2014-2019 stormwater capital improvement plan

35
2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN MAY 2013 PUBLIC WORKS DEPARTMENT STORMWATER UTILITY

Upload: hoangthu

Post on 13-Feb-2017

221 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

2014-2019 STORMWATER

CAPITAL IMPROVEMENT PLAN

MAY 2013

PUBLIC WORKS DEPARTMENT

STORMWATER UTILITY

Page 2: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN
Page 3: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

2014-2019 Stormwater Capital Improvement Plan May 2013

1 | P a g e

OVERVIEW

The 2014-2019 Stormwater Capital Improvement Plan (Plan) was developed to give Utility staff

and City leaders guidance and direction on what priority projects should be advanced for design

and construction during the next six years. As adopted by City Council, the plan allows Utility

staff to apply for grants to assist in funding the projects listed in the plan. It also helps in the

preparation of annual budgets in future years. This document outlines the current goals of the

Capital Program, the 2014-2019 plan development, immediate year proposed budget levels,

project summary listing, and proposed project locations, descriptions, and planning level cost

estimates.

CAPITAL PROGRAM GOALS

The 2014-2019 Plan developed with the following program goals in mind:

1. Improve failing locations or areas that show the highest possibilities of flood damage.

2. Reduce the number of City-owned stormwater outfalls to surface waters in half by 2020.

3. Eliminate or reduce the highest potential threats to groundwater from stormwater

facilities.

4. Maximize impact of local funding available for stormwater projects by receiving

available grant funding.

IMPROVEMENT PLAN DEVELOPMENT

The plan’s basis came about through the review, assessment, and evaluation of current needs

and the assumed availability of future resources.

IDENTIFIED NEEDS

Stormwater needs were identified and included improvement of water quantity and quality

benefits. The needs list came from the following:

1. Citizen action requests dealing with street runoff. These were investigated and

evaluated for the seriousness and legitimacy of the cases reported.

2. A State Department of Ecology required assessment and retrofit plan of City-owned

drywells to reduce threats to groundwater.

Page 4: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

2014-2019 Stormwater Capital Improvement Plan May 2013

2 | P a g e

3. The NPDES Permit requiring improvements to protect surface waters of the State.

4. Staff identified problem locations in storm drainages, flood ways, and floodplains that

run through, and infiltrate within the City limits.

Conceptual ideas to improve or mitigate priorities were further developed into proposed

projects, these included general information regarding size and scope of the proposed work,

and incorporated a planning level estimate. Many estimates in this plan do not have a

complete or clear project definition. Planning level cost estimates include an error factor of up

to 100% over the initial estimate since there are many unknowns in each of these concepts. As

projects are better defined and unknowns are uncovered through the process, the cost

estimate range of accuracy will improve.

FUTURE RESOURCES

Future resources that were identified included grant funding, local stormwater utility fees, and

aquifer protection fees:

Current levels of grant funding have increased over the past several years as the City

seized on opportunities available through State Department of Ecology grants. The City

won over $2,144,000 from these grants over the past 3 years. It appears that the State

will continue to offer these types of grants, although the total amount available to the

City is up to the Legislature, a competitive selection process, and the City’s ability to

compete. Because the City has enjoyed a healthy capital fund balance in the

Stormwater Utility fund each year, the City has been able to meet the typical 25%

required local match for most grant opportunities.

Local stormwater utility fees and budgets have offered approximately $400,000 each

year towards Stormwater Improvements, which this plan anticipates to continue.

Aquifer Protection Fees generate approximately $500,000 each year for the City, but will

sunset in 2025 under the current arrangement passed by voters in 2004.

