PARSONS Technical Memorandum To: Sanath Bandara, P.Eng Manager of Engineering Services From: Todd Bowie, P.Eng Date: December 9, 2015 Re: East Porpoise Bay Sanitary Sewer Expansion Study 1 Scope This Technical Memorandum presents the proposed conceptual sanitary servicing plan for the future East Porpoise Bay (EPB) sanitary sewer servicing area. The conceptual sanitary servicing plan was established based on the proposed landuse plan for the area, existing topography, and population growth assumptions. The conceptual sanitary servicing plan establishes conceptual infrastructure requirements and minimum pipe sizes based on existing average ground slopes. Final pipe sizing, infrastructure requirements and associated capital costs will need to be verified during preliminary and detailed design activities based on actual pipe slopes. Funding options are also discussed using preliminary capital cost estimates from the conceptual sanitary servicing plan as a basis. The next steps for finalizing the servicing plan and funding requirements are also provided. 2 Background Parsons was retained by the District of Sechelt (District) in 2011 to assess and develop a sanitary servicing plan for the East Porpoise Bay (EPB) area. Two memorandums were prepared: The first memo dated November 30, 2011 presented zoning, the design population and high level flow estimates. The second memo dated December 20, 2011 presented two conceptual servicing arrangements based on the layout of the existing facilities and future land use. Following submission of these two technical memorandums, the project was placed on hold pending changes to the District’s sewage treatment strategy. With the treatment strategy now established and in the process of being implemented, the District requested that Parsons update the conceptual servicing strategy for the EPB area and complete the EPB Sewer Expansion Study.

Upload: others

Post on 05-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

PARSONS Technical Memorandum To:  Sanath Bandara, P.Eng   Manager of Engineering Services 

From:  Todd Bowie, P.Eng 

Date:  December 9, 2015 

Re:  East Porpoise Bay Sanitary Sewer Expansion Study 

1 Scope 

This Technical Memorandum presents  the proposed  conceptual  sanitary  servicing plan  for  the  future 

East Porpoise Bay (EPB) sanitary sewer servicing area.   

The  conceptual  sanitary  servicing plan was  established based on  the proposed  land‐use plan  for  the 

area, existing topography, and population growth assumptions.   The conceptual sanitary servicing plan 

establishes conceptual  infrastructure requirements and minimum pipe sizes based on existing average 

ground slopes.  Final pipe sizing, infrastructure requirements and associated capital costs will need to be 

verified during preliminary and detailed design activities based on actual pipe slopes. 

Funding options are also discussed using preliminary capital cost estimates from the conceptual sanitary 

servicing plan as a basis.   The next steps for finalizing the servicing plan and funding requirements are 

also provided.  

2 Background 

Parsons  was  retained  by  the  District  of  Sechelt  (District)  in  2011  to  assess  and  develop  a  sanitary 

servicing plan for the East Porpoise Bay (EPB) area.  Two memorandums were prepared: The first memo 

dated November 30, 2011 presented zoning, the design population and high  level flow estimates. The 

second memo dated December 20, 2011 presented  two conceptual  servicing arrangements based on 

the  layout of  the existing  facilities and  future  land use.   Following  submission of  these  two  technical 

memorandums,  the  project was  placed  on  hold  pending  changes  to  the District’s  sewage  treatment 

strategy.  

With  the  treatment  strategy  now  established  and  in  the  process  of  being  implemented,  the District 

requested that Parsons update the conceptual servicing strategy for the EPB area and complete the EPB 

Sewer Expansion Study.   

Page 2: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

East Porpoise Bay Sanitary Sewer Expansion Study 

Page 2 of 7 

 

3 Conceptual Sewer Servicing Strategy 

3.1 Study Area 

The  proposed  EPB  sanitary  sewer  expansion  area  and  existing  zoning  is  displayed  in  Figure  1.    The 

existing land use for the expansion area is primarily residential and industrial.  Future zoning is displayed 

in  Figure  2.    Proposed  changes  include  increased  densities  in  residential  areas,  increased  industrial 

areas, and the addition of commercial areas. 

We understand that there is a proposed development (Sechelt Sustainable Community) that is situated 

north of the EPB sewer service area.  Conveyance of flows from developments north of the EPB area are 

not included in this study.   

