4-21 col sfpe

Upload: salil-deshpande

Post on 14-Apr-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 4-21 col SFPE

    1/36

    High Rise Buildingsand

    Large firesStructural loads & thermal strainWhat can happen?

    As presented to the Northern California-Nevada Chapter of theSociety of Fire Protection Engineers

    On April 21, 2006 in Walnut Creek, California.

    by Edward Munyak, [email protected]

    mailto:[email protected]:[email protected]
  • 7/27/2019 4-21 col SFPE

    2/36

    Probable Maximum Loss

    PML assumes a fire scenariowith a loss of one suppressionsystem and a delay in manualfire fighting.

    The 9/11 Commission reportignores the collapse of WTC 7

    The NIST Report on WTC 1,2 &7 implies that global collapsewas inevitable for these steelstructures.

  • 7/27/2019 4-21 col SFPE

    3/36

    Is there a new paradigm

    for building collapse? What follows is a study of steel frame

    building response to maximum fireconditions based on:

    Historical catastrophic fires in high rise buildingsfrom 1986 to 2005

    Actual fire tests in steel frame buildings in the UK

    Thermodynamic simulations

  • 7/27/2019 4-21 col SFPE

    4/36

    Fire Resistance

    Unprotected steel that resists high windsand seismic forces has considerable fireresistance.

    Adding dead weight at a cost of 20% ?

    Structures need to be designed to resisthigher wind, seismic loads and increasedfire resistance will automatically follow.

  • 7/27/2019 4-21 col SFPE

    5/36

    Inherent fire resistance

    In many instances, particularly in tallbuildings or massive structures, the mass ofsteel required to support loads and resistmoments is very large and thus the thermal

    mass of the steel itself provides inherentresistance to weakening by fire fire exposurefor periods of time that can be determined byengineering analysis page 17 NISTstructural steel report GCR 04-872 7/2004

  • 7/27/2019 4-21 col SFPE

    6/36

    ASTM E-119 is the standard test for fullsize structural components.

    Oven temperature(not structure) versustime.

    One side of the structure is exposed toheat.

    If temperature on unexposed side isexcessive or if deflection is above a

    certain limit after the test duration, thecomponent fails.

    Structure is always within the elasticrange

  • 7/27/2019 4-21 col SFPE

    7/36

    ASTM vs Real fires

    Recent and historical large firesin steel frame buildings havedemonstrated that actual fireperformance of the structuralsystem is much better thanresults of the test of a singlecomponent.

    Broadgate Fire in UK occurredprior to fire proofing. Structureexceeded 650 degree C. but didnot collapse.

  • 7/27/2019 4-21 col SFPE

    8/36

    mu a ons o an arFires

    on whole frame designPerformance based approachdeleted fire proofing on most

    secondary steel.Catenary action on beams and

    Tensile membrane action offloor slabs compensated for thereduction of strength at highertemperatures

  • 7/27/2019 4-21 col SFPE

    9/36

    High rise Building fires

    20 year time spanMontreal, Canada 1986, 15

    stories

    Los Angeles, 1988, FirstInterstate Bank

    One Meridian Plaza,Philadelphia, 1991

    WTC 1, 2 & 7, NYC. 9/11/2001

    Parque Central, Caracas,Venezuela 2004

    Edificio Madrid, Spain 2005

  • 7/27/2019 4-21 col SFPE

    10/36

    Montreal, Canada

    October 26, 1986 15 story SFRM Steel frame building with a

    fire load estimated to be at least twice WTC (10 - 11 lbs/sq ft vs 4 lbs/ sq ft in WTC)

    Fire burned for over 13 hours on multiplefloor levels due to vertical openings.

    A 30ft x 40ft section on the 11th floor fell tothe 10th floor when welded clips failed. Noinelastic deformation noted on surroundingstructure.

    Loss demonstrated the need for automaticsprinkler protection and protection of verticalopenings.

    Interesting example of girder to columnfailure of weld clip.

  • 7/27/2019 4-21 col SFPE

    11/36

    First Interstate Bank Fire

    Los Angeles, May 4, 198862 story type II. SFRM steel frame,

    open floor plan

    Fire duration was 3 1/2 hours

    Fire spread vertically from 12 th to15th floors internally and externally.

    Many broken windows resulted in asevere fire and auto-ignition

    Smoke spread throughout buildingbut there was no structural framedamage.

    Fire damper in HVAC failed at

    critical point

  • 7/27/2019 4-21 col SFPE

    12/36

    One Meridian Plaza, Philadelphia,Pa

    February 23, 1991 Fire gutted 8 floors of a 38 story building

    3 fire fighters died,$100 million in direct fire loss,$ 4 billion civil damage

    Fire burned for over 19 hours Major power and water supply failure

    Severe fire broke most windows on the fire floors

    Fire spread externally by auto-ignition

    Fire was stopped by automatic sprinklers on the30th floor.

    Vertical columns were not damaged, horizontalbeams sagged as much as 3 feet.

  • 7/27/2019 4-21 col SFPE

    13/36

    WTC 1 and 2

    NYC Sept 11, 2001

    Applying the equal-area

    principle for the time-temperature curve, fires werenot as severe as ASTM standardand less than all otherexamples.

