2013 environmental and social performance report for the

28
Environmental and Social Performance Report Annual Report June 2014 2013 Environmental and Social Performance Report for the PRC: Municipal District Energy Infrastructure Development Project Prepared by Dalkia Asia Pte. Ltd. for the Asian Development Bank (ADB)

Upload: others

Post on 05-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Environmental and Social Performance Report Annual Report June 2014

2013 Environmental and Social Performance Report

for the PRC: Municipal District Energy Infrastructure

Development Project

Prepared by Dalkia Asia Pte. Ltd. for the Asian Development Bank (ADB)

SCHEDULE 18

SEMI-ANNUAL ENVIRONMENTAL AND SOCIAL

PERFORMANCE REPORT

(ESPR)

Reporting Period: From 01/2013 to 04/2014 (to include heating season 13/14)

ESPR Completion Date: June 30th

, 2014

1

I. Introduction

A. Main Information

Dalkia (Jiamusi) Urban Heating Co.,

Ltd.

Dalkia Sunshine (Harbin) Heat Power

Co., Ltd.

Incorporation 2007-4-5 2007-7-13

Number of

Employees (2013) 595 580

Corporate Structure

• Dalkia Asia Pte. Ltd. (65%)

• Jiamusi New Times Urban

Infrastructure Construction

and Investment (Group) Co.

Ltd. (35%)

• Dalkia Asia Pte. Ltd. (95%)

• Harbin Property Heating Group

Co. Ltd (5%)

B. Description

a) Dalkia Jiamusi

In 2007, Dalkia Asia signed a concession agreement with the municipality of Jiamusi, for a twenty-five-year duration, to manage the former Jiamusi Heating Company s et o k a d t e le its size. Dalkia Asia set up a JV, Dalkia (Jiamusi) Urban Heating Co., Ltd., with Jiamusi New Times Urban Infrastructure Construction and Investment (Group) Co., Ltd. (which belongs to the municipality).

Dalkia Jiamusi is mainly involved in heating distribution and employs five hundred ninety five (595) persons at April of Year 2013. During the heating season 13/14, the heated area reached around ten point nine (10.9) million square meters. Primary network length was extended to one hundred and fifty (150) kilometres, and the number of substations increased to two hundred eighty-nine (289).

Over the years, Dalkia Jiamusi achieved important improvements in energy savings and pollution reduction while improving heating service quality at the same time.

During this heating season, Dalkia Jiamusi still faced the problem of situation from the two (2) third-party cogenerations, the main suppliers of heat; this situation has been improved quite a lot thanks to the technical assistance and advances last summer done by Dalkia China, which led to an important improvement of the heat capacity of the west cogeneration, and the connection with the paper pulp mill near east cogeneration. In summer of 2012, Dalkia Jiamusi and Dalkia China helped the est oge e atio to e o ate a d i p o e its fa ilities situatio fo ensuring its heat supplying capacity. The renovation includes heavy overhaul on boilers, turbines, and its auxiliaries as well. This situation therefore helped Dalkia Jiamusi to performance better during the entire heating season of 2013/14. The small peak boilers did shorten its operation period accordingly. In the mean while, the paper pulp mill has more capacity of steam supplying which can satisfy heat demand of 450,000m

2.

Thus, the overall satisfaction rate of customers increased a lot (96.89%) compared with the year before.

b) Dalkia Harbin

In 2007 also, Dalkia also acquired majority stakes in Yangguang, the company undertaking the development and operation of the South West heating network of Harbin City. The remaining shares of Yangguang are held by the municipal heating group of Harbin City. The a ui ed o pa y s name thereafter changed to Dalkia Sunshine (Harbin) Heat Power Co., Ltd..

Dalkia Harbin is involved both in production and distribution of heating and employs five hundred eighty (580) persons at the April of Year 2013. After 2 years of construction, Dalkia Harbin currently owes a large-scale-coal-fired plant (6 x 58 MWth); and also owns 1 CHP plant (construction started at the end of 2011) whose capacity is 4 x 220 t/h + 2 x 50 MWe, half of this CHP was in operation last heating season while the other half was in commissioning. Besides that, Dalkia Sunshine owes two (2) other small peak boiler houses: one coal-fired boiler house (1 x 20 t/h) and one gas-fired boiler houses (3 x 2 t/h). Finally, the whole CHP plant and HOBs would be taken into operation next heating season.

2

During the heating season 13/14, the heated area increased to around thirteen point eight (13.8) million square meters; the primary network was extended to eighty-six point eighteen (86.18) kilometres and the number of substations reached one hundred forty-six (146) substations. In 2013, twenty-eight (28) independent boilers houses were removed.

Dalkia Harbin contributes to energy savings and pollution reduction.

c) Performance analysis

The following indicators are used to monitor our operations in district heating worldwide. To be more relevant, these indicators are calculated at the end of each heating seasons.

Items

DALKIA JIAMUSI DALKIA HARBIN

Heating Seasons Variation

Heating Seasons Variation

12/13 13/14 12/13 13/14

Heated Area (m2) 10 925 273 11 186 449 2,4% 10 101 944 13 884 380 37,4%

Heating Seasons Period Oct 15 - April 25 Oct 14- April 15 -9days Oct 13 - April 21 Oct 13 - April 20 -1day

Day Degree ase 18°C or DD 5 574 4 972 -11% 5 481 4 781 -12,8%

P1 Margin (%) 50,00 54,00 8% 56,90 60,60 6,5%

Heat Efficiency (Wh/m2*DD) 26,7 27,6 3,7% 27,09 26,43 -2,4%

Electricity Efficiency network

(Wh/m2*DD)

0,22 0,23 2,5% 0,19 0,199 5,0%

Electricity Efficiency plants

(Wh/GJ) 6 074 7 010 15,4% 8 541 8 059 -5,6%

Water Efficiency (kg/m2*DD) 0,09 0,10 7,6% 0,01 0,004 -35,3%

Water Loss (l/m2/day) 2,64 2,66 0,7% 0,19 0,11 -43,3%

Coal Savings (Sd.t) 15 206 9 874 -35,1% 19 451 5 390 -72,3%

CO2 emissions (t) 549 404 531 183 -3,3% 519 419 623 961 20,1%

CO2/sq.meter (t/m2) 0,050 0,047 -5,6% 0,051 0,045 -12,6%

CO2 Savings (t) 42 330 24 617 -41,8% 53 288 15 004 -71,8%

SO2 emissions (t) 264 102 -61,2% 1 336 1 123 -15,9%

SO2/sq.meter (t/m2) 0,000024 0,000009 -62,1% 0,00013 0,000081 -38,8%

NOX emissions (t) 366 245 -33,0% 2 673 4 610 72,4%

NOx/sq.meter (t/m2) 0,000033 0,0000219 -34,5% 0,000265 0,000332 25,5%

Network Failures (days and m2)

6h - 46,469 m2

8h - 52,799 m2

8h - 46,134 m2

6h - 63,772 m2

8h - 51,952 m2

6h - 107,881 m2

10h - 56,282 m2

6h - 51,952 m2

4h - 46,223 m2

8h - 56,282 m2

6h - 123,170 m2

6h - 51,864 m2

4h - 56,282 m2

46h - 396,526 m2

24h - 79,282 m2

28h - 91,755 m2

11h - 1,521,783 m2

23h - 56,856 m2

46h - 396,526 m2

24h - 151,012 m2

11h - 87,868 m2

12h - 142,603 m2

12h - 239,155 m2

11h - 711,714 m2

13h - 85,793 m2

14h - 211,861 m2

13h - 378,956 m2

13h - 239,155 m2

24h - 149,206 m2

-

8h - 10,101,944 m2

216h - 90,000m2

48h - 460,000m2

6h - 100,000m2

8h - 800,000m2

17h - 90,000m2

2h - 132,693m2 -

Remark 1: Sd. t Coal means standard ton Coal (heat value 7,000 kCal/kg).