3.2 Design Assumptions 

Guidelines,  parameters,  and  assumptions  used  to  establish  sanitary  sewer  flow  predictions  for  the 

future  zoning  are  summarized  in  Table  1.     Deviations  from Bylaw  430  have  been  agreed  to  by  the 

District. 

Table 1:   Summary of Design Assumptions 

Parameter  Value  Reference Source / Comments 

Residential Areas     

Residential Density  8 units/hectare   Provided by the District  

Population per Household  2.25 people/household  Sechelt Sewer Functional Plan 

Sanitary per Capita Demand  410 litres/capita/day  Bylaw No. 430 

Residential Area Summary  7,380 litres/hectare/day   

Industrial Areas     

Industrial Area per Capita Demands 

68 litres/capita/employee 40 employees/hectare =2,720 litres/hectare/day 

Sewerage System Standard Practice Manual. (Less than Bylaw 430).  Assumes development is not water intensive such as industrial park.  No industrial waste. 

Commercial Areas     

Hotel Demands  100 Rooms (assumed) 366 litres/day/room 

Sewerage System Standard Practice Manual 

Campground Demands  50 Sites (assumed) 365 litres/day/site 

Sewerage System Standard Practice Manual 

Other Parameters     

Inflow & Infiltration  0.05 litres/hectare/sec  Sechelt Sewer Functional Plan  (Less than Bylaw 430) 

Peaking Factor  Harmon  Sechelt Sewer Functional Plan (Less than Bylaw 430) 

Page 3: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

East Porpoise Bay Sanitary Sewer Expansion Study 

Page 3 of 7 

 

Parameter  Value  Reference Source / Comments 

Design flow for Sanitary Sewers 

Full build‐out of population based on future zoning. 

 

Design Flow for Pump Stations 

20 year population projection. 

 

Population Growth  2.5% per year   Provided by the District 

Starting Population  272 residents  Provided by the District 

2034 Population  811 residents  2.5 % growth rate.  Assumes that the Onni Development (261 residents) is fully populated by 2019. 

Industrial / Commercial Growth 

Assume 100% developed by 2034 

 

 

3.3 Conceptual Sewer Servicing Strategy 

Two  conceptual  servicing  strategy arrangements were presented  in  the draft  technical memorandum 

dated  December  20,  2011  for  the  District’s  consideration.  The  District’s  preference was  Conceptual 

Arrangement  #2, with  some modifications  to  adapt  to  the  revised  sewage  treatment  strategy.    The 

revised concept plan for the EPB sanitary sewer servicing strategy is presented in Figure 3 and described 

below. 

The  EPB  sanitary  sewer  area was  subdivided  into  three  primary  catchments with  a  separate  pump 

station required for each catchment. 

One pump station (PS#1) will be required at the east end of Marmot Road to service existing residences 

north of Heron Road.   This  low‐head pump station would  lift the sanitary sewage to a manhole at the 

intersection of Marmot Road and Heron Road.  It  is anticipated that construction of this section of the 

network can be deferred until requested by the local residents.  These properties currently discharge to 

private disposal fields. 

A second pump station (PS#2) will be required at the foot of Yew Road to service areas north of Allen 

Road. A gravity main would be  installed along the waterfront  from Allen Road to Burnett Road.     This 

pump  station would  direct  flows  through  a  new  forcemain  and  tie‐in  to  the  existing  350mm  HDPE 

forcemain  at  the  intersection  of Dusty  Road  and  Sechelt  Inlet  Road.    This  existing  forcemain would 

convey flow to the Ebbtide Wastewater Treatment Plant.   

A  third pump  station  (PS#3) was constructed as part of  the Onni Development.   We understand  that 

PS#3 has the capacity to service the entire EPB collection area.  Given the available capacity in the pump 

station,  the  District  could  consider  directing  PS#2  flows  to  PS#3  prior  to  pumping  to  the  Ebbtide 

Page 4: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

East Porpoise Bay Sanitary Sewer Expansion Study 

Page 4 of 7 

 

Wastewater Treatment Plant; however,  it  is anticipated that the operating costs would be higher with 

that arrangement. 

Based on Conceptual Arrangement  #2, most of  the oceanfront properties wanting  to  connect  to  the 

District’s  collection  system within  the  EPB  servicing  area will  need  to  pump  to  the  proposed  gravity 

sewers to the east of their properties. 