    Each tower was more massivethan other high rise examples.

    NIST report, page 77, estimates

    a fuel loading of 4 lbs/ sq ft or60 tons of combustibles er

  • 7/27/2019 4-21 col SFPE

    14/36

    WTC 1 & 2 Structure

    Designed in accordance with the 1968 NYCbuilding code with a 50 year wind storm ofjust under 100 mph which exceeds existingand current codes.

    Designed to resist the impact of a Boeing707@ 600 mph

    Originally designed with gypsum board andSFRM to protect core.

    Building core supported gravity load, external

    high strength columns could be undercompression or tension

  • 7/27/2019 4-21 col SFPE

    15/36

    ASTM vs WTC South

    0

    200

    400

    600

    800

    1000

    1200

    1400

    0 100 200 300 400 500 600

    temperature

    WTC South Temperature

    After the initial fireball1050 C for 2min.

    Fuel burns off in 10 minutes

    4 lbs/ ft fire load equates

    To 30-40 min duration.

  • 7/27/2019 4-21 col SFPE

    16/36

    NIST analysis of WTC

    collapseThe towers withstood the

    impact and would haveremained standing if not for thedislodged insulation(fireproofing) and subsequent multi-floor fires.

    Towers were built in accordancewith 1968 NYC Building Code.

    Recommended objective shouldbe survival of an uncontrollablefire without local or globalcollapse.

  • 7/27/2019 4-21 col SFPE

    17/36

    WTC Tower structure

    Gravity loads were supported by47 steel columns in the core.

    Wind loads were resisted by 59columns on each of 4 sides thatcould be in compression ortension.

    The floors were compositeconcrete and steel. Steel trusseshad viscoelastic dampers onbottom chord.

  • 7/27/2019 4-21 col SFPE

    18/36

    Thermal simulation of south

    tower A steel frame building with the mass of WTC 1 or 2

    could have partial structural collapse after aircraftimpact only if the heat output was at least 100 timesthe heat release rate of the accountable fuel load and

    ventilation conditions in the south tower. This fire would need to involve every floor from

    impact floor to the roof with most windows brokenand providing plenty of oxygen as in the EdificioWindsor fire in Madrid.

    This most severe fire would need to burn for at least12 hours before loss of strength from heat; andthermal strains from expansion and contractioncaused partial collapse.

  • 7/27/2019 4-21 col SFPE

    19/36

    Anomalies within an Anomaly

    Unprecedented total collapse of a steelframe building.

    The tower with the least structural damageand smallest fire collapsed first.

    If lack of fire proofing brought down WTC 1& 2 why did intact fire proofing not help

    WTC 7? On the scene professional fire fighters

    knew that the building was not damaged tothe verge of collapse.

  • 7/27/2019 4-21 col SFPE

    20/36

    WTC 7

    WTC 7 was one city blockaway from Towers

    No damage to fire proofing

    Small fires were observed

    Global collapse was initiatedon the lowest level

    Different structure

  • 7/27/2019 4-21 col SFPE

    21/36

    Parque Central Office BuildingCaracas, Venezuela

    October 15, 2004 South Americas Tallest building at 56 stories

    Automatic sprinkler system impaired

    The fire burned for over 24 hours and consumed 17floors at a rate one floor every 2 1/2 hours.

    Five spray fire proofed structural steel sections weresandwiched between concrete protected steel macroslabs that were supported by exterior reinforced columns

    Fire spread by auto-ignition and through unrated floorpanels in the two hour rated floors. Total glass breakageon fire floors..

    Two floor areas partially collapsed, fire chief ordered fire

    fighters to abandon interior fire fighting but there was nofurther collapse.

  • 7/27/2019 4-21 col SFPE

    22/36

    Edificio Windsor

    Madrid, Spain 12 Feb, 2005 Fire started on the 21 st floor of a 32 story

    concrete core column building with unprotectedsteel beams on perimeter with unprotectedperimeter columns

    Building was being renovated; there were largeunprotected vertical openings.

    Unknown fire load but judging by the 18- 20 hourfire duration, and massive flames, the fire loadmust have been high.

    The suspicious fire spread from the 21 floor to the

    top 32nd floor within one hour and then downwardto the lowest floor(4th) within the next 10 +hours.

    Property was valued at 72 million Euros before thefire that gutted it.

    A portion of the floor slabs above the 17th floor

    that was supported by unprotected steel beamscollapsed but the reinforced concrete core

  • 7/27/2019 4-21 col SFPE

    23/36

    Madrid,Spain12/2/2005

  • 7/27/2019 4-21 col SFPE

    24/36

    Edificio Windsor Madrid, Spain

  • 7/27/2019 4-21 col SFPE

    25/36

    Edificio Windsor, Madrid 2/12/2005

  • 7/27/2019 4-21 col SFPE

    26/36

    Edificio Windsor

  • 7/27/2019 4-21 col SFPE

    27/36

    Theorem of CastiglianoElements of Strength of Materials by Timoshenko & Young 4th edition

    page, p. 246-263

    Strain energy that must be overcome beforelimit collapse is complete is proportional toall forces squared and inversely

    proportional to high strength modulus ofelasticity.