Remark 2: For Dalkia Jiamusi, CO2 emissions (t) include data from third-party cogenerations while SO2 and NOx emissions do not

as it was not possible to collect the Flue Gas Desulphurization data from these third-party cogenerations.

3

Remark 3: For Dalkia Harbin, increase of emission quantity of CO2 / SO2 / NOx was mainly due to start of electricity production of

power plant since October 2013.

Dalkia Jiamusi still faced the problem of situation from the two third-party cogeneration. The network failures in Jiamusi this year increased, but happened mainly on primary network, which was less uncontrollable, and the failure on the secondary network was reduced, which was still the positive impact resulting from technical renovation last summer; Dalkia Harbin faced only one important network failures to railway station, because of pump explosion problem.

Energy efficiency is highlighted through three main items:

Heat efficiency: The ratio calculates the energy used to heat a sq. meter in accordance with the exterior temperature. For Jiamusi we can notice a slight increase of this ratio this year while the customer satisfaction rate increased a big part: from 86% to 96.89% in Jiamusi while the heating target rate realized 99.38%. A 2.4% improvement for Dalkia Harbin in the mean time due to the higher efficiency of power plant being taken into operation since last heating season. This is a big achievement for Dalkia Harbin site.

Electricity efficiency: a 5.6% improvement for Dalkia Harbin while a 37.4% increasing of heati g a ea, it s a o ious accomplishment for this site;

Water efficiency: this ratio decreased more than last heating season in Harbin from 21.7% to 35.3%. The whole network had been improved & maintenance much better than before.

The increase of the quantity of CO2 / NOx for Dalkia Harbin is mainly due to operation of power plant (Phase II) with which the energy efficiency increases a lot as mentioned above and, the enormous increase of heated area. Dalkia Harbin needed to produce more heat for further heat demand because of the huge heat market increasing of Harbin city. However, main indicators show that our operations both in Jiamusi and Harbin lead relatively to a positive impact on the natural resources and environment:

Coal savings are still positives for both entities;

CO2 savings is still positives and CO2/sq.meter decreased in Dalkia Jiamusi while along with the increase of heating area and operation of Phase II in Dalkia Harbin, the internal energy consumption increases itself which had been obviously decreased in this heating season;

The indicator, NOx/sq.meter, increases in Harbin, these indicators increased due to the operation of Phase II which consumes more energy internally.

One indicator, SO2/sq.meter shows a sensitive decrease for both sites due to the efficient desulfurization facilities renovation done last summer. We changed the limestone feeding system for increasing its de-SOx efficiency and consuming less limestone.

Dalkia Jiamusi and Dalkia Harbin achieved important improvements in energy savings and pollution reduction while improving heating service quality at the same time.

4

II. Environmental and Social Management

A. ESPR Preparer

Report prepared by: Mr. QI Hui, Environment Manager, Dalkia China

Telephone: +86 10 5953 2550 E-mail: [email protected]

Signature: Report Date: June 30th

, 2013

In cooperation with:

Mr. Thierry STIEVENARD, Vice General Manager of Dalkia China,

Telephone: +86 10 5953 2557

E-mail: [email protected]

Mr. CUI Wanlong, Safety & Health Manager, Dalkia China

Telephone: +86 10 5953 2517

E-mail: [email protected]

B. Environmental and Social Responsibility

The individuals below hold responsibility for environmental/social and safety performance:

Senior Manager with responsibility for environment and social matters for Dalkia China

Thierry STIEVENARD, Chief Operating Officer

QI Hui, Environment Manager

CUI Wanlong, Quality, Safety & Health Manager

Senior Manager with responsibility for environment and social matters for our entities

Dalkia Harbin: TIAN Dong, President of the board, General Manager

Dalkia Jiamusi: DU Peng, General Manager

Environmental / Safety Manager in our entities

Dalkia Jiamusi: SHAN Baojie, QEHS Manager

Dalkia Harbin: DING Puxia, QEHS Manager

5

C. Environmental Management System Implementation

In December 2013, the Environmental Policy of Dalkia China (on the right) was updated based on our experiences, audits/inspections, and on the framework of Dalkia China EMS deployment:

Implementing the ISO & OHSAS standards: ISO 9001, ISO 14001 and OHSAS 18001;

Dalkia HRB was certified in August of 2013.

environmental impacts identification along with new construction of network and heat source;

internal auditor for ISO & OHSAS standards training;

internal audit & management review;

external audit by Certifying Company: annual supervision on all sites except HRB;

pollution preventive facilities improvement: including dust filters renovation and limestone feeding system;

organization optimization with QHSE standards in all Chinese entities;

qualified individuals and teams;

QHSE training;

Certification renewing on Jiamusi site and Dalkia China in September of 2012.

Note that the implementation of ISO 14001 management standard on Harbin site has restarted in September of 2012

because of its capacity expanding construction.

Under the responsibility of Dalkia China and Mr. Thierry STIEVENARD, specific departments have been settled to deal with environmental and social matters since we took over the two entities, in which qualified employees are constantly involved in the implementation of QHSE procedures and standards. Other upper-management employees are also responsible for the good implementation of these procedures.

Moreover, a wide range of training courses and seminars were held to e ha e ou lo al tea s ability and their performance. The training targeted not only the employees in charge of QHSE, but also operators and technicians, managers, the de-NOx & de-SOx training and lab manager training, for instance. (Refer to subpart V.c) of this Report and to the Operation Report).

Along with supervision auditing of ISO & OHSAS standards on all sites, the general manual of Dalkia China and sub-manual for every site were optimized and improved for standardizing our managerial and operation / maintenance. In 2013, many related procedures were improved or revised for fitting site situation and national regulations better, and making operation more reasonable and simpler.

