272583_633940143828092500
TRANSCRIPT
-
8/3/2019 272583_633940143828092500
1/29
Material Requirement
Planning
By
GROUP-8Debojit Roy H66Sritanu Das Mahapatra H57Abhisek Sahu H3Krishnakant Pandey H25
Biswajit Ghosh H12
-
8/3/2019 272583_633940143828092500
2/29
#
Material Requirement Planning
MRP is a systematic planningMRP is a systematic planning--andand--control methodologycontrol methodologyfor production and inventory.for production and inventory.
Specifically, it is a procedure for planning andSpecifically, it is a procedure for planning andcontrolling the raw material, purchased parts, and workcontrolling the raw material, purchased parts, and workin progress (WIP) inventories required in manufacturingin progress (WIP) inventories required in manufacturinga product.a product.
MRP is designed to answer three questions:MRP is designed to answer three questions: whatwhatisisneeded,needed, how muchhow much is needed, andis needed, and whenwhen is it needed.is it needed.
-
8/3/2019 272583_633940143828092500
3/29
#
END PRODUCT
COMPONENT OF END PRODUCT
RAW MATERIAL
Order Point
Time
LTLT
TimeLT
TimeLT
Independent and Dependent DemandInventory
Order Point
Order Point
LT
-
8/3/2019 272583_633940143828092500
4/29
#
The Benefits of MRPThe Benefits of MRP
Inventory reduction.Inventory reduction.
Reduction in production & delivery time.Reduction in production & delivery time.
Increased efficiency.Increased efficiency.
Faster response to market changes.Faster response to market changes.
Improved labour & equipment utilization.Improved labour & equipment utilization.
Better inventory planning & scheduling.Better inventory planning & scheduling.
Reduced inventory levels without reduced customerReduced inventory levels without reduced customer
service.service.
-
8/3/2019 272583_633940143828092500
5/29
#
WHENWHENT
OT
O USE MRP?USE MRP?
It is useful for..
Dependent Demand (table top, table leg).
Discrete Demand (demand for leg at last).
Complex Products (subassembly before final assembly).
Assemble-to-Order (major assemblies & sub assembliesis done in advance).
-
8/3/2019 272583_633940143828092500
6/29
#
Limitations of Order-point
techniques
As each part in inventory is managed separately &
independently of all others. So even though these
techniques can provide extremely high service level forindividual parts, the service level for combination of Parts
(subassemblies) & for the complete end product can be
low.
-
8/3/2019 272583_633940143828092500
7/29
#
Overview of the MRP System
MasterProductionSchedule
MaterialRequirements
Planning
ProductStructure
File
ItemMaster
file
PlannedOrder
Release
Workorders
PurchaseOrders
Reschedulingnotices
-
8/3/2019 272583_633940143828092500
8/29
#
Information Needed for MRP
It collects information through.
1.1. Master Production Schedule (MPS),Master Production Schedule (MPS),
2.2. The Bill of Material (BOM), ingredients for the endThe Bill of Material (BOM), ingredients for the endproduct,product,
3.3. Inventory Data,Inventory Data,
4.4. Balance on Hand (BOH),Balance on Hand (BOH),
5.5. Scheduled receipts,Scheduled receipts,
6.6. Purchasing/Fabrication lead times.Purchasing/Fabrication lead times.
-
8/3/2019 272583_633940143828092500
9/29
#
MRP Inputs
Master Production Schedule
Product Structure File Inventory Master File
-
8/3/2019 272583_633940143828092500
10/29
#
Product Structure File
Bill ofMaterials:
It is a materials list that providesinformation useful to reconstruct themanufacturing process. It is the masterproduct definition that contains asdesigned information
-
8/3/2019 272583_633940143828092500
11/29
#
Bill of materialBill of material
LEVELLEVEL PRODUCTPRODUCT LEAD TIMELEAD TIME
Level 0Level 0 TwoTwo --drawer filedrawer filecabinetcabinet
Level 1Level 1 Case (1)Case (1) 2 weeks2 weeks
Level 2Level 2 Drawer slide (4)Drawer slide (4) 3 weeks3 weeks
Formed case (1)Formed case (1) 2 weeks2 weeks
Level 3Level 3 Sheet steel (1)Sheet steel (1) 4 weeks4 weeks
Level 1Level 1 Drawers (2)Drawers (2) 1 week1 week
Level 2Level 2 Formed drawer (1)Formed drawer (1) 2 weeks2 weeks
Handle (1)Handle (1) 3 weeks3 weeks
Support rollers (2)Support rollers (2) 3 weeks3 weeks
Level 3Level 3 Sheet steel(1)Sheet steel(1) 4 weeks4 weeks
-
8/3/2019 272583_633940143828092500
12/29
#
Master Production Schedule
Schedule of Finished Products
Represents Production, not Demand
Combination of Customer Orders and Demand Forecasts
What Needs to be Produced
-
8/3/2019 272583_633940143828092500
13/29
#
Inventory Master File
On-Hand Quantities.
