400kv protection_ gk

Upload: moinuddin-mohammed

Post on 15-Oct-2015

111 views

Category:

Documents


12 download

DESCRIPTION

this is a protection guide for 400 KV switchgear system. from ap Transco.

TRANSCRIPT

  • 400KV PROTECTION400KV PROTECTIONPREPARED BYPREPARED BY

    GOPALA KRISHNA PALEPUGOPALA KRISHNA PALEPUADE/MRT(PROTECTION)ADE/MRT(PROTECTION)

  • BASICS BASICS OF OF

    ONE AND HALF ONE AND HALF CIRCUIT BREAKER CIRCUIT BREAKER

    SCHEMESCHEMEPREPARED BY

    GOPALA KRISHNA PALEPUADE/MRT(PROTECTION)

  • ONE & HALF BREAKER DESCRIPTIONONE & HALF BREAKER DESCRIPTIONBUS-1 1. IN THIS TWO BUSES ARE PRIOVIDED.

    BUS-2

    2. THESE TWO BUSES ARE INTER CONNECTED BY THREE BREAKERS.3. THEY ARE DESIGNATED AS 1-52 CB, 2-52 CB, 3-52 CB.

    1-52 CB

    2-52 CB

    3-52 CB

    4. LINE-1 IS CONNECTED IN BETWEEN 1-52 CB & 2-52 CB.

    LINE-1

    5. LINE-2 IS CONNECTED IN BETWEEN 3-52 CB & 2-52 CB.

    LINE-2

    6. LINE-1 HAVING TWO FEEDING PATHS i.eA. VIA BUS-1 & 1-52 CBB. VIA BUS-2, 3-52 CB & 2-52 CB

    7. LINE-2 HAVING TWO FEEDING PATHS i.eA. VIA BUS-2 & 3-52 CBB. VIA BUS-1, 1-52 CB & 2-52 CB

    8. FOR INTURUPTING LINE-1 THE 1-52CB AND 2-52CB IS TO BE TRIPPED.9. FOR INTURUPTING LINE-2 THE 3-52CB & 2-52CB IS TO BE TRIPPED.

    10. FOR ANY PROBLEM IN LINE-1 OR LINE-2 THE MIDDLE BREAKER(2-52 CB) MUST TRIP.

    13. SO THESE TWO FEEDERS CONTROLLING BY THREE CIRCUIT BREAKERS IT IS CALLED ONE & HALF BREAKER SYSTEM.

    M

    A

    I

    N

    B

    A

    Y

    (

    1

    S

    T

    B

    A

    Y

    )

    F

    O

    R

    F

    E

    E

    D

    E

    R

    -

    1

    M

    A

    I

    N

    B

    A

    Y

    (

    3

    R

    D

    B

    A

    Y

    )

    F

    O

    R

    F

    E

    E

    D

    E

    R

    -

    2

    15. THE BAY BETWEEN LINE-1 & LINE-2 IS CALLED TIE BAY FOR FEEDER-1 & 2. 16. THE BAY BETWEEN BUS-2 & LINE-2 IS CALLED MAIN BAY FOR FEEDER-2.

    T

    I

    E

    B

    A

    Y

    (

    2

    N

    D

    B

    A

    Y

    )

    F

    O

    R

    F

    E

    E

    D

    E

    R

    -

    1

    &

    2

    GOPALA KRISHNA PALEPU M.Tech(EMID), (MBA)

    ADE/MRT/400KV SS/APTRANSCOMAMIDIPALLY, HYDERABAD

    11. NORMALLY IN ALL TYPES OF BUSBAR CONFIGUARATIONS ONE BREAKER IS SUFFICIENT FOR ONE FEEDER.

    14. THE BAY BETWEEN BUS-1 & LINE-1 IS CALLED MAIN BAY FOR FEEDER-1.

    12. HERE TWO FEEDERS ARE CONTROLLING BY THREE BREAKERS.

  • ONE & HALF BREAKER SYSTEMONE & HALF BREAKER SYSTEM(4CTS METHOD)(4CTS METHOD)