6

The chart below summarizes the range of operational and managerial procedures implemented following our integrated QEHS management system in Dalkia (China) sites:

No. Dept./Business Numbering Documents (Procedure/Regulation/Guide/Norm) Effect

Date

1

Quality, Health and

Safety

M-001/11-A/0-DCEM/QEHS QEHS Management Manual 2012/01/01

2 P-001/11-A/0-DCEM/QEHS Documents Control Procedure 2011/11/01

3 P-002/11-A/0-DCEM/QEHS Record Control Procedure 2011/11/01

4 P-003/11-A/0-DCEM/QEHS Target, Index and Management Program Control Procedure 2011/11/01

5 P-004/11-A/0-DCEM/QEHS Hazard Identification & Risk Evaluation/Control Planning Procedure 2011/11/01

6 P-005/11-A/0-DCEM/QEHS Environment Identification/Evaluation/Control Planning Procedure 2011/11/01

7 P-006/11-A/0-DCEM/QEHS Management Review Control Procedure 2011/11/01

8 P-007/11-A/0-DCEM/QEHS Internal Audit Control Procedure 2011/11/01

9 P-008/11-A/0-DCEM/QEHS Information Communication Control Procedure 2011/11/01

10 P-009/11-A/0-DCEM/QEHS Law/Regulation Identification and Compliance Evaluation Management

Procedure 2011/11/15

11 P-010/11-A/0-DCEM/QEHS Accident/Incident Investigation, Report and Treatment Procedure 2011/11/15

12 P-011/11-A/0-DCEM/QEHS Non-conforming Product Control Procedure 2011/11/30

13 P-012/11-A/0-DCEM/QEHS Non-conformity Corrective & Preventive Control Procedure 2011/11/15

14 P-013/11-A/0-DCEM/QEHS EHS Performance Monitoring and Measuring Control Procedure 2011/11/15

15 P-014/11-A/0-DCEM/QEHS Interested Party Management Procedure 2011/11/15

16 P-015/11-A/0-DCEM/QEHS Asbestos Management Procedure 2011/11/15

17 P-016/11-A/0-DCEM/QEHS Legionnella Risk Prevention Control Procedure 2011/11/15

18 P-017/11-A/0-DCEM/QEHS Special Equipment Management Procedure 2011/11/15

19 P-018/11-A/0-DCEM/QEHS Special Operation & Personnel Control Procedure 2011/11/15

20 P-019/11-A/0-DCEM/QEHS Dangerous Work Management Procedure 2011/11/15

21 P-020/11-A/0-DCEM/QEHS PPE Management Procedure 2011/11/15

22 P-021/11-A/0-DCEM/QEHS Machinery Equipment Safety Control Procedure 2011/11/15

23 P-022/11-A/0-DCEM/QEHS Fire Prevention Control Procedure 2011/11/15

24 P-023/11-A/0-DCEM/QEHS Oil and Chemical Control Procedure 2011/11/15

25 P-024/11-A/0-DCEM/QEHS Electricity Safety Control Procedure 2011/11/30

26 P-025/11-A/0-DCEM/QEHS Female Worker Labor Protection Management Procedure 2011/11/15

27 P-026/11-A/0-DCEM/QEHS Vehicle Safety Control Procedure 2011/11/30

28 P-027/11-A/0-DCEM/QEHS Food Safety Control Procedure 2011/11/30

29 P-029/11-A/0-DCEM/QEHS EHS Inspection Management Regulation 2011/11/30

30 P-030/11-A/0-DCEM/QEHS Sub-constructor EHS Management Regulation 2011/11/30

31 P-031/11-A/0-DCEM/QEHS Energy Isolation (LOTO) Management Regulation 2011/11/30

32 P-032/11-A/0-DCEM/QEHS Emergency Preparation and Responding Control Procedure 2012/01/01

33 P-033/11-A/0-DCEM/QEHS Construction Project EHS Management Procedure 2011/11/15

34 G-001/11-A/0-DCEM/QEHS Safety Operation & Personal Health Protection inside Confined Spaces 2011/11/15

35

Environment

P-034/11-A/0-DCEM/QEHS Environment Management Procedure 2012/01/01

36 P-035/11-A/0-DCEM/QEHS Solid Waste Material Management Procedure 2012/01/01

37 P-036/11-A/0-DCEM/QEHS Noise Control Procedure 2012/01/01

38 P-037/11-A/0-DCEM/QEHS Sewage Control Procedure 2012/01/01

39 P-038/11-A/0-DCEM/QEHS Air Pollution Control Procedure 2012/01/01

40 P-039/11-A/0-DCEM/QEHS Energy and Resource Consumption Control Procedure 2012/01/01

41 P-040/11-A/0-DCEM/QEHS Coal Management Procedure 2012/01/01

42 P-041/11-A/0-DCEM/QEHS Coal Yard Management Procedure 2012/01/01

43 P-042/11-A/0-DCEM/QEHS Coal Sampling Control Procedure 2012/01/01

44 P-043/11-A/0-DCEM/QEHS Coal Analyze Management Procedure 2012/01/01

45

Technique

P-001/11-A/0-DCEM/TEC Technical Change Management Procedure 2011/11/30

46 P-002/11-A/0-DCEM/TEC Project Study Application Procedure 2012/01/01

47 P-003/11-A/0-DCEM/TEC Project Study Procedure 2012/01/01

48

Engineering Project

P-001/11-A/0-DCEM/ENG Construction Project Planning Management Procedure 2012/01/01

49 P-002/11-A/0-DCEM/ENG Construction Project Prophase Management Procedure 2012/01/01

50 P-003/11-A/0-DCEM/ENG Construction Project Implementation Management Procedure 2012/01/01

51 G-001/11-A/0-DCEM/ENG Pre-insulation Pipe Installation Regulation 2011/11/15

52 Operation

Maintenance

P-001/11-A/0-DCEM/OPM Data Analysis Control Procedure 2011/12/31

53 P-002/11-A/0-DCEM/OPM Technical Operation Control Procedure 2011/12/31

7

No. Dept./Business Numbering Documents (Procedure/Regulation/Guide/Norm) Effect

Date

54 P-003/11-A/1-DCEM/OPM Equipment Management Procedure 2012/06/20

55 P-004/11-A/0-DCEM/OPM Cogeneration Plant Operation Control Procedure 2011/12/31

56 P-005/11-A/0-DCEM/OPM Heating Network Operation Control Procedure 2011/12/31

57 Quality Control,

Measurement P-001/11-A/0-DCEM/QCM Monitoring and Measuring Equipment Control Procedure 2011/12/15

58

Purchase, warehouse

P-001/11-A/0-DCEM/PUR Purchase Control Procedure 2011/12/31

59 P-002/11-A/0-DCEM/PUR Coal Purchase Control Procedure 2011/12/31

60 P-003/11-A/0-DCEM/PUR Tender Management Procedure 2011/12/31

61 P-004/11-A/0-DCEM/PUR Supplier Management Procedure 2011/12/31

62 P-005/11-A/0-DCEM/PUR Materials Acceptance and Inventory Management Procedure 2011/12/31

63 P-006/11-A/0-DCEM/PUR Spare Parts Safety Storage Management Procedure 2011/12/31

64

Human Resource

P-001/11-A/0-DCEM/HR Recruitment Management Procedure 2011/12/15

65 P-002/11-A/1-DCEM/HR Training Management Procedure 2013/06/01

66 P-003/11-A/0-DCEM/HR Performance Evaluation Management Procedure 2012/01/01

67 P-004/11-A/0-DCEM/HR Organizational Change Management Procedure 2012/01/01

68 P-005/11-A/0-DCEM/HR Employee Internal Transfer Management Procedure 2012/01/01

P-001/12-A/0-DCEM/HR Personnel Handbook

69 Law, contract

P-001/11-A/0-DCEM/LEG Contract Application and Approval Procedure 2011/9/30

70 P-002/11-A/0-DCEM/LEG Legal Seal Management Procedure 2012/01/01

71 Finance

P-001/11-A/1-DCEM/FIN Investment Plan Application and Approval Procedure 2014/04/01

72 P-001/14-A/0-DCEM/FIN Purchase Management Procedure 2014/05/01

73 Business

Development P-001/11-A/0-DCEM/BD Business Development Procedure 2011/12/15

74 IT P-001/11-A/1-DCEM/IT IT Policy 2012/11/10

75 Administration P-001/11-A/0-DCEM/ADM Office EHS Management Procedure 2011/12/15

76 Commercial, sales P-001/11-A/0-DCEM/COM Customer Service Management Procedure 2011/12/15

77 P-002/11-A/0-DCEM/COM Customer Satisfaction Measure Control Procedure 2011/11/15

These procedures have been implemented to enhance skills of our employees, improve our overall operations, and therefore ensure QHSE performance; they comprise practical engineering, technical methods, operational software, etc. in accordance with our group, international and national standards (such as ISO and OHSAS standards). Our operations thus comply with ISO & OHSAS standards as well as national and local regulations / standards and with Environmental Policy of our Group and Dalkia China as well.