Page 5: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

2014-2019 Stormwater Capital Improvement Plan May 2013

3 | P a g e

2014 – 2019 STORMWATER CAPITAL IMPROVEMENT PLAN SUMMARY

Project 2014 2015 2016 2017 2018 2019 Total Grant? APA

Annual Small Works Projects 600,000 600,000 300,000 300,000 300,000 300,000 2,400,000

x

Retrofits w/Pavement Preservation Projects

300,000 300,000 300,000 300,000 300,000 300,000 1,800,000 x x

Broadway, Havana to Fancher SD Retrofit

100,000 1,200,000 1,300,000 x x

Havana-Yale Diversion 300,000 300,000 x x

Ponderosa Surface Water Diversion 250,000 250,000 x x

Strategic Property Acquisition(s) 250,000 250,000

x

Chester Cr Wetland Overflow Improvements

200,000 200,000 x x

SE Yardly Retrofits (Area SE of Fancher/Broadway)

100,000 900,000 1,000,000 x x

Wellhead Protection Study and Pre-Design

80,000 80,000 x x

Dishman-Mica Infiltration Facility Plan 40,000 40,000 x x

Glenrose Surface Water Diversion 300,000 300,000 x x

Montgomery, Argonne to Mansfield Retrofit

115,000 1,185,000 1,300,000 x x

Petroleum Transport Routes, Spill Protection

200,000 200,000 x x

NW Yardly Retrofits (Area NW of Fancher/Broadway)

100,000 1,150,000 1,250,000 x x

Dishman-Mica, 16th to Appleway Retrofits

300,000 300,000 x x

NE Yardly Retrofits (Area East of Fancher & North of I-90

100,000 900,000 1,000,000 x x

Veracrest Groundwater/Stormwater Conveyance

350,000 350,000

x

Argonne, I-90 to Montgomery Retrofits 400,000 400,000 x x

Sloan's Addition (15th/Stanley) 250,000 250,000

x

Totals: 1,800,000 2,480,000 2,155,000 2,285,000 2,100,000 2,150,000 12,970,000

Page 6: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

2014-2019 Stormwater Capital Improvement Plan May 2013

4 | P a g e

402 STORMWATER UTILITY PROPOSED NON-RECURRING 2014 BUDGET

REVENUE Total

2013 Working Capital Balance (reserve) 1,850,000

Non-Recurring Budget Allocation 400,000

Grant Reimbursements 225,000

Total Funding Available: 2,475,000

EXPENDITURES Total

Small Works Projects 600,000

Retrofits w/Pavement Preservation Projects 300,000

Strategic Property Acquisition(s) 250,000

Total Expenditures: 1,150,000

403 APA FUND PROPOSED NON-RECURRING 2014 BUDGET

REVENUE Total

Spokane County 500,000

Grant Reimbursements 400,000

Total Funding Available: 900,000

EXPENDITURES Total

Broadway, Havana to Fancher SD Retrofit 100,000

Havana-Yale Diversion 300,000

Ponderosa Surface Water Diversion 250,000

Total Expenditures: 650,000

Page 7: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

2014-2019 SIP PROJECT DETAIL SHEETSSheet 1 of 29

Description: Improvements of stormwater facilities at various locations throughout the City on an annual basis. These projects were developed and prioritized from Stormwater Action Requests that staff have evaluated. Typically designed and managed by utility staff.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2014 Stormwater Small Works Projects

Proposed Start: 2014

Fund Amount Fund Yr

SW Utility - Fund 402 $560,000.00 2014

Total $560,000.00

Phase Year EstCost

Design 2014 $80,000.00

Construction 2014 $480,000.00

Total $560,000.00

May 2013

Page 8: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 2 of 29

Description: Annual program to address stormwater improvements on Arterials associated with the Pavement Preservation Program. Based on pavement preservation project list and the UIC Retrofit Plan.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2014 Retrofits with Pavement Preservation Projects

Proposed Start: 2014

Fund Amount Fund Yr

SW Utility - Fund 402 $260,000.00 2014

Total $260,000.00

Phase Year EstCost

Design 2014 $40,000.00

Construction 2014 $220,000.00

Total $260,000.00

May 2013

Page 9: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 3 of 29

Description: Project will provide a needed UIC retrofit. This project will improve or abandon existing drywells by providing conveyance and treatment facilities. Ranks as the top UIC retrofit project after the Sprague UIC Retrofit, Park to Thierman project. Project is a strong candidate for State stormwater grants. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Broadway, Havana to Fancher SD Retrofit

Proposed Start: 2014

Fund Amount Fund Yr

Ecology Grant $0.00 2015

APA - Fund 403 $100,000.00 2014

APA - Fund 403 $200,000.00 2015

Total $300,000.00

Phase Year EstCost

Design 2014 $100,000.00

Construction 2015 $1,200,000.00

Total $1,300,000.00

May 2013

Page 10: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 4 of 29

Description: Intercept possible discharges to City of Spokane Sewer System. Route stormwater discharges out of Spokane sewer to new stormwater swale, and provide infiltration to ground. Will help the City meet current stormwater permit requirements. Grant candidate. Planning level estimate shown.