On-Order Quantities.
Lot Sizes.
Safety Stock.
Lead Time.
Past-Usage Figures.
-
8/3/2019 272583_633940143828092500
14/29
#
Product structure treeProduct structure tree
TwoTwo--Drawer File CabinetDrawer File CabinetLevel 0Level 0 Two drawer
File cabinet
Case(1)2 week
Drawers(2)1 week
Drawer slide(4)3 week
Formed case(1)2 week
Sheet steel(1)4 week
FormedDrawer(1)
2 weekHandle(1)
3 week
SupportRollers(2)3 week
Sheet steel(1)4week
Level 1Level 1
Level 2Level 2
Level 3Level 3
Level 0Level 0
-
8/3/2019 272583_633940143828092500
15/29
#
Drawer Subassembly Requirement
WEEKWEEK 11 22 33 44 55 66
GROSSGROSSREQUIREMENTSREQUIREMENTS
2020 3030 4040 1010 5050 6060
SCHEDULEDSCHEDULED
RECEIPTSR
ECEIPTS
00 00 00 00 00 00
BALANCE ON HANDBALANCE ON HAND9090
7070 4040 00 --1010 --5050 --6060
PLANNEDPLANNED--ORDERORDERRELEASERELEASE
00 00 1010 5050 6060 00
weekweek 11 22 33 44 55 66
quantityquantity 1010 1515 2020 55 2525 3030
MPS for two-drawer file cabinet
-
8/3/2019 272583_633940143828092500
16/29
#
Description
90 drawer subassemblies are currently in hand forrequirement in first 3 week.
Ending balance on hand = beginning BOH + scheduledreceipt gross requirement.
In week 4 negative inventory balance indicates a netrequirement for drawer subassemblies.
The net requirements will trigger planned-order releasesfor more drawer subassemblies in earlier period.
-
8/3/2019 272583_633940143828092500
17/29
#
Description
Lot for lot method generating the planned quantitiesin each period value by value directly from the netrequirements in subsequent period, with no economicbatching of orders, is called the lot for lot method.
Time phasing the process of subtracting an item'slead time from its due date to determine when an ordershould be released. Time-phasing coordinates the
quantity of parts and components held in inventory withassemble or final production needs as determined bythe MPS.
-
8/3/2019 272583_633940143828092500
18/29
#
SUPPORT ROLLER REQUIREMENTSWEEKWEEK 11 22 33 44 55 66
GROOS REQUIREMENTGROOS REQUIREMENT 00 00 2020 100100 120120 00
SCHEDULED RECEIPTSSCHEDULED RECEIPTS 00 4040 00 00 00 00
BALANCED ON HAND 60BALANCED ON HAND 60 6060 100100 8080 --2020 --120120 00
PLANNEDPLANNED--ORDERORDERRELEASERELEASE
2020 120120 00 00 00 00
week
quantity
1 2 3 4 5 6
0 0 10 50 60 0
Drawer subassemblies
-
8/3/2019 272583_633940143828092500
19/29
#
Two important conceptsTwo important concepts
Planned order releases at higher levels generate grossPlanned order releases at higher levels generate grossrequirements at lower levels.requirements at lower levels.
Inventories of higher level subassemblies alreadyInventories of higher level subassemblies alreadyinclude the necessary lower level components, and thisinclude the necessary lower level components, and thisfact is automatically allowed for by the net requirementsfact is automatically allowed for by the net requirementscalculation.calculation.
-
8/3/2019 272583_633940143828092500
20/29
#
Regeneration vs. net change
Regeneration
Complete replanning of requirements and update ofinventory status for all items
High data processing efficiency
Usually initiated by weekly update of master schedule
Net change
Daily update based on inventory transactions
More responsive to changing conditions
Requires more discipline in file maintenance
-
8/3/2019 272583_633940143828092500
21/29
#
Manufacturing Resource Planning
(MRP II)
Manufacturing Resource Planning (MRP II) is
defined as a method for the effective planning of allresources of a manufacturing company. Ideally, itaddresses operational planning in units, financialplanning in dollars, and has a simulation capability toanswer "what-if" questions and extension of closed-loopMRP.
