Team x Revised Project Management Plan Project Name: Video Delivery Client Organisation: Video Game 2U Project Start Date: 10/10/11 Project Finish Date: 21/09/12 Project Manager: Belinda Love [email protected] xxxxxxxx Team: Andy Cotton [email protected] xxxxxxxx Sandy Guston [email protected] xxxxxxxx Carrin Groworld [email protected] xxxxxxxx Robin Knocks [email protected] xxxxxxxx

Upload: nen-tran-ngoc

Post on 06-Feb-2016

22 views

Category:

Documents


0 download

DESCRIPTION

Project Management

TRANSCRIPT

Page 1: 252311_1_2-pmp-2012-27

Team x Revised Project Management Plan Project Name: Video Delivery Client Organisation: Video Game 2U Project Start Date: 10/10/11 Project Finish Date: 21/09/12 Project Manager: Belinda Love [email protected] xxxxxxxx Team: Andy Cotton [email protected] xxxxxxxx Sandy Guston [email protected] xxxxxxxx Carrin Groworld [email protected] xxxxxxxx Robin Knocks [email protected] xxxxxxxx

Page 2: 252311_1_2-pmp-2012-27

Table of Contents Table of Contents ................................................................................................................................. 2

Executive Summary .......................................................................................................................... 3

1.0 Project Objectives ....................................................................................................................... 4

1.1 Approach .................................................................................................................................. 4

1.2 Roles and Responsibilities .................................................................................................... 4

2.0 Stake Holders .............................................................................................................................. 5

3.0 Scope Statement......................................................................................................................... 5

4.0 Organisational Chart .................................................................................................................. 6

5.0 Milestone Report ......................................................................................................................... 6

6.0 Work Breakdown Structure ....................................................................................................... 7

7.0 Gantt Chart .................................................................................................................................. 8

8.0 Network Diagram ........................................................................................................................ 9

9.0 Risk Management ..................................................................................................................... 11

9.1 Risk Register ......................................................................................................................... 11

9.2 Probability Impact Matrix ..................................................................................................... 18

9.3 Responsibility Assignment Matrix ...................................................................................... 18

10.0 Revised Budget....................................................................................................................... 19

10.1 Budget Summary ................................................................................................................ 19

10.2 Detailed Budget .................................................................................................................. 19

10.3 Resource Work Summary Report .................................................................................... 20

10.4 Resource Graphs ............................................................................................................... 21

11.0 Change Request From ........................................................................................................... 27

11.1 Change Request Process ................................................................................................. 28

12.0 Lessons Learned Report ....................................................................................................... 29

Page 3: 252311_1_2-pmp-2012-27

Executive Summary

This Project Management Plan has been created by 'Team Two' project group, to develop a Web-Based system for customers to rent video games, for Video Game 2U.

This system is designed for users to rent video games on a monthly basis For

example, a customer might pay a monthly fee and then be able to order several video games over the Internet, receive the games via express mail, return those games via express mail, and keep receiving additional games. The system is estimated to bring in $1million the year after completion and $2million the following two years.

The following document contains the project plan for the Video Delivery system that

includes the projects objectives, relevant stakeholders and their contact information, the projects scope statement, the work break down structure of the project, potential risks that the project may encounter and the budget that the project is going to follow. Sponsor Details: Lori White VP, Marketing 04 1001 666 123 [email protected]

Page 4: 252311_1_2-pmp-2012-27

1.0 Project Objectives Develop and produce a web based service that allows customers to rent video games. The system must include several important features, such as the main focus on sports and educational games. Payment options should not be limited to credit cards, support multiple consoles, other than just PC, to send the games via express mail and be available in multiple different languages.

1.1 Approach 1. Team 2 will gather information on task that is given and document then provide

the report for reviewing by sponsor 2. Requirements will be looked at, and appropriate documentation will be finalised

for project start 3. Budgets will be finalised before any purchasing or large payments are made 4. Major design brief will be developed and finalised, allowing room for changes 5. While software is implemented, user testing, server testing, payment system

tests and general integration tests will be performed 6. Meeting with sponsor to address the systems progress, to check the project is

on the correct path and meets sponsors standards and standards by the P.M.P are met