Some special handbooks/guidelines from Dalkia headquarter have been introduced/implemented in Dalkia China for the management and operation of subsidiaries. As for example, the quarterly report regarding legionella has been implemented and it is sent to Dalkia s headquarter (the report layout is shown on right side).

Finally, Dalkia China shall annually report to the headquarters and the Group about its energy consumption and general efficiency, emission level, H&S situation etc. The reporting shall be done at the beginning of each year.

This reporting is mandatory for each entity worldwide and thus enables Dalkia Company to follow up and develop tools and procedures to ha o ize Dalkia Co pa y s o e all ope atio s.

These indicators are published and shared within all

entities within our Group. Audits from the Group can

be planned in order to monitor, control and

implement action/corrective plan (if needed).

2013 Date :

Dalkia entity : Writer : Function

Cooling tower : 6 Cooling tower : 6

Hot water : 1 Hot water : 1

January February March April May June July August September October November December

Level A 6 6 6 6 6 6 6 6 6 6 6 6

Level B

Level C

Level D

Level E

Number of cooling systems 6 6 6 6 6 6 6 6 6 6 6 6 Total

< 0 6 CFU/L

≥ 0 6 and < 0 6 CFU/L

≥ 0 6 CFU/L

no detected no detected no detected no detected no detected no detected no detected no detected no detected no detected no detected no detected

January February March April May June July August September October November December

Level A 1 1 1 1 1 1 1 1 1 1 1 1

Level B

Level C

Level D

Level E

Number of networks 1 1 1 1 1 1 1 1 1 1 1 1 Total

< 0 1 CFU/L

≥ 0 1 and < 0 1 CFU/L

≥ 0 1 CFU/L

no detected no dected no dected no detected no detected no detected no detected no detected no detected

January February March April May June July August September October November December

Comments

Risk prevention for bacteriological development / index d - December 2008

2014/1/14

CHINA DCEM QI Hui Environmental Manager

Reference internal documents

Key reference external documents

- Regulation

- Recommendations

- Guides

- Etc …

Technical Alert Threshold (TAT) :

Number of networks

HOT WATER - with continuous chlorination

Nb o

f

analy

sis

Comments

Security

levels

COOLING TOWER

Nb o

f

analy

sis

CONTROL PLAN FOR LEGIONELLA RISK - YEAR

Threshold value for the country (CFU/L)

Month

Month

HOT WATER NETWORKS - HEALTH FACILITIES

Security

level

Comments

Maximum Technical Threshold (MTT)

:

Month

Standard examination methods for public place (GB 18204-2000), Hygiene specification of ventilation system of central air-conditioning in public places

?

?

?

?

?

?

?

change of the year

8

13燃油使用

Use of oil

资源消耗

Resource

consumption

1 1 0 2 √

14

尾气排放高浓度铅和CO2

NOx

CO2 and NOx emission

大气污染

Air pollution1 1 2 2 1 7 √

15噪声排放

Noise emission

噪声污染

Noise pollution1 1 4 2 3 11 √

16零配件更换

Replacement of spare parts

土地污染

Land pollution1 1 2 2 2 8 √

17车辆冲洗中水消耗

Water consumption during

cleaning

水资源浪费

Consumption of

water

1 2 4 2 3 12 √

18日光灯管的丢弃

Abandon of fluorescent light

土地污染

Land pollution1 1 2 2 2 8 √

19装修垃圾的产生

Creation of decoration waste

占用土地

Land occupation1 1 4 2 3 11 √

20油漆等材料使用

Use of painting material

污染土地

Land pollution1 1 2 2 2 8 √

21

施工过程中的噪音排放

Emission of noise during

construction

噪声污染

Noise pollution1 1 2 2 2 8 √

22机房管理

IT room management

机房设备辐射

Radiation

电磁辐射

Eletromagnetism

radiation

3 1 0 4 √

Note

1. A B C D E=M 若M≧14 即判定为重要环境因素;A=环境影响范围,B=环境影响程度,C=发生概率,D=相关方的关注度,E= 可改进程度

A B C D E=M if M≧14 it is important environment factor, A= environment effect scope, B= environment effect degree, C= happening probability, D=relative party focus degree, E=improve

degree

2. A B C D E各因子中有一个为5分者 即判定为重要环境因素

If any facor amon "A, B, C, D, E" >5, it should be evaluated as important factor

3. 当F=5或G=5或两项之和H F+G ≧6时确定为重要环境因素,F=消耗量,G=节约程度

When F=5 or G=5 or H (F+G)≧6, it should be evaluated as important factor, F=consumption amount, G=saving degree

评估人

Evaluator

部门主管 /经理

Department Chief/Manager

质量、环境、健康安全部经理

QEHS Manager

日期 Date 日期 Date 日期 Date

限制人员进入

Limit staff entry

采购和消费控制 行车记录

Procurement and expense control

提高燃油品质 定期清洗油路

Improve oil quality and periodically

clean the oil channel

定期保养车辆

Periodic maintenance

指定维修点

Appointed repair station

相关方管理

Stakeholder management

相关方回收

Recycled by relavant party

执行物业相关规定

Implement the rules of property

management company

相关方回收

Recycled by relavant party

执行物业相关规定

Implement the rules of property

management company

节约用水

Save water during cleaning

车辆使用

Vehicle use

III. COMPLIANCE WITH THE ENVIRONMENTAL AND SOCIAL REQUIREMENTS AS SPECIFIED IN THE LOAN AGREEMENT

A. Compliance with Country Requirements

One of Dalkia main objectives is to comply with national and local laws, regulations, standards and codes.

• As previously mentioned in the last reports, in order to meet this important objective, Dalkia China has a special engineer dedicated to the follow-up of all the amendment of national and local laws, regulations, standards and codes (more than 400 items, as below). Moreover, every employee of our entities in China has a continuous access to the intranet of Dalkia China where the national and local laws, regulations, standards and codes are continuously uploaded (bilingual version). Departments dedicated to QHSE in each entity have the responsibility to continuously inform the employees (under the supervision of Dalkia China).

• Moreover, internal QHSE inspections or audits are being conducted by Dalkia China on a quarterly basis. An action plan is prepared after an inspection / audit (if needed), and its appli atio a d pe fo a e is u de supe isio of e tities e ployees i charge of QHSE and Dalkia China. The following snapshots are examples of internal audit: environmental impacts identification and evaluation form.

9

• April 2011, the implementation process of ISO & OHSAS standards started in Dalkia China, including all of its entities. The integrated QEHS management system stengthens standardization of our management on QEHS issues. Throughout the implementation, a list of strengths and weaknesses was drawn in order for Dalkia China and its entities to comply with the best international practices required by the Group and the national/local laws, regulations, standards and codes.

