  • W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc

    SOCIEDAD MINERA CERRO VERDE S.A.A. CERRO VERDE PRODUCTION UNIT EXPANSION

    PROJECT NO. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL,

    PERUVIAN PACKAGE SCOPE OF WORK

    DOCUMENT NO. 240K-C2-SW-15-008 REV. C

    08 MAY 2012

  • W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 1 of 12

    This document has been revised as indicated below. Changes after Revision 0 are identified by vertical bars at the right side of the page, with additions being underlined. Please replace all pages of this specification and destroy the superseded copies.

    Rev No. Originator Rev Date Revision Description A -- -- Not Used B -- -- Not Used C Nick Tullan 8May12 Issued for Quotation

    New Issue Entire Document Re-issued

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 2 of 12

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 3 of 12

    TABLE OF CONTENTS

    1. SCOPE OF WORK........................................................................................................................................ 5 2. DESCRIPTION OF WORK............................................................................................................................ 5

    2.1 General .............................................................................................................................................5 2.2 Related Documents ..........................................................................................................................5

    3. DESCRIPTION OF WORK SPECIFIC....................................................................................................... 6 3.1 Scope of Facilities ............................................................................................................................6 3.2 Structural Steel Quantities................................................................................................................7 3.3 Scope of Services.............................................................................................................................7 3.4 Exclusions from Scope of Work........................................................................................................8

    4. MATERIALS AND EQUIPMENT FURNISHED BY COMPANY AND CONTRACTOR.............................. 8 5. QUANTITIES ................................................................................................................................................. 8

    5.1 Unit Rates .........................................................................................................................................8 5.2 Quantities..........................................................................................................................................9 5.3 Revisions, Additions and Deletions ..................................................................................................9 5.4 Substitutions ...................................................................................................................................10

    6. SCHEDULE ................................................................................................................................................. 10 6.1 Milestones.......................................................................................................................................10 6.2 Submittals for Bid ...........................................................................................................................10 6.3 Available Production Capacity........................................................................................................11

    7. ATTACHMENTS.......................................................................................................................................... 11

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 4 of 12

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 5 of 12

    1. SCOPE OF WORK

    Except as otherwise expressly provided herein, Seller shall supply all adequate and competent labor, supervision, administration, management, services, tools, equipment, warehousing, installed and consumable materials, testing devices, and each and every item of expense necessary for performing operations required to detail, supply, and fabricate, and all resource planning, receiving, handling, packing, and loading, as well as testing, evaluation, and quality control for the prescribed portion of structural and miscellaneous steel supply for the Sociedad Minera Cerro Verde, S.A.A. Cerro Verde Production Unit Expansion herein called the Work.

    2. DESCRIPTION OF WORK

    2.1 General

    A. Seller shall perform the Work in a timely and workmanlike manner to industry professional standards in accordance with sound construction practices and local, state, and federal laws, orders, codes, and regulations applicable to the Work.

    B. All articles defining the Work to be performed by Seller are presented for the purpose of clarifying the Work, but shall not constitute a complete list of the Work, nor limit the Work, nor guarantee the Work.

    C. The steelwork supply described herein as prescribed in Unit Rate Schedules. Bidders to provide corresponding prices and unit rates.

    D. Bidder shall indicate clearly any and all implications with respect to prices, delivery and unit rates if PO packages or portions of a Package are removed or added to the total number of Packages submitted in the bid.

    E. Bidder shall indicate clearly any and all implications with respect to prices, delivery and unit rates if there are schedule delays to any packages or portions of a Package in the bid.

    F. See Attachment 5 for description and Steel Quantity Estimates.

    G. Bidder shall verify capability to perform and assume responsibility for engineering design and detailing of connections.

    H. Bidder shall indicate method and software to be used for connection engineering design and detailing. Names and capacities of detailing subcontractors shall be submitted, if the work is not to be detailed in-house by the Bidder.

    I. Sequencing of steelwork fabrication and delivery shall be coordinated with the Buyer. Steel shall be delivered in erectable packages, from the ground up, including fall arrest devices, stairs, platforms and handrails to facilitate construction progress.

    2.2 Related Documents

    A. Seller shall perform all Work in strict accordance with the following documents:

    240K-C2-CS-15-012 Grouts 240K-C2-CS-15-021 Fabrication of Structural and Miscellaneous Steel

    240K-C2-CS-15-022 Erection Of Structural Steel 240K-C2-CS-15-024 Metal Decking 240K-C2-DC-10-002 General Site Conditions Design Criteria 240K-C2-ES-55-002 Paint Specification

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 6 of 12

    240K-C2-SD-15-021 Fabrication of Structural & Misc. Steel Supplier Drawing & Data Commitment (SDDC) Form

    B. Engineering Drawings

    1. Refer to Attachment 1 for list of Reference Drawings.

    2. Representative complexity drawings have been included to define complexity of steelwork for typical buildings and structures. Actual engineering drawings may vary.

    C. The Seller shall review all documents and ascertain that he fully understands the extent and complexity of the scope of work of these packages.

    3. DESCRIPTION OF WORK SPECIFIC

    The Work described in Articles of this document shall include, but may not necessarily be limited to, the following areas and activities:

    3.1 Scope of Facilities

    A. Area 3100 Primary Crushing and Coarse Ore Handling

    1. Area 3110 Primary Crusher platform, stairs and equipment supports

    2. Area 3120 Coarse Ore Handling

    a. Coarse ore conveyor No. 1 C-3120-CV-012

    b. Coarse ore conveyor No. 2 C-3120-CV-022

    B. Area 3200 Secondary and Tertiary Crushing

    1. Area 3210 Coarse Ore Reclaim

    a. Coarse ore reclaim chamber equipment supports, platforms and stairs

    b. Coarse ore reclaim conveyor No. 1 C-3210-CV-013

    c. Coarse ore reclaim conveyor No. 2 C-3210-CV023

    2. Area 3220 Secondary Crushing

    a. Secondary crusher discharge conveyor No. 1 C-3220-CV-016

    b. Secondary crusher discharge conveyor No. 2 C-3220-CV-026

    3. Area 3230 Tertiary Crushing

    a. HPGR discharge conveyor No.1 C-3230-CV-017

    b. HPGR discharge conveyor No.2 C-3230-CV-027

    c. HPGR product conveyor No. 1 C-3230-CV-018

    d. HPGR product conveyor No. 2 C-3230-CV-028

    4. Area 3240 Screening

    a. Coarse ore oversize conveyor No. 1 C-3240-CV-015

    b. Coarse ore oversize conveyor No. 2 C-3240-CV-025

    c. Tertiary crusher bin feed conveyor No. 1 C-3240-CV-031

    d. Tertiary crusher bin feed conveyor No. 2 C-3240-CV-041

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 7 of 12

    C. Area 3300 Grinding

    1. Area 3310 Ball Mill Feed

    a. Ball mill screen oversize conveyor No. 1 C-3310-CV-019

    b. Ball mill screen oversize conveyor No. 2 C-3310-CV-029

    D. Area 3400 Copper Flotation

    1. Area 3410 & 3440 Rougher Floatation and Cleaner Flotation

    a. Overhead crane support structure

    b. Pipe, cable and equipment supports

    2. Area 3420 & 3430 Regrind and Cleaner Columns

    a. Overhead crane support structure

    Lateral moment frame structure longitudinally braced with interior columns supporting floors and stair tower.

    b. Cleaner column annex

    c. Pipe, cable and equipment supports

    E. Area 3500 Moly Plant

    1. Equipment and pipe supports

    2. Access floors, platforms and stairs

    F. Area 3600 Concentrate Dewatering and Loadout

    1. Enclosed Filter Press Building

    2. Equipment, pipe and cable tray supports

    3. Platforms and stairs

    G. Area 3700 Tailing Thickening

    1. Equipment, pipe and cable tray supports

    2. Platforms and stairs

    H. Area 3900 Process Utilities and Reagents

    1. Equipment, pipe and cable tray supports

    2. Platforms and stairs

    I. Area 5000 Utilities & Ancillaries

    3.2 Structural Steel Quantities

    Refer to Attachment 5.

    3.3 Scope of Services

    A. Supply of all structural steel shapes, bars, plates, pins, connections etc. necessary to fabricate the steelwork as described in the drawings and specifications

    B. Preparation of all erection and shop detail drawings necessary for the fabrication of the steelwork

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 8 of 12

    C. Preparing, priming and painting of all steelwork as noted

    D. Packaging and loading all steelwork and attachments

    E. Supply the necessary touch-up primer and paint for site use

    3.4 Exclusions from Scope of Work

    The following works shall be excluded from the Contractors Scope of Work:

    A. Off-loading of the steelwork at site

    B. Erection of the steelwork at site

    C. Touch-up painting of the erected steelwork

    D. Steel embedded in concrete

    4. MATERIALS AND EQUIPMENT FURNISHED BY COMPANY AND CONTRACTOR

    Not Applicable.

    5. QUANTITIES

    5.1 Unit Rates

    A. Prices shall be submitted on a unit rate basis as indicated on the attached Unit Rates Schedules (Attachments 2 and 3).

    B. Unit rates shall remain effective and unchanged for the duration of the overall work and are independent of changes in the following:

    1. Complexity

    a. Actual types of structures and final choice of structural components may result in variances from categories and representative building/structure types submitted with the bid, but are adequate to establish fixed unit rate.

    b. Distribution and available selection of weight ranges in unit rate categories are adequate to account for variance in complexity and weight between sections of varied unit weight within a category.

    2. Quantities

    a. Final quantities and distribution of quantities amongst categories and structures may vary from those indicated in the unit rates list, milestones and other documents issued to date.

    b. Awarded and final quantities may increase or decrease by +/- 20 percent from the bid quantities.

    c. Portions of the work may, at the discretion of the Buyer, with prior written notice to the Seller, be awarded to another supplier.

    3. Schedule

    Final milestone dates, IFC and RAS, for portions of the work may vary from those indicated.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 9 of 12

    C. Unit rates shall identify for each category the following activities:

    1. Connection allowance (unique to each category)

    2. Detailing (including connection engineering design)

    3. Supply

    4. Fabrication

    5. Surface preparation and painting

    D. The bidder shall clearly indicate any and all implications with respect to unit rates and/or schedule resulting from removal of detailing from the scope of work.

    E. Submittals for Bid

    1. Prices shall be submitted on a unit rate basis as indicated on the attached Unit Rates Schedules (Attachments 2 and 3).

    2. Unit rates shall be provided for each category, regardless of indicated quantity (even for zero quantity).

    3. The bidder shall submit unit rates in compliance with the categories indicated.

    4. Quantities indicated include connection allowance, end plates, clip angles, gusset plates, stiffeners, doublers, welds, and shop bolts etc. required for field and shop connections.

    5. Bidder shall advise the Buyer prior to submittal of bid of variance from categories per the Unit Rates Schedules.

    6. Any variance from or additions to the standard Unit Rates List shall be submitted in the same format as the attachments.

    5.2 Quantities

    A. Final quantities and distribution amongst categories and structures may vary from those indicated.

    B. Refer to Attachment 5 for estimated quantities.

    5.3 Revisions, Additions and Deletions

    A. Changes to structural and miscellaneous steel after initial issue of engineering drawings for construction are likely.

    B. Separate prices on a unit rate basis shall be provided in each category included in the Unit Rate Schedules for material additions and deletions.

    1. Material Additions

    a. Members or sections added to engineering drawings (based on unit rate weight).

    b. Additional materials for end plates, clip angles, gusset plates, stiffeners, doublers, welds, shop bolts and field bolts shall not be considered as additions for the purposes of calculating prices.

    2. Material Deletions

    Credit for members or sections deleted from engineering drawings (based on unit rate weight).

    3. The format for additions and deletions shall be the same as the Unit Rates Schedules.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 10 of 12

    C. An hourly rate for detailing of additions and deletions shall be submitted by the bidder.

    5.4 Substitutions

    Bid prices shall be prepared on the basis of materials identified by the project specifications.

    A. Bidder shall provide statement of compliance with all material requirements.

    B. Any deviation from specified materials, sections, products, practices or methods shall be clearly stated and qualified in the bid.

    6. SCHEDULE

    6.1 Milestones

    A. Refer to Attachment 4 for current schedule milestones.

    B. Engineering drawings IFC dates are planned as issuance 16 weeks prior to RTS dates. Bidder to confirm if the IFC dates can be delayed or advanced based on Fabrication and Delivery capacities.

    C. Confirm with Buyer the requirement of IFP (Mill Order).

    D. Final milestone dates may vary from those indicated.

    E. The bidder shall clearly indicate in the bid any and all implications with respect to unit rates resulting from a change, either advancement or delay, in milestone dates.

    6.2 Submittals for Bid

    A. Schedule shall be submitted in bar chart form identifying milestones and durations including as a minimum, but not necessarily limited to, the following:

    1. PO award

    2. Quantity take-offs

    3. Mill order (bidder to identify if required)

    4. Material supply

    5. Connection design

    6. Detailing

    7. Review of shop drawings by Buyer (2 weeks)

    8. Cutting

    9. Fabrication

    10. Painting

    11. Pre-assembly

    12. Preparation for shipping

    13. Shipping

    14. PO Closure

    B. Schedule shall be reviewed and re-submitted in the same format prior to award.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 11 of 12

    6.3 Available Production Capacity

    The bidder shall provide sufficient information to confirm ability and availability to perform the Work, including but not limited to the following:

    A. Shop capacity

    B. Proven sustained (over a minimum 6 months) monthly shop production capacity

    C. Production capacity available to the Buyer by month for the period from February 2013 to June 2014

    7. ATTACHMENTS

    Attachment 1 Reference Drawing List Attachment 2 Unit Pay Class Schedule Attachment 3 Unit Rate Pay Class Schedule Attachment 4 Steel Delivery Schedule Attachment 5 Structural Steel Quantity Estimate

    End of Scope of Work

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 12 of 12

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 1 of 8

    Attachment 1 Reference Drawing List

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 2 of 8

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 3 of 8

    REFERENCE DRAWING LIST

    Drawing Number Title 240K-C2-0000-15S-101 R General Standards Structural Steel General Notes 240K-C2-0000-15S-102 R General Standards Structural Steel Details Sheet 1 240K-C2-0000-15S-103 R Standards Structural Steel Stair And Handrail Details 240K-C2-0000-15S-104 R General Standards Structural Steel Ladder Details 240K-C2-0000-15S-105 R Standards Structural Steel Grating And Floor Plate Details

    C-3100-15S-111 Primary Crushing & C.O. Handling - Primary Crusher - Structural Steel - Elevation Sh 1

    C-3200-15S-111 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Elevations

    C-3200-15S-112 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Tail End Arrangement Sh 1

    C-3200-15S-113 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Tail End Arrangement Sh 2

    C-3200-15S-114 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Head End Arrangement

    C-3200-15S-115 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Misc Details Sh 1

    C-3200-15S-116 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Head End Details

    C-3200-15S-117 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Trolley Details

    C-3200-15S-118 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV0003 Counterweight Details

    C-3200-15S-201 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Base Plate Plan

    C-3200-15S-202 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2704.494 & 2703.450

    C-3200-15S-203 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2709.100 & 2709.410

    C-3200-15S-204 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2711.900

    C-3200-15S-205 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2714.100

    C-3200-15S-206 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2718.300

    C-3200-15S-207 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2722.420

    C-3200-15S-208 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TO Rail 2724.500

    C-3200-15S-209 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2727.230

    C-3200-15S-210 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Plan @ TOS EL 2733.500

    C-3200-15S-211 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Truss Plan @ TOS EL 2733.500

    C-3200-15S-212 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Truss 'A' & 'B'

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 4 of 8

    Drawing Number Title

    C-3200-15S-213 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Truss 'C', 'D', 'E' & Sway Frame 'F' & 'G'

    C-3200-15S-214 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Feeder Bin Spile Bar Pull Out Beams

    C-3200-15S-216 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline 'A'

    C-3200-15S-217 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline 'B'

    C-3200-15S-218 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline 'C' & 'D'

    C-3200-15S-219 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '8'

    C-3200-15S-220 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '9'

    C-3200-15S-221 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '10'

    C-3200-15S-222 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '11'

    C-3200-15S-223 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '12'

    C-3200-15S-224 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '13'

    C-3200-15S-225 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Elevation @ Bayline '14'

    C-3200-15S-226 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Coarse Ore Screen Frame Plans

    C-3200-15S-227 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Coarse Ore Screen Frame Sections

    C-3200-15S-228 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Bent Elevations @ Bayline '17'

    C-3200-15S-231 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Bin Wall Arrangement

    C-3200-15S-232 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Bin Wall Arrangement

    C-3200-15S-233 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Bin Wall Arrangement

    C-3200-15S-234 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Bin Plan @ EL 2732.350

    C-3200-15S-235 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Bin Plan @ EL 2727.230 & 2724.980

    C-3200-15S-241 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Stair Tower 'A' - Plans

    C-3200-15S-242 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Stair Tower 'A' - Sections

    C-3200-15S-244 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Stair Tower 'B' - Plans

    C-3200-15S-245 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Stair Tower 'B' - Sections

    C-3200-15S-246 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Misc Details Sh 1

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 5 of 8

    Drawing Number Title

    C-3200-15S-247 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Misc Details Sh 2

    C-3200-15S-248 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Girt Details

    C-3200-15S-249 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Misc Details Sh 3

    C-3200-15S-251 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV004 - Elevations

    C-3200-15S-252 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV004 Head End Arrangement

    C-3200-15S-253 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Truss CV-004-A/B Details

    C-3200-15S-254 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Truss CV-004-C/D Details

    C-3200-15S-255 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV004 - Tail End Arrangement

    C-3200-15S-256 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - Tail End Details CONV CV-004

    C-3200-15S-261 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV003/004/005 Transfer Plans Sh 1

    C-3200-15S-262 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV003/004/005 Transfer Plans Sh 2

    C-3200-15S-263 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV003/004/005 Transfer Elevations Sh 1

    C-3200-15S-271 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel Plan & Details - CV005 Arrangement

    C-3200-15S-272 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV-005 Details

    C-3200-15S-281 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV-007 Arrangement

    C-3200-15S-282 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV-007 Details

    C-3200-15S-287 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV-006/007/008/011 Transfer Plans Sh 2

    C-3200-15S-288 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV-006/007/008/011 Transfer Elevations Sh 1

    C-3200-15S-289 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV-006/007/008/011 Transfer Elevations Sh 2

    C-3200-15S-318 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Crane Rail Plan @ TOS EL 2720.604

    C-3200-15S-322 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Roof Plan

    C-3200-15S-331 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Elevation on Line 'E'

    C-3200-15S-332 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Elevation on Line 'F'

    C-3200-15S-335 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Elevation on Line 1,2,3,4,5 & 6

    C-3200-15S-336 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Elevation on Line 7, 7.2, 7.3, & 8

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 6 of 8

    Drawing Number Title

    C-3200-15S-341 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Girt Elevations Sh 1

    C-3200-15S-344 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Girt Elevations Sh 3

    C-3200-15S-355 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Bin Wall Elevations

    C-3200-15S-356 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Bin Elevations & Details Sh 1

    C-3200-15S-357 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Bin Elevations & Details Sh 2

    C-3200-15S-358 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Bin Elevations & Details Sh 3

    C-3200-15S-359 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Bin Elevations & Details Sh 4

    C-3200-15S-361 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Truss Details

    C-3200-15S-362 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Truss Details

    C-3200-15S-367 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - Sections & Details Sh 3

    C-3200-15S-391 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 Elevations

    C-3200-15S-392 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - Tail End Arrangement

    C-3200-15S-393 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - Take up Tower Sh 1

    C-3200-15S-394 Primary Crushing & C.O. Handling - Coarse Ore Conveying - Structural Steel - CV010 Take up Tower Sh 2

    C-3200-15S-395 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - Take up Tower Sh 3

    C-3200-15S-396 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - Head End Arrangement

    C-3200-15S-397 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - Head End Details

    C-3200-15S-398 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - ''Truss - A''

    C-3200-15S-399 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - ''Truss - B''

    C-3200-15S-400 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - ''Truss - A'' Details

    C-3200-15S-401 Secondary & Tertiary Crushing - Tertiary Crushing - Structural Steel - CV010 - ''Truss - B'' Details

    C-3200-15S-402 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV010 Counterweight Details

    C-3200-15S-410 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV014 Elevations

    C-3200-15S-411 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV014 Tail End Arrangement

    C-3200-15S-412 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV014 Tail End Arrangement Sh 2

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 7 of 8

    Drawing Number Title

    C-3200-15S-413 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV014 - "Truss CV-014-A"

    C-3200-15S-414 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV014 - "Truss CV-014-B"

    C-3200-15S-415 Secondary & Tertiary Crushing - Coarse Ore Reclaim - Structural Steel - CV014 - "Truss CV-014-C"

    C-3200-15S-430 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 Elevations

    C-3200-15S-431 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 Tail End Arrangement

    C-3200-15S-432 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 Tail End Details

    C-3200-15S-433 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 Take up Tower Sh 1

    C-3200-15S-434 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 Take up Tower Sh 2

    C-3200-15S-435 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 "Truss CV008-A"

    C-3200-15S-436 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 "Truss CV008-B"

    C-3200-15S-437 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 "Truss CV008-C"

    C-3200-15S-438 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 "Truss CV008-D"

    C-3200-15S-439 Secondary & Tertiary Crushing - Secondary Crushing - Structural Steel - CV008 Truss Sections & Details Sh 1

    C-3300-15S-001 Grinding - General - Structural Steel - Base Plate Plan C-3300-15S-002 Grinding - General - Structural Steel - Base Plate Details C-3300-15S-011 Grinding - General - Structural Steel - Roof Framing Plan Sh 1 C-3300-15S-012 Grinding - General - Structural Steel - Roof Framing Plan Sh 2 C-3300-15S-014 Grinding - General - Structural Steel - Crane Girder Layout C-3300-15S-022 Grinding - General - Structural Steel - Elevations on Gridline B C-3300-15S-023 Grinding - General - Structural Steel - Elevations on Gridline C C-3300-15S-024 Grinding - General - Structural Steel - Elevations on Gridline D C-3300-15S-025 Grinding - General - Structural Steel - Elevations on Gridline E C-3300-15S-026 Grinding - General - Structural Steel - Elevations on Gridline F C-3300-15S-027 Grinding - General - Structural Steel - Elevations on Gridline G C-3300-15S-028 Grinding - General - Structural Steel - Elevations on Gridline H C-3300-15S-030 Grinding - General - Structural Steel - Elevations on Gridline K C-3300-15S-031 Grinding - General - Structural Steel - Elevations on Gridline L C-3300-15S-032 Grinding - General - Structural Steel - Elevations on Gridline 2 C-3300-15S-033 Grinding - General - Structural Steel - Elevations on Gridline 3 C-3300-15S-035 Grinding - General - Structural Steel - Elevations on Gridline 8 C-3300-15S-036 Grinding - General - Structural Steel - Elevations on Gridline 10 C-3300-15S-039 Grinding - General - Structural Steel - Miscellaneous Details Sh 2 C-3300-15S-041 Grinding - General - Structural Steel - Connections Details Sh 1 C-3300-15S-046 Grinding - General - Structural Steel - Column Splice Details C-3300-15S-056 Grinding - General - Structural Steel - Crane Girder Details Sh 1 C-3300-15S-057 Grinding - General - Structural Steel - Girder Splice Details C-3300-15S-059 Grinding - General - Structural Steel - Crane Rail, Stop, & Clip Details

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 1

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 8 of 8

    Drawing Number Title C-3500-15S-201 Moly Plant - Flotation - Structural Steel - Base Plate Plan C-3500-15S-202 Moly Plant - Flotation - Structural Steel - Base Plates & Col. Splice Details C-3500-15S-203 Moly Plant - Flotation - Structural Steel - Roof Steel Bottom Chord Plan C-3500-15S-204 Moly Plant - Flotation - Structural Steel - Roof Steel Top Chord Plan C-3500-15S-205 Moly Plant - Flotation - Structural Steel - Elevations @ Grid Line A C-3500-15S-206 Moly Plant - Flotation - Structural Steel - Elevations @ Grid Line F C-3600-15S-211 Concentrate Dewatering Building - Structural Steel - Filter Floor - Plan C-3600-15S-212 Concentrate Dewatering Building - Structural Steel - Filter Floor - Details Sh 1 C-3600-15S-213 Concentrate Dewatering Building - Structural Steel - Filter Floor - Details Sh 2 C-3600-15S-214 Concentrate Dewatering Building - Structural Steel - Filter Floor - Details Sh 3

    C-3600-15S-221 Concentrate Dewatering Building - Loadout Filter Building - Elevated Slab Details

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 1 of 16

    Attachment 2 Unit Pay Class Schedule

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 2 of 16

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 3 of 16

    Item Unit of Measure

    Pay Class Description

    FABRICATION The line items below are for Seller's provision of all fabricated material,

    miscellaneous material, in accordance with the contract documents, project specifications/standard drawings, and design drawings. All unit prices are inclusive of costs for engineering, design, detailing, inspection, material, labor, paint, inspecting, tagging, crating, handling, and loading. Steel grade is either A992 or A36 per project specifications, unless noted otherwise. All steel is painted as per project specifications unless noted otherwise Seller shall identify on the shop fabrication drawings the pay class of each piece mark.

    CLASS 1 LIGHT Structural steel, shop fabricated from rolled section or equivalent weights 0 to

    30 kg/m, including but not limited to items listed in the definition of Pay Class 4, as well as brackets, access platforms, pipe and electrical cable supports, equipment and conduit supports. This definition applies to line item 1.

    1 Tonne CLASS 1 LIGHT STEEL

    CLASS 2 MEDIUM

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 31 kg/m, up to and including 60 kg/m, including but not limited to items listed under the definition of Pay Class 4. This definition applies to line item 2.

    2 Tonne CLASS 2 MEDIUM STEEL

    CLASS 3 HEAVY

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 61 kg/m, up to and including 90 kg/m, including but not limited to items listed under the definition of Pay Class 4. This definition applies to line item 3.

    3 Tonne CLASS 3 HEAVY

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 4 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 4 X HEAVY

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 91 kg/m, up to and including 180 kg/m, including but not limited to columns, beams, frames, bracing with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes, and clips as per applicable ASTM, excluding Field Bolts. Applies to line item 4.

    4 Tonne CLASS 4 X HEAVY STEEL

    CLASS 5 XX HEAVY

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 181 kg/m, and up to 360 kg/m including but not limited to, columns, beams, frames, bracing with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes, and clips as per applicable ASTM, excluding Field Bolts. Applies to line item 5.

    5 Tonne CLASS 5 XX HEAVY STEEL

    CLASS 6 XXX HEAVY

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 361 kg/m including but not limited to, columns, beams, frames, bracing, framing, with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes, and clips as per and clips as per applicable ASTM, excluding Field Bolts. Applies to line item 6.

    6 Tonne CLASS 6 XXX HEAVY STEEL

    CLASS 7 JUMBO SHAPE OVER 642 kg/m Structural steel, shop fabricated from rolled jumbo sections or equivalent weights

    greater than 642 kg/m, including but not limited to columns, beams, frames, bracings with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes, clips as per applicable ASTM, excluding field bolts. Applies to line item 7.

    7 Tonne CLASS 7 JUMBO SHAPES OVER 642 kg/m

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 5 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS E4 BUILT-UP SECTIONS

    Shop fabricated from plates as per applicable ASTM, including but not limited to shop attached stiffeners, clips, gussets, plates and rolled shapes. This definition applies to line item E4.

    E4 Tonne CLASS E4 BUILT-UP SECTIONS

    CLASS 8 MONORAIL

    Structural steel, shop fabricated from section including but not limited to beams, with shop attached appurtenances, base plates, connection plates, stiffeners, rolled shapes, and clips as per applicable ASTM, excluding field bolts. This definition applies to line item 8.

    8 Tonne CLASS 8 MONORAIL CLASS 9 SHOP BUILT ROOF TRUSS Structural steel, shop fabricated from rolled section including but not limited to items

    listed in the definition of pay class 1 through 4. This definition applies to Line Item 9.

    9 Tonne CLASS 9 SHOP BUILT ROOF TRUSS CLASS 12 PLATEWORKS, BINS & HOPPERS Structural Steel, shop fabricated from sections and plates including but not limited to

    items listed in the definition of Pay Class A to E as well as plates, stiffeners, hoppers, bin walls and bottoms, excluding columns, beams, and braces supporting the bins which are included by Class A to E. This definition applies to item 12a- 12d.

    12a Tonne CLASS 12 a PLATEWORKS, BINS & HOPPERS, 5/16INCH THICK , 7.9MM 12b Tonne CLASS 12 b PLATEWORKS, BINS & HOPPERS, 3/8INCH THICK , 9.5MM 12c Tonne CLASS 12 c PLATEWORKS, BINS & HOPPERS, 1/2INCH THICK , 12.7MM 12d Tonne CLASS 12 d PLATEWORKS, BINS & HOPPERS, 5/8INCH THICK , 15.9MM

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 6 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 13, CRANE RAIL W/SPLICES

    Crane rails, as per ASTM A1 or A759 as applicable, including joint bars and Bolts. This definition applies to line item 13a-13g.

    13a Tonne CLASS 13-a 40 lbs/yd RAIL

    13b Tonne CLASS 13-b 60 lbs/yd RAIL

    13c Tonne CLASS 13-c 80 lbs/yd RAIL

    13d Tonne CLASS 13-d 104 lbs/yd RAIL

    13e Tonne CLASS 13-e 135 lbs/yd RAIL

    13f Tonne CLASS 13-f 171 lbs/yd RAIL

    13g Tonne CLASS 13-g 175 lbs/yd RAIL

    CLASS K1, COUNTER WT FRAME

    Structural steel, shop fabricated from rolled section 0 kg/m up to and including 30 kg/m or equivalent weights in counter wt frames. This definition applies to line item K1.

    K1 Tonne CLASS K1, COUNTER WT FRAME

    CLASS K2, COUNTER WT FRAME Structural steel, shop fabricated from rolled section 31 kg/m up to and including 60

    kg/m or equivalent weights in counter wt frames. This definition applies to line item K2.

    K2 Tonne CLASS K2, COUNTER WT FRAME

    CLASS K3, COUNTER WT FRAME Structural steel, shop fabricated from rolled section 61 kg/m up to and including 90

    kg/m or equivalent weights in counter wt frames. This definition applies to line item K3.

    K3 Tonne CLASS K3, COUNTER WT FRAME

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 7 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS K4, COUNTER WT FRAME ASTM A36 Plate Plain Material

    K4 Tonne CLASS K4, COUNTER WT FRAME CLASS H1 GIRTS LIGHT WEIGHT

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 0 kg/m, up to and including 30 kg/m with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes and clips per applicable ASTM excluding field bolt. This definition applies to line item H1.

    H1 Tonne CLASS H1 GIRTS LIGHT WEIGHT

    CLASS H2 GIRTS MEDIUM WEIGHT

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 31 kg/m, up to and including 60 kg/m with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes and clips per applicable ASTM excluding field bolt. This definition applies to line item H2.

    H2 Tonne CLASS H2 GIRTS MEDIUM WEIGHT

    CLASS H3 GIRTS HEAVY WEIGHT

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 61 kg/m, up to and including 90 kg/m with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes and clips per applicable ASTM excluding field bolt. This definition applies to line item H3.

    H3 Tonne CLASS H3 GIRTS HEAVY WEIGHT

    CLASS J1 PURLINS LIGHT WEIGHT

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 0 kg/m, up to and including 30 kg/m with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes and clips per applicable ASTM excluding field bolt. This definition applies to line item J1.

    J1 Tonne CLASS J1 PURLINS LIGHT WEIGHT

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 8 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS J2 PURLINS MEDIUM WEIGHT

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 31 kg/m, up to and including 60 kg/m with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes and clips per applicable ASTM excluding field bolt. This definition applies to line item J2.

    J2 Tonne CLASS J2 PURLINS MEDIUM WEIGHT

    CLASS J3 PURLINS HEAVY WEIGHT

    Structural steel, shop fabricated from rolled section or equivalent weights greater than 61 kg/m, up to and including 90 kg/m with shop attached appurtenances, base plates, plates, stiffeners, rolled shapes and clips per applicable ASTM excluding field bolt. This definition applies to line item J3

    J3 Tonne CLASS J3 PURLINS HEAVY WEIGHT

    14 CLASS 14 crane rail (Gantrex Weldable) clips crane tie down clamps and bolts, nuts and washers. This definition applies to line items 14a-14g.

    14a EA CLASS 14a WELDLOK 10 14b EA CLASS 14b WELDLOK 15

    14c EA CLASS 14c WELDLOK 18

    14d EA CLASS 14d WELDLOK 20

    14e EA CLASS 14e WELDLOK 24

    14f EA CLASS 14f WELDLOK 32

    14g EA CLASS 14g WELDLOK 43

    CLASS 15 STAIRS C/W 2 HANDRAILS

    Structural steel, shop fabricated per standard drawing, stair treads to be shop attached. This definition applies to line item 15.

    15 Tonne CLASS 15 STAIRS C/W 2 HANDRAILS

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 9 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 15 STAIR TREADS

    Shop fabricated, and marked in accordance with project specifications. All welded steel serrated grating 278 mm x 762 mm with 32 mm x 5 mm bearing bars, including checkered nosing and side carrier plates with bolting holes, A307 bolts as required with nuts and washers. Carrier plates to be in accordance with NAAM, (National Association of Architectural Metals). Treads to be shop bolted to stair stringers. This definition applies to line Item 15a, 15g.

    15a EA CLASS 15a - STAIR TREADS

    CLASS 16 FLOOR BAR GRATING

    Welded , serrated steel bar grating to ASTM A569 with 32 mm x 5 mm bearing bars, c/w banding at all openings. Grating to be connected to steel with removable saddle clamps. Clamps to be included with 5% surplus. This definition refers to line items 16, 16g and 16gc.

    16 Sq. m CLASS 16 BAR GRATING 32 mm DEEP

    16gc ea CLASS 16gc GRATING CLAMPS, HILTI DIX FASTENERS

    16s Sq. m CLASS 16s Bar GRATING 32mm DEEP SERRATED

    16ssc ea CLASS 16ssc GRATING CLAMPS, STAINLESS G-CLAMPS CLASS 17a HEAVY DUTY 51 mm DEEP GRATING

    Welded , serrated steel bar grating to ASTM A569 with 51 mm x 6 mm bearing bars, c/w banding at all openings. Grating to be connected to steel with removable saddle clamps. Clamps to be included with 5% surplus. This definition refers to line items 17.

    17a Sq. m CLASS 17 HEAVY DUTY 51 mm DEEP GRATING

    17b HEAVY DUTY 76 mm DEEP GRATING 76 mm x 6 mm Bearing Bars

    17c HEAVY DUTY 101 mm DEEP GRATINGS 101 mm x 6 mm Bearing Bars CLASS 18 ROOF DECKING GALVANIZED, 22 Ga, 38 mm DEEP

    18 Sq. m CLASS 18 ROOF DECKING GALVANIZED, 22 Ga, 38 mm DEEP

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 10 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 19 FLOOR DECKING GALVANIZED, 20 Ga, 38 mm DEEP

    Steel deck plate to ASTM A653 Grade A. 38 mm deep with ribs at 150 mm C/C and a minimum thickness of 0.9 mm. Minimum properties Ix=275000 mm4/m and Sx=12000 mm3/m. This definition refers to line items 19.

    19 Sq. m CLASS 19 FLOOR DECKING GALVANIZED , 20 Ga, 38 mm DEEP

    CLASS 20 FLOOR DECKING GALVANIZED, 20 Ga, 76 mm DEEP

    Steel deck plate to ASTM A653 Grade A. 76 mm deep with ribs at 200 mm C/C and a minimum thickness of 0.9 mm. Minimum properties Ix=1060000 mm4/m and Sx=28500 mm3/m. This definition refers to line items 20.

    20a Sq. m CLASS 20a FLOOR DECKING GALVANIZED , 20 Ga, 76 mm DEEP

    20b Sq. m CLASS 20b FLOOR DECKING GALVANIZED, 18 Ga 76 mm DEEP

    CLASS 21 STEEL DECK PLATE

    Shop fabricated, 12 gauge shop welded to trusses, line item 21.

    21 Sq. m CLASS 21 STEEL DECK PLATE (SHOP WELD TO TRUSSES)

    CLASS 22 CHECKER PLATE

    ASTM A786 6 mm raise pattern, shop fabricated flat or bent, c/w banding at all openings. To be field welded unless noted to supporting steel including but not limited to opening closures, seals, lifting eyes, and handles, and removable covers with appurtenances. Provide 14 mm diameter holes per sq. m. This definition applies to line item 22.

    22 Sq. m CLASS 22 CHECKER PLATE

    CLASS 23 GRIP STRUT WALKWAY

    762 mm wide 11 gauge. Shop fabricated preformed, hot dip galvanized, ASTM A525, G-90, 762 mm wide, 11 gauge, as manufactured by Fisher & Ludlow (ISG safety GRIP walkway. This definition refers to line item 23.

    23 Lin. m CLASS 23 GRIP STRUT. WALKWAY

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 11 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 25 HANDRAIL C/W KICKPLATE

    Shop fabricated, with bar kickplate, 102 mm x 6 mm, 2 rail fabricated from 38 mm dia. STD ASTM A53 Type E or S smooth pipe, including but not limited to horizontal bar rails, vertical posts and all related items, as per Fluor standard drawing line item 25.

    25 Tonne CLASS 25 HANDRAIL C/W KICK PLATE

    CLASS 26 LADDERS WITHOUT CAGES

    Shop fabricated, line item 26.

    26 Tonne CLASS 26 LADDER WITHOUT CAGE

    CLASS 27 LADDERS WITH CAGES

    Shop fabricated, line item 27.

    27 Tonne CLASS 27 LADDER WITH CAGE

    CLASS 28 SAFETY GATES Shop fabricated, self closing for front or side entry ladder, with supporting angle

    posts attachments, and appurtenances, per standard drawing 240K-C2-0000-15S-103. This definition applies to the item 28.

    28 EA CLASS 28 SAFETY GATE FIELD BOLTS, CLASSES 29a THROUGH 30d

    29a through

    30d

    Tonne Field bolts Classes 29a through 30d shall be provided as required as indicated in the project specifications. These are not to be included with other classes of structural steel. All bolts, nuts, and washers are to be packaged and tagged. Unit prices for all bolts are per type, by weight, independent of size.

    CLASS 29a BOLTS, NUTS, & WASHERS ASTM A307

    Bolts, nuts and washers, unfinished, in accordance with ASTM A307, Class C, complete, including standard washers. Each container is to be clearly marked "ASTM A307" for identification.

    29a Tonne CLASS 29a BOLTS, NUTS & WASHERS ASTM A307

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 12 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 29b >2 DIA A307 ANCHORS BOLTS 2 dia and greater A307 anchor bolts c/w 2 HEX nuts and one flat washer as per

    Fluor Standard Drawing 240K-C2-0000-15R-102.

    29b Tonne CLASS 29b >2 DIA A307 ANCHOR BOLTS

    CLASS 29c SAG RODS Rod c/w 2- HEX Nut and 2- Dia Flat Washers. This definition

    applies to item 29c.

    29c Tonne CLASS 29c SAG RODS GALVANIZED

    CLASS 30a BOLTS, NUTS & WASHERS ASTM A325

    Bolts, nuts and washers, high strength, carbon steel, in accordance with ASTM A325 per project specification. Each container is to be clearly marked, "ASTM A325" for identification.

    30 Tonne CLASS 30a BOLTS, NUTS & WASHERS ASTM A325

    CLASS 30b BOLTS NUTS AND WASHERS ASTM F1852 Bolts, nuts and washers unfinished in accordance with ASTM F1852 per project

    specification. Each container is to be clearly marked ASTM F1852 for identification.

    30b Tonne CLASS 30b BOLTS NUTS AND WASHERS ASTM F1852

    CLASS 30c BOLTS NUTS AND WASHERS ASTM A490 Bolts, nuts and washers, high strength, unfinished in accordance with ASTM A490

    per project specification. Each container to be clearly marked ASTM A490 for identification.

    30c Tonne CLASS 30c BOLTS NUTS AND WASHERS ASTM A490

    CLASS 30d BOLTS NUTS AND WASHERS ASTM F2280 Bolts, nuts, and washers, high strength, unfinished in accordance with ASTM F2280

    per project specification. Each container is to be clearly marked ASTM F2280 for identification.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 13 of 16

    Item Unit of Measure

    Pay Class Description

    30d Tonne CLASS 30d BOLTS NUTS AND WASHERS ASTM F2280

    CLASS 31 STAINLESS STEEL BOLTS, NUTS AND WASHERS

    Bolts, nuts and washers, unfinished, in accordance with ASTM 316 or 304 as applicable, complete, including standard washers. Each container is to be clearly marked "ASTM 316" or "ASTM 304" for identification.

    31 Tonne CLASS 31 STAINLESS STEEL BOLTS AND WASHERS CLASS 32 CONVEYOR SLIDING CONNECTION ASSEMBLY

    Conveyor sliding connection assembly as per Fluor standard drawing. Provide price per unit. This definition applies to item 32.

    32 EA CLASS 32 CONVEYOR SLIDING CONNECTION ASSEMBLY

    CLASS 33 CONVEYOR FIXED CONNECTION ASSEMBLY Conveyor fixed connection assembly as per Fluor standard drawing. Provide price

    per unit. This definition applies to Item 33.

    33 EA CLASS 33 CONVEYOR FIXED CONNECTION ASSEMBLY CLASS F1 LIGHT STEEL CONVEYOR TRUSSES Structural steel, shop fabricated from rolled section or equivalent weights 0 to 30

    kg/m, including but not limited to items listed in the definition of Pay Class 4, as well as brackets, access platforms, pipe and electrical code cable supports, equipment and conduit supports. This definition applies to line item F1.

    F1 Tonne CLASS F1 LIGHT STEEL CONVEYOR TRUSSES

    CLASS F2 MEDIUM STEEL CONVEYOR TRUSSES Structural steel, shop fabricated from rolled section or equivalent weights greater

    than 31 kg/m, up to and including 60 kg/m, including but not limited to items listed under the definition of Pay Class. This definition applies to line item F2.

    F2 Tonne CLASS F2 MEDIUM STEEL CONVEYOR TRUSSES

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 14 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS F3 HEAVY STEEL CONVEYOR TRUSSES Structural steel, shop fabricated from rolled section or equivalent weights greater

    than 61 kg/m, up to and including 90 kg/m, including but not limited to items listed under the definition of Pay Class. This definition applies to line item F3.

    F3 Tonne CLASS F3 HEAVY STEEL CONVEYOR TRUSSES

    CLASS G1 LIGHT FEEL OVERLAND CONVEYOR TABLES AND SUPPORTS Structural steel, shop fabricated from rolled section or equivalent weights 0 to 30

    kg/m, including but not limited to items listed in the definition of Pay Class 4, as well as brackets, access platforms, pipe and electrical cable supports, equipment and conduit supports. This definition applies to line item G1.

    G1 Tonne CLASS G1 LIGHT STEEL OVERLAND CONVEYOR TABLES AND SUPPORTS

    GLASS G2 MEDIUM STEEL OVERLAND CONVEYOR TABLES AND SUPPORTS Structural steel, shop fabricated from rolled section or equivalent weights greater

    than 31 kg/m, up to and including 60 kg/m, including but not limited to items listed under the definition of Pay Class. This definition applies to line item G2.

    G2 Tonne CLASS G2 MEDIUM STEEL OVERLAND CONVEYOR TABLES AND SUPPORTS

    CLASS 34- COMBINED SECTIONS

    Not applicable.

    34 Tonne CLASS 34 COMBINED SECTIONS

    CLASS 37a and 37b SHIM PLATES

    As per ASTM A36.

    37a Tonne CLASS 37a - IDLER SHIM PLATES

    37b Tonne CLASS 37b - COMMON SHIM PLATES

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 15 of 16

    Item Unit of Measure

    Pay Class Description

    CLASS 38a PRIMER PAINT

    For touch-up at the job site, in addition to that required by project specification primer paint. This definition applies to line items 38a.

    38 Liter CLASS 38a PRIMER PAINT

    CLASS 38b TOP COAT PAINT

    For touch-up at the job site, in addition to that required by project specification top coat paint. This definition applies to line items 38b.

    38 Liter CLASS 38b TOP COAT PAINT

    CLASSES 39 THRU 42 SHOP TESTING, is defined as additional work performed as a result of Buyer's

    engineering direction over and above applicable AWS and project specifications. All charges must be properly supported. This definition applies to line items 39 to 42.

    39 Lin. m MAGNETIC PARTICLE TESTING

    40 Lin. m ULTRASONIC TESTING, (UT), GROOVE WELDS

    41 Sq. m ULTRASONIC TESTING, (UT), SURFACE SCAN

    42 EA RADIOGRAPHIC TESTING, PER FILM

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 2

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    UNIT PAY CLASS SCHEDULE

    This schedule of pay classes is valid ONLY for unit rate PO/Contracts and for additions/deletions to scope of lump sum PO/Contracts

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 16 of 16

    Item Unit of Measure

    Pay Class Description

    CLASSES 43 THRU 46 SHOP REWORK - Labor for shop rework shall be at the unit rates listed in line items

    43, 44 and shall apply to all contract steel pay classes. Material for shop rework shall be chargeable at the unit prices in the respective pay classes for fabrication. Invoices for shop rework shall be submitted separately by release and shall include supporting documentation, to include reasons for rework, records of Buyer's directives causing such rework, time cards, status of work at time of receipt of change directive, and pertinent drawings.

    SHOP REWORK is defined as additional work performed in the Seller's shop required as a result of revisions at Buyer's direction, to completed or partially completed work. Unit prices for shop rework include all overhead and supervision required to revise completed or partially completed fabrication.

    43 HR SHOP REWORK - FABRICATION

    44 HR SHOP REWORK - PAINTING (INCLUDING SURFACE PREPARATION)

    45 HR DETAILING AND ENGINEERING

    46 HR SITE REPRESENTATIVE

    CLASS 47 SHEAR STUDS FOR FIELD WELDING

    47 EA CLASS 47 SHEAR STUDS FOR FIELD WELDING

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 3

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 1 of 6

    Attachment 3 - Unit Rate Pay Class Schedule

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 3

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 2 of 6

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 3

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 3 of 6

    Unit Rate Pay Class Schedule

    The following table outlines the unit rate pay classes used during the bid process as well as invoicing for the structural steel contract. A complete detailed description and/or outline will also be included in all RFQs and structural steel contracts.

    Class Description Criteria Units Structural Steel (Include Painting Where Required) BEAMS

    A1 Light weight 0 to 30 kg/m metric ton A2 Medium Weight 31 to 60 kg/m metric ton A3 Heavy Weight 61 to 90 kg/m metric ton A4 X Heavy Weight 91 to 180 kg/m metric ton A5 XX Heavy Weight 181 to 360 kg/m metric ton A6 XXX Heavy Weight over 361 kg/m (except Jumbos) metric ton A7 Jumbo Shape over 642 kg/m metric ton

    COLUMNS B1 Light weight 0 to 30 kg/m metric ton B2 Medium Weight 31 to 60 kg/m metric ton B3 Heavy Weight 61 to 90 kg/m metric ton B4 X Heavy Weight 91 to 180 kg/m metric ton B5 XX Heavy Weight 181 to 360 kg/m metric ton B6 XXX Heavy Weight over 361 kg/m (except Jumbos) metric ton B7 Jumbo Shape over 642 kg/m metric ton

    VERTICAL BRACING C1 Light weight 0 to 30 kg/m metric ton C2 Medium Weight 31 to 60 kg/m metric ton C3 Heavy Weight 61 to 90 kg/m metric ton C4 X Heavy Weight 91 to 180 kg/m metric ton C5 XX Heavy Weight over 181 kg/m metric ton

    HORIZONTAL BRACING D1 Light weight 0 to 30 kg/m metric ton D2 Medium Weight 31 to 60 kg/m metric ton D3 Heavy Weight 61 to 90 kg/m metric ton D4 X Heavy Weight 91 to 180 kg/m metric ton D5 XX Heavy Weight over 181 kg/m metric ton

    3 PLATE BEAMS AND COLUMNS E4 X Heavy Weight 91 to 180 kg/m metric ton

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 3

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 4 of 6

    Class Description Criteria Units E5 XX Heavy Weight 181 to 360 kg/m metric ton E6 XXX Heavy Weight over 361 kg/m (except Jumbos) metric ton E7 Jumbo Shape over 642 kg/m metric ton

    CONVEYOR TRUSSES F1 Light weight 0 to 30 kg/m metric ton F2 Medium Weight 31 to 60 kg/m metric ton F3 Heavy Weight over 90 kg/m metric ton

    OVERLAND CONVEYOR TABLES & SUPPORTS G1 Light weight 0 to 30 kg/m metric ton G2 Medium Weight over 60 kg/m metric ton

    GIRTS H1 Light weight 0 to 30 kg/m metric ton H2 Medium Weight 31 to 60 kg/m metric ton H3 Heavy Weight 61 to 90 kg/m metric ton

    PURLINS J1 Light weight 0 to 30 kg/m metric ton J2 Medium Weight 31 to 60 kg/m metric ton J3 Heavy Weight 61 to 90 kg/m metric ton MISC. FRAMES < 200KG & COUNTERWEIGHT FRAMES

    K1 Light weight 0 to 30 kg/m metric ton K2 Medium Weight 31 to 60 kg/m metric ton K3 Heavy Weight 61 to 90 kg/m metric ton K4 Counterweight Plates metric ton 8 Monorail beams metric ton 9 Shop Built Roof Trusses metric ton

    12a Plateworks, Bins & Hoppers 7.9 mm (5/16 inch) metric ton 12b Plateworks, Bins & Hoppers 9.5 mm (3/8 inch) metric ton 12c Plateworks, Bins & Hoppers 12.7 mm (1/2 inch) metric ton 12d Plateworks, Bins & Hoppers 15.9 mm (5/8 inch) metric ton 13a Crane Rail w/splices (40#) metric ton 13b Crane Rail w/splices (60#) metric ton 13c Crane Rail w/splices (85#) metric ton 13d Crane Rail w/splices (104#) metric ton 13e Crane Rail w/splices (135#) metric ton 13f Crane Rail w/splices (171#) metric ton 13g Crane Rail w/splices (175#) metric ton

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 3

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 5 of 6

    Class Description Criteria Units 14a Gantrex Weldable Rail Clips Weldlok 10 each 14b Gantrex Weldable Rail Clips Weldlok 15 each 14c Gantrex Weldable Rail Clips Weldlok 18 each 14d Gantrex Weldable Rail Clips Weldlok 20 each 14e Gantrex Weldable Rail Clips Weldlok 24 each 14f Gantrex Weldable Rail Clips Weldlok 32 each 14g Gantrex Weldable Rail Clips Weldlok 43 each 15 Stairs c/w 2 handrails metric ton 15a Stair Treads 32x5 bearing bars (1.25 inch

    deep), price with one shop coat primer only, shop bolted to stringers

    each

    16 Floor Grating 32x5 bearing bars (1.25 inch deep), price with one shop coat primer only

    m2

    16s Floor Grating Serrated 32x5 bearing bars (1.25 inch deep), price with one shop coat primer only

    m2

    16gc Grating Clamps (Hilti DIX Fasteners) Not included in 16 or 16g above each 16ssc Grating Clamps (Stainless G-Clips) Not included in 16 or 16g above each 17a Heavy duty 2" deep grating (51mm deep) Price with one shop coat primer

    only m2

    17b Heavy duty 3" deep grating (76mm deep) Price with one shop coat primer only

    m2

    17c Heavy duty 4" deep grating (102mm deep) Price with one shop coat primer only

    m2

    18 Roof Decking Galvanized 38 deep x 0.76 (22 ga 1.5 inch deep)

    m2

    19 Roof/Floor Deck Galvanized 38 deep x 0.91 (20 ga 1.5 inch deep)

    m2

    20a Roof/Floor Deck Galvanized 76 deep x 0.91 (20 ga 3 inch deep)

    m2

    20b Roof/Floor Deck Galvanized 76 deep x 1.22 (18 ga 3 inch deep)

    m2

    21 Deck Plate 2.67 mm (12 ga) m2 22 Checker Plate 6.4 mm (1/4 inch) m2 23 Grip Strut Walkway 762 wide x 127 deep x 3.13

    galvanized (2.5 foot wide 11 ga) lin m

    25 Handrail c/w kickplate metric ton 26 Ladder without Cage metric ton

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 3

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 6 of 6

    Class Description Criteria Units 27 Ladder with Cage metric ton 28 Safety Gate each 29a Bolts, Nuts & washers ASTM A307 metric ton 29b Bolts, Nuts & washers(Anchor Bolt) ASTM A307 metric ton 29c Sag rods, galvanized, nuts & washers ASTM A307 metric ton 30a Bolts, Nuts & washers ASTM A325 metric ton 30b Bolts, Nuts & washers ASTM F1852 twist off metric ton 30c Bolts, Nuts & washers ASTM A490 metric ton 30d Bolts, Nuts & washers ASTM F2280 twist off metric ton 31 Stainless steel Bolts, Nuts & Washers metric ton 32 Conveyor Sliding Connection Assembly each 33 Conveyor Fixed Connection Assembly each 34 Fabreeka impact absorbing pads 100 x 100 x 50 (size to be

    confirmed) each

    37a Idler Shim Plates metric ton 37b Common Shim Plates metric ton 38a Paint Primer Touch-up paint liter 38b Paint Touch-up Paint liter 39 Magnetic Particle Testing lin m 40 Ultrasonic Testing, UT, groove welds lin m 41 Ultrasonic Testing, UT, surface scan m2 42 Radiographic Testing, per film hour 43 Shop Rework - Fabrication hour 44 Shop Rework - Painting hour 45 Shop Rework - Detailing and Engineering hour 46 Site Representative day 47 Shear Studs for Field Weld each

    Note: Connection material included in tonnages

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 4

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 1 of 4

    Attachment 4 Steel Delivery Schedule

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 4

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 2 of 4

    This page is intentionally blank.

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 4

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 3 of 4

    Structural Steel Key Fabrication Dates and Estimated Quantities

    WBS Description WBI IFP IFC RTS Tonnage 3110 Primary Crusher 1 131A01AAC2 16-Dec-13 13-Jan-14 5-May-14 59.0 3110 Primary Crusher 2 131D01AAC2 15-Sep-13 13-Oct-13 2-Feb-14 59.0 3120 Coarse Ore Conveyor 012 Drives 131C12AAC2 28-Aug-13 25-Sep-13 15-Jan-14 95.4 3120 Coarse Ore Conveyor 012 Trusses 131C12AAC4 28-Aug-13 25-Sep-13 15-Jan-14 286.2 3120 Coarse Ore Conveyor 022 Drives 131C22AAC2 17-May-13 14-Jun-13 4-Oct-13 95.4 3120 Coarse Ore Conveyor 022 Trusses 131C22AAC4 17-May-13 14-Jun-13 4-Oct-13 286.2 3210 Coarse Ore Conveyor 013 Drives 132C13AAC2 30-Jun-13 28-Jul-13 17-Nov-13 23.2 3210 Coarse Ore Conveyor 013 Trusses 132C13AAC4 30-Jun-13 28-Jul-13 17-Nov-13 69.5 3210 Coarse Ore Conveyor 023 Drives 132C23AAC2 19-Mar-13 16-Apr-13 6-Aug-13 23.2 3210 Coarse Ore Conveyor 023 Trusses 132C23AAC4 19-Mar-13 16-Apr-13 6-Aug-13 69.5 3210 Coarse Ore Reclaim Tunnel 1 132U01AAC2 23-Jan-14 20-Feb-14 12-Jun-14 10.4 3210 Coarse Ore Reclaim Tunnel 2 132U02AAC2 9-Jan-14 6-Feb-14 29-May-14 6.4 3220 Screening Conveyor 016 Drives 132C16AAC2 1-Jan-13 29-Jan-13 21-May-13 104.8 3220 Screening Conveyor 016 Trusses 132C16AAC4 1-Jan-13 29-Jan-13 21-May-13 314.3 3220 Screening Conveyor 026 Drives 132C26AAC2 1-Jan-13 29-Jan-13 21-May-13 104.8 3220 Screening Conveyor 026 Trusses 132C26AAC4 1-Jan-13 29-Jan-13 21-May-13 314.3 3230 Screening Conveyor 017 Drives 132C17AAC2 1-Jan-13 29-Jan-13 21-May-13 97.3 3230 Screening Conveyor 017 Trusses 132C17AAC4 1-Jan-13 29-Jan-13 21-May-13 291.8 3230 Screening Conveyor 018 Drives 132C18AAC2 1-Jan-13 29-Jan-13 21-May-13 311.8 3230 Screening Conveyor 027 Drives 132C27AAC2 1-Jan-13 29-Jan-13 21-May-13 97.3 3230 Screening Conveyor 027 Trusses 132C27AAC4 1-Jan-13 29-Jan-13 21-May-13 291.8 3230 Screening Conveyor 028 Drives 132C28AAC2 1-Jan-13 29-Jan-13 21-May-13 411.4 3230 Screening Conveyor 050-055 (HPGR Feed) 132C50AAC4 1-Jan-13 29-Jan-13 21-May-13 50.0 3240 Screening Conveyor 015 132C15AAC2 17-Dec-12 14-Jan-13 6-May-13 121.2 3240 Screening Conveyor 025 Drives 132C25AAC2 17-Dec-12 14-Jan-13 6-May-13 121.2 3240 Screening Conveyor 031 Drives 132C31AAC2 17-Dec-12 14-Jan-13 6-May-13 401.7 3240 Screening Conveyor 041 Drives 132C41AAC2 20-Jan-13 14-Jan-13 6-May-13 401.7 3310 Fine Ore Bin Lower Platforms 133A01AAC2 20-Jan-13 17-Feb-13 9-Jun-13 166.9 3310 Fine Ore Bin Towers and Stairs 133A01AAC4 17-Feb-13 17-Mar-13 7-Jul-13 166.9 3310 Fine Ore Bin Tripper Platforms 133A01ACC2 17-Mar-13 14-Apr-13 4-Aug-13 667.7 3310 Grinding Conveyor 019 Drives 133C19AAC2 7-Jul-13 4-Aug-13 24-Nov-13 30.1 3310 Grinding Conveyor 019 Trusses 133C19AAC4 7-Jul-13 4-Aug-13 24-Nov-13 90.2 3310 Grinding Conveyor 029 Drives 133C29AAC2 18-Dec-13 15-Jan-14 7-May-14 35.0 3310 Grinding Conveyor 029 Trusses 133C29AAC4 18-Dec-13 15-Jan-14 7-May-14 104.9 3310 Grinding Conveyor 060-065 133C60BAC2 17-Feb-13 17-Mar-13 7-Jul-13 55.6 3310 Grinding Conveyor 066-071 133C66BAC2 17-Feb-13 17-Mar-13 7-Jul-13 55.6 3410 Flotation Base Plates 234A00AAC1 14-Jun-13 12-Jul-13 1-Nov-13 14.0 3410 Flotation 234A00AAC2 14-Jun-13 12-Jul-13 1-Nov-13 265.6 3410 Flotation Crane Trusses 234A00AAC4 12-Jul-13 9-Aug-13 29-Nov-13 265.6 3410 Flotation Sampling 234A03AAC2 9-Aug-13 6-Sep-13 27-Dec-13 76.9 3410 Flotation Cell Platforms 234A03EAC2 9-Aug-13 6-Sep-13 27-Dec-13 76.9 3410 Flotation Piperacks 234A06AAC3 9-Aug-13 6-Sep-13 27-Dec-13 69.1 3420 Regrind 234B02AAC1 18-Aug-13 15-Sep-13 5-Jan-14 452.3 3420 Regrind Floors 234B02AAC2 1-Sep-13 29-Sep-13 19-Jan-14 361.8

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 4

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-Structural\240K-C2-SW-15-008_PeruvianFabrication\240K-C2-SW-15-008-C.doc Page 4 of 4

    Structural Steel Key Fabrication Dates and Estimated Quantities WBS Description WBI IFP IFC RTS Tonnage 3420 Regrind Piperacks 234B05AAC3 15-Sep-13 13-Oct-13 2-Feb-14 21.1 3430 Column Flotation 234B01AAC2 18-Aug-13 15-Sep-13 5-Jan-14 90.5 3510 Moly Plant 235D00AAC1 7-Aug-13 4-Sep-13 25-Dec-13 584.1 3510 Moly Plant Platforms/Stairs 235D00AAC2 24-Jul-13 21-Aug-13 11-Dec-13 584.1

    3510 Moly Plant / Concentrate Thickening / Filtering Piperacks 235F00AAC3 10-Jul-13 7-Aug-13 27-Nov-13 54.7

    3610 Concentrate Thickening Storage Platform 236D00AAC2 28-Oct-13 25-Nov-13 17-Mar-14 216.5

    3620 Concentrate Filter Building 236E01AAC2 10-Sep-13 8-Oct-13 28-Jan-14 367.2 3630 Concentrate Storage / Loadout 236E02AAC2 6-Feb-14 6-Mar-14 26-Jun-14 32.8

    3710 Tailing Thickening Recycle Water Chamber 237A05AAC2 25-Dec-13 22-Jan-14 14-May-14 965.6

    3710 Tailing Thickening Launder and Sampler 237A08AAC2 8-Jan-14 5-Feb-14 28-May-14 184.0

    3710 Tailing Thickening Piperack 237A09AAC2 29-Jan-14 26-Feb-14 18-Jun-14 40.4 3810 Tailing Handling System 338A00AAC2 21-Feb-13 21-Mar-13 11-Jul-13 122.6 3820 Tailing Cyclone Facility 338B00AAC2 5-Aug-13 2-Sep-13 23-Dec-13 153.7 3830 Tailing Distribution System 338D00AAC2 23-Oct-13 20-Nov-13 12-Mar-14 491.8 3840 Reclaim Water System 338E00AAC2 1-Nov-13 29-Nov-13 21-Mar-14 69.8 3850 Seepage Water System 338F00AAC2 5-Jan-14 2-Feb-14 25-May-14 13.8 3910 Reagent System Tank Platforms 239B00AAC2 10-Jun-13 8-Jul-13 28-Oct-13 3.0 3910 Reagent System Piperack 239B10AAC3 10-Jun-13 8-Jul-13 28-Oct-13 3.0 3920 Lime System Platforms 239A00AAC2 11-Sep-13 9-Oct-13 29-Jan-14 3.6 3920 Lime System Piperacks 239A03AAC3 11-Sep-13 9-Oct-13 29-Jan-14 3.6 5100 Fresh Water System 551Z00AAC2 15-Nov-12 13-Dec-12 4-Apr-13 28.3 5220 Electrical 220kV Main Substation 352B00AAC1 1-Apr-13 29-Apr-13 19-Aug-13 28.7 5230 Electrical (Mat'l Handling) Substation 352E00AAC1 1-Apr-13 29-Apr-13 19-Aug-13 28.7 5720 Truck Shop 357Z00AAC1 8-Sep-13 6-Oct-13 26-Jan-14 86.0 6220 Concentrator Site Roads 0.0 11,651.2

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW-15-008 Cerro Verde Production Unit Expansion Revision C Project No. A6CV Attachment 5

    FABRICATION OF STRUCTURAL AND MISCELLANEOUS STEEL, PERUVIAN PACKAGE SCOPE OF WORK

    W:\103_PROJ_ADMIN\109_ENG DOCS\109.2R_SW\15-STRUCTURAL\240K-C2-SW-15-008_PERUVIANFABRICATION\240K-C2-SW-15-008-C.DOC

    Attachment 5 Structural Steel Quantity Estimate

  • Sociedad Minera Cerro Verde S.A.A. Document No. 240K-C2-SW