7. Finalisation of project before closing, last minute changes and/or testing

1.2 Roles and Responsibilities Belinda Love Project Manager [email protected]

0000111222

Sandy Guston Financial Advisor [email protected] 0000111222

Robin Knocks IT Professional [email protected] 0000111222

Andy Cotton Marketing Specialist [email protected] 0000111222

Carrin Groworld Web Master [email protected] 0000111222

Page 5: 252311_1_2-pmp-2012-27

2.0 Stake Holders Lori White Julie & ECF Team 2 ABC Corp

Organisation Video Game Delivery Educational Consulting Firm

Project Management Team

Web Application Provider

Role in Project Sponsor of project Determining user requirements

Delivering the complete package

Providing a web application for the project

Level of Interest

High Medium-Low High Medium

Level of Influence

High Medium-Low Medium Medium

Suggestions on Managing Relationship

Maintain good communication and offer update on deliverables when able

Make sure to update on how the help provided is being used

Good communication and checking in with team members on a daily basis

Open dialogue with company as application is implemented

3.0 Scope Statement Description: The Project aim and goal is to create a web-based service that allows customers to rent video games via the internet on a monthly basis. Certain and varying types of fees would apply per different game that is offered and able to order several different games at a time. Games would mainly; the main focus for game themes will be sports and educational games. Allowing access to all platforms. The games would be delivered via express mail and returned in the same fashion. The systems design will allow for international marketing, access to multiple languages and offer great user-friendly options. Highlighting the importance of a search function, able to track the delivery of the rental items as well as the referrals/advertisements and offer more than just online payment options, keeping a dynamic memory of customer rental patterns. The project is assumed to take twelve months to complete with a total budget of $500,000 with the potential to earn $1M in the first year. Characteristics and Requirements:

• Web-site must focus on games designed for education and sports • Games must be available on different platforms, not just PC • A detailed but simple searching feature with multiple options • There must be options for user input on the games featured • Language features for countries other than English • ABC Corp will be developing the Web-Based application • Julie and colleagues from the educational consulting firm will be aiding in

Page 6: 252311_1_2-pmp-2012-27

determining user requirements Project Acceptance Criteria

• A project is assumed to take 12 months to complete • The project is expected to cost $500,000 • Monthly costs are expected to be around $50,000 and increase to $60,000 the

following • The payment system must have more than one working method of payment • The method these games will be delivered, is by express mail delivery and return

4.0 Organisational Chart (TBA)

5.0 Milestone Report Prepared by: Andy Cotton Date: 24/10/11 Milestone Scheduled

Completion Date Status Responsible Issues/Comments

Finalize Project Charter

Fri 18/11/11

Incomplete

Belinda Love

Close Initiating Phase

Fri 2/12/11

Incomplete

Team 2

Sign off team contract

Fri 9/12/11

Incomplete

Team 2

Client sign off scope statement

Fri 9/12/11

Incomplete

Belinda Love

Finalize Gantt Chart

Fri 3/02/12

Incomplete

Robin Knocks

Close Planning Phase

Fri 10/02/12

Incomplete

Team 2

Resources ordered

Fri 9/03/12

Incomplete

Mary Knowls

3.3.5 Search Engine

Fri 6/04/12

Incomplete

Carrin Groworld

Close Executing Phase

Fri 20/07/12

Incomplete

Team 2

Close Project

Fri 14/09/12

Incomplete

Team 2

Page 7: 252311_1_2-pmp-2012-27

6.0 Work Breakdown Structure

Page 8: 252311_1_2-pmp-2012-27

7.0 Gantt Chart

Page 9: 252311_1_2-pmp-2012-27

8.0 Network Diagram

Page 10: 252311_1_2-pmp-2012-27
Page 11: 252311_1_2-pmp-2012-27

9.0 Risk Management 9.1 Risk Register

No. R001 Rank 1

Risk Going over the estimated budget ($500 000)

Description Real cost of the games delivery project exceeding initial budget

Category financial risk

Root Cause Inaccuracies in initial budget

Triggers cost overrun(s)

Risk Response Develop accurate budget estimates by seeking out reliable sources. Belinda to review the budget periodically & request additional funding when required

Risk Owner Belinda Love

Probability High

Impact High

Status February 2012: Software customisation to cost $100,000 over initial budget. Funding approved by senior management. At close of project: Final cost for system was $120,000 over initial budget ($20,000 over revised budget).