Category: Outfall Elimination

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Havana-Yale Diversion

Proposed Start: 2014

Fund Amount Fund Yr

Ecology Grant 2014

APA - Fund 403 $75,000.00 2014

Total $75,000.00

Phase Year EstCost

Construction 2014 $300,000.00

Total $300,000.00

May 2013

Page 11: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 5 of 29

Description: Route existing stormwater discharges currently going to the Chester Creek to project constructed stormwater treatment and provide infiltration to ground. Would help the City meet current stormwater permit requirements. Grant candidate. Planning level estimate shown.

Category: Outfall Elimination

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Ponderosa Surface Water Diversion

Proposed Start: 2014

Fund Amount Fund Yr

Ecology Grant 2014

APA - Fund 403 $62,500.00 2014

Total $62,500.00

Phase Year EstCost

Construction 2014 $250,000.00

Total $250,000.00

May 2013

Page 12: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 6 of 29

Description: For securing and maintaining in perpetuity for the public interest floodways and floodplains. Possible secondary benefit of future Park or Open Space. For the possible support of public/private partnerships.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: Strategic Floodway Property Acquisition(s)

Proposed Start: 2014

Fund Amount Fund Yr

SW Utility - Fund 402 $250,000.00 2014

Total $250,000.00

Phase Year EstCost

Property 2014 $250,000.00

Total $250,000.00

May 2013

Page 13: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 7 of 29

Description: Improvements of stormwater facilities at various locations throughout the City on an annual basis. These projects were developed and prioritized from Stormwater Action Requests that staff have evaluated. Typically designed and managed by utility staff.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2015 Stormwater Small Works Projects

Proposed Start: 2015

Fund Amount Fund Yr

SW Utility - Fund 402 $40,000.00 2014

SW Utility - Fund 402 $580,000.00 2015

Total $620,000.00

Phase Year EstCost

Design 2014 $40,000.00

Design 2015 $40,000.00

Construction 2015 $540,000.00

Total $620,000.00

May 2013

Page 14: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 8 of 29

Description: Annual program to address stormwater improvements on Arterials associated with the Pavement Preservation Program. Based on pavement preservation project list and the UIC Retrofit Plan.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2015 Retrofits with Pavement Preservation Projects

Proposed Start: 2015

Fund Amount Fund Yr

SW Utility - Fund 402 $40,000.00 2014

SW Utility - Fund 402 $260,000.00 2015

Total $300,000.00

Phase Year EstCost

Design 2014 $40,000.00

Construction 2015 $260,000.00

Total $300,000.00

May 2013

Page 15: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 9 of 29

Description: Project to replace existing embankment overflow channel with a concrete embankment overflow channel to mitigate vegetation clogging the current flow path from the existing wetland area. This work will help decrease the overflows from the wetland area across Thorpe Road during heavy runoff volumen periods in Chester Creek. Within City-owned easement. Possible candidate for a FEMA flood grant. Planning level estimate shown.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Chester Creek Wetland Overflow Improvements

Proposed Start: 2015

Fund Amount Fund Yr

SW Utility - Fund 402 $50,000.00 2015

Total $50,000.00

Phase Year EstCost

Design 2015 $50,000.00

Construction 2015 $150,000.00

Total $200,000.00

May 2013

Page 16: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 10 of 29

Description: A number of locations have ongoing drainage problems due to narrow pavement and truck parking areas along existing roadways. Project will retrofit and install treatment to drywells identified in UIC Assessment and Retrofit Plan. Strong candidate for State stormwater grant funding. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: SE Yardly Retrofits (Area SE of Fancher/Broadway)

