle inspected. Where gouges up to 20 of the

    steel member thickness have been made, then after grinding and testing they shall

    be

    repair

    welded to an approved procedure. Where gouges exceed 20

    of

    the material thickness, the

    repair procedure or alternative solution shall be proposed by the Contractor and be subject

    to

    the approval

    of

    the Company.

    8.6.3 Temporary Cut-Outs

    The need for temporary cut-outs shall be subject to approval by the Company

    in

    each

    instance unless they are detailed on the Contract drawings.

    When temporary cut-outs are necessary, they shall be prepared with the same degree of care

    as for permanent cut-outs and shall be cut-out prior to erection of the member(s).

    Special care shall be taken to ensure that the weld preparation applied to the cut-out is

    appropriate to the final erected orientation

    of

    cut-out at the time

    of

    rewelding. The cut-out shall

    be trial fitted prior to erection

    of

    the member. An approved welding sequence developed such

    that welding will be minimized shall be followed. All cut-outs shall

    be

    prepared with radius

    corners not less than 50 mm.

    8.7 Finishing

    Of

    Surfaces

    a) Prior to completion, Contractor shall remove all burrs, tack welds and other marks

    made by welding, scaffolding or temporary bracing used in the fabrication procedures.

    b

    Any plate defects resultant from handling or fabrication works shall be repaired

    mechanically or to an approved welding procedure in accordance with the requirements

    of this SpeCification. The method applied for plate repairs shall be subject to the

    approval of the Company and shall comply with the limits of BS 4360.

    c) For areas with arc strikes see 7.4.13.

  • 8/17/2019 20.104 Construction of Steelwork

    33/52

    8 8 Repair nd Remedial Procedures

    8.8.1

    Repair Welding

    Weld repairs shall be carried out in accordance with an approved welding procedure. See

    5.1g.

    In

    the case of repairing cracks, the cause of cracking shall first

    be

    established satisfactorily

    before repair

    is

    allowed.

    8.8.2 Straightening Of Distorted Members

    a) Prior to straightening of a distorted member, calculations of the strains involved shall be

    submitted

    to

    the Company for approval. Members may

    be

    straightened

    cold

    if

    the

    deformation does not exceed

    3

    strain.

    b) When carried out hot, the temperature of heated areas, measured by methods

    approved by the Company shall not exceed 600 °C.

    The part

    to

    be heated shall

    be

    substantially free of stress

    and

    from external forces

    except those stresses imposed resulting

    from the

    mechanical straightening used

    in

    conjunction with

    the

    application of heat.

    c) Flame heating rectification shall be carried out only in accordance with appro