-
8/3/2019 272583_633940143828092500
22/29
#
Business Planning
Sales Planning
Production Planning
ResourcesOK?
Master Scheduling
Material Planning
Capacity Planning
PlanningOK?
PerformanceMeasurement
Shop Floor Control
Purchasing
Objectives
Demands
Routing
Inventory Status
Bills of
Material
Products
Materials
Capacity
Parts
Hours
Accountability
Objectives
Top ManagementPlanning
OMP
OperationsManagement
Execution
Yes
No
No
Yes
FE
EDB
ACK
-
8/3/2019 272583_633940143828092500
23/29
#
Just-in-time (JIT)
A highly coordinated processing system in which goods
move through the system, and services are performed,
just as they are needed.
In short, the just-in-time inventory system is all about
having the right material, at the right time, at the right
place, and in the right quantity without the safety net of
Inventory, the implications of which are broad for theImplementers.
-
8/3/2019 272583_633940143828092500
24/29
#
History of JIT
The technique was first used by the Ford Motorcompany as described explicitly by Henry Fords MyLife and Work(1922)
The technique was subsequently adopted andpublicised by Toyota Motor Corporation of Japan as partof its Toyota Production System (TPS).
-
8/3/2019 272583_633940143828092500
25/29
#
Benefits of JIT
The benefits of JIT are listed below.The benefits of JIT are listed below.
Lower stock holding means a reduction in storage spaceLower stock holding means a reduction in storage spacewhich saves rent and insurance costswhich saves rent and insurance costs
As stock is only obtained when it is needed, lessAs stock is only obtained when it is needed, lessworking capital is tied up in stockworking capital is tied up in stock
There is less likelihood of stock perishing, becomingThere is less likelihood of stock perishing, becomingobsolete or out of dateobsolete or out of date
Avoids the buildAvoids the build--up of unsold finished product that canup of unsold finished product that can
occur with sudden changes in demandoccur with sudden changes in demand Less time is spent on checking and reLess time is spent on checking and re--working theworking the
product of others as the emphasis is on getting theproduct of others as the emphasis is on getting thework right first timework right first time
-
8/3/2019 272583_633940143828092500
26/29
#
Problems of JIT
There is little room for mistakes as minimal stock iskept for re-working faulty product.
Production is very reliant on suppliers and if stock is notdelivered on time, the whole production schedule can bedelayed .
There is no spare finished product available to meet
unexpected orders, because all product is made to meetactual orders however, JIT is a very responsivemethod of production.
-
8/3/2019 272583_633940143828092500
27/29
#
-
8/3/2019 272583_633940143828092500
28/29
#
MRP vs. JIT
For a company which is small and just starting up I feel anFor a company which is small and just starting up I feel anMRP ordering system would be better suitedMRP ordering system would be better suited if youif youimplemented JIT then as a small company you would beimplemented JIT then as a small company you would betrying to break into a market, if the JIT system goes wrongtrying to break into a market, if the JIT system goes wrong(as I am sure we all agree this is very risky) then youll be un(as I am sure we all agree this is very risky) then youll be un--able to get your product on the shelves for customers to buyable to get your product on the shelves for customers to buyand if this happened on a regular occasion then yourand if this happened on a regular occasion then yourreputation from consumers wont be goodreputation from consumers wont be good which is criticalwhich is criticalfrom a new companies point of view.from a new companies point of view.
On the other handOn the other hand being a large reputable company with abeing a large reputable company with asolid reputation and brand image maybe the JIT systemsolid reputation and brand image maybe the JIT systemshould be implemented as this type of company will be able toshould be implemented as this type of company will be able toinvest at making this system a success, as JIT dramaticallyinvest at making this system a success, as JIT dramaticallyreduces cost and waste these savings will influence the pricereduces cost and waste these savings will influence the price
of the product in order to compete with other competitors.of the product in order to compete with other competitors.
-
8/3/2019 272583_633940143828092500
29/29
#
Summary
In the era of computer and IT, it is necessary to usenew technologies for fester growing organization. Anycompany wants to lead in the competetitive market by
introducing qualitative product with in a short period oftime. Like that in manufacturing organization MRPsystem helps to reduce the manufacturing time of aproduct by insuring the availability of materials forproduct assembly in the necessary quantities at therequired time. It also help to reduce raw materialpurchasing ,purchases parts & working processinventory. So MRP uses reducing inventory cost,reducing completion time of manufacturing withmaintaining quality. It provides customer, a greaterreturn value of their money.