3.4 Design Flow Predictions 

Sanitary sewer flows were calculated for two scenarios: 1) the 20‐year development horizon (2034); and 

2)  the  full build‐out  scenario.   Population and  flow predictions  for  the  three pump‐station catchment 

areas  are  summarized  in  Table  2.    Design  flow  predictions  are  based  on  the  population  growth 

assumptions for the catchment areas noted in Table 1.  Calculations are included in Appendix A. 

Table 2:  Sanitary Design Flow Predictions 

Parameter  20‐year Horizon (2034)  Full Build‐Out 

Pump Station 1     

Residential Population  82 residents  82 residents 

Peak Wet Weather Flow  161 m3/day  161 m3/day 

Pump Station 2     

Residential Population  338 residents  1247 residents 

Peak Wet Weather Flow  925 m3/day  2268 m3/day 

Pump Station 3     

Residential Population  474 residents  480 residents 

Peak Wet Weather Flow  1523 m3/day  1533 m3/day 

East Porpoise Bay Service Area     

Residential Population  811 residents  1727 residents 

Peak Wet Weather Flow  2370 m3/day  3623 m3/day 

4 Sanitary Servicing Capital Funding Mechanism 

The District identified implementation of a district‐wide development cost charge (DCC) as the preferred 

method of funding the EPB sanitary sewer servicing plan.  The capital costs attributable to growth in the 

EPB  area  were  incorporated  into  the  district‐wide  capital  costs  established  in  the  DCC  Background 

Report.  Based on this, revised preliminary district‐wide DCC rates are identified which includes the EPB 

area.   

Page 5: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

East Porpoise Bay Sanitary Sewer Expansion Study 

Page 5 of 7 

 

4.1 East Porpoise Bay DCC Projects 

Preliminary  capital  cost  estimates  for  the  components of  the preferred  conceptual  sanitary  servicing 

plan  have  been  produced  and  the  costs  attributable  to  growth  are  summarized  below.    The District 

anticipates 25% of  the project  funding  for  future capital works  in  the East Porpoise Bay area  to come 

from grant funding sources.  Detailed cost estimates are attached in Appendix A. 

Project  Capital  Costs  Attributable  to 

Growth   

$ 4,674,000 

Less Assumed Grant Funding (25%)  $ (1,168,000) 

Less Municipal Assist Factor (1%)  $ (47,000) 

Preliminary estimate of capital costs to be 

recovered through DCC’s  

$ 3,459,000 

4.2 Updated Sanitary Sewer DCC Rates 

The DCC Background Report established growth projections for the District and  identified DCC projects 

within the existing Sechelt sewer service area.  Based on this information, preliminary DCC rates for the 

District were established.   

Capital costs for servicing the EPB area were not included in the previous analysis and establishment of 

DCC  rates.   However,  it  is  assumed  that  the  growth  projections  established  in  the DCC  Background 

Report did include growth that may occur in the EPB area.   

Updated sanitary sewer DCC rates accounting for the EPB DCC projects are summarized in Table 3. 

Table 3:  District‐Wide DCC Rate per Equivalent Unit Calculations (including EPB) 

Description  Value 

# of Equivalent Units (Draft DCC Background Report)  1,603 

Net DCC Costs (Draft DCC Background Report)  $   8,487,000 

Net DCC Costs (East Porpoise Bay Area)    $ 3,459,000 

Total Net DCC Costs  $ 11,946,000 

DCC per Equivalent Unit  $ 7,452 

 

The changes to the originally proposed DCC rates, established in the DCC Background Report, as a result 

of  adding  the  EPB  area  are  provided  in  Table  4.    The  original  proposed  DCC  rates  from  the  DCC 

Background Report are included for comparison. 

   

Page 6: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

East Porpoise Bay Sanitary Sewer Expansion Study 

Page 6 of 7 

 

 

Table 4:  District‐Wide DCC Rate Comparison 

Description  Updated DCC Rate 

including EPB Area 

Original DCC Rate from 

Background Report 

Single Family /Unit  $ 7,452  $ 5,294 

Townhouse /Unit  $ 6,185  $ 4,394 

Apartment /Unit  $ 4,993  $ 3,547 

Congregate Care/ Bed  $ 3,130  $ 2,223 

Commercial /m2  $ 14.90  $ 10.59 

Industrial /m2    $ 14.90  $ 10.59 

Institutional /m2  $ 14.90  $ 10.59 

5 Staging and Funding 

Sanitary servicing of the EBP area is anticipated to require significant advanced funding from the District.  