    LINE 1

    1-89

    1-89A

    11--52CB52CB

    1-CT3

    3

    3

    3-89

    3-89A

    33--52CB52CB

    3-CT3

    22--52CB52CB

    2-ACT 2-BCT

    2-89A 2-89B

    1-89L 3-89T

    BUS-1 BUS-2

    T/F-1

    P1

    P1 P1

    P1

    P2 P2

    P2 P2

  • ONE & HALF BREAKER SYSTEMONE & HALF BREAKER SYSTEM(5CTS METHOD)(5CTS METHOD)

    LINE 1

    1-89A

    11--52CB52CB

    1-CT3

    3

    3

    3-89

    3-89A

    33--52CB52CB

    3-CT3

    22--52CB52CB

    1-LCT

    2-CT

    2-89A 2-89B

    1-89L 3-89T

    BUS-1 BUS-2

    T/F-1

    3 3-TCT

    1-89

    P2

    P1

    P2

    P2

    P2

    P1 P1

    P2

    P1 P1

  • ONE & HALF BREAKER SYSTEMONE & HALF BREAKER SYSTEM(6CTS METHOD)(6CTS METHOD)

    LINE 1

    1-89A

    11--52CB52CB

    1B-CT33

    3

    3-89

    3-89A

    33--52CB52CB

    3B-CT3

    22--52CB52CB

    2B-CT

    2-89A 2-89B

    1-89L 3-89T

    BUS-1 BUS-2

    T/F-1

    3

    1-89

    P2

    P1P2

    P2

    P2

    P1 P1

    P2P1

    P13

    P2

    P11A-CT

    2A-CT

    3A-CT

  • ONE & HALF BREAKER SYSTEMONE & HALF BREAKER SYSTEM(6CTS METHOD)(6CTS METHOD)

    LINE 1

    1-89A

    11--52CB52CB

    1B-CT33

    3

    3-89

    3-89A

    33--52CB52CB

    3B-CT3

    22--52CB52CB

    2B-CT

    2-89A 2-89B

    1-89L 3-89T

    BUS-1 BUS-2

    T/F-1

    3

    1-89

    P2

    P1P2

    P2

    P2

    P1 P1

    P2P1

    P13P2

    P11L-CT

    2A-CT

    3T-CT

  • PROTECTION TRIP SCHEMEPROTECTION TRIP SCHEME

    BUS-1 BUS-2

    1-52CB 3-52CB2-52CB

    8686--AAMTR/MTR/HSTRHSTR

    ABBABBREL521REL521MAINMAIN--11

    8686--BBMTR/MTR/HSTRHSTR

    8686--BBMTR/MTR/HSTRHSTR

    8686--AAMTR/MTR/HSTRHSTR

    8686--BBMTR/MTR/HSTRHSTR

    8686--AAMTR/MTR/HSTRHSTR

    ABBABBREL521REL521MAINMAIN--11

    ABBABBREL316REL316MAINMAIN--22

    ABBABBRET521RET521MAINMAIN--11

    ABBABBRET316RET316MAINMAIN--22

    TRIP COIL-1 TRIP COIL-1 TRIP COIL-1

    TRIP COIL-2 TRIP COIL-2 TRIP COIL-2

    8686--A : GROUPA : GROUP--A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 8686--B : GROUPB : GROUP--B MASTER TRIP RELAY / HIGH SPEED TRIP RELAYB MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

  • SINGLE BUS SYSTEMSINGLE BUS SYSTEM

    11--52CB52CB1-89 1-89L

    3

    1-CT

    P2 P13 33 3

    CORES1 2 3 4 5

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    P

    R

    O

    T

    M

    E

    T

    E

    R

    I

    N

    G

    M

    E

    T

    E

    R

    I

    N

    G

    M

    A

    I

    N

    M

    A

    I

    N

    -

    -

    2

    /

    B

    A

    C

    K

    U

    P

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    2

    /

    B

    A

    C

    K

    U

    P

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    M

    A

    I

    N

    M

    A

    I

    N

    -

    -

    1

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    1

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    BUS

    1-CVT

    3

    3

    331 2 333

    3

    3

    3

    2

    1

  • CURRENT TRANSFORMERCURRENT TRANSFORMERCONNECTIONS IN 4CT METHODCONNECTIONS IN 4CT METHOD

    11-- CTCT 22--BCTBCT 22--ACTACT 33--CTCTCORECORE--1 1

    (PS)(PS)