• In September of 2012, Dalkia China and its all entities in China mainland were certified with ISO 9001, ISO 14001 and OHSAS 18001 while Dalkia Harbin who was certified in August of 2013 due to its enlargement of Phase II: from HOBs to cogeneration. Certificates of Dalkia Jiamusi are shown as below.

• There have been or have no any QHSE issues that did or will lead to any event of default.

B. Compliance with Environmental and Social Requirements

Existing projects are in compliance with the Environmental and Social Requirements defined in the Facility Agreement and Dalkia policy as well:

• A Reporting System has been implemented to communicate on a Annually, Semi-Annually and Immediate basis as defined in Clauses 17 and 19;

• Implementation of an EMS (in accordance to Schedules 7) is continuously improved (constant updates to comply with the best international practices required by the Group, ADB and the national/local laws, regulations, standards and codes);

Implementation of Schedule 8 (together with Schedule 17) is still in progress; Dalkia Jiamusi and Dalkia Harbin, with the support of Dalkia China and Asia, are closely working with ADB and its consultant to implement necessary resettlement and retrenchment frameworks. Indeed, issues were raised regarding the whereabouts of the employees from the connected boilers.

Important progresses have been made. Indeed, both entities cooperated with ADB in order to implement a comprehensive reporting system to monitor and protect the rights of the affected employees from the connection of their boilers. This was made possible with the venue of an ADB s o sulta t du i g this su e o oth sites.

From 2012, both entities have started to prepare a comprehensive report each year regarding the affected employees as follows:

Re-employment Plan: this plan describes the potential people to be affected through the development of our networks and what measures can be taken to protect their rights. This plan needs to be submitted each summer during the construction period.

10

Re-employment Plan & Monitoring Report: this plan is an update of the Re-employment Plan, and describes what measures are implemented to protect affected people rights (including some testimonies). This report needs to be submitted before the end of each year.

For the year 2013, these reports were submitted for Harbin, but not for Jiamusi as there were no connections in 2013.

• Co ti uous oope atio ith ADB a d its o sulta t to o ply ith ADB s so ial and environmental safeguards and implementation of action plans;

• Compliance with national and local laws, regulations, standards and codes;

• Implementation of departments dedicated to QHSE;

• Implementing ISO & OHSAS standards;

• An integrated manual has been issued complying with ISO 9001, ISO14001 and OHSAS 18001 standards;

• Dalkia Jiamusi was certified in 2012.

• Dalkia Harbin was in August of 2013.

• Continuous reinforcement/improvement of the QHSE policies, standards and objectives;

• Integration in the organization of QHSE standards and procedures through management, trainings, seminars, QHSE campaign and other means (general manual, sub-manual of subsidiaries, ha d ooks… ;

• Implementation of audits and inspections;

• Experience and competencies are continuously shared within Dalkia and Veolia E i o e e t s entities all over the world;

• Improvement of community relations.

11

IV. ENVIRONMENTAL AND SOCIAL PROGRESS OF PROJECT(S) UNDERWAY

Compare to heating season 12/13, the heated surface increased by 2.4% in Jiamusi and 37.4% in Harbin. The development of the heating surface did not lead to an increase of the unit energy consumption. Indeed, through the improvement of operation and maintenance, our local teams succeeded in saving energy sensitively (Refer to section I.B.c) ); and in improving heating services and customer satisfaction on the other part.

In order to develop our network, we connect small boilers to destroy them or use them as sub-stations which contribute greatly to the reduction of emissions. Indeed, there are many small boilers with low energy efficiency and high emission especially in Harbin. A total amount twenty-eight (28) of independent HOBs were removed Harbin in 2013. In the heating occupied region of Dalkia Jiamusi, all small HOBs has been destroyed by connection with our main networks since 2012.

The connected small boilers are mainly old (more than twenty years), and mostly do not meet QHSE sta da ds o e issio t eat e ts, as estos, i a ad state… , a d thus may endanger/harm the life of the workers and of the community as well.

Due to the 2 third-party cogenerations saturation, Dalkia Jiamusi faced tremendous challenges to supply heat and encountered important failures on almost all part of its network. However, Dalkia Jiamusi tried to connect network with a pulp mill which had additional heat source in order to ensure a reliable service to its customers, and thus the problem is well improved compare to previous heating season.

In order to be better complied with national & local regulations and standards, Dalkia HRB started to renovated the de-Dust system: filter renovation. 6 bag filters of Phase I were replaced by new bag for better efficiency because the new limit would be 30mg/Nm

3 from Jul. 1

st of 2014 on, which was 50mg/Nm

3 before this date. Besides that,

a de-NOx system was studied during summer of 2013, and, it would be installed the next summer for improving emission situation, to be complied with new national emission limits in the future.

During the reporting period, there was no land acquisition, resettlement, or indigenous people issues. Indeed, networks are usually built along the road and the space necessary for the CHP of Harbin is already comprised in the land originally dedicated to Dalkia Ha i s capacity production.

Dalkia Jiamusi and Dalkia Harbin, with the support of Dalkia China and Asia, are closely working with ADB and its consultant to implement necessary and retrenchment frameworks. Indeed, issues were raised regarding the whereabouts of the employees from the connected boilers.

A framework that complies ith ADB s so ial safegua ds was successfully implemented in 2013.

Social Due Diligences regarding the last three years were conducted for Dalkia Jiamusi and Dalkia Harbin and submitted to ADB during summer 2013.

During this reporting period, there were NO environmental and social issues, or unanticipated environmental or social impacts;

There are no unresolved social and environmental status;

Our local entities comply with the Environmental and Social Requirements (national, local and our Group).

In order to improve our operations and service quality, the chart below summarizes the description, status, and completion timetable of our EMS (Year 2013).

11

Step EMS items Discription Entities Status

1Structure and

responsibility

The Dalkia China has entrusted the Technical & Operation Department, in which Environmental Dept.

is involved, with the establishment and deployment of the Environmental Management System

necessary to the application of its Environmental Policy.

The subsidiaries of Dalkia has designated an environment manager, in charge in

particular of the deployment of this system within his/her scope.Done

2Environmental

policy

Dalkia China has defined its environmental policy (Zhang Zeming, Dec. 2008) in the framework of the

commitment to sustainable development of Dalkia Asia (Roland Schoorl, September 2008 ).

The subsidiaries deploy this policy within its scope and distributes to all its

personnel.Done

3

Identification of

significant

environmental

impacts

Dalkia China has identified main environmental impacts relating to environmental performance

associated with our activities. The priority risks and its relevant audit and inspection rules, to verify

the deployment of measures designed to comply with contractual obligations and control priority

risks, are in progress.

The subsidiaries of Dalkia Chiina should identify the installations and sites

concerned (priority installations), and evaluates the reality of the impacts and

risks on each one of them, in particular by deploying the audit and inspection

plans on these priority installations.

Done

4 Regulatory watch

Dalkia China is now defining a regulation management process that applies in particular for

requirements of national laws, regulations and standards about environmental protection and

sustainable development. Each Functional Department ensures a watch and updates, if necessary, the

provisions implemented in its domain (documents, tools, directives etc.).

Dalkia China makes sure that updates issued by the Country and the Group are

applied within its scope and conducts a watch and an update of its own measures.

regularly

checked

5Training of

personnel

Dalkia China is building a training modules based on the Group’s environmental management system.Moreover, a level of application of the environmental aspect characterizes each training module

identified in the Group’s training catalogue.

