23821974 construction costing

33
Construction contracts

Upload: mrlobbo

Post on 14-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 1/33

Construction contracts

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 2/33

Name Roll

number 

Topic

Srinivas K 49 Introduction & definition.

Shruti N 44 Procurement of contract.

Virupaksha 56 Contract analysis.

Zakir 58 Cost estimation.

Sharada 40 Types of payments.

Sangameshwar 36 Types of costs.

Saroj 38 Collection of costs.

Shilpa S 42 Indian example.

Soumya B 47 International example.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 3/33

Construction contract

A construction contract is a contract

specifically negotiated for the

construction of an asset or a combinationof assets that are closely interrelated or 

interdependent in terms of their design,

technology and function or their ultimate purpose or use.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 4/33

Construction contract is a

formal agreement for construction,

alteration, or repair of 

 buildings or structures (bridges,dams, facilities, roads, tanks, etc.). A

construction contract is distinct from a

contract to assemble, fabricate,or manufacture.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 5/33

Contract costing

Contract costing is defined as “the form of 

specific order costing which is

undertaken for customer’s specialrequirements and each order is of long

duration, the work is usually

constructional and in general the methodis similar to job costing” 

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 6/33

Procurement methods of contract

•Traditional

•Design and Build

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 7/33

• Two Stage Tendering

• Management Contracting

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 8/33

• Construction Management

• Framework Agreements

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 9/33

Analysis of construction company

 project

•Plan

•Secure

•Achieve

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 10/33

Factors

• Plan:Plan is developed to describe

activities associated with the project .The

resource required to achieve the best

 possible outcomes for it &must be agreed

on by all key characters.

• Scope < Time < Cost < Quality < Humanresource < Communication < Risk <

Procurement.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 11/33

• Secure: Once the project team is

established they should secure the

 project. It means maintaining control over where the project is and where it is

headed.

• Achieve: Completing the project goals

and objectives. Achieving the goals set

out at the beginning of it ,with a

successful project outcome.

• Example : NICE construction company

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 12/33

Cost Estimation :

The costs in a construction contract

includes both the initial capital cost

and the subsequent operation andmaintenance costs. Each of these

major cost categories consists of a

number of cost components.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 13/33

•Initial Capital cost – Land acquisition

 – Planning and feasibility studies

 – Construction, including materials, equipment and labor 

 – Insurance and taxes during construction

•Operation and maintenance cost

 – Operating staff  – Labor and material for maintenance and repairs

 – Utilities

 – Periodic renovations

 – Insurance and taxes

•Unexpected cost during construction – Design development changes

 – Schedule adjustments

 – General administration changes

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 14/33

Types of construction cost estimates

•Design Estimates – Screening estimates (or order of magnitude estimates)

 – Preliminary estimates (or conceptual estimates)

 – Detailed estimates (or definitive estimates)

 – Engineer's estimates based on plans and specifications

•Bid Estimates – As a contractor, a bid estimate is submitted to the owner either for 

competitive bidding or negotiation.

•Control Estimates – Budget estimate for financing

 – Budgeted cost after contracting but prior to construction

 – Estimated cost to completion during the progress of construction.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 15/33

TYPES OF PAYMENTS

Upfront payment/deposit:• Upfront payments or deposits will

generally be used for jobs where high

level of material cost is foundPeriodic payment:

• It is based on the interim valuation of the

work 

• The main contractor then makes a down

stream payment

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 16/33

 

Stage payments:

• Depends on events rather than time• The parties agree at the out set that payment will be

released on completion of the agreed stages of work.

Milestone payment:

• It is a derivative of stage payment

• It will be setout in a schedule to the contract & the

contractor will notify the employer when it considers

that all work to be performed for a milestone.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 17/33

 

Retention payment:

Retention payments act as an incentive for the contractor to finish the job.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 18/33

Types of costs

• Direct Materials

• Direct Labor 

• Indirect Costs• Direct expenses

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 19/33

 

Direct Materials.Provide a consolidated priced summary of individual material

quantities included in the various tasks, orders, or contract lineitems being proposed and the basis for pricing (vendor quotes,invoice prices, etc.).

Include raw materials like sand, stone, cement, and steel to beproduced or performed by others

Direct Labor .

workers who are engaged directly in the constructionprocess. Provide a time-phased (e.g., monthly, quarterly, etc.)

.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 20/33

 

• Ind irect Costs . Indirect costs are those for 

activities or services that benefit more than one project.Their precise benefits to a specific project are oftendifficult or impossible to trace. For example, it may bedifficult to determine precisely how the activities of the

director of an organization benefit a specific project 

• Direct expenses. all other costs other than the

above mentioned costs (e.g., architects, designs,carriage inward, ) and provide bases for pricing.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 21/33

Collection of cost

Material cost:

• Materials required for contract are purchasedand delivered at the site

• Materials in stock are valued and credited to

the contract account ,the contract account getsdebited by the value of material consumedduring the year 

Labour cost:

• Depending upon the contract, wages are paiddirectly at the site

• Allocation of wages to various sub units is

easy

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 22/33

Plants & Equipment cost:

• They are purchased or hired

• Depreciation on owned plant &equipment are debited to the contract

account

• The written down value is carried over asa balance to the next accounting period

in which it is credited

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 23/33

Sub contracts cost :

• Specialised nature tasks are assigned to

the sub contractors

• They are paid at agreed rate.

• Direct expense

• Contract account is debited on the basisof invoice received from the sub

contractor 

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 24/33

Godavari rail bridge

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 25/33

Godavari Rail Bridge is a bridge over the

river Godavari connecting Rajamandri andKovur in Andhrapradesh.

• Inaugurated in 2003.

• Length : 2730m.• Constructed by : Hindustan Construction

Company (HCC).

• Total cost: Rs. 1.5 cr.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 26/33

DIRECT EXPENSES:DIRECT MATERIAL: 44,10,000DIRECT LABOUR: 15,75,000DIRECT EXPENSES: 7,77,000

PRIME COST 67,62,000

INDIRECT EXPESES:

OVERHEADS:POWER 2,10,000INSURANCE 4,20,000TRANSPORTATION 3,25,500

FIELD ENGINEERS 5,28,000DESIGN ENGINEERS 4,72,500

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 27/33

MANAGERS SALARY 7,68,000

SECURITIES SALARY 3,84,000

CONTRACTOR’S FEE 6,30,000

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 28/33

Hamilton construction company undertook 

the construction of Winchester Bridge inRoseburg, Oregon, USA.

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 29/33

Winchester Bridge 

• Built:1923

• Crosses: North Umpqua River.

• Total length :269.4 m• Construction costs: $29,40,000

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 30/33

Particulars Amount

Direct materials: $ 16,80,000

Direct labour: $ 8,40,000

Direct expenses: $ 2,80,000

Prime cost: $28,00,000

Overheads:Power: $35,000

Transportation: $20,000

Supervisor’s salary:  $25,000

Engineering: $30,000

Fuel: $15,000

Other expenses: $15,000

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 31/33

Assumption

• Power: @ $2/unit for 10000 units.

• Supervisors salary @ $2000/ month.

Absorption of overhead

• % of Direct Material=8.33%

• % of Direct Labour= 16.6%

• % of Prime Cost= 5%

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 32/33

Sources

• Principles and practice of cost accounting: Asish K. Bhattacharyya.

• Cost Accounting: Jawahar lal.

• Cost accounting: Tukaram.

• Websites:

• www.wikipedia.com• www.futureaccountant.com

• www.slideshare.com

7/27/2019 23821974 Construction Costing

http://slidepdf.com/reader/full/23821974-construction-costing 33/33

Thank you