3 month look ahead update 22-28 april 2012
TRANSCRIPT
-
7/29/2019 3 Month Look Ahead Update 22-28 April 2012
1/6
-
7/29/2019 3 Month Look Ahead Update 22-28 April 2012
2/6
-
7/29/2019 3 Month Look Ahead Update 22-28 April 2012
3/6
-
7/29/2019 3 Month Look Ahead Update 22-28 April 2012
4/6
-
7/29/2019 3 Month Look Ahead Update 22-28 April 2012
5/6
-
7/29/2019 3 Month Look Ahead Update 22-28 April 2012
6/6
ID Task name %om let
Duration RemainingDuration
ActualDuration
Start Finish Est Qty Plan Unit Total QtyActual
EstimateProductivit
Remaining Remaks
326 Fabrication 0% 12 d 12 d 0 d Wed 02 May '12 Tue 15 May '12 Not Start Yet
327 Install Fromwork 0% 6 d 6 d 0 d Wed 16 May '12 Fri 25 May '12 Not Start Yet
328 Leanconcrete 0% 5 d 5 d 0 d Sat 26 May '12 Thu 31 May '12 75 M3 0 - 75 Not Start Yet
329 Install Rebar 0% 6 d 6 d 0 d Fri 01 J un '12 Thu 07 J un '12 Not Start Yet
330 Pouring Concrete 0% 15 d 15 d 0 d Fri 08 J un '12 Mon 25 J un '12 1350 M3 0 - 1350 Not Start Yet
331 pedestal for RC Windshield 0% 30 d 30 d 0 d Tue 26 J un '12 Mon 30 J ul '12 Not Start Yet
332 UPPER STRUCTURE 0% 115 d 115 d 0 d Tue 31 Jul '12 Tue 11 Dec '12 Not Start Yet
336 ARCHITECTURAL WORK 0% 135 d 135 d 0 d Wed 12 Dec '12 Tue 21 May '13 Not Start Yet
340 FLUE DUCT 1% 365,11 d 359,78 d 5,34 d Mon 16 Apr '12 Thu 20 Jun '13 Not Start Yet
341 PILING WORK 23% 37 d 28,37 d 8,63 d Mon 16 Apr '12 Tue 29 May '12 On Progress
342 Piling work for Flu duct structure 23% 30 d 23 d 7 d Mon 16 Apr '12 Tue 29 May '12 52 Point 16 10 36 On Progress
343 FOUNDATION WORK 0% 78 d 78 d 0 d Wed 30 May '12 Mon 27 Aug '12 Not Strat Yet
346 UPPER STRUCTURE 0% 232,22 d 232,22 d 0 d Mon 17 Sep '12 Thu 20 Jun '13 Not Strat Yet
353 TRANSFORMER AREA ( 108 ) 0% 232,56 d 232,56 d 0 d Mon 30 Apr '12 Wed 30 Jan '13 N/Y started
364 150 KV SWITCH YARD ( 109 ) 0% 253,56 d 253,56 d 0 d Tue 10 Jul '12 Fri 03 May '13 N/Y started
369 20kV switchgear (110) 0% 150 d 150 d 0 d Tue 10 Jul '12 Tue 01 Jan '13 N/Y started
374 COAL PART 0% 365,33 d 365,33 d 0 d Mon 30 Apr '12 Mon 08 Jul '13 N/Y started
435 ASH DISPOSAL PART 0% 150 d 150 d 0 d Mon 21 May ' 12 Fri 09 Nov '12 N/Y start ed
461 WATER SUPPLY and CHEMICAL WATERCREATMENT PART
0% 280 d 280 d 0 d Mon 30 Apr '12 Wed 27 Mar '13 N/Y started
532 PERTAIN BUILDING PART 0% 150 d 150 d 0 d Wed 16 May '12 Thu 08 Nov '12 N/Y started
23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 1323 Apr '12 30 Apr '12 07 May '12
Task
Split
Milestone
Summary
Project Summary
Project Summary RFI- II
Summary RFI-II
Task RFI-II
Milestone RFI-II
Project Summary RFI- I
Summary RFI-I
Task RFI-I
Milestone RFI-I
Baseline Project Summary
Baseline Summary
Base line Task
Base line Split
Base line Milestone
External Tasks
External Milestone
Deadline
Progress
COAL FIRED STEAM POWER PLANT PROJECT 2x110 MW TENAYAN RIAU
3 MONT LOOK AHEAD
UPDATE 22-28 APRIL 2012
Submitted by : Approved by :
AAcknowledged by :
Prepared by : Herry STracking until : Sat 28 Apr '12