Dalkia China and its subsidiaries are planning to raise the awareness of its

personnel to environmental issues and organizes training sessions for the

concerned people.

Done

6

Emvironmental

management

program

Dalkia China has described the main operational impact control instructions (air releases, soil, water,

waste, noise etc.) and the emergency measures related to our major risks (pollution, fire, explosion,

leak etc.). Operating tools (CAM, energy management etc.) include environmental instructions (the

handbooks) related to its activities. Action plans are implemented at the country level to control

environmental impacts and risks. All these measures form the EMP of Dalkia China.

The subsidiaries deploy the instructions and emergency measures within their

scope and the operating tools (or makes sure that those in place incorporate

regulatory and internal requirements on the environment). Within their scopes

they deploy Group & Dalkia China's action plans and develop their own

environmental impact and risk control plans, in particular after audits and

inspections performed on priority installations.

Done

7 Reporting

Dalkia China is identifying the main environmental data necessary to establish performance

measurement indicators in this field and to the progress of the action plans undertaken. The

reporting framework is described and managed by the Technical & Operation Department. Data are

annually reported to the Veolia Environnement Sustainable Development Report.

The subsidiaries take the measures necessary to the acquisition of data in the

required reliability conditions and supplies country reporting as well as the Group

reporting. At its level it analyzes progress and performance indicators.

regularly

reported

8Management

review

Environmental systems should be deployed and their effectiveness monitored by the QHSE managers

under the responsibility of the Technical and Operations Director. The latter participates in the top

management of Dalkia China.

The subsidiaries include in its annual management review the examination of

environmental systems within its scope, their effectiveness and decides on the

actions necessary as applicable.

regularly

checked

9Customer

Relations

Dalkia China has designed offers focused on controlling the environment. Awareness and reporting

systems (satisfaction survey, complaint handling etc.) take into account the environmental aspect.

The subsidiaries deploy awareness and reporting systems within its scope with a

large share aimed at environmental issues. It widely distributes institutional

media related to the environment.

regularly

checked

12

V. SUMMARY OF SAFETY PERFORMANCE AND ANY CORRECTIVE ACTIONS

a) Accident and Incident data from sites in 2013

Indicators Jiamusi Harbin

Number of accident without Lost Days 0 0

Number of Accident with Lost Days 1 3

Number of fatal accident 0 0

Number of Lost Days from Accident 34 180

Frequency Rate FR1 (Accidents with Lost Days) 0.8 3

Frequency Rate FR2 (Accidents with and without Lost Days) 0.8 3

Severity Rate SR 0.03 0.18

Note:

• Brief description of three accidents in Harbin:

One repairer walked to a substation for an inspection, when he dodged passing vehicles, due to slippery road, he slipped and felt a slight pain of his right foot, he continued his work, after that, he felt his foot pain worse and reported to his supervisor, then went to a hospital, the exam shown the his right foot fibula fractured.

One repairer who join the repairing for the primary air fan motor wanted to go down the fan platform about 1 m high, because the platform stairs was blocked, he choice to throw over the platform rails, unlikely, he tumbled and had an injury of his right leg.

One employee taken a car with two co-workers to a substation for a technical inspection, while arriving an intersection, to avoid an opposition direction vehicle, the car hit the curb-stone on the road, the car accident led to the right arm fracture of the employee who was seated at the co-pilot position.

• Brief description of the accident in Jiamusi:

One operator was stumbled by a pipe on the floor inside the substation and his left knee knocked against a filter and fractured.

After these accidents occurred, they were reported according to relevant accident reporting procedures, in order to analyze the causes of these accidents and take relevant corrective and preventive measures which were implemented. The following snapshots show a sample about the relevant documents concerning accident reporting and completion of corrective and preventive actions.

Accident report Measure completion form Accident process simulation

13

b) Highlights on H&S improvement in 2013

Jiamusi site

Completed the annual internal audit and management review for local integrated QEHS management system including ISO9001, ISO14001&OHSAS18001, and passed the annual supervision audit by external certification company in April of 2014.

Continuous safety inspections and corrective action plan implementation in 2013 141 improvement actions were carried out such as:

• Improved the lighting condition and the operating platforms in the LongJiangfu heating substation.

• Equipped two small boiler houses with new ventilating equipment to improve ventilation condition on site.

• Improved the ventilation fan for the works to enter into the confined space to ensure safety of workers.

Implemented several H&S trainings for management, workers and subcontractors the total training time is 1592 hours.

Continued to promote the implementation of 6 H&S Good Practices and 5S management accident/incident analysis, self-assessment of risk at workplace, senior manager safety walk-about, team H&S meeting, good cleaning, stop 5 minutes for safety and other activities.

Carried out 100% regular inspection of special equipment and kept 100% operation certificates of special jobs.

Reinforced safety inspection and management for the subcontractors for repairing and engineering construction.

Implementation of the annual H&S Week Programs in November including H&S knowledge contest, fire extinguisher use instruction, fire escape drill and etc...

Combined safety performance of each employee with their annual performance appraisal.

Harbin site

Established and implemented local integrated QEHS management system including ISO9001, ISO14001 & OHSAS18001, passed the first certification audit in April of 2013, and got the certificates in Sept. 2013.

Implemented several H&S trainings for management, workers and subcontractors the total training time is 1,170 hours.

Organized the implementation of annual occupational health exam for 75 employees who contact to occupational hazard factors, the result are no problem.

Completed an official safety evaluation for the grid connection of 1# power unit of phase2.

Implementation of the annual H&S Week Programs in November including watched H&S video from Dalkia HQ and put up the posters, electric safety training and etc...

Planned and implemented emergency plan drills for the accidents of thermal power plant.

Realized the integration of the fire fighting control system of phase1 and phase2, and passed the fire fighting inspection and acceptance by local fire fighting department.

Completed regular safety inspections for special equipments, safety accessories, electrical equipment and lightning- protection facilities according to relevant regulations.

Reinforced safety inspection and management for the phase2 construction site and coal tippler installation site, mainly for PPE wearing, dangerous work permission and follow up corrective actions implementation for the findings from the daily and special inspection.

Continued to reinforce accident/incident control and reporting (three related-working injury accidents occurred).

14

c) Trainings and programs on H&S

The completed QEHS training are summarized in the following table (for the complete list, please refer to the Operation Report for Year 2013):

Dalkia Jiamusi

Dalkia Harbin

Contents Position of

attendees

Name/Type of

the training

Contents Position of

attendees

Name/Type of

the training

Safety training for special

equipment management

Special equipment

management

personnel

Safety Integrated management

system training

Managers and

internal auditors QEHS

Integrated management

system training Junior employees QEHS

Management system

document training

Managers and

supervisors of the

heating plant

QEHS

Occupational health

training

Employees who

expose to hazard

factors

H&S Dangerous and hot works

safety management training

Management

personnel

of heating plant and

network Dept.

H&S

New employee

orientation training All new employees EHS Legionella risk prevention

Chemical, boiler and

turbine operators H&S

Training for temporary

workers

All temporary

workers H&S H&S best practices training

Managers of heating

plant and network

Dept.

H&S

Job-transfer training All job-transfer

employees H&S

New employee orientation

safety training All new employees EHS

Safety knowledge contest

and escape drill Junior employees H&S

Environment protection and

safety training

Management

personnel

of heating plant and

network Dept.

