PARSONS Technical Memorandum To: Sanath Bandara, P.Eng Manager of Engineering Services
From: Todd Bowie, P.Eng
Date: December 9, 2015
Re: East Porpoise Bay Sanitary Sewer Expansion Study
1 Scope
This Technical Memorandum presents the proposed conceptual sanitary servicing plan for the future
East Porpoise Bay (EPB) sanitary sewer servicing area.
The conceptual sanitary servicing plan was established based on the proposed land‐use plan for the
area, existing topography, and population growth assumptions. The conceptual sanitary servicing plan
establishes conceptual infrastructure requirements and minimum pipe sizes based on existing average
ground slopes. Final pipe sizing, infrastructure requirements and associated capital costs will need to be
verified during preliminary and detailed design activities based on actual pipe slopes.
Funding options are also discussed using preliminary capital cost estimates from the conceptual sanitary
servicing plan as a basis. The next steps for finalizing the servicing plan and funding requirements are
also provided.
2 Background
Parsons was retained by the District of Sechelt (District) in 2011 to assess and develop a sanitary
servicing plan for the East Porpoise Bay (EPB) area. Two memorandums were prepared: The first memo
dated November 30, 2011 presented zoning, the design population and high level flow estimates. The
second memo dated December 20, 2011 presented two conceptual servicing arrangements based on
the layout of the existing facilities and future land use. Following submission of these two technical
memorandums, the project was placed on hold pending changes to the District’s sewage treatment
strategy.
With the treatment strategy now established and in the process of being implemented, the District
requested that Parsons update the conceptual servicing strategy for the EPB area and complete the EPB
Sewer Expansion Study.
East Porpoise Bay Sanitary Sewer Expansion Study
Page 2 of 7
3 Conceptual Sewer Servicing Strategy
3.1 Study Area
The proposed EPB sanitary sewer expansion area and existing zoning is displayed in Figure 1. The
existing land use for the expansion area is primarily residential and industrial. Future zoning is displayed
in Figure 2. Proposed changes include increased densities in residential areas, increased industrial
areas, and the addition of commercial areas.
We understand that there is a proposed development (Sechelt Sustainable Community) that is situated
north of the EPB sewer service area. Conveyance of flows from developments north of the EPB area are
not included in this study.
3.2 Design Assumptions
Guidelines, parameters, and assumptions used to establish sanitary sewer flow predictions for the
future zoning are summarized in Table 1. Deviations from Bylaw 430 have been agreed to by the
District.
Table 1: Summary of Design Assumptions
Parameter Value Reference Source / Comments
Residential Areas
Residential Density 8 units/hectare Provided by the District
Population per Household 2.25 people/household Sechelt Sewer Functional Plan
Sanitary per Capita Demand 410 litres/capita/day Bylaw No. 430
Residential Area Summary 7,380 litres/hectare/day
Industrial Areas
Industrial Area per Capita Demands
68 litres/capita/employee 40 employees/hectare =2,720 litres/hectare/day
Sewerage System Standard Practice Manual. (Less than Bylaw 430). Assumes development is not water intensive such as industrial park. No industrial waste.
Commercial Areas
Hotel Demands 100 Rooms (assumed) 366 litres/day/room
Sewerage System Standard Practice Manual
Campground Demands 50 Sites (assumed) 365 litres/day/site
Sewerage System Standard Practice Manual
Other Parameters
Inflow & Infiltration 0.05 litres/hectare/sec Sechelt Sewer Functional Plan (Less than Bylaw 430)
Peaking Factor Harmon Sechelt Sewer Functional Plan (Less than Bylaw 430)
East Porpoise Bay Sanitary Sewer Expansion Study
Page 3 of 7
Parameter Value Reference Source / Comments
Design flow for Sanitary Sewers
Full build‐out of population based on future zoning.
Design Flow for Pump Stations
20 year population projection.