Proposed Start: 2015

Fund Amount Fund Yr

Ecology Grant 2016

APA - Fund 403 $100,000.00 2015

APA - Fund 403 $150,000.00 2016

Total $250,000.00

Phase Year EstCost

Design 2015 $100,000.00

Construction 2016 $900,000.00

Total $1,000,000.00

May 2013

Page 17: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 11 of 29

Description: Study work would identify and develop projects that would meet upcoming wellhead protection parameters. Projects will help protect water purveyor's wells from possible contamination from existing City Utility stormwater infiltration systems. Generate list of projects, develop possible solution alternatives, and provide cost estimates. Possible Centennial Water grant candidate. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Wellhead Protection Study and Pre-Design

Proposed Start: 2015

Fund Amount Fund Yr

APA - Fund 403 $20,000.00 2015

Total $20,000.00

Phase Year EstCost

Pre-Design 2015 $80,000.00

Total $80,000.00

May 2013

Page 18: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 12 of 29

Description: Improvements of stormwater facilities at various locations throughout the City on an annual basis. These projects were developed and prioritized from Stormwater Action Requests that staff have evaluated. Typically designed and managed by utility staff.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2016 Stormwater Small Works Projects

Proposed Start: 2016

Fund Amount Fund Yr

SW Utility - Fund 402 $20,000.00 2015

SW Utility - Fund 402 $280,000.00 2016

Total $300,000.00

Phase Year EstCost

Design 2015 $20,000.00

Design 2016 $10,000.00

Construction 2016 $270,000.00

Total $300,000.00

May 2013

Page 19: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 13 of 29

Description: Annual program to address stormwater improvements on Arterials associated with the Pavement Preservation Program. Based on pavement preservation project list and the UIC Retrofit Plan.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2016 Retrofits with Pavement Preservation Projects

Proposed Start: 2016

Fund Amount Fund Yr

SW Utility - Fund 402 $40,000.00 2015

SW Utility - Fund 402 $260,000.00 2016

Total $300,000.00

Phase Year EstCost

Design 2015 $40,000.00

Construction 2016 $260,000.00

Total $300,000.00

May 2013

Page 20: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 14 of 29

Description: Determine current capacity of infiltration pit located near Dishman-Mica and 28th Ave, provide routine inspection and maintenance plan. Upgrade facility with suggested recommendations. Grant candidate under Ecology Centennial Water. Planning level estimate shown.

Category: Operations

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: Dishman-Mica Infiltration Facility Plan

Proposed Start: 2016

Fund Amount Fund Yr

Ecology Grant 2016

SW Utility - Fund 402 $10,000.00 2016

Total $10,000.00

Phase Year EstCost

Pre-Design 2016 $40,000.00

Total $40,000.00

May 2013

Page 21: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 15 of 29

Description: Route existing stormwater discharges currently going to Glenrose Drainage to new treatment facilities. Negotiate easements, improve existing facilities, and provide infiltration to ground. Will help the City meet current stormwater permit requirements. Grant candidate. Planning level estimate shown.

Category: Outfall Elimination

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Glenrose Surface Water Diversion

Proposed Start: 2016

Fund Amount Fund Yr

Ecology Grant 2016

APA - Fund 403 $75,000.00 2016

Total $75,000.00

Phase Year EstCost

Design 2016 $60,000.00

Construction 2016 $240,000.00

Total $300,000.00

May 2013

Page 22: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 16 of 29

Description: Project will retrofit and install treatment to drywells identified in UIC Assessment and Retrofit Plan. Strong candidate for State stormwater grant funding. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Montgomery, Argonne to Mansfield Retrofit

Proposed Start: 2016

Fund Amount Fund Yr

Ecology Grant 2017

APA - Fund 403 $115,000.00 2016

APA - Fund 403 $185,000.00 2017

Total $300,000.00

Phase Year EstCost

Design 2016 $115,000.00

Construction 2017 $1,185,000.00

Total $1,300,000.00

May 2013

Page 23: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 17 of 29

Description: Identify major petroleum transport routes, size and install spill protection on existing city drywells on those routes. Good candidate for State stormwater grant. Planning level estimate shown.