EHS

ISO9001&OHSAS18001

standards training

Internal auditors

and supervisors

QHS PPE use training Employees of heating

plant H&S

HV safety training Electricians Safety Safety operation training in

the confined spaces

Repairing and

maintenance

workers of heating

plant and network

Dept.

H&S

Safety management and

accident analysis training

Managers and

supervisors H&S

Measuring and monitoring

equipment training

Instrument

technicians of

heating plant and

network Dept.

QEHS

Electric safety and LOTO

training

Electricians and

repairers Safety HV safety training

Electricians of

network Dept. and

management

personnel

Safety

Training about Special

equipment Law Safety engineer Safety

Safety management of

electric power plant

Management

personnel of heating

plant

H&S

InsBuilding firemen skills

training Full-time firemen Safety Post risk evaluation training

Technicians of

heating plant and

network Dept.

H&S

Safety training about

Longjiangfu substation

Employees in the

substation H&S

Safety training for

subcontractors

Staffs of seven

subcontractors H&S

Safety training for

subcontractors

Staffs of seven

subcontractors H&S

d) Fires and other Emergencies

During the reporting term, there were no incidents such as fires, or explosions, or major accidental releases to the environment.

15

VI. SUSTAINABLE DEVELOPMENT INITIATIVES AND COMMUNITY RELATIONS.

A. Customer Relations and satisfaction

a) General

In order to communicate about Dalkia Group and specifically about its operation in Asia, the website of Dalkia in China has been improved by using the new management system which is provided by Dalkia Coporate, and managed locally in China. (http://www.dalkia.cn/).

Using the same system architecture with Dalkia global website, Dalkia.cn focuses more on China market and contracts operated

among Asia area.

A new and more professional user service website is under progress of development which is expected to replace the closing local official page. The skin of this new website will follow the latest brand graphic standard. In addition to the basic functions for announcement and communication, the new one covers more than the previous website including vote, user information inquiry, edit and update, even forum. It will be more interactive with users.

Dalkia Jiamusi has developed many means in order to communicate with the community as the acquired company had been operating the heating network for many years which is different for Dalkia Harbin. However, Dalkia Harbin implements more and more means as the size of its supplied area rapidly increases.

b) Customers communication

The means below are detailed in the Reporting for Year 2013.

Local newspapers / magazines

Internet

Local radio

Local TV

New flyers & posters distributed in our supplied area (as shown below).

(Jiamusi) (Harbin)

16

Harbin Heilongjiang province TV interviewed Dalkia Harbin

Harbin TV interviewed Dalkia Harbin about Phase 2 plants

TV interviewed Dalkia Jiamusi TV interviewed Heat users (Jiamusi)

Radio Q&A (Jiamusi) New flyer (Jiamusi)

17

Harbin lighting ceremony (interviewed by Heilongjiang TV and Harbin TV)

c) Customers Services Improvement

In order to improve the service quality of our newly acquired entities, we implement new systems that successfully work in our other operation sites worldwide.

Centralized Collecting Office

Befo e the a uisitio , a ui ed e tities hea ily elied o fee olle to s to e o e heati g fees. As this method is not efficient, we decided to centralize the fees recovery into one sole collecting office. The advantages of the centralized collecting office are summarized below:

The information of the customers are all centralized in an ERP system which facilitates and accelerates the fee collection treatment

Easy for the customers to come and pay. Moreover in Jiamusi, all customers did receive a personal magnetic card to pay the fees at a counter or to an automatic machine which avoid long paperwork process.

Colle ti g offi e s a s a e a aila le to pi k-up old and handicapped people.

Help Desk

Dalkia implemented help desk to ensure a quick response to any incidents and in order to ensure customers 24/7 availability of the heating supply.

The establishment of a unique help desk provides a one-stop-shop for all customers to report faults, request services and/or information relating to the heating supply.

Contact number can be easily found in the newspapers, flyers or broadcasted on TV or radio. Dalkia Harbin even distributed cards on which the contact information of our customer services and our help desk were printed. It is also possible to found the contact number of the substation that supplies your block which is also convenient for customers in case of emergency.

A form will be automatically filled up by the called maintenance team and signed by the customer for each repair in order to keep track.

P.S. Help desk is 24/7 at your service during heating season, and is still available by working time in the other months not providing heat.

In 2013, Dalkia harbin help desk has received 23,400 calls from customers, and paid 1688 return visits by the telephone.

Payment collection – Bank services

18

During the first half year of 2013, Dalkia Jiamusi opens the bank service with Bank of China and Agricultural Bank of China to collect heating payment from Dalkia s customers. Heat users may be awarded by souvenirs if they pay their bills during 15

th Aug until 15

th Sep. by using this new way of

paying.

Simply 2 steps of paying:

Provide the AP code together with your ID card to the bank counter;

Follow and complete the payment procedure with your bank agent.

Satisfaction survey

Dalkia gained an 88% of satisfactory rate during the first half year of 2013 via the service survey system.

As for Har i , the a tio s to i pro e usto ers’ satisfa tio are listed elo :

Shanghai Pudong Development Ba k Pufa - Dalkia Bank Card

This debit bank card can be used to pay heating fee and it includes customer information; all heating related transactions will be visible on i di idual s a k a ou t.

The card does not have any management service charge. In the future, this card could be used for the household metering systems which it is started to be implemented in China.

Specialized counters were opened in Pufa Bank located in the center of Haxi district (within Dalkia Ha i s se i es pe i ete , hi h p o ided eal o e ie ce to customers who lived nearby, and to ensure the cash security as well.

Customer Services Handbook had been distributed among Dalkia employees serving at site

Together with this handbook, a satisfaction survey was taken among 8,200 residences, which covers 10% of the total heating residences in Harbin. Dalkia got a 95% satisfaction as a result.

New Bank service opened in Harbin for payment collection

A new bank service had been opened towards Dalkia s customers in Harbin for payment collection since 15

th August. To coordinate with

this new service, a handbook which explained in detail about the service and relevant information was distributed to each customer (about 49,100 customers).

To remind heat users to pay the heating fee, Dalkia Harbin has post 15,000 notices of the payment.

19

B. Community

a) Social responsibility

Through its ultimate mother company, Veolia Environnement, Dalkia has a strong social policy which is reflected in our entities as well. Dalkia actively involves itself in the local community as we believe that not only through energy we can build a better environment but through the community as well.

A donation within Dalkia Jiamusi was initiated for poor families who couldn t afford the heating charge.

In 2013, Dalkia Jiamusi also donated RMB 10.05 million to Tongjiang city for reconstruction.

All types of donation from Dalkia Jiamusi could be cumulated to RMB 12.2 million since 2008, excluding goods donated.

C. Awards

Over the past years, Dalkia has been rewarded locally and even internationally for its involvement. The table below summarizes awards/prizes during Year 2013:

Dalkia Jiamusi awards/prizes

Date Award Jury Level

January 2013 Advanced individual- Mr. Han Jingbin

Heilongjiang Province labor union,

Supervision Department,

Chamber of commerce,

Organization department,

Human Resources and Social

Security Department,

People's Government State-owned

Assets Supervision and

Administration Commission and

Commission for Discipline

Inspection

Provincial

January 2013 2011-2012 Credit Unit Administration Bureau for Industry

and Commerce Provincial

20

COMMENTS TO THE

Semi-Annual Environmental and Social Performance Report

Year 2013

Reporting Period-January 2013 to April 2014

ESPR Completion date: June 2014

Page/Section Comments Client’s Response

General comment Please complete the meaning of

all abbreviations used in the

report.

