272583_633940143828092500

Upload: vinod-verma

Post on 06-Apr-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 272583_633940143828092500

    1/29

    Material Requirement

    Planning

    By

    GROUP-8Debojit Roy H66Sritanu Das Mahapatra H57Abhisek Sahu H3Krishnakant Pandey H25

    Biswajit Ghosh H12

  • 8/3/2019 272583_633940143828092500

    2/29

    #

    Material Requirement Planning

    MRP is a systematic planningMRP is a systematic planning--andand--control methodologycontrol methodologyfor production and inventory.for production and inventory.

    Specifically, it is a procedure for planning andSpecifically, it is a procedure for planning andcontrolling the raw material, purchased parts, and workcontrolling the raw material, purchased parts, and workin progress (WIP) inventories required in manufacturingin progress (WIP) inventories required in manufacturinga product.a product.

    MRP is designed to answer three questions:MRP is designed to answer three questions: whatwhatisisneeded,needed, how muchhow much is needed, andis needed, and whenwhen is it needed.is it needed.

  • 8/3/2019 272583_633940143828092500

    3/29

    #

    END PRODUCT

    COMPONENT OF END PRODUCT

    RAW MATERIAL

    Order Point

    Time

    LTLT

    TimeLT

    TimeLT

    Independent and Dependent DemandInventory

    Order Point

    Order Point

    LT

  • 8/3/2019 272583_633940143828092500

    4/29

    #

    The Benefits of MRPThe Benefits of MRP

    Inventory reduction.Inventory reduction.

    Reduction in production & delivery time.Reduction in production & delivery time.

    Increased efficiency.Increased efficiency.

    Faster response to market changes.Faster response to market changes.

    Improved labour & equipment utilization.Improved labour & equipment utilization.

    Better inventory planning & scheduling.Better inventory planning & scheduling.

    Reduced inventory levels without reduced customerReduced inventory levels without reduced customer

    service.service.

  • 8/3/2019 272583_633940143828092500

    5/29

    #

    WHENWHENT

    OT

    O USE MRP?USE MRP?

    It is useful for..

    Dependent Demand (table top, table leg).

    Discrete Demand (demand for leg at last).

    Complex Products (subassembly before final assembly).

    Assemble-to-Order (major assemblies & sub assembliesis done in advance).

  • 8/3/2019 272583_633940143828092500

    6/29

    #

    Limitations of Order-point

    techniques

    As each part in inventory is managed separately &

    independently of all others. So even though these

    techniques can provide extremely high service level forindividual parts, the service level for combination of Parts

    (subassemblies) & for the complete end product can be

    low.

  • 8/3/2019 272583_633940143828092500

    7/29

    #

    Overview of the MRP System

    MasterProductionSchedule

    MaterialRequirements

    Planning

    ProductStructure

    File

    ItemMaster

    file

    PlannedOrder

    Release

    Workorders

    PurchaseOrders

    Reschedulingnotices

  • 8/3/2019 272583_633940143828092500

    8/29

    #

    Information Needed for MRP

    It collects information through.

    1.1. Master Production Schedule (MPS),Master Production Schedule (MPS),

    2.2. The Bill of Material (BOM), ingredients for the endThe Bill of Material (BOM), ingredients for the endproduct,product,

    3.3. Inventory Data,Inventory Data,

    4.4. Balance on Hand (BOH),Balance on Hand (BOH),

    5.5. Scheduled receipts,Scheduled receipts,

    6.6. Purchasing/Fabrication lead times.Purchasing/Fabrication lead times.

  • 8/3/2019 272583_633940143828092500

    9/29

    #

    MRP Inputs

    Master Production Schedule

    Product Structure File Inventory Master File

  • 8/3/2019 272583_633940143828092500

    10/29

    #

    Product Structure File

    Bill ofMaterials:

    It is a materials list that providesinformation useful to reconstruct themanufacturing process. It is the masterproduct definition that contains asdesigned information

  • 8/3/2019 272583_633940143828092500

    11/29

    #

    Bill of materialBill of material

    LEVELLEVEL PRODUCTPRODUCT LEAD TIMELEAD TIME

    Level 0Level 0 TwoTwo --drawer filedrawer filecabinetcabinet

    Level 1Level 1 Case (1)Case (1) 2 weeks2 weeks

    Level 2Level 2 Drawer slide (4)Drawer slide (4) 3 weeks3 weeks

    Formed case (1)Formed case (1) 2 weeks2 weeks

    Level 3Level 3 Sheet steel (1)Sheet steel (1) 4 weeks4 weeks

    Level 1Level 1 Drawers (2)Drawers (2) 1 week1 week

    Level 2Level 2 Formed drawer (1)Formed drawer (1) 2 weeks2 weeks

    Handle (1)Handle (1) 3 weeks3 weeks

    Support rollers (2)Support rollers (2) 3 weeks3 weeks

    Level 3Level 3 Sheet steel(1)Sheet steel(1) 4 weeks4 weeks

  • 8/3/2019 272583_633940143828092500

    12/29

    #

    Master Production Schedule

    Schedule of Finished Products

    Represents Production, not Demand

    Combination of Customer Orders and Demand Forecasts

    What Needs to be Produced

  • 8/3/2019 272583_633940143828092500

    13/29

    #

    Inventory Master File

    On-Hand Quantities.