Population Growth 2.5% per year Provided by the District
Starting Population 272 residents Provided by the District
2034 Population 811 residents 2.5 % growth rate. Assumes that the Onni Development (261 residents) is fully populated by 2019.
Industrial / Commercial Growth
Assume 100% developed by 2034
3.3 Conceptual Sewer Servicing Strategy
Two conceptual servicing strategy arrangements were presented in the draft technical memorandum
dated December 20, 2011 for the District’s consideration. The District’s preference was Conceptual
Arrangement #2, with some modifications to adapt to the revised sewage treatment strategy. The
revised concept plan for the EPB sanitary sewer servicing strategy is presented in Figure 3 and described
below.
The EPB sanitary sewer area was subdivided into three primary catchments with a separate pump
station required for each catchment.
One pump station (PS#1) will be required at the east end of Marmot Road to service existing residences
north of Heron Road. This low‐head pump station would lift the sanitary sewage to a manhole at the
intersection of Marmot Road and Heron Road. It is anticipated that construction of this section of the
network can be deferred until requested by the local residents. These properties currently discharge to
private disposal fields.
A second pump station (PS#2) will be required at the foot of Yew Road to service areas north of Allen
Road. A gravity main would be installed along the waterfront from Allen Road to Burnett Road. This
pump station would direct flows through a new forcemain and tie‐in to the existing 350mm HDPE
forcemain at the intersection of Dusty Road and Sechelt Inlet Road. This existing forcemain would
convey flow to the Ebbtide Wastewater Treatment Plant.
A third pump station (PS#3) was constructed as part of the Onni Development. We understand that
PS#3 has the capacity to service the entire EPB collection area. Given the available capacity in the pump
station, the District could consider directing PS#2 flows to PS#3 prior to pumping to the Ebbtide
East Porpoise Bay Sanitary Sewer Expansion Study
Page 4 of 7
Wastewater Treatment Plant; however, it is anticipated that the operating costs would be higher with
that arrangement.
Based on Conceptual Arrangement #2, most of the oceanfront properties wanting to connect to the
District’s collection system within the EPB servicing area will need to pump to the proposed gravity
sewers to the east of their properties.
3.4 Design Flow Predictions
Sanitary sewer flows were calculated for two scenarios: 1) the 20‐year development horizon (2034); and
2) the full build‐out scenario. Population and flow predictions for the three pump‐station catchment
areas are summarized in Table 2. Design flow predictions are based on the population growth
assumptions for the catchment areas noted in Table 1. Calculations are included in Appendix A.
Table 2: Sanitary Design Flow Predictions
Parameter 20‐year Horizon (2034) Full Build‐Out
Pump Station 1
Residential Population 82 residents 82 residents
Peak Wet Weather Flow 161 m3/day 161 m3/day
Pump Station 2
Residential Population 338 residents 1247 residents
Peak Wet Weather Flow 925 m3/day 2268 m3/day
Pump Station 3
Residential Population 474 residents 480 residents
Peak Wet Weather Flow 1523 m3/day 1533 m3/day
East Porpoise Bay Service Area
Residential Population 811 residents 1727 residents
Peak Wet Weather Flow 2370 m3/day 3623 m3/day
4 Sanitary Servicing Capital Funding Mechanism
The District identified implementation of a district‐wide development cost charge (DCC) as the preferred
method of funding the EPB sanitary sewer servicing plan. The capital costs attributable to growth in the
EPB area were incorporated into the district‐wide capital costs established in the DCC Background
Report. Based on this, revised preliminary district‐wide DCC rates are identified which includes the EPB
area.
East Porpoise Bay Sanitary Sewer Expansion Study
Page 5 of 7
4.1 East Porpoise Bay DCC Projects
Preliminary capital cost estimates for the components of the preferred conceptual sanitary servicing
plan have been produced and the costs attributable to growth are summarized below. The District
anticipates 25% of the project funding for future capital works in the East Porpoise Bay area to come
from grant funding sources. Detailed cost estimates are attached in Appendix A.