This  area  is  essentially  a  green‐field  and will  require  construction of pump  stations,  forcemains,  and 

sanitary trunk sewers to service this area.  It is likely that this infrastructure will need to be constructed 

prior to collection of sufficient DCC’s to fund the works. 

The  project  staging  and  available  funds  will  largely  be  driven  by  development.    Development  and 

construction  of  the  sanitary  infrastructure would  preferably  occur  from  south  to  north.    PS  #3 was 

constructed as part of the ONNI development.  This allows for relatively cost effective expansion of the 

sanitary sewer network in the PS#3 catchment area.  However, once development starts to occur in the 

PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed.  

In  addition,  based  on  the  preferred  Conceptual  Arrangement,  the  PS#1  catchment  area  cannot  be 

serviced  until  the  infrastructure  to  service  the  PS#2  catchment  area  has  been  constructed.    If 

development  in  the EPB area proceeds  from north  to south, a significant  investment  in  infrastructure 

will be required, potentially in advance of collecting adequate funds through DCC’s. 

Sources of advanced funding that the District could consider, to fund capital projects within the EPB area 

include: 

Applicable DCC reserves; 

Borrowing; 

General taxation; and, 

Senior Government grants. 

These sources will need to be considered at the time infrastructure funding is required. 

Page 7: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

East Porpoise Bay Sanitary Sewer Expansion Study

6 Conclusions and Recommendations The conceptual sanitary servicing plan was established based on the proposed land-use plan for the

area, existing topography, and population growth assumptions. The conceptual sanitary servicing plan

establishes conceptual infrastructure requirements and minimum pipe sizes based on existing average

ground slopes.

If the District decides to proceed with sanitary servicing to East Porpoise Bay, a preliminary design of the

complete servicing strategy should be completed to verify infrastructure sizing and inverts and to

confirm capital costs. Detailed designs can then proceed on a segmented basis as required to support

development.

A preliminary capital cost estimate was developed for the conceptual sanitary servicing plan. Costs

attributable to growth in the EPB area were added to the capital costs attributable to growth for the

remainder of Sechelt as established in the District of Sechelt DCC Background Report. This combined

capital cost was used as the basis to identify the preliminary district-wide DCC rates that include

servicing of the EPB area.

The addition of the costs attributable to growth in the EPB area to the district-wide DCC's result in an

approximate increase to the sanitary DCC's of 40 percent.

If the District intends to proceed with funding the EPB sanitary sewer expansion under DCC's, the DCC

Background Report and Draft DCC Bylaw should be updated to including the capital costs attributable to

development in EPB area to establish the final sanitary sewer DCC rate.

7 Closure

The conclusions and recommendations presented in this report are based on the reference information

provided by the District and the assumptions outlined above. We trust the above conceptual servicing

strategy meets the current requirements of the District and establishes a baseline for future studies.

Sincerely,

Enclosures: Figures 1 to 3

Appendix A: Flow Calculations

Appendix B: Cost Estimates

Page 7 of 7

Page 8: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

~ J, c:

~ i c: ,__

"' ~ ;;; ~ € /

~ Q_ X w ,__ z w :;' C' 4 0

! >-;:; w w

~ :;' ,__ w ~ ,__ w I 0 w w m ~

" € /

Legend:

0 Industrial 1

~ Industrial 3

0 Industrial 6

0 Industrial 7

~ Marine 1

~ Park, Recreation & Assembly 1

~ Residential 1

~ Residential 3

~ Residential 4

0 100 300m

1 6500

PARSONS

2000 PVC SANITARY SEWER (FOR FUTURE CONNECTION)

RR-2

R-3

RR-2

DUSTY ROAD WASTEWATER TREATMENT PLANT

Sechelt DISTRICT OF SECHEL T Naturally Spirited

East Porpoise Bay Sewer Expansion Study

Existing Land Use EB3759 November 2014 Figure 1

0~----------------------------------------------------------------------------------------------------~

Page 9: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

0

i': u J, c:

~ i c: ,__

"' ~ ;;; ~ € /

~ Q_ X w ,__ z w :;' C' 4 0

! >-;:; w w

~ :;' ,__ w ~ ,__ w I 0 w w m ~

" € /

Legend:

~ Commercial 2

[§] Commercial 3

0 Industrial 1

0 Industrial 3

0 Industrial 6

~ Marine 1

~ Multifamily/Mixed Residenti

B Public Assembly

0 Low Density Residential

~ Rural Residential

East Pporpoise Bay -··- Sanitary Service Area

0 100 300m

1 6500

PARSONS

R

R

ALLEN

1-3

Sechelt DISTRICT OF SECHEL T Naturally Spirited

East Porpoise Bay Sewer Expansion Study

Proposed Land Use EB3759 November 2014 Figure 2

0~----------------------------------------------------------------------------------------------~

Page 10: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

0

i': ri J, c:

~ i c: ,__

"' ~ ;;; ~ € /

~ Q_ X w ,__ z w :;' C' 4 0

! >-;:; w w

~ :;' ,__ w ~ ,__ w I 0 w w m ~

" € /

Legend:

------------- Existing Gravity Sewer

- - - - Existing Forcemain

Proposed Gravity Sewer

- - Proposed Forcemain

@ Proposed Pump Station

- - - - - - - Proposed Road Right-of Way

- • • - Pump Station 1 Catchment Area

- • • - Pump Station 2 Catchment Area

- • • - Pump Station 3 Catchment Area

@ Sanitary Node Number

0 100 300m

1 6500

PARSONS

Sechelt DISTRICT OF SECHEL T Naturally Spirited

East Porpoise Bay Sewer Expansion Study

Proposed Sanitary Sewer Network EB3759 November 2014 Figure 3

0~--------------------------------------------------------------------------------------------------------------------~

Page 11: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

SANITARY SEWER DESIGN SHEET Sechelt District - East Porpoise Bay Sewer Expansion Study

Formulas

Q(d)=Q(p)+Q(c)+Q(l) (L/s) Average Design Flow Rates Peaking Factors Capacity

Q(p)=PQM/86.4 (L/s) Q(d)=Peak Design Flow Residential Harmon Formula

Q(p)=Peak Population Flow (L/s) Residential 410 lpcd Commercial/Industrial Harmon Formula Hotel 100 units

Q(c)= commercial flow Commercial Hospitality 366 l/day/unit Equivalent Pop. Campsite 50 sites

Q= average daily flow per capita (L) Recreational 365 l/day/site Residential Densities

Q(I)=peak extraneous flow Industrial 40 employees/hectarre type density

68 l/employee/day

Q(I)=IA (L/s) 2720 l/ha/day Unit 2.25 people/lot

A=area in ha Extraneous Residential Density 8.00 units/ha

I=unit of peak extraneous flow (L/s/ha) Inflow and infiltration 0.05 l/s/ha

M=1+(14/4+P^0.5) (Harmon formula)

P=population in thousands n= 0.013

M=peak factor

DESIGN FLOW

Street From To AREA LOTS LOTS PPL ADWF AREA AREA ADWF AREA AREA ADWF AREA AREA ADWF ADWF POP EQ. PEAK PDWF AREA AREA I & I PWWF Type of Diameter Slope Length Capacity Velocity Capacity Velocity

num accum accum accum. accum. accum. FACTOR accum. Pipe mm >0.6m/sha ea ea ea L/s ha ha L/s ha ha L/s ha ha L/s L/s ea M L/s ha ha L/s L/s nom. act. % m L/s m/s

Marmot Road #1 S0 S1 0.6 5 5 11 0.05 0.05 10.80 4.41 0.23 0.60 0.60 0.03 0.26 PVC 200 203 7.00 77 90.3 2.79 OK OK

S2 S1 1.2 10 10 22 0.10 0.10 21.60 4.38 0.45 1.20 1.20 0.06 0.51 PVC 200 203 12.00 36 118.2 3.65 OK OK

S1 S3 (PS #1) 2.41 22 36 82 0.39 0.39 81.90 4.27 1.66 2.41 4.21 0.21 1.87 PVC 200 203 2.30 217 51.8 1.60 OK OK

Marmot Rd #2 S4 S5 4.58 37 73 164 0.78 0.78 164.34 4.18 3.26 4.58 8.79 0.44 3.70 PVC 200 203 2.90 394 58.1 1.80 OK OK

New Rd S6 S5 2.08 17 17 37 0.18 0.18 37.44 4.34 0.77 2.08 2.08 0.10 0.87 PVC 200 203 3.00 103 59.1 1.83 OK OK