    On-Order Quantities.

    Lot Sizes.

    Safety Stock.

    Lead Time.

    Past-Usage Figures.

  • 8/3/2019 272583_633940143828092500

    14/29

    #

    Product structure treeProduct structure tree

    TwoTwo--Drawer File CabinetDrawer File CabinetLevel 0Level 0 Two drawer

    File cabinet

    Case(1)2 week

    Drawers(2)1 week

    Drawer slide(4)3 week

    Formed case(1)2 week

    Sheet steel(1)4 week

    FormedDrawer(1)

    2 weekHandle(1)

    3 week

    SupportRollers(2)3 week

    Sheet steel(1)4week

    Level 1Level 1

    Level 2Level 2

    Level 3Level 3

    Level 0Level 0

  • 8/3/2019 272583_633940143828092500

    15/29

    #

    Drawer Subassembly Requirement

    WEEKWEEK 11 22 33 44 55 66

    GROSSGROSSREQUIREMENTSREQUIREMENTS

    2020 3030 4040 1010 5050 6060

    SCHEDULEDSCHEDULED

    RECEIPTSR

    ECEIPTS

    00 00 00 00 00 00

    BALANCE ON HANDBALANCE ON HAND9090

    7070 4040 00 --1010 --5050 --6060

    PLANNEDPLANNED--ORDERORDERRELEASERELEASE

    00 00 1010 5050 6060 00

    weekweek 11 22 33 44 55 66

    quantityquantity 1010 1515 2020 55 2525 3030

    MPS for two-drawer file cabinet

  • 8/3/2019 272583_633940143828092500

    16/29

    #

    Description

    90 drawer subassemblies are currently in hand forrequirement in first 3 week.

    Ending balance on hand = beginning BOH + scheduledreceipt gross requirement.

    In week 4 negative inventory balance indicates a netrequirement for drawer subassemblies.

    The net requirements will trigger planned-order releasesfor more drawer subassemblies in earlier period.

  • 8/3/2019 272583_633940143828092500

    17/29

    #

    Description

    Lot for lot method generating the planned quantitiesin each period value by value directly from the netrequirements in subsequent period, with no economicbatching of orders, is called the lot for lot method.

    Time phasing the process of subtracting an item'slead time from its due date to determine when an ordershould be released. Time-phasing coordinates the

    quantity of parts and components held in inventory withassemble or final production needs as determined bythe MPS.

  • 8/3/2019 272583_633940143828092500

    18/29

    #

    SUPPORT ROLLER REQUIREMENTSWEEKWEEK 11 22 33 44 55 66

    GROOS REQUIREMENTGROOS REQUIREMENT 00 00 2020 100100 120120 00

    SCHEDULED RECEIPTSSCHEDULED RECEIPTS 00 4040 00 00 00 00

    BALANCED ON HAND 60BALANCED ON HAND 60 6060 100100 8080 --2020 --120120 00

    PLANNEDPLANNED--ORDERORDERRELEASERELEASE

    2020 120120 00 00 00 00

    week

    quantity

    1 2 3 4 5 6

    0 0 10 50 60 0

    Drawer subassemblies

  • 8/3/2019 272583_633940143828092500

    19/29

    #

    Two important conceptsTwo important concepts

    Planned order releases at higher levels generate grossPlanned order releases at higher levels generate grossrequirements at lower levels.requirements at lower levels.

    Inventories of higher level subassemblies alreadyInventories of higher level subassemblies alreadyinclude the necessary lower level components, and thisinclude the necessary lower level components, and thisfact is automatically allowed for by the net requirementsfact is automatically allowed for by the net requirementscalculation.calculation.

  • 8/3/2019 272583_633940143828092500

    20/29

    #

    Regeneration vs. net change

    Regeneration

    Complete replanning of requirements and update ofinventory status for all items

    High data processing efficiency

    Usually initiated by weekly update of master schedule

    Net change

    Daily update based on inventory transactions

    More responsive to changing conditions

    Requires more discipline in file maintenance

  • 8/3/2019 272583_633940143828092500

    21/29

    #

    Manufacturing Resource Planning

    (MRP II)

    Manufacturing Resource Planning (MRP II) is

    defined as a method for the effective planning of allresources of a manufacturing company. Ideally, itaddresses operational planning in units, financialplanning in dollars, and has a simulation capability toanswer "what-if" questions and extension of closed-loopMRP.