    CT SECONDARY CT SECONDARY CORE IS CORE IS

    CONNECTED TO CONNECTED TO BUSBARBUSBAR--1 1

    PROTECTIONPROTECTION

    SPARESPARE SPARESPARE CT SECONDARY CT SECONDARY CORE IS CORE IS

    CONNECTED TO CONNECTED TO BUSBARBUSBAR--2 2

    PROTECTION PROTECTION

    CORECORE--2 2 (PS)(PS)

    BUSBARBUSBAR--1 1 CHECKUP CHECKUP

    PROTECTION PROTECTION (SPARE)(SPARE)

    SPARESPARE SPARESPARE BUSBARBUSBAR--2 2 CHECKUP CHECKUP

    PROTECTION PROTECTION (SPARE)(SPARE)

    CORECORE--3 3 (0.5/0.2)(0.5/0.2)

    2CTs SECONDARIES ARE 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED IN PARALLEL AND

    CONNECTED TO CONNECTED TO PANEL METERS & ENERGY METERPANEL METERS & ENERGY METER

    2CTs SECONDARIES ARE 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED IN PARALLEL AND

    CONNECTED TO CONNECTED TO PANEL METERS & ENERGY METERPANEL METERS & ENERGY METER

    CORECORE--4 4 (PS)(PS)

    2CTs SECONDARIES ARE 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED IN PARALLEL AND

    CONNECTED TO CONNECTED TO MAINMAIN--2 PROTECTION2 PROTECTION

    AFTER LBB/BFRAFTER LBB/BFR

    2CTs SECONDARIES ARE 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED IN PARALLEL AND

    CONNECTED TO CONNECTED TO BACKUP PROTECTIONBACKUP PROTECTION

    AFTER LBB/BFRAFTER LBB/BFR

    CORECORE--5 5 (PS)(PS)

    2CTs SECONDARIES ARE 2CTs SECONDARIES ARE CONNECTED CONNECTED

    IN PARALLEL AND CONNECTED TO IN PARALLEL AND CONNECTED TO MAINMAIN--1 PROTECTION1 PROTECTION

    2CTs SECONDARIES ARE 2CTs SECONDARIES ARE CONNECTED CONNECTED

    IN PARALLEL AND CONNECTED TO IN PARALLEL AND CONNECTED TO MAIN PROTECTIONMAIN PROTECTION

  • LINE PROTECTIONLINE PROTECTION(CT CONNECTIONS(CT CONNECTIONS IN IN 4CTs METHOD)4CTs METHOD)

    LINE 1

    1-89

    1-89A

    11--52CB52CB

    3-89

    3-89A

    33--52CB52CB

    22--52CB52CB2-89A

    2-89B1-89L3-89T

    BUS-1 BUS-2

    T/F-1

    1-CT

    P1

    P2

    33

    33

    3

    CO

    RE

    S1

    23

    45

    3

    3

    3

    3

    3

    CORES1 2 3 4 5

    2B-CT

    P1 P2

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    METERINGMETERING

    MAINMAIN--2 PROTECTION2 PROTECTION

    MAINMAIN--1 PROTECTION1 PROTECTION

    333

    3

    3

    2

    1

    1-CVT

    ..

    .

  • LINE 1

    1-89

    1-89A

    11--52CB52CB

    3-89

    3-89A

    33--52CB52CB

    22--52CB52CB2-89A

    2-89B1-89L3-89T

    BUS-1 BUS-2

    T/F-1

    3

    3

    3

    3

    3

    CORES1 2 3 4 5

    33

    33

    3

    C

    O

    R

    E

    S

    5

    4

    3

    2

    1

    P1

    P2

    2A-CT

    3-CT

    P1P2

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    METERINGMETERING

    MAINMAIN--2 PROTECTION2 PROTECTION

    MAINMAIN--1 PROTECTION1 PROTECTION

    TRANSFORMER PROTECTIONTRANSFORMER PROTECTION(CT CONNECTIONS(CT CONNECTIONS IN IN 4CTs METHOD)4CTs METHOD)

    LV CT

    333

    3

    32

    1

    333

    3

    3

    2

    1 333

    3

    12

    3

    .