No. R002 Rank 2

Risk Disagreement between team members

Description There may be conflict in regards to the team's approach to completing each task

Category people risk

Root Cause Differences in expertise and work ethic amongst team members

Triggers Lack of team morale, wasted time, time overruns

Risk Response Team members to raise any issues with Belinda. Belinda to mediate any conflict and find a solution

Risk Owner Belinda Love

Probability Medium

Impact High

Status February 2012: Purchasing specialist Ryan replaced by Mary due to disagreement about suppliers

Page 12: 252311_1_2-pmp-2012-27

No. R003 Rank 3

Risk Project going overtime (over 12 months)

Description Date of closing project (21/09/12) exceeded

Category market risk

Root Cause Unrealistic / inaccurate schedule

Triggers Deadlines being missed. Starting of tasks delayed

Risk Response Develop an accurate schedule. Identify the critical path. Team to assess progress and identify schedule delays. Client to be consulted on requests for more time allocated to the project

Risk Owner Belinda Love, Team 2

Probability Medium

Impact High

Status Project completed on schedule. Functionality limited to ensure timely completion

No. R004 Rank 4

Risk Inaccurate functionality of the web application

Description The final product may contain errors that inhibit usability or render the application useless

Category technology risk

Root Cause Script errors, bugs, server crashes

Triggers User complaints

Risk Response User testing (30/04/12 - 08/06/12). Checking of errors. Back up power for server. Belinda to consult client on what downtime will result from errors present at launch

Risk Owner Carrin Groworld, Robin Knocks

Probability Medium

Impact High

Status

Page 13: 252311_1_2-pmp-2012-27

No. R005 Rank 5

Risk Achievement of the projected NPC, ROI and Payback estimates

Description Lower returns on investment than forecast

Category financial risk

Root Cause NPC, ROI and payback estimate inaccurate. Unforeseen change in global financial environment

Triggers Project missing projected forecasts. Lower investor confidence.

Risk Response Sean to report on financial performance of project on a regular basis. Belinda to consult with client to assess project performance

Risk Owner Sandy Guston

Probability Medium

Impact High

Status

No. R006 Rank 6

Risk Lack of communication between team members

Description There is a risk that communication amongst the project team is poor.

Category people risk

Root Cause Poor comm skills / lack of clear comm channel

Triggers Team members unaware of proj updates / missing meetings & milestones

Risk Response Beau to establish clear channel of communication. Team to be informed that it is each member's responsibility to ensure contact details are correct

Risk Owner Belinda Love

Probability Low

Impact High

Status Accurate team contact details provided. Good attendance to meetings

Page 14: 252311_1_2-pmp-2012-27

No. R007 Rank 7

Risk Dispute with the client

Description Dispute with Video Game Delivery may include issues involving budget, time & quality constraints

Category people risk

Root Cause Changes made to project w/o prior consent by Video Game Delivery

Triggers Lack of client confidence, wasted time, time overruns

Risk Response Client to sign off project scope statement. Lori to be kept informed on project status. Belinda to call meeting with Lori when project updates need to be discussed

Risk Owner Belinda Love

Probability Low

Impact High

Status

No. R008 Rank 8

Risk Lack of user involvement

Description Little or no consultation with end user

Category structure/process risk

Root Cause Poorly planned testing regime of the web application

Triggers Little or no user feedback

Risk Response Web application testing period 30/04/12 - 08/06/12 to be worked towards and adhered to. Feedback to be communicated to Belinda

Risk Owner Carrin Groworld, Robin Knocks

Probability Low

Impact High

Status

Page 15: 252311_1_2-pmp-2012-27

No. R009 Rank 9

Risk Lack of support from executive management

Description A risk to project failure is inadequate support from Lori and the executive management of Video Game Delivery

Category structure/process risk

Root Cause Lack of communication and/or mistrust between exec management and proj manager

Triggers Hostile communications between management. Rejected requests for funding/time extensions. Generally poor outlook for project completion

Risk Response Belinda to maintain communication with Lori (sponsor) regarding project status. Team to work in a professional manner

Risk Owner Belinda Love, Team 2

Probability Low

Impact High

Status Considerable degree of support from executive management. Additional funding approved and a follow-up project to be proposed

No. R010 Rank 10

Risk Product quality not meeting client needs

Description Video Game Delivery may be dissatisfied with the quality of the web application

Category market risk

Root Cause Quality metrics undefined

Triggers Client showing dissatisfaction with web-application at project completion

Risk Response Requirements to be signed and understood by client. Belinda to negotiate with client if further time and funds are required to meet client needs

Risk Owner Belinda Love, Team 2

Probability Low

Impact High

Status Pending response from final project presentation. It is hoped top management will be satisfied with the minimum functionality of the web application

Page 16: 252311_1_2-pmp-2012-27

No. R011 Rank 11

Risk Unforeseen risk

Description Any circumstances that could not have been foreseen (for example a natural disaster)

Category environmental risk

Root Cause Unknown

Triggers Project disruption. Compromised safety of staff

Risk Response Depending on severity, Belinda to discuss with client suitable delay period for recommencing project. All staff to be made aware of local emergency procedures.

Risk Owner Belinda Love, Team 2

Probability Low

Impact High

Status

No. R012 Rank 12

Risk Technical incompetency of the staff

Description Team members not qualified to do the technical work

Category people risk

Root Cause Hiring of staff that are not qualified for the task

Triggers Lack of professionalism. Inefficient completion of deliverables. Lower staff morale

Risk Response Project manager (Belinda) to hand picks project team. Skills required by staff to be communicated to outsourced services

Risk Owner Belinda Love

Probability Low

Impact High

Status Belinda hand-picked project team, negating this risk amongst the team

Page 17: 252311_1_2-pmp-2012-27

No. R013 Rank 13

Risk No accessibility to hardware and software at proper time

Description Scheduling conflict in regards to team member access to project resources

Category technology risk

Root Cause Miscommunication b/w team members. Schedule clashes

Triggers Conflict amongst team members

Risk Response Team members to coordinate with each other to ensure each has access to resources at the appropriate time. Belinda to mediate any conflict arising

Risk Owner Belinda Love, Team 2

Probability Low

Impact Medium

Status

No. R014 Rank 14

Risk New technology roll out over duration of project

Description With developments in games technology, new hardware may need to be marketed for

Category market risk

Root Cause Computing and games technology development

Triggers Demand for particularly new product

Risk Response Marketing specialists (Sandy & Andy) to keep Belinda appraised of any new technology announcements

Risk Owner Sandy Guston & Andy Cotton

Probability Low

Impact Low

Status

Page 18: 252311_1_2-pmp-2012-27

9.2 Probability Impact Matrix

IMPACT

Low Med High

R001 High P

RO

BA

BIL

ITY

R002 R003 R004 R005 Med

R014 R013

R006 R007 R008 R009 R010 R011

R012

Low

9.3 Responsibility Assignment Matrix

Page 19: 252311_1_2-pmp-2012-27

10.0 Revised Budget 10.1 Budget Summary The budget for the Video Game Delivery Project has been broken down into the three following areas: Hardware, Labour and consulting and outsourcing. This is a revised budget with an extra $100,000 dollars allocated to the budget. Total hardware cost: $6,475.45 Total labour cost: $249,972.45 Total consulting and outsourcing cost: $ 363,552.10 Total cost for project: $620,000.00 10.2 Detailed Budget

Hardware Budget

Amount Allocated $6,500

Purchases Quantity Description Cost

(AU$)

Cost

Type

Dell

PowerEdge

T710

1

This server will host

the application that

ABC Corporation are

producing for this

project.

2,799.00 Variable

Uninterruptible

Power Supply 1

Will maintain a suply

of power to the server 648.87 Variable

External

Information

Back up

1

Backs the servers

information up at an

external location

@$252.3 per month

3,027.58 Variable

Total Hardware costs 6,475.45

Percent of Budget 1%

We are assuming that Belinda is contracted to be paid for 1,000 hours even though he only worked 970 hours as long as he works a minimum of 960 hours.

Staff Budget

Amount Allocated $250 000

Resources Members

Name

Hourly

Rate

(AU$)

Total

Hours

Worked

(Hrs)

Cost

Type

Total Cost

(AU$)

Project

Manager

Belinda

Love $80 1,000 Fixed 80,000.00

Page 20: 252311_1_2-pmp-2012-27

Finance Sandy

Guston $57.50 522 Fixed 30,015.00

I.T.

Specialist

Robin

Knocks $60.50 780 Fixed 47,190.00

Marketer Andy

Cotton $57.25 497 Fixed 28,453.25

Web

Master

Carrin

Groworld $60 724 Fixed 43,440.00

Sales

Expert

Mary

Knowls $52.80 387 Fixed 20,433.60

Total Staff Payments $249,531.85

Percent of Budget 49.91%

Consulting and Outsourcing Budget

Amount Allocated $343,552.10

Purchase Quantity Outsourced

Company Description Cost (AU$) Cost Type

Web Based

Aplication 1

ABC

Corporation

This web based

aplication alows

consumers to

hire video

games over the

internet

265,564.10 Variable

Consultation 1

Education

Consulting

firm

This company

will provide

consultation on

user

requirements

for the web

based

application

98,428.60 Variable

Total Consulting and Outsourcing costs 363,992.70

Percent of budget 61%

Total Expenses on project $620,000.00

10.3 Resource Work Summary Report

(TBA) This Graph shows how much work (hours) was done in comparison to how many hours were available to work on the project. ABC Corporation: 421 hours Andy Cotton: 497 hours Belinda Love: 970 hours

Page 21: 252311_1_2-pmp-2012-27

Carrin Groworld: 724 hours Education Consulting Firm: 124 hours Robin Knocks: 780 hours Ryan Smith: 387 hours Sandy Guston: 522 hours We are assuming that Belinda was contracted to be paid for 1,000 hours even though he only worked 970 hours in the end she has to work a minimum of 960 hours though. 10.4 Resource Graphs

Belinda Love – Project Manager

Page 22: 252311_1_2-pmp-2012-27

Sandy Guston - Finance

Page 23: 252311_1_2-pmp-2012-27

Robin Knocks – IT Specialist

Page 24: 252311_1_2-pmp-2012-27

Andy Cotton – Marketer

Page 25: 252311_1_2-pmp-2012-27

Carrin Groworld – Web Master

Page 26: 252311_1_2-pmp-2012-27

Mary Smith – Sales Expert

Page 27: 252311_1_2-pmp-2012-27

11.0 Change Request From

Project Name: Submitted By: Date: / / (dd/mm/yyyy) Severity: Change Request Title: Change Request Number: Type of Change Request: Description of the problem:

Description of the solution to the problem:

Future impacted on the project:

Required Approval: Name Position Date Accept/Reject Signature Lon White Vice President

Project Sponsor 00/00/0000

Belinda Love Project Manager

Page 28: 252311_1_2-pmp-2012-27

11.1 Change Request Process The change request form is freely available to all team members and sponsors in the project. These are the steps that are required before a change can be added or implemented in to the project.

1. Fill in the information in the change request form. 2. Submit the change request form to your manager. 3. The change request form will be addressed in the weekly sponsor meeting. 4. If the change request form is agreed to and signed by the sponsor and all

managers. 5. Then the change will be implemented as soon as possible to minimum the

down time for the project.

Page 29: 252311_1_2-pmp-2012-27

12.0 Lessons Learned Report Project Name: Video Delivery Project Sponsor: Lori White Project Manager: Belinda Love Project Dates: 10/10/2011 – 21/09/2012 Final Budget: $620,000

Did the project meet scope, time, and cost goals?

This project met the schedule time but didn’t meet the scope or the cost goals. What was the success criteria listed in the project scope statement?

The criteria for this project were: A project is assumed to take 12 months to complete The project is expected to cost $500,000 The payment system must have more than one working method of payment The method these games will be delivered, is by express mail delivery and return

If we meet all these criteria then all the goals set for by Lori White would have been meet and the project would be a success.

Reflect on whether or not you met the project success criteria.

The project criteria that are listed above was not all met. The criteria’s that was meted was:

That the project was produced in the schedule time, which was 12 months. That the program has more than one payment method.

The criteria’s that wasn’t met was: • That the project didn’t cost $500,000 but instead the cost of the project was

increase two times first by $100,000, then by $20,000 making the total cost of the project $620,000.

• That the monthly cost was more than $50,000. In terms of managing the project, what were the main lessons your team learned?

The main lesson that was learned during this project was: 8. How to use Microsoft project and how easy it is to see the timeline of the project. 9. That using the project management tool help simpler and improve the making of

a project management plan. 10. The challenge of getting everyone in the team all together at the same time. 11. Learned some of the principles and technique on how to create a project

management plan and how working with others makes a more in-depth plan. Describe one example of what went right on this project.

That the team didn’t waste time discussing who would do which deliverables for the project management plan, because we didn’t argue over the deliverable we just choose another one to do if someone else want to do the same one. This made the making of the project management plan run smoothly.

Describe one example of what went wrong on this project.

Page 30: 252311_1_2-pmp-2012-27

A problem that come up during the project was an issues to do one of the team member who was unhappy with the supplier, which raised their prices in the middle of the project. This causes that team member to become very hostile with the rest of the team who were happy with the supplier. That team member couldn’t convince anyone else to see his way, so he went over the project manager head to the senior management to suggest terminating the supplier. This causes more problems between the project manager, the team and that team member. This whole issues or problem was resorted by firing that team member who had a problem with the supplier and replacing that team member with another person. This made the project and everyone else is the team to settle down and get the back on track.

What will you do differently on the next project based on your experience working

on this project? What the team would do different on the project if it was done again was to do a better job at planning the time and budget of the project before starting it. This would allow the team to meet all the goals of the project stated by the sponsors. What would be done differently on making the project management plan if the project was done again was to work out the available time of everyone sooner. This would mean the project team could meet sooner and regally to plan the project management plan quick and easier.