HOBs

QEHS

Dalkia HRB (Dalkia Harbin)

CHP

HOBs: heat only boilers

QEHS: quality, environment,

health, safety

Dalkia HRB: Dalkia Harbin

CHP: Combined heat and power

p.1: Description-Dalkia Jiamusi

The renovation includes heavy

overhaul on boilers, turbines,

and its auxiliaries as well.

These boilers may potentially

contain asbestos, which is

considered as a hazardous

material. Please ensure that

proper handling and disposal

were implemented for these

boilers and all permits and

clearance were secured prior to

their disposal. Also, include a

brief description on the disposal

option for these boilers (i.e.

waste treaters/haulers for these

boilers).

Firstly, all replaced boilers were

disposed by its owners. Dalkia is

not responsible for that.

In addition, there has been

internal managerial procedure

for asbestos management.

p.2

Performance analysis

For comparison, please include

the applicable national and

international ambient air quality

standards for CO2, SO2 and NOx

in the table of performance

analysis.

If available, please also include

the results on water quality

monitoring or include a brief

discussion about the status of

the compliance of the company

for water quality.

The ambient air quality standard

is not relevant to us. The power

plants or boiler owners only

need to meet the national

emission standard. There is no

emission limit for CO2 but for

SO2 and NOx.

Emission limit for JMS (HOB):

Before Jul 1, 2014:

SO2 800mg/Nm3, no limit for

NOx; (GB 13271-2001)

After July 1, 2014:

SO2 400mg/Nm3,

NOx 400mg/Nm3. (GB 13271-

2014)

Emission limit for HRB (HOB &

CHP):

Before Jul 1, 2014:

SO2 400mg/Nm3,

NOx 450mg/Nm3; (GB 13223-

2003)

After July 1, 2014:

SO2 200mg/Nm3,

NOx 200mg/Nm3. (GB 13223-

2011)

There is not waste water

discharged in Dalkia HRB. In JMS,

the main pollutant is suspended

solid from water preparing

process and it has been sent to

the municipal sewage treatment

plant.

p.3

Dalkia Harbin faced only

one important network failures

to railway station, because of

pump explosion problem.

Please state on what are the

measures to be implemented by

Dalkia to prevent network

failures. Also, the corrective

action on the occurrence of

pump explosion.

Corrective measure:

Replacement of the default

pump by a new pump of the

same capacity within 24h after

the event

Preventive measure:

1. Welding up a steel

encasement at the exterior

of the pump, sealing over

with steel confinement of

the hydraulic part (exclude

the electric motor part) to

prevent any leakage even in

worst case.

2. After two years of successive

tests on increasing the

primary network supply

temperature with successful

result, the supply

temperature of the primary

network will be increased

by >5 degree. In this case,

the flow and pressure drop

of the primary network will

be reduced dramatically,

thus, reducing largely the

expected operation hour of

the concerned pump. So, the

probability of failure of the

pump is also largely reduced.

3. Planned to build a pipeline at

Keyan road with will release

the pressure of the network

and exempt the usage of the

pump.

p.5

Environmental

Management System

Implementation

Dalkia HRB was certified in

August 2013

What is name of this certification

given to HRB in August 2013?

Please include the date of

validity for the ISO, OHSAS

standards.

Please explain why there was no

annual supervision on Harbin

(HRB).

As stated in the 2012 ESPR,

Dalkia Harbin is expected to be

ISO 1400 certified in the second

semester of 2014. Please give an

update on the ISO 14001

certification.

ISO 9001, ISO 14001, OHSAS

18001.

Dalkia HRB was certified (ISO

9001, ISO 14001, OHSAS 18001)

in 2013, thus there was no

supervision audit in 2013 but the

certifying audit.

Certification has been attached.

p. 8

A. Compliance with Country

Requirements

As previously mentioned in the

last reports, in order to meet this

important objective, Dalkia

China has a specialized engineer

dedicated to the follow-up of all

the amendment/additional of

national and local laws,

regulations, standards and codes

(more than 400 items, as shown

below).

What is the meaning of special

engineer in the statement?

Suggestion: Please include the

exact expertise or position of

this person (i.e. health and

safety engineer).

The specialized engineer is the

Environment Engineer in

Environment Department of

Dalkia China.

JD of environment engineer is

available when needed.

p.9

In September of 2012, Dalkia

China and its all entities in China

mainland were certified with ISO

9001, ISO 14001 and OHSAS

18001 while Dalkia Harbin who

was certified in August of 2013

due to its enlargement of Phase

II: from HOBs to cogeneration.

Certificates of Dalkia Jiamusi are

shown as below

Please show the certificate for

the Dalkia Jiamusi.

Already in the report

p.10

Compliance with Environmental

and Social Requirements

Dalkia Jiamusi was certified in

2012

Dalkia Harbin was in August

2013

Please indicate the name of the

certificate issued to Dalkia

Jiamusi and Dalkia Harbin.

ISO 9001, ISO 14001, OHSAS

18001.

p.11

Environmental and Social

Progress of Project(s) Underway

The connected small boilers are

mainly old (more than twenty

years), and mostly do not meet

QHSE standards (no emission

treatments, asbestos, in a bad

state…), and thus may

endanger/harm the life of the

workers and of the community

as well.

Please ensure that proper

handling and disposal of

asbestos should be implemented

(i.e. Proper Handling and

Disposal of Asbestos-Containing

Material). Also, all permits and

clearance must be secured prior

to disposal.

All replaced boilers were

disposed by its owners; Dalkia is

not responsible for that.

In addition, there has been

internal managerial procedure

for asbestos management.

p.11

Completion table on ESMS

Minor typographical error:

Please edit: Description

p.12

Summary of Safety Performance

and any corrective actions

Brief description of the accident

in Harbin

Please include the corrective

actions implemented for the said

accident.

For the implemented corrective

actions for the said accidents,

please refer to the attached

documents “Updated

information for accidents in the

reports to ADB (2011-2013)”.

p.13

Highlights on H&S improvement

in 2013.

Implementation of the annual

occupational health exam to 75

employees in Harbin site.

Suggestion:

Please provide annual health

exam to all employees of Jiamusi

and Harbin site.

In fact, the health exam is

provided to all employees of two

sites each year, on this basis, a

special occupational health exam

is provided additionally to those

employees who exposed to

occupational hazardous factors

like as dust, noise.

p.14

(c) Training and programs on

H&S

Please include the following

details in the table: number of

attendees and date of the

training

The required information have

been added into the training

table, please refer to attached

document “Updated information

for H&S training in the reports to

ADB (2011-2013)”.

p.15

Sustainable Development

Please include the discussions on

initiatives to improve

See to Attachment ”Sustainable

Development Initiatives”

Initiatives and Community

relations

environmental performance and

improve sustainable

development in operations.

p.17

C. Customer relations and

satisfaction

The information of the

customers are all centralized in

an ERP system which facilitates

and accelerates the fee

collection treatment.

Please include the meaning of

ERP (Enterprise Resource

Planning?).

ERP (Enterprise Resource

Planning)