23821974 construction costing
TRANSCRIPT
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 1/33
Construction contracts
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 2/33
Name Roll
number
Topic
Srinivas K 49 Introduction & definition.
Shruti N 44 Procurement of contract.
Virupaksha 56 Contract analysis.
Zakir 58 Cost estimation.
Sharada 40 Types of payments.
Sangameshwar 36 Types of costs.
Saroj 38 Collection of costs.
Shilpa S 42 Indian example.
Soumya B 47 International example.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 3/33
Construction contract
A construction contract is a contract
specifically negotiated for the
construction of an asset or a combinationof assets that are closely interrelated or
interdependent in terms of their design,
technology and function or their ultimate purpose or use.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 4/33
Construction contract is a
formal agreement for construction,
alteration, or repair of
buildings or structures (bridges,dams, facilities, roads, tanks, etc.). A
construction contract is distinct from a
contract to assemble, fabricate,or manufacture.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 5/33
Contract costing
Contract costing is defined as “the form of
specific order costing which is
undertaken for customer’s specialrequirements and each order is of long
duration, the work is usually
constructional and in general the methodis similar to job costing”
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 6/33
Procurement methods of contract
•Traditional
•Design and Build
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 7/33
• Two Stage Tendering
• Management Contracting
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 8/33
• Construction Management
• Framework Agreements
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 9/33
Analysis of construction company
project
•Plan
•Secure
•Achieve
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 10/33
Factors
• Plan:Plan is developed to describe
activities associated with the project .The
resource required to achieve the best
possible outcomes for it &must be agreed
on by all key characters.
• Scope < Time < Cost < Quality < Humanresource < Communication < Risk <
Procurement.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 11/33
• Secure: Once the project team is
established they should secure the
project. It means maintaining control over where the project is and where it is
headed.
• Achieve: Completing the project goals
and objectives. Achieving the goals set
out at the beginning of it ,with a
successful project outcome.
• Example : NICE construction company
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 12/33
Cost Estimation :
The costs in a construction contract
includes both the initial capital cost
and the subsequent operation andmaintenance costs. Each of these
major cost categories consists of a
number of cost components.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 13/33
•Initial Capital cost – Land acquisition
– Planning and feasibility studies
– Construction, including materials, equipment and labor
– Insurance and taxes during construction
•Operation and maintenance cost
– Operating staff – Labor and material for maintenance and repairs
– Utilities
– Periodic renovations
– Insurance and taxes
•Unexpected cost during construction – Design development changes
– Schedule adjustments
– General administration changes
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 14/33
Types of construction cost estimates
•Design Estimates – Screening estimates (or order of magnitude estimates)
– Preliminary estimates (or conceptual estimates)
– Detailed estimates (or definitive estimates)
– Engineer's estimates based on plans and specifications
•Bid Estimates – As a contractor, a bid estimate is submitted to the owner either for
competitive bidding or negotiation.
•Control Estimates – Budget estimate for financing
– Budgeted cost after contracting but prior to construction
– Estimated cost to completion during the progress of construction.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 15/33
TYPES OF PAYMENTS
Upfront payment/deposit:• Upfront payments or deposits will
generally be used for jobs where high
level of material cost is foundPeriodic payment:
• It is based on the interim valuation of the
work
• The main contractor then makes a down
stream payment
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 16/33
Stage payments:
• Depends on events rather than time• The parties agree at the out set that payment will be
released on completion of the agreed stages of work.
Milestone payment:
• It is a derivative of stage payment
• It will be setout in a schedule to the contract & the
contractor will notify the employer when it considers
that all work to be performed for a milestone.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 17/33
Retention payment:
Retention payments act as an incentive for the contractor to finish the job.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 18/33
Types of costs
• Direct Materials
• Direct Labor
• Indirect Costs• Direct expenses
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 19/33
Direct Materials.Provide a consolidated priced summary of individual material
quantities included in the various tasks, orders, or contract lineitems being proposed and the basis for pricing (vendor quotes,invoice prices, etc.).
Include raw materials like sand, stone, cement, and steel to beproduced or performed by others
Direct Labor .
workers who are engaged directly in the constructionprocess. Provide a time-phased (e.g., monthly, quarterly, etc.)
.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 20/33
• Ind irect Costs . Indirect costs are those for
activities or services that benefit more than one project.Their precise benefits to a specific project are oftendifficult or impossible to trace. For example, it may bedifficult to determine precisely how the activities of the
director of an organization benefit a specific project
• Direct expenses. all other costs other than the
above mentioned costs (e.g., architects, designs,carriage inward, ) and provide bases for pricing.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 21/33
Collection of cost
Material cost:
• Materials required for contract are purchasedand delivered at the site
• Materials in stock are valued and credited to
the contract account ,the contract account getsdebited by the value of material consumedduring the year
Labour cost:
• Depending upon the contract, wages are paiddirectly at the site
• Allocation of wages to various sub units is
easy
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 22/33
Plants & Equipment cost:
• They are purchased or hired
• Depreciation on owned plant &equipment are debited to the contract
account
• The written down value is carried over asa balance to the next accounting period
in which it is credited
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 23/33
Sub contracts cost :
• Specialised nature tasks are assigned to
the sub contractors
• They are paid at agreed rate.
• Direct expense
• Contract account is debited on the basisof invoice received from the sub
contractor
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 24/33
Godavari rail bridge
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 25/33
Godavari Rail Bridge is a bridge over the
river Godavari connecting Rajamandri andKovur in Andhrapradesh.
• Inaugurated in 2003.
• Length : 2730m.• Constructed by : Hindustan Construction
Company (HCC).
• Total cost: Rs. 1.5 cr.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 26/33
DIRECT EXPENSES:DIRECT MATERIAL: 44,10,000DIRECT LABOUR: 15,75,000DIRECT EXPENSES: 7,77,000
PRIME COST 67,62,000
INDIRECT EXPESES:
OVERHEADS:POWER 2,10,000INSURANCE 4,20,000TRANSPORTATION 3,25,500
FIELD ENGINEERS 5,28,000DESIGN ENGINEERS 4,72,500
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 27/33
MANAGERS SALARY 7,68,000
SECURITIES SALARY 3,84,000
CONTRACTOR’S FEE 6,30,000
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 28/33
Hamilton construction company undertook
the construction of Winchester Bridge inRoseburg, Oregon, USA.
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 29/33
Winchester Bridge
• Built:1923
• Crosses: North Umpqua River.
• Total length :269.4 m• Construction costs: $29,40,000
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 30/33
Particulars Amount
Direct materials: $ 16,80,000
Direct labour: $ 8,40,000
Direct expenses: $ 2,80,000
Prime cost: $28,00,000
Overheads:Power: $35,000
Transportation: $20,000
Supervisor’s salary: $25,000
Engineering: $30,000
Fuel: $15,000
Other expenses: $15,000
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 31/33
Assumption
• Power: @ $2/unit for 10000 units.
• Supervisors salary @ $2000/ month.
Absorption of overhead
• % of Direct Material=8.33%
• % of Direct Labour= 16.6%
• % of Prime Cost= 5%
7/27/2019 23821974 Construction Costing
http://slidepdf.com/reader/full/23821974-construction-costing 32/33
Sources
• Principles and practice of cost accounting: Asish K. Bhattacharyya.
• Cost Accounting: Jawahar lal.
• Cost accounting: Tukaram.
• Websites:
• www.wikipedia.com• www.futureaccountant.com
• www.slideshare.com