  • 8/3/2019 272583_633940143828092500

    22/29

    #

    Business Planning

    Sales Planning

    Production Planning

    ResourcesOK?

    Master Scheduling

    Material Planning

    Capacity Planning

    PlanningOK?

    PerformanceMeasurement

    Shop Floor Control

    Purchasing

    Objectives

    Demands

    Routing

    Inventory Status

    Bills of

    Material

    Products

    Materials

    Capacity

    Parts

    Hours

    Accountability

    Objectives

    Top ManagementPlanning

    OMP

    OperationsManagement

    Execution

    Yes

    No

    No

    Yes

    FE

    EDB

    ACK

  • 8/3/2019 272583_633940143828092500

    23/29

    #

    Just-in-time (JIT)

    A highly coordinated processing system in which goods

    move through the system, and services are performed,

    just as they are needed.

    In short, the just-in-time inventory system is all about

    having the right material, at the right time, at the right

    place, and in the right quantity without the safety net of

    Inventory, the implications of which are broad for theImplementers.

  • 8/3/2019 272583_633940143828092500

    24/29

    #

    History of JIT

    The technique was first used by the Ford Motorcompany as described explicitly by Henry Fords MyLife and Work(1922)

    The technique was subsequently adopted andpublicised by Toyota Motor Corporation of Japan as partof its Toyota Production System (TPS).

  • 8/3/2019 272583_633940143828092500

    25/29

    #

    Benefits of JIT

    The benefits of JIT are listed below.The benefits of JIT are listed below.

    Lower stock holding means a reduction in storage spaceLower stock holding means a reduction in storage spacewhich saves rent and insurance costswhich saves rent and insurance costs

    As stock is only obtained when it is needed, lessAs stock is only obtained when it is needed, lessworking capital is tied up in stockworking capital is tied up in stock

    There is less likelihood of stock perishing, becomingThere is less likelihood of stock perishing, becomingobsolete or out of dateobsolete or out of date

    Avoids the buildAvoids the build--up of unsold finished product that canup of unsold finished product that can

    occur with sudden changes in demandoccur with sudden changes in demand Less time is spent on checking and reLess time is spent on checking and re--working theworking the

    product of others as the emphasis is on getting theproduct of others as the emphasis is on getting thework right first timework right first time

  • 8/3/2019 272583_633940143828092500

    26/29

    #

    Problems of JIT

    There is little room for mistakes as minimal stock iskept for re-working faulty product.

    Production is very reliant on suppliers and if stock is notdelivered on time, the whole production schedule can bedelayed .

    There is no spare finished product available to meet

    unexpected orders, because all product is made to meetactual orders however, JIT is a very responsivemethod of production.

  • 8/3/2019 272583_633940143828092500

    27/29

    #

  • 8/3/2019 272583_633940143828092500

    28/29

    #

    MRP vs. JIT

    For a company which is small and just starting up I feel anFor a company which is small and just starting up I feel anMRP ordering system would be better suitedMRP ordering system would be better suited if youif youimplemented JIT then as a small company you would beimplemented JIT then as a small company you would betrying to break into a market, if the JIT system goes wrongtrying to break into a market, if the JIT system goes wrong(as I am sure we all agree this is very risky) then youll be un(as I am sure we all agree this is very risky) then youll be un--able to get your product on the shelves for customers to buyable to get your product on the shelves for customers to buyand if this happened on a regular occasion then yourand if this happened on a regular occasion then yourreputation from consumers wont be goodreputation from consumers wont be good which is criticalwhich is criticalfrom a new companies point of view.from a new companies point of view.

    On the other handOn the other hand being a large reputable company with abeing a large reputable company with asolid reputation and brand image maybe the JIT systemsolid reputation and brand image maybe the JIT systemshould be implemented as this type of company will be able toshould be implemented as this type of company will be able toinvest at making this system a success, as JIT dramaticallyinvest at making this system a success, as JIT dramaticallyreduces cost and waste these savings will influence the pricereduces cost and waste these savings will influence the price

    of the product in order to compete with other competitors.of the product in order to compete with other competitors.

  • 8/3/2019 272583_633940143828092500

    29/29

    #

    Summary

    In the era of computer and IT, it is necessary to usenew technologies for fester growing organization. Anycompany wants to lead in the competetitive market by

    introducing qualitative product with in a short period oftime. Like that in manufacturing organization MRPsystem helps to reduce the manufacturing time of aproduct by insuring the availability of materials forproduct assembly in the necessary quantities at therequired time. It also help to reduce raw materialpurchasing ,purchases parts & working processinventory. So MRP uses reducing inventory cost,reducing completion time of manufacturing withmaintaining quality. It provides customer, a greaterreturn value of their money.