Category: Aquifer Protection

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Petroleum Transport Routes, Spill Protection

Proposed Start: 2016

Fund Amount Fund Yr

Ecology Grant 2016

APA - Fund 403 $50,000.00 2016

Total $50,000.00

Phase Year EstCost

Design 2016 $20,000.00

Construction 2016 $180,000.00

Total $200,000.00

May 2013

Page 24: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 18 of 29

Description: Improvements of stormwater facilities at various locations throughout the City on an annual basis. These projects were developed and prioritized from Stormwater Action Requests that staff have evaluated. Typically designed and managed by utility staff.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2017 Stormwater Small Works Projects

Proposed Start: 2017

Fund Amount Fund Yr

SW Utility - Fund 402 $20,000.00 2016

SW Utility - Fund 402 $280,000.00 2017

Total $300,000.00

Phase Year EstCost

Design 2016 $20,000.00

Design 2017 $10,000.00

Construction 2017 $270,000.00

Total $300,000.00

May 2013

Page 25: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 19 of 29

Description: Annual program to address stormwater improvements on Arterials associated with the Pavement Preservation Program. Based on pavement preservation project list and the UIC Retrofit Plan.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2017 Retrofits with Pavement Preservation Projects

Proposed Start: 2017

Fund Amount Fund Yr

SW Utility - Fund 402 $40,000.00 2016

SW Utility - Fund 402 $260,000.00 2017

Total $300,000.00

Phase Year EstCost

Design 2016 $40,000.00

Construction 2017 $260,000.00

Total $300,000.00

May 2013

Page 26: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 20 of 29

Description: A number of locations have ongoing drainage problems due to narrow pavement and truck parking areas along existing roadways. Project will retrofit and install treatment to drywells identified in UIC Assessment and Retrofit Plan. Strong candidate for State stormwater grant funding. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: NW Yardly Retrofits (Area NW of Fancher/Broadway)

Proposed Start: 2017

Fund Amount Fund Yr

Ecology Grant 2018

APA - Fund 403 $100,000.00 2017

APA - Fund 403 $150,000.00 2018

Total $250,000.00

Phase Year EstCost

Design 2017 $100,000.00

Construction 2018 $1,150,000.00

Total $1,250,000.00

May 2013

Page 27: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 21 of 29

Description: Project will retrofit and install treatment to drywells identified in UIC Assessment and Retrofit Plan as needing improvements. Possible use of existing railroad right of way to take stormwater from roadway and treat in new swales to be built with the project. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Dishman-Mica, 16th to Appleway Retrofits

Proposed Start: 2017

Fund Amount Fund Yr

Ecology Grant 2017

APA - Fund 403 $75,000.00 2017

Total $75,000.00

Phase Year EstCost

Design 2017 $50,000.00

Construction 2017 $250,000.00

Total $300,000.00

May 2013

Page 28: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 22 of 29

Description: A number of locations have been ongoing drainage problems due to narrow pavement and truck parking areas along existing roadways. Project will retrofit and install treatment to drywells identified in UIC Assessment and Retrofit Plan as needing improvements. Project will convey and treat stormwater prior to using existing infiltration facilities. Strong candidate for State stormwater grant funding. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: NE Yardly Retrofits (Area East of Fancher & North of I-90)

Proposed Start: 2017

Fund Amount Fund Yr

Ecology Grant 2019

APA - Fund 403 $100,000.00 2017

APA - Fund 403 $150,000.00 2019

Total $250,000.00

Phase Year EstCost

Design 2017 $100,000.00

Construction 2019 $900,000.00

Total $1,000,000.00

May 2013

Page 29: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 23 of 29

Description: Improvements of stormwater facilities at various locations throughout the City on an annual basis. These projects were developed and prioritized from Stormwater Action Requests that staff have evaluated. Typically designed and managed by utility staff.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2018 Stormwater Small Works Projects

Proposed Start: 2018

Fund Amount Fund Yr

SW Utility - Fund 402 $20,000.00 2017

SW Utility - Fund 402 $280,000.00 2018

Total $300,000.00

Phase Year EstCost

Design 2017 $20,000.00

Design 2018 $10,000.00

Construction 2018 $270,000.00

Total $300,000.00

May 2013

Page 30: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 24 of 29

Description: Annual program to address stormwater improvements on Arterials associated with the Pavement Preservation Program. Based on pavement preservation project list and the UIC Retrofit Plan.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2018 Retrofits with Pavement Preservation Projects