Project Capital Costs Attributable to
Growth
$ 4,674,000
Less Assumed Grant Funding (25%) $ (1,168,000)
Less Municipal Assist Factor (1%) $ (47,000)
Preliminary estimate of capital costs to be
recovered through DCC’s
$ 3,459,000
4.2 Updated Sanitary Sewer DCC Rates
The DCC Background Report established growth projections for the District and identified DCC projects
within the existing Sechelt sewer service area. Based on this information, preliminary DCC rates for the
District were established.
Capital costs for servicing the EPB area were not included in the previous analysis and establishment of
DCC rates. However, it is assumed that the growth projections established in the DCC Background
Report did include growth that may occur in the EPB area.
Updated sanitary sewer DCC rates accounting for the EPB DCC projects are summarized in Table 3.
Table 3: District‐Wide DCC Rate per Equivalent Unit Calculations (including EPB)
Description Value
# of Equivalent Units (Draft DCC Background Report) 1,603
Net DCC Costs (Draft DCC Background Report) $ 8,487,000
Net DCC Costs (East Porpoise Bay Area) $ 3,459,000
Total Net DCC Costs $ 11,946,000
DCC per Equivalent Unit $ 7,452
The changes to the originally proposed DCC rates, established in the DCC Background Report, as a result
of adding the EPB area are provided in Table 4. The original proposed DCC rates from the DCC
Background Report are included for comparison.
East Porpoise Bay Sanitary Sewer Expansion Study
Page 6 of 7
Table 4: District‐Wide DCC Rate Comparison
Description Updated DCC Rate
including EPB Area
Original DCC Rate from
Background Report
Single Family /Unit $ 7,452 $ 5,294
Townhouse /Unit $ 6,185 $ 4,394
Apartment /Unit $ 4,993 $ 3,547
Congregate Care/ Bed $ 3,130 $ 2,223
Commercial /m2 $ 14.90 $ 10.59
Industrial /m2 $ 14.90 $ 10.59
Institutional /m2 $ 14.90 $ 10.59
5 Staging and Funding
Sanitary servicing of the EBP area is anticipated to require significant advanced funding from the District.
This area is essentially a green‐field and will require construction of pump stations, forcemains, and
sanitary trunk sewers to service this area. It is likely that this infrastructure will need to be constructed
prior to collection of sufficient DCC’s to fund the works.
The project staging and available funds will largely be driven by development. Development and
construction of the sanitary infrastructure would preferably occur from south to north. PS #3 was
constructed as part of the ONNI development. This allows for relatively cost effective expansion of the
sanitary sewer network in the PS#3 catchment area. However, once development starts to occur in the
PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed.
In addition, based on the preferred Conceptual Arrangement, the PS#1 catchment area cannot be
serviced until the infrastructure to service the PS#2 catchment area has been constructed. If
development in the EPB area proceeds from north to south, a significant investment in infrastructure
will be required, potentially in advance of collecting adequate funds through DCC’s.
Sources of advanced funding that the District could consider, to fund capital projects within the EPB area
include:
Applicable DCC reserves;
Borrowing;
General taxation; and,
Senior Government grants.
These sources will need to be considered at the time infrastructure funding is required.
East Porpoise Bay Sanitary Sewer Expansion Study
6 Conclusions and Recommendations The conceptual sanitary servicing plan was established based on the proposed land-use plan for the
area, existing topography, and population growth assumptions. The conceptual sanitary servicing plan
establishes conceptual infrastructure requirements and minimum pipe sizes based on existing average
ground slopes.
If the District decides to proceed with sanitary servicing to East Porpoise Bay, a preliminary design of the
complete servicing strategy should be completed to verify infrastructure sizing and inverts and to
confirm capital costs. Detailed designs can then proceed on a segmented basis as required to support
development.