Shoreline #1 S5 S7 0 0 90 202 0.96 0.96 201.78 4.15 3.97 0.00 10.87 0.54 4.51 PVC 200 203 3.80 51 66.5 2.06 OK OKS7 PS#2 2.38 19 109 245 1.16 1.16 244.62 4.11 4.78 2.38 13.25 0.66 5.44 PVC 200 203 0.80 400 30.5 0.94 OK OK

Burnett Rd S8 S9 28 224 224 504 2.39 0.00 0.00 0.00 2.39 504.00 3.97 9.50 28.00 28.00 1.40 10.90 PVC 200 203 8.30 360 98.3 3.04 OK OK

Sechelt Inlet Rd S9 S11 0 0 224 504 2.39 0.00 0.00 0.00 2.39 504.00 3.97 9.50 0.00 28.00 1.40 10.90 PVC 200 203 1.40 400 40.4 1.25 OK OK

Yew Rd S10 S11 15.64 125 125 282 1.34 4.42 4.42 0.14 1.48 310.84 4.07 6.01 20.06 20.06 1.00 7.01 PVC 200 203 1.30 512 38.9 1.20 OK OK

Sechelt Inlet Rd S12 S11 2.71 22 22 49 0.23 0.00 0.00 0.00 0.23 48.78 4.32 1.00 2.71 2.71 0.14 1.13 PVC 200 203 4.10 379 69.1 2.14 OK OK

Yew Rd S11 PS#2 3.73 30 401 901 4.28 0.00 4.42 0.14 4.42 930.76 3.82 16.87 3.73 54.50 2.73 19.60 PVC 200 203 3.30 110 62.0 1.92 OK OK

New Rd S13 S14 1.38 11 11 25 0.12 0.12 24.84 4.37 0.51 1.38 1.38 0.07 0.58 PVC 200 203 5.20 299 77.8 2.40 OK OK

Shoreline #2 S14 PS#2 4.23 34 45 101 0.48 0.48 100.98 4.24 2.03 4.23 4.23 0.21 2.24 PVC 200 203 1.50 438 41.8 1.29 OK OK

PS#2 Combined Flows All PS#2 68.94 554 1247 5.92 4.42 4.42 0.14 6.06 1276.36 3.73 22.59 73.36 73.36 3.67 26.25 PVC 200 203 2.20 127 50.6 1.56 OK OK

Allen Rd S15 S16 9.39 75 75 169 0.80 1.71 1.71 0.05 0.86 180.36 4.16 3.56 11.10 11.10 0.56 4.12 PVC 200 203 6.10 534 84.3 2.60 OK OK

Sechelt Inlet Rd S16 S17 2.78 22 97 219 1.04 0.00 1.71 0.05 1.09 230.40 4.12 4.51 2.78 13.88 0.69 5.20 PVC 200 203 2.20 127 50.6 1.56 OK OK

Dusty Rd S18 S19 0 0 0 0 0.00 4.05 4.05 0.14 14.55 14.55 0.46 0.60 126.20 4.21 2.52 18.60 18.60 0.93 3.45 PVC 200 203 5.50 380 80.0 2.47 OK OK

Sechelt Inlet Rd S17 S19 0 0 97 219 1.04 2.89 2.89 0.42 2.03 6.08 0.21 7.30 23.56 0.74 2.42 509.14 3.97 9.59 12.22 44.70 2.24 11.83 PVC 200 203 2.50 392 54.0 1.67 OK OK

S20 S19 0 0 0 0 0.00 6.80 6.80 0.21 0.21 45.11 4.32 0.93 6.80 6.80 0.34 1.27 PVC 200 203 1.70 316 44.5 1.37 OK OK

S19 PS#3 0 0 97 219 1.04 0.00 2.89 0.42 0.00 6.08 0.21 0.00 30.36 0.96 2.63 554.25 3.95 10.39 0.00 51.50 2.58 12.97 PVC 200 203 3.50 143 63.8 1.97 OK OK

Onni PS#3 5 116 116 261 1.24 1.24 261.00 4.10 5.08 5.00 5.00 0.25 5.33 PVC 200 203 1.70 316 44.5 1.37 OK OK

PS#3 Combined Flows All PS#2 17.17 0 213 480 2.28 2.89 2.89 0.42 6.08 6.08 0.21 30.36 30.36 0.96 3.87 815.25 3.86 14.92 56.50 56.50 2.83 17.74 PVC 200 203 2.20 127 50.6 1.56 OK OK

SUMMARIES

PS#1 PS#2 4.21 36 82 0.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.39 81.90 4.27 1.66 2.41 4.21 0.21 1.87

PS#2 FM 68.94 0 554 1247 5.92 0.00 0.00 0.00 0.00 0.00 0.00 4.42 4.42 0.14 6.06 1276.36 3.73 22.59 73.36 73.36 3.67 26.25

PS#3 FM 17.17 0 213 480 2.28 2.89 2.89 0.42 6.08 6.08 0.21 30.36 30.36 0.96 3.87 815.25 3.86 14.92 56.50 56.50 2.83 17.74

All WWTP 86.11 0 767.60 1727 8.20 2.89 2.89 0.42 6.08 6.08 0.21 34.78 34.78 1.09 9.93 2091.62 3.57 35.44 129.86 129.86 6.49 41.93

3623 cu.m

REMARKSCOMMERCIAL HOSPITALITY FLOWRESIDENTIAL FLOW RECREATIONAL FLOW INDUSTRIAL FLOW EXTRANEOUS FLOWS SEWER DATACOMBINED FLOWS

Page 12: 2015-12-09 EPB DCC Final Report document...Dec 09, 2015  · PS#2 catchment, the pump station, forcemain, and trunk sewer for this area will need to be constructed. In addition, based

EAST PORPOISE BAY SANITARY SEWER EXPANSION STUDY 19-Nov-14

PROPOSED SANITARY NETWORK ESTIMATED COSTS

Street Location InfrastructureLength

(m)Ground Surface

Construction Cost

Contingency (30%)

Engineering (12.5%)

Project CostDCC

PortionDCC Cost

Grant Funding

Assist Factor

Net DCC Recovery

NORTH PART OF STUDY AREA (PUMP STATION #1 CATCHMENT)

GRAVITY SEWERSMarmot Road Heron to Pump Station #1 Sanitary Sewer 330 Paved 165,000$ 49,500$ 20,625$ 235,125$ 28% 65,313$ 25% 1% 48,331$

Subtotal (Gravity Sewers) 235,125$ 65,313$ 48,331$

PUMP STATION #1 AND FORCEMAINMarmot Road PS#1 to Heron Forcemain 330 Paved 115,500$ 34,650$ 14,438$ 164,588$ 28% 45,719$ 25% 1% 33,832$

Marmot Road West end Pump Station #1 - - 300,000$ 90,000$ 37,500$ 427,500$ 28% 118,750$ 25% 1% 87,875$

Subtotal (Pump Station #1 and Forcemain) 592,088$ 164,469$ 121,707$

TOTAL (PUMP STATION #1 CATCHMENT AREA) 170,038$

CENTRAL PART OF STUDY AREA (PUMP STATION #2 CATCHMENT)

NORTH SUBCATCHMENT GRAVITY SEWERSMarmot Rd Heron to Burnett Gravity Sewer 395 Paved 197,500$ 59,250$ 24,688$ 281,438$ 100% 281,438$ 25% 1% 208,264$

Burnett Road Sechelt Inlet Rd to Shoreline Gravity Sewer 155 Paved 77,500$ 23,250$ 9,688$ 110,438$ 100% 110,438$ 25% 1% 81,724$

Shoreline Burnett Road to PS#2 Gravity Sewer 400 Natural 150,000$ 45,000$ 18,750$ 213,750$ 100% 213,750$ 25% 1% 158,175$

Subtotal (Gravity Sewers) 605,625$ 605,625$ 448,163$

CENTRAL SUBCATCHMENT GRAVITY SEWERSBurnett Rd East End to Sechelt Inlet Rd Gravity Sewer 360 Gravel 153,000$ 45,900$ 19,125$ 218,025$ 100% 218,025$ 25% 1% 161,339$

Sechelt Inlet Rd Burnett to Yew Gravity Sewer 400 Paved 200,000$ 60,000$ 25,000$ 285,000$ 100% 285,000$ 25% 1% 210,900$

Yew Rd East End to Sechelt Inet Road Gravity Sewer 510 Paved 255,000$ 76,500$ 31,875$ 363,375$ 100% 363,375$ 25% 1% 268,898$