Proposed Start: 2018

Fund Amount Fund Yr

SW Utility - Fund 402 $40,000.00 2017

SW Utility - Fund 402 $260,000.00 2018

Total $300,000.00

Phase Year EstCost

Design 2017 $40,000.00

Construction 2018 $260,000.00

Total $300,000.00

May 2013

Page 31: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 25 of 29

Description: Secure conveyance and treatment easement(s), install groundwater drains, install pretreatment and stormwater pipe, connect to existing Stormwater Treatment Ponds. This work would likely coincide with a roadway rebuild project. Subsurface drainage improvements would help preserve the roads longer. Funding could come from Stormwater Utility 402, formation of an RID, or new Neighborhood "Drainwater Account" that would pay back the Stormwater fund over a series of years for the improvements installed. Planning level estimate shown.

Category: Groundwater Conveyence

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: Veracrest Groundwater/Stormwater Conveyance

Proposed Start: 2018

Fund Amount Fund Yr

SW Utility - Fund 402 $350,000.00 2018

Total $350,000.00

Phase Year EstCost

Design 2018 $70,000.00

Construction 2018 $280,000.00

Total $350,000.00

May 2013

Page 32: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 26 of 29

Description: Improvements of stormwater facilities at various locations throughout the City on an annual basis. These projects were developed and prioritized from Stormwater Action Requests that staff have evaluated. Typically designed and managed by utility staff.

Category: Flood Mitigation

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2019 Stormwater Small Works Projects

Proposed Start: 2019

Fund Amount Fund Yr

SW Utility - Fund 402 $20,000.00 2018

SW Utility - Fund 402 $280,000.00 2019

Total $300,000.00

Phase Year EstCost

Design 2018 $20,000.00

Construction 2019 $260,000.00

Total $280,000.00

May 2013

Page 33: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 27 of 29

Description: Annual program to address stormwater improvements on Arterials associated with the Pavement Preservation Program. Based on pavement preservation project list and the UIC Retrofit Plan.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: SW Utility - Fund 402

Grant Candidate

Grant Received

Project: 2019 Retrofits with Pavement Preservation Projects

Proposed Start: 2019

Fund Amount Fund Yr

SW Utility - Fund 402 $40,000.00 2018

SW Utility - Fund 402 $260,000.00 2019

Total $300,000.00

Phase Year EstCost

Design 2018 $40,000.00

Construction 2019 $260,000.00

Total $300,000.00

May 2013

Page 34: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 28 of 29

Description: This project is an identified need from the UIC Assessment and Retrofit Plan. Includes estimated costs for stormwater improvements for grant applications for possible street rebuild or PCC project. Planning level estimate shown.

Category: Aquifer Protection - UIC Retrofit

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Argonne, I-90 to Montgomery Retrofits

Proposed Start: 2019

Fund Amount Fund Yr

Other 2019

APA - Fund 403 $100,000.00 2019

Total $100,000.00

Phase Year EstCost

Design 2019 $80,000.00

Construction 2019 $320,000.00

Total $400,000.00

May 2013

Page 35: 2014-2019 STORMWATER CAPITAL IMPROVEMENT PLAN

Sheet 29 of 29

Description: Secure conveyance and treatment easement(s), install groundwater drains, connect to existing structures in 15th one block away that appear to be working adequately. This work would likely coincide with a roadway rebuild project. Subsurface drainage improvements would help preserve the roads longer. Funding could come form Stormwater Utility, formation of an RID, or though the formation of a new Neighborhood "Drainwater Account" that would pay back the Stormwater fund over a series of years for the improvements installed. Planning level estimate

Category: Groundwater Conveyence

FUNDING ESTIMATED COSTS

Managing Fund: APA - Fund 403

Grant Candidate

Grant Received

Project: Sloan's Addition (15th/Stanley) Groundwater/Stormwater Conveyance

Proposed Start: 2019

Fund Amount Fund Yr

SW Utility - Fund 402 $250,000.00 2019

Total $250,000.00

Phase Year EstCost

Design 2019 $50,000.00

Construction 2019 $200,000.00

Total $250,000.00

May 2013