A preliminary capital cost estimate was developed for the conceptual sanitary servicing plan. Costs
attributable to growth in the EPB area were added to the capital costs attributable to growth for the
remainder of Sechelt as established in the District of Sechelt DCC Background Report. This combined
capital cost was used as the basis to identify the preliminary district-wide DCC rates that include
servicing of the EPB area.
The addition of the costs attributable to growth in the EPB area to the district-wide DCC's result in an
approximate increase to the sanitary DCC's of 40 percent.
If the District intends to proceed with funding the EPB sanitary sewer expansion under DCC's, the DCC
Background Report and Draft DCC Bylaw should be updated to including the capital costs attributable to
development in EPB area to establish the final sanitary sewer DCC rate.
7 Closure
The conclusions and recommendations presented in this report are based on the reference information
provided by the District and the assumptions outlined above. We trust the above conceptual servicing
strategy meets the current requirements of the District and establishes a baseline for future studies.
Sincerely,
Enclosures: Figures 1 to 3
Appendix A: Flow Calculations
Appendix B: Cost Estimates
Page 7 of 7
~ J, c:
~ i c: ,__
"' ~ ;;; ~ € /
~ Q_ X w ,__ z w :;' C' 4 0
! >-;:; w w
~ :;' ,__ w ~ ,__ w I 0 w w m ~
" € /
Legend:
0 Industrial 1
~ Industrial 3
0 Industrial 6
0 Industrial 7
~ Marine 1
~ Park, Recreation & Assembly 1
~ Residential 1
~ Residential 3
~ Residential 4
0 100 300m
1 6500
PARSONS
2000 PVC SANITARY SEWER (FOR FUTURE CONNECTION)
RR-2
R-3
RR-2
DUSTY ROAD WASTEWATER TREATMENT PLANT
Sechelt DISTRICT OF SECHEL T Naturally Spirited
East Porpoise Bay Sewer Expansion Study
Existing Land Use EB3759 November 2014 Figure 1
0~----------------------------------------------------------------------------------------------------~
0
i': u J, c:
~ i c: ,__
"' ~ ;;; ~ € /
~ Q_ X w ,__ z w :;' C' 4 0
! >-;:; w w
~ :;' ,__ w ~ ,__ w I 0 w w m ~
" € /
Legend:
~ Commercial 2
[§] Commercial 3
0 Industrial 1
0 Industrial 3
0 Industrial 6
~ Marine 1
~ Multifamily/Mixed Residenti
B Public Assembly
0 Low Density Residential
~ Rural Residential
East Pporpoise Bay -··- Sanitary Service Area
0 100 300m
1 6500
PARSONS
R
R
ALLEN
1-3
Sechelt DISTRICT OF SECHEL T Naturally Spirited
East Porpoise Bay Sewer Expansion Study
Proposed Land Use EB3759 November 2014 Figure 2
0~----------------------------------------------------------------------------------------------~
0
i': ri J, c:
~ i c: ,__
"' ~ ;;; ~ € /
~ Q_ X w ,__ z w :;' C' 4 0
! >-;:; w w
~ :;' ,__ w ~ ,__ w I 0 w w m ~
" € /
Legend:
------------- Existing Gravity Sewer
- - - - Existing Forcemain
Proposed Gravity Sewer
- - Proposed Forcemain
@ Proposed Pump Station
- - - - - - - Proposed Road Right-of Way
- • • - Pump Station 1 Catchment Area
- • • - Pump Station 2 Catchment Area
- • • - Pump Station 3 Catchment Area
@ Sanitary Node Number
0 100 300m
1 6500
PARSONS
Sechelt DISTRICT OF SECHEL T Naturally Spirited
East Porpoise Bay Sewer Expansion Study
Proposed Sanitary Sewer Network EB3759 November 2014 Figure 3
0~--------------------------------------------------------------------------------------------------------------------~
SANITARY SEWER DESIGN SHEET Sechelt District - East Porpoise Bay Sewer Expansion Study
Formulas
Q(d)=Q(p)+Q(c)+Q(l) (L/s) Average Design Flow Rates Peaking Factors Capacity
Q(p)=PQM/86.4 (L/s) Q(d)=Peak Design Flow Residential Harmon Formula
Q(p)=Peak Population Flow (L/s) Residential 410 lpcd Commercial/Industrial Harmon Formula Hotel 100 units
Q(c)= commercial flow Commercial Hospitality 366 l/day/unit Equivalent Pop. Campsite 50 sites
Q= average daily flow per capita (L) Recreational 365 l/day/site Residential Densities
Q(I)=peak extraneous flow Industrial 40 employees/hectarre type density
68 l/employee/day
Q(I)=IA (L/s) 2720 l/ha/day Unit 2.25 people/lot
A=area in ha Extraneous Residential Density 8.00 units/ha
I=unit of peak extraneous flow (L/s/ha) Inflow and infiltration 0.05 l/s/ha
M=1+(14/4+P^0.5) (Harmon formula)
P=population in thousands n= 0.013
M=peak factor
DESIGN FLOW
Street From To AREA LOTS LOTS PPL ADWF AREA AREA ADWF AREA AREA ADWF AREA AREA ADWF ADWF POP EQ. PEAK PDWF AREA AREA I & I PWWF Type of Diameter Slope Length Capacity Velocity Capacity Velocity
num accum accum accum. accum. accum. FACTOR accum. Pipe mm >0.6m/sha ea ea ea L/s ha ha L/s ha ha L/s ha ha L/s L/s ea M L/s ha ha L/s L/s nom. act. % m L/s m/s
Marmot Road #1 S0 S1 0.6 5 5 11 0.05 0.05 10.80 4.41 0.23 0.60 0.60 0.03 0.26 PVC 200 203 7.00 77 90.3 2.79 OK OK
S2 S1 1.2 10 10 22 0.10 0.10 21.60 4.38 0.45 1.20 1.20 0.06 0.51 PVC 200 203 12.00 36 118.2 3.65 OK OK
S1 S3 (PS #1) 2.41 22 36 82 0.39 0.39 81.90 4.27 1.66 2.41 4.21 0.21 1.87 PVC 200 203 2.30 217 51.8 1.60 OK OK
Marmot Rd #2 S4 S5 4.58 37 73 164 0.78 0.78 164.34 4.18 3.26 4.58 8.79 0.44 3.70 PVC 200 203 2.90 394 58.1 1.80 OK OK
New Rd S6 S5 2.08 17 17 37 0.18 0.18 37.44 4.34 0.77 2.08 2.08 0.10 0.87 PVC 200 203 3.00 103 59.1 1.83 OK OK
Shoreline #1 S5 S7 0 0 90 202 0.96 0.96 201.78 4.15 3.97 0.00 10.87 0.54 4.51 PVC 200 203 3.80 51 66.5 2.06 OK OKS7 PS#2 2.38 19 109 245 1.16 1.16 244.62 4.11 4.78 2.38 13.25 0.66 5.44 PVC 200 203 0.80 400 30.5 0.94 OK OK
Burnett Rd S8 S9 28 224 224 504 2.39 0.00 0.00 0.00 2.39 504.00 3.97 9.50 28.00 28.00 1.40 10.90 PVC 200 203 8.30 360 98.3 3.04 OK OK
Sechelt Inlet Rd S9 S11 0 0 224 504 2.39 0.00 0.00 0.00 2.39 504.00 3.97 9.50 0.00 28.00 1.40 10.90 PVC 200 203 1.40 400 40.4 1.25 OK OK
Yew Rd S10 S11 15.64 125 125 282 1.34 4.42 4.42 0.14 1.48 310.84 4.07 6.01 20.06 20.06 1.00 7.01 PVC 200 203 1.30 512 38.9 1.20 OK OK
Sechelt Inlet Rd S12 S11 2.71 22 22 49 0.23 0.00 0.00 0.00 0.23 48.78 4.32 1.00 2.71 2.71 0.14 1.13 PVC 200 203 4.10 379 69.1 2.14 OK OK
Yew Rd S11 PS#2 3.73 30 401 901 4.28 0.00 4.42 0.14 4.42 930.76 3.82 16.87 3.73 54.50 2.73 19.60 PVC 200 203 3.30 110 62.0 1.92 OK OK
New Rd S13 S14 1.38 11 11 25 0.12 0.12 24.84 4.37 0.51 1.38 1.38 0.07 0.58 PVC 200 203 5.20 299 77.8 2.40 OK OK
Shoreline #2 S14 PS#2 4.23 34 45 101 0.48 0.48 100.98 4.24 2.03 4.23 4.23 0.21 2.24 PVC 200 203 1.50 438 41.8 1.29 OK OK
PS#2 Combined Flows All PS#2 68.94 554 1247 5.92 4.42 4.42 0.14 6.06 1276.36 3.73 22.59 73.36 73.36 3.67 26.25 PVC 200 203 2.20 127 50.6 1.56 OK OK
Allen Rd S15 S16 9.39 75 75 169 0.80 1.71 1.71 0.05 0.86 180.36 4.16 3.56 11.10 11.10 0.56 4.12 PVC 200 203 6.10 534 84.3 2.60 OK OK
Sechelt Inlet Rd S16 S17 2.78 22 97 219 1.04 0.00 1.71 0.05 1.09 230.40 4.12 4.51 2.78 13.88 0.69 5.20 PVC 200 203 2.20 127 50.6 1.56 OK OK
Dusty Rd S18 S19 0 0 0 0 0.00 4.05 4.05 0.14 14.55 14.55 0.46 0.60 126.20 4.21 2.52 18.60 18.60 0.93 3.45 PVC 200 203 5.50 380 80.0 2.47 OK OK
Sechelt Inlet Rd S17 S19 0 0 97 219 1.04 2.89 2.89 0.42 2.03 6.08 0.21 7.30 23.56 0.74 2.42 509.14 3.97 9.59 12.22 44.70 2.24 11.83 PVC 200 203 2.50 392 54.0 1.67 OK OK
S20 S19 0 0 0 0 0.00 6.80 6.80 0.21 0.21 45.11 4.32 0.93 6.80 6.80 0.34 1.27 PVC 200 203 1.70 316 44.5 1.37 OK OK
S19 PS#3 0 0 97 219 1.04 0.00 2.89 0.42 0.00 6.08 0.21 0.00 30.36 0.96 2.63 554.25 3.95 10.39 0.00 51.50 2.58 12.97 PVC 200 203 3.50 143 63.8 1.97 OK OK
Onni PS#3 5 116 116 261 1.24 1.24 261.00 4.10 5.08 5.00 5.00 0.25 5.33 PVC 200 203 1.70 316 44.5 1.37 OK OK
PS#3 Combined Flows All PS#2 17.17 0 213 480 2.28 2.89 2.89 0.42 6.08 6.08 0.21 30.36 30.36 0.96 3.87 815.25 3.86 14.92 56.50 56.50 2.83 17.74 PVC 200 203 2.20 127 50.6 1.56 OK OK
SUMMARIES
PS#1 PS#2 4.21 36 82 0.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.39 81.90 4.27 1.66 2.41 4.21 0.21 1.87
PS#2 FM 68.94 0 554 1247 5.92 0.00 0.00 0.00 0.00 0.00 0.00 4.42 4.42 0.14 6.06 1276.36 3.73 22.59 73.36 73.36 3.67 26.25
PS#3 FM 17.17 0 213 480 2.28 2.89 2.89 0.42 6.08 6.08 0.21 30.36 30.36 0.96 3.87 815.25 3.86 14.92 56.50 56.50 2.83 17.74
All WWTP 86.11 0 767.60 1727 8.20 2.89 2.89 0.42 6.08 6.08 0.21 34.78 34.78 1.09 9.93 2091.62 3.57 35.44 129.86 129.86 6.49 41.93
3623 cu.m
REMARKSCOMMERCIAL HOSPITALITY FLOWRESIDENTIAL FLOW RECREATIONAL FLOW INDUSTRIAL FLOW EXTRANEOUS FLOWS SEWER DATACOMBINED FLOWS
EAST PORPOISE BAY SANITARY SEWER EXPANSION STUDY 19-Nov-14
PROPOSED SANITARY NETWORK ESTIMATED COSTS
Street Location InfrastructureLength
(m)Ground Surface
Construction Cost
Contingency (30%)
Engineering (12.5%)
Project CostDCC
PortionDCC Cost
Grant Funding
Assist Factor
Net DCC Recovery
NORTH PART OF STUDY AREA (PUMP STATION #1 CATCHMENT)
GRAVITY SEWERSMarmot Road Heron to Pump Station #1 Sanitary Sewer 330 Paved 165,000$ 49,500$ 20,625$ 235,125$ 28% 65,313$ 25% 1% 48,331$
Subtotal (Gravity Sewers) 235,125$ 65,313$ 48,331$
PUMP STATION #1 AND FORCEMAINMarmot Road PS#1 to Heron Forcemain 330 Paved 115,500$ 34,650$ 14,438$ 164,588$ 28% 45,719$ 25% 1% 33,832$
Marmot Road West end Pump Station #1 - - 300,000$ 90,000$ 37,500$ 427,500$ 28% 118,750$ 25% 1% 87,875$
Subtotal (Pump Station #1 and Forcemain) 592,088$ 164,469$ 121,707$
TOTAL (PUMP STATION #1 CATCHMENT AREA) 170,038$
CENTRAL PART OF STUDY AREA (PUMP STATION #2 CATCHMENT)
NORTH SUBCATCHMENT GRAVITY SEWERSMarmot Rd Heron to Burnett Gravity Sewer 395 Paved 197,500$ 59,250$ 24,688$ 281,438$ 100% 281,438$ 25% 1% 208,264$
Burnett Road Sechelt Inlet Rd to Shoreline Gravity Sewer 155 Paved 77,500$ 23,250$ 9,688$ 110,438$ 100% 110,438$ 25% 1% 81,724$
Shoreline Burnett Road to PS#2 Gravity Sewer 400 Natural 150,000$ 45,000$ 18,750$ 213,750$ 100% 213,750$ 25% 1% 158,175$
Subtotal (Gravity Sewers) 605,625$ 605,625$ 448,163$
CENTRAL SUBCATCHMENT GRAVITY SEWERSBurnett Rd East End to Sechelt Inlet Rd Gravity Sewer 360 Gravel 153,000$ 45,900$ 19,125$ 218,025$ 100% 218,025$ 25% 1% 161,339$
Sechelt Inlet Rd Burnett to Yew Gravity Sewer 400 Paved 200,000$ 60,000$ 25,000$ 285,000$ 100% 285,000$ 25% 1% 210,900$
Yew Rd East End to Sechelt Inet Road Gravity Sewer 510 Paved 255,000$ 76,500$ 31,875$ 363,375$ 100% 363,375$ 25% 1% 268,898$
Sechelt Inlet Rd Allen to Yew Gravity Sewer 380 Paved 190,000$ 57,000$ 23,750$ 270,750$ 100% 270,750$ 25% 1% 200,355$
Yew Rd Sechelt Inlet Rd to PS#2 Gravity Sewer 110 Paved 55,000$ 16,500$ 6,875$ 78,375$ 100% 78,375$ 25% 1% 57,998$
Subtotal (Gravity Sewers) 1,215,525$ 1,215,525$ 899,489$
SOUTH SUBCATCHMENT GRAVITY SEWERSAllen Rd Sechelt Inlet Rd to Shoreline Gravity Sewer 181 Paved 90,500$ 27,150$ 11,313$ 128,963$ 100% 128,963$ 25% 1% 95,432$
Shoreline Allen Road to PS#2 Gravity Sewer 438 Natural 164,250$ 49,275$ 20,531$ 234,056$ 100% 234,056$ 25% 1% 173,202$
Subtotal (Gravity Sewers) 363,019$ 363,019$ 268,634$
PUMP STATION #2 AND FORCEMAINSYew Rd PS#2 to Dusty/Sechelt Inlet Forcemain 800 Paved 280,000$ 84,000$ 35,000$ 399,000$ 100% 399,000$ 25% 1% 295,260$
Yew Rd At shoreline Pump Station #2 - - 400,000$ 120,000$ 50,000$ 570,000$ 100% 570,000$ 25% 1% 421,800$
Subtotal (Pump Station #2 and Forcemain) 969,000$ 969,000$ 717,060$
TOTAL(PUMP STATION #2 CATCHMENT AREA) 2,333,345$
SOUTH PART OF STUDY AREA (PUMP STATION #3 CATCHMENT)
GRAVITY SEWERSAllen Rd East End to Sechelt Inlet Gravity Sewer 534 Gravel 226,950$ 68,085$ 28,369$ 323,404$ 100% 323,404$ 25% 1% 239,319$
Sechelt Inlet Rd Allen to Dusty Gravity Sewer 127 Paved 63,500$ 19,050$ 7,938$ 90,488$ 100% 90,488$ 25% 1% 66,961$
Dusty Rd East End to Sechelt Inlet Gravity Sewer 380 Paved 190,000$ 57,000$ 23,750$ 270,750$ 100% 270,750$ 25% 1% 200,355$
Sechelt Inlet Rd Dusty to PS#3 access road Gravity Sewer 392 Paved 196,000$ 58,800$ 24,500$ 279,300$ 100% 279,300$ 25% 1% 206,682$
Sechelt Inlet Rd Delta to PS#3 access road Gravity Sewer 316 Paved 158,000$ 47,400$ 19,750$ 225,150$ 100% 225,150$ 25% 1% 166,611$
PS#3 Access Rd Sechelt Inlet to PS#3 Gravity Sewer 143 Paved 71,500$ 21,450$ 8,938$ 101,888$ 100% 101,888$ 25% 1% 75,397$
Subtotal (Gravity Sewers) 1,290,979$ 1,290,979$ 955,324$
Pump Station #3 and ForcemainPS access road PS#2 to Dusty/Sechelt Inlet Forcemain 115 Paved 40,250$ 12,075$ 5,031$ 57,356$ 0% -$ -$
PS access road At shoreline Pump Station #3 - - 450,000$ 135,000$ 56,250$ 641,250$ 0% -$ -$
Subtotal (Pump Station #3 and Forcemain) 698,606$ -$ -$
TOTAL (PUMP STATION #3 CATCHMENT AREA) 955,324$
TOTAL EAST PORPOISE BAY AREA
5,969,966$ 4,673,929$ 3,458,707$
Estimated Unit CostsUnit Cost Unit Notes
Gravity Sewers Under Paved Surface 500$ per metre 1 - Paved ground surface: Pipes in paved areas are assumed to be installed per MMCD G4 - Paved with 100mm asphaltGravity Sewers Under Gravel Surface 425$ per metre 2 - Gravel ground surface: Pipes under gravel roads are assumed to be installed per MMCD G4 - Paved, but without asphalt.Gravity Sewers Under Natural Surface 375$ per metre 3 - Natural ground surface: Pipe in natural areas are assumed to be installed per MMCD G4 - Boulevards and EasementsForcemains Under Paved Surface 350$ per metre