Sechelt Inlet Rd Allen to Yew Gravity Sewer 380 Paved 190,000$ 57,000$ 23,750$ 270,750$ 100% 270,750$ 25% 1% 200,355$

Yew Rd Sechelt Inlet Rd to PS#2 Gravity Sewer 110 Paved 55,000$ 16,500$ 6,875$ 78,375$ 100% 78,375$ 25% 1% 57,998$

Subtotal (Gravity Sewers) 1,215,525$ 1,215,525$ 899,489$

SOUTH SUBCATCHMENT GRAVITY SEWERSAllen Rd Sechelt Inlet Rd to Shoreline Gravity Sewer 181 Paved 90,500$ 27,150$ 11,313$ 128,963$ 100% 128,963$ 25% 1% 95,432$

Shoreline Allen Road to PS#2 Gravity Sewer 438 Natural 164,250$ 49,275$ 20,531$ 234,056$ 100% 234,056$ 25% 1% 173,202$

Subtotal (Gravity Sewers) 363,019$ 363,019$ 268,634$

PUMP STATION #2 AND FORCEMAINSYew Rd PS#2 to Dusty/Sechelt Inlet Forcemain 800 Paved 280,000$ 84,000$ 35,000$ 399,000$ 100% 399,000$ 25% 1% 295,260$

Yew Rd At shoreline Pump Station #2 - - 400,000$ 120,000$ 50,000$ 570,000$ 100% 570,000$ 25% 1% 421,800$

Subtotal (Pump Station #2 and Forcemain) 969,000$ 969,000$ 717,060$

TOTAL(PUMP STATION #2 CATCHMENT AREA) 2,333,345$

SOUTH PART OF STUDY AREA (PUMP STATION #3 CATCHMENT)

GRAVITY SEWERSAllen Rd East End to Sechelt Inlet Gravity Sewer 534 Gravel 226,950$ 68,085$ 28,369$ 323,404$ 100% 323,404$ 25% 1% 239,319$

Sechelt Inlet Rd Allen to Dusty Gravity Sewer 127 Paved 63,500$ 19,050$ 7,938$ 90,488$ 100% 90,488$ 25% 1% 66,961$

Dusty Rd East End to Sechelt Inlet Gravity Sewer 380 Paved 190,000$ 57,000$ 23,750$ 270,750$ 100% 270,750$ 25% 1% 200,355$

Sechelt Inlet Rd Dusty to PS#3 access road Gravity Sewer 392 Paved 196,000$ 58,800$ 24,500$ 279,300$ 100% 279,300$ 25% 1% 206,682$

Sechelt Inlet Rd Delta to PS#3 access road Gravity Sewer 316 Paved 158,000$ 47,400$ 19,750$ 225,150$ 100% 225,150$ 25% 1% 166,611$

PS#3 Access Rd Sechelt Inlet to PS#3 Gravity Sewer 143 Paved 71,500$ 21,450$ 8,938$ 101,888$ 100% 101,888$ 25% 1% 75,397$

Subtotal (Gravity Sewers) 1,290,979$ 1,290,979$ 955,324$

Pump Station #3 and ForcemainPS access road PS#2 to Dusty/Sechelt Inlet Forcemain 115 Paved 40,250$ 12,075$ 5,031$ 57,356$ 0% -$ -$

PS access road At shoreline Pump Station #3 - - 450,000$ 135,000$ 56,250$ 641,250$ 0% -$ -$

Subtotal (Pump Station #3 and Forcemain) 698,606$ -$ -$

TOTAL (PUMP STATION #3 CATCHMENT AREA) 955,324$

TOTAL EAST PORPOISE BAY AREA

5,969,966$ 4,673,929$ 3,458,707$

Estimated Unit CostsUnit Cost Unit Notes

Gravity Sewers Under Paved Surface 500$ per metre 1 - Paved ground surface: Pipes in paved areas are assumed to be installed per MMCD G4 - Paved with 100mm asphaltGravity Sewers Under Gravel Surface 425$ per metre 2 - Gravel ground surface: Pipes under gravel roads are assumed to be installed per MMCD G4 - Paved, but without asphalt.Gravity Sewers Under Natural Surface 375$ per metre 3 - Natural ground surface: Pipe in natural areas are assumed to be installed per MMCD G4 - Boulevards and EasementsForcemains Under Paved Surface 350$ per metre