    Integration of area under the stress-straincurve represents a massive amount ofstrain energy that must be overcomebefore collapse is complete in the caseWTC 1, 2 & 7.

    The only available source of energy of thatmagnitude is the potential energy of atleast 10 floors and it had to be released in

  • 7/27/2019 4-21 col SFPE

    28/36

    Energy available for

    releaseFire tests in the UK shown the

    structure under load at veryhigh temperatures slowlyreleasing potential energy ofmass and height by plasticdeformation of the heated steel.

    Chemical energy in the fuel andpotential energy (mass xheight) is released by plasticdeformation wheretemperatures are hottest.

    The load path then shifts to

  • 7/27/2019 4-21 col SFPE

    29/36

    Steel in plastic range

  • 7/27/2019 4-21 col SFPE

    30/36

    Magnitude of Available Energysources

    Chemical energy in jet fuel(2 planes)=6.9.e+10metric joules

    (applied over 5 -10 minute time duration)

    Kinetic energy (2 planes) = 1.9 e+9 metric joules(less than one second)

    Potential energy (2 towers) =6.8 e=11 metric joules

    (controlled demolition can release this in less than

    one second)

  • 7/27/2019 4-21 col SFPE

    31/36

    Releasing Gravitational

    Energy Collapse in WTC was initiated near the floors of

    Impact.

    The center core suddenly dropped without anyresistance from the structures below.

    If column severing energy was sequentially timed sothat as the total mass accelerating down met minimalresistance for 2 or 3 floor enough potential energywill be converted into downward momentum so thatin the words of the NIST report global collapse was

    inevitable. All potential energy was suddenly released and

    available for inelastic deformation of steel andsimultaneous pulverizing of concrete within a timespan of about 10 seconds

  • 7/27/2019 4-21 col SFPE

    32/36

    RecommendationReimbursement of any loss must be

    contingent upon access to and analysis offire damaged structure:

    The wreckage of WTC 1, 2 & 7 was worthhundreds of millions of dollars in terms ofresearch and practical knowledge.

    There was evidence of sulfadation on beamsfrom explosive material

    The severed ends of beams were observedto be partially molten for days after clean-

    up. This is characteristic of thermite.

    WTC C ll

  • 7/27/2019 4-21 col SFPE

    33/36

    WTC CollapseProfessor Steven Jones of BYU

    Department of Physics and Astronomy

    WTC 7 collapsed rapidly and symmetrically-even though fires were randomly scattered in

    the building

    Where is the delay that must be expected dueto conservation of momentum-one of thefoundational laws of physics

  • 7/27/2019 4-21 col SFPE

    34/36

    http://www.implosionworld.com/cinema.htm

    What is incredible in the fire effectscontinua is routine in the world ofcontrolled demolition.

    Even with explosives, achieving suchresults requires a great deal of pre-planning and expertise

    The explosive demolition hypothesisbetter satisfies tests of repeatability andparsimony states Professor Steven Jones

    http://www.physics.byu.edu/research/energy/htm7.html

    http://www.physics.byu.edu/research/energy/htm7.htmlhttp://www.physics.byu.edu/research/energy/htm7.htmlhttp://www.physics.byu.edu/research/energy/htm7.htmlhttp://www.physics.byu.edu/research/energy/htm7.html
  • 7/27/2019 4-21 col SFPE

    35/36

    To be continued

    For additional informationcontact

    Edward Munyak, P.E.

    esmunyak@ earthlink.net

    (650)948-8035

  • 7/27/2019 4-21 col SFPE

    36/36

    References NFPA Journal, March/April 2005 Fire Unchecked page 47 Caracas, Venezuela Fire

    Culver, Charles, Characteristics of fire loads in office buildings Fire Technology1978, Vol 14, No.1 pages 51-60

    NFPA investigation of High Rise office Building Fire, Montreal, Canada, October 26,1986

    NFPA investigations of May 4, 1988 First Bank Building Bank Fire, Los Angeles, Ca

    WWW. Implosionworld.com

    http://911reserach.wtc7.net

    Building Regulatory Systems in a post-September 11 World by Richard Bukowski,P.E. NIST Building and Fire Research Laboratory

    http://www.mace.manchester.ac.uk/project/research/structures/casestudy/historicfires/building fires/default.htm

    http://www.physics.byu.edu/research/energy/htm7.html

    Fire Protection of Structural Steel in High Rise Buildings, NIST GCR 04-872

    Moscatelli, Frank, WETC energy calculations

    9/11 Commission Report, Omissions and Distortions. David Ray Griffin

    9/11 Synthetic Terror-Made in the USA, Webster Griffin Tarpley

    http://www.mace.manchester.ac.uk/project/research/structures/casestudy/historichttp://www.physics.byu.edu/research/energy/htm7.htmlhttp://www.physics.byu.edu/research/energy/htm7.htmlhttp://www.mace.manchester.ac.uk/project/research/structures/casestudy/historic