    .

  • CURRENT TRANSFORMER CURRENT TRANSFORMER CONNECTIONS IN 5CT METHODCONNECTIONS IN 5CT METHOD

    11--CTCT 11--LCTLCT 22--CTCT 33--TCTTCT 33--CTCT

    CORECORE--1 1 (PS)(PS)

    BUSBARBUSBAR--11PROTECTIONPROTECTION

    TEED PROTTEED PROT--11(BAY 1&2)(BAY 1&2)

    TEED PROTTEED PROT--11(BAY 2&3)(BAY 2&3)

    TEED PROTTEED PROT--11(BAY 2&3)(BAY 2&3)

    BUSBARBUSBAR--22PROTECTIONPROTECTION

    CORECORE--2 2 (PS)(PS)

    BUSBARBUSBAR--1 1 CHECKUP CHECKUP

    PROTECTION PROTECTION (SPARE)(SPARE)

    TEED PROTTEED PROT--22(BAY 1&2)(BAY 1&2)

    TEED PROTTEED PROT--22(BAY 2&3)(BAY 2&3)

    TEED PROTTEED PROT--22(BAY 2&3)(BAY 2&3)

    BUSBARBUSBAR--2 2 CHECKUP CHECKUP

    PROTECTION PROTECTION (SPARE)(SPARE)

    CORECORE--3 3 (0.5/0.2)(0.5/0.2)

    SPARESPARE METERING &METERING &ENERGY ENERGY METERMETER

    SPARESPARE METERING &METERING &ENERGY ENERGY METERMETER

    SPARESPARE

    CORECORE--4 4 (PS)(PS)

    TEED PROTTEED PROT--22(BAY 1&2) (BAY 1&2)

    AFTERAFTERLBB/BFRLBB/BFR

    (1(1--52) 52)

    MAINMAIN--22PROTECTIONPROTECTION

    TEED PROTTEED PROT--22(BAY 1&2) (BAY 1&2)

    AFTERAFTERLBB/BFRLBB/BFR

    (2(2--52) 52)

    BACKUPBACKUPPROTECTIONPROTECTION

    TEED PROTTEED PROT--22(BAY 2&3) (BAY 2&3)

    AFTERAFTERLBB/BFR LBB/BFR

    (3(3--52)52)

    CORECORE--5 5 (PS)(PS)

    TEED PROTTEED PROT--11(BAY 1&2)(BAY 1&2)

    MAINMAIN--11PROTECTIONPROTECTION

    TEED PROTTEED PROT--11(BAY 1&2)(BAY 1&2)

    MAINMAINPROTECTIONPROTECTION

    TEED PROTTEED PROT--11(BAY 2&3)(BAY 2&3)

  • LINE PROTECTIONLINE PROTECTION(CT CONNECTIONS(CT CONNECTIONS IN IN 5CTs METHOD)5CTs METHOD)

    LINE 1

    1-89

    1-89A

    11--52CB52CB

    3-89

    3-89A

    33--52CB52CB

    22--52CB52CB2-89A

    2-89B1-89L3-89T

    BUS-1 BUS-2

    T/F-1

    1-CT

    P1

    P2

    33

    33

    3

    CO

    RE

    S1

    23

    4

    5

    333 33CORES

    12345

    2-CTP1 P2

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    METERINGMETERINGMAINMAIN--2 PROTECTION2 PROTECTION

    MAINMAIN--1 PROTECTION1 PROTECTION

    333

    3

    1

    2

    3

    1-CVT

    33

    33

    3

    C

    O

    R

    E

    S

    5

    4

    3

    2

    1

    1L-CT

    P1

    P2

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    .

  • T/F PROTECTIONT/F PROTECTION(CT CONNECTIONS(CT CONNECTIONS IN IN 5CTs METHOD)5CTs METHOD)

    LINE 1

    1-89

    1-89A

    11--52CB52CB

    3-89

    3-89A

    33--52CB52CB

    22--52CB52CB2-89A

    2-89B1-89L3-89T

    BUS-1 BUS-2

    T/F-1

    3-CT

    P1

    P2

    333 33CORES

    12345

    2-CTP1 P2

    METERINGMETERINGMAINMAIN--2 PROTECTION2 PROTECTIONMAINMAIN--1 PROTECTION1 PROTECTION

    333

    3

    1

    2

    3

    1-CVT

    33

    33

    3

    CO

    RE

    S1

    23

    45

    3T-CT

    P1

    P2

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    1

    &

    2

    )

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    2

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    T

    E

    E

    D

    T

    E

    E

    D

    -

    -

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    1

    P

    R

    O

    T

    (

    B

    A

    Y

    2

    &

    3

    )

    .

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    P

    R

    O

    T

    E

    C

    T

    I

    O

    N

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    B

    U

    S

    B

    A

    R

    C

    H

    E

    C

    K

    U

    P

    P

    R

    O

    T

    33

    33

    3

    CO

    RE

    S

    1

    2

    34

    5.

    3

    3

    3

    3

    1 2 3

    3

    3

    3

    3

    3 2 1

    LV CT

  • CURRENT TRANSFORMERCURRENT TRANSFORMERCONNECTIONS IN 6CT METHODCONNECTIONS IN 6CT METHOD

    (GIS or AIS with DEAD TANK CBs) (GIS or AIS with DEAD TANK CBs)

    1B1B--CTCT 1A1A--CTCT 2B2B--CTCT 2A2A--CTCT 3A3A--CTCT 3B3B--CTCT

    CORECORE--1 1 (PS)(PS)

    BUSBARBUSBAR--1 1 PROTECTIONPROTECTION

    2CTs SECONDARIES 2CTs SECONDARIES ARE CONNECTED ARE CONNECTED IN PARALLEL AND IN PARALLEL AND CONNECTED TO CONNECTED TO

    MAINMAIN--1 PROTECTION1 PROTECTION

    2CTs SECONDARIES 2CTs SECONDARIES ARE CONNECTED ARE CONNECTED IN PARALLEL AND IN PARALLEL AND CONNECTED TO CONNECTED TO

    MAINMAIN--1 PROTECTION1 PROTECTION

    BUSBARBUSBAR--2 2 PROTECTIONPROTECTION

    CORECORE--2 2 (PS)(PS)

    BUSBARBUSBAR--1 1 CHECKUP CHECKUP PROTECTION PROTECTION

    (SPARE)(SPARE)

    2CTs SECONDARIES 2CTs SECONDARIES ARE CONNECTED INARE CONNECTED IN

    PARALLEL AND PARALLEL AND CONNECTED TOCONNECTED TO

    MAINMAIN--2 PROTECTION 2 PROTECTION AFTER LBB/BFRAFTER LBB/BFR

    2CTs SECONDARIES 2CTs SECONDARIES ARE CONNECTED INARE CONNECTED IN

    PARALLEL AND PARALLEL AND CONNECTED TO CONNECTED TO

    BACKUP PROTECTION BACKUP PROTECTION AFTER LBB/BFRAFTER LBB/BFR

    BUSBARBUSBAR--2 2 CHECKUP CHECKUP PROTECTION PROTECTION

    (SPARE)(SPARE)

    CORECORE--3 3 (0.5/0.2)(0.5/0.2)

    SPARESPARE 2CTs SECONDARIES 2CTs SECONDARIES ARE CONNECTED INARE CONNECTED IN

    PARALLEL AND PARALLEL AND CONNECTED TO CONNECTED TO

    PANEL METERS & PANEL METERS & ENERGY METERENERGY METER

    2CTs SECONDARIES 2CTs SECONDARIES ARE CONNECTED INARE CONNECTED IN

    PARALLEL AND PARALLEL AND CONNECTED TO CONNECTED TO

    PANEL METERS & PANEL METERS & ENERGY METERENERGY METER

    SPARESPARE

  • CURRENT TRANSFORMERCURRENT TRANSFORMERCONNECTIONS IN 6CT METHODCONNECTIONS IN 6CT METHOD

    11--CTCT 1L1L--CTCT 2A2A--CTCT 2B2B--CTCT 3T3T--CTCT 33--CTCTCORECORE--1 1 (PS)(PS)

    BUSBARBUSBAR--11PROTECTIONPROTECTION

    TEED PROTTEED PROT--11(BAY 1&2)(BAY 1&2)

    SPARESPARE SPARESPARE

    SPARESPARE

    SPARESPARE

    TEED PROTTEED PROT--22(BAY 1&2) (BAY 1&2)

    AFTER LBB/BFRAFTER LBB/BFR(2(2--52)52)

    TEED PROTTEED PROT--11(BAY 1&2)(BAY 1&2)

    BUSBARBUSBAR--22PROTECTIONPROTECTION

    CORECORE--2 2 (PS)(PS)

    BUSBARBUSBAR--1 1 CHECKUP CHECKUP PROTECTION PROTECTION

    (SPARE)(SPARE)

    TEED PROTTEED PROT--22(BAY 1&2)(BAY 1&2)

    SPARESPARE

    TEED PROTTEED PROT--11(BAY 2&3)(BAY 2&3)

    TEED PROTTEED PROT--22(BAY 2&3)(BAY 2&3)

    METERING &METERING &ENERGY ENERGY METERMETER

    BACKUPBACKUPPROTECTIONPROTECTION

    BUSBARBUSBAR--2 2 CHECKUPCHECKUPPROTECTION PROTECTION

    (SPARE)(SPARE)

    CORECORE--3 3 (0.5/0.2)(0.5/0.2)

    SPARESPARE METERING &METERING &ENERGY ENERGY METERMETER

    SPARESPARE SPARESPARE

    MAINMAINPROTECTIONPROTECTION

    CORECORE--4 4 (PS)(PS)

    TEED PROTTEED PROT--22(BAY 1&2) (BAY 1&2)

    AFTER LBB/BFR AFTER LBB/BFR (1(1--52) 52)

    MAINMAIN--22PROTECTIONPROTECTION

    TEED PROTTEED PROT--22(BAY 2&3)(BAY 2&3)

    TEED PROTTEED PROT--22(BAY 2&3) (BAY 2&3)

    AFTER LBB/BFR AFTER LBB/BFR (3(3--52)52)

    CORECORE--5 5 (PS)(PS)

    TEED PROTTEED PROT--11(BAY 1&2)(BAY 1&2)

    MAINMAIN--11PROTECTIONPROTECTION

    TEED PROTTEED PROT--11(BAY 2&3)(BAY 2&3)

    TEED PROTTEED PROT--11(BAY 2&3)(BAY 2&3)

  • COMPARISION BETWEEN COMPARISION BETWEEN 4CT METHOD & 5CT METHOD4CT METHOD & 5CT METHOD

    CT PURPOSECT PURPOSE 5 CT METHOD5 CT METHOD 4 CT METHOD4 CT METHODBUSBAR &

    BUSBAR CHECKUP PROTECTION

    1 CT FOR BUS1 CT FOR BUS--1 & 1 & 3 CT FOR BUS3 CT FOR BUS--22

    1 CT FOR BUS1 CT FOR BUS--1 & 1 & 3 CT FOR BUS3 CT FOR BUS--22

    MAIN-1, MAIN-2 PROTECTION &

    METERING

    1L CT FOR FEEDER1L CT FOR FEEDER--1 & 1 & 3L CT FOR FEEDER3L CT FOR FEEDER--22

    1 CT & 2B CT SECONDARIES ARE CONNECTED 1 CT & 2B CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDERPARALLEL FOR FEEDER--1 & 1 &

    3 CT & 2A CT SECONDARIES ARE CONNECTED 3 CT & 2A CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDERPARALLEL FOR FEEDER--22

    ADDITIONAL PROTECTION

    TEEDTEED--1 PROTECTION (HIGH Z)1 PROTECTION (HIGH Z)(1 CT, 1L CT & 2 CT FOR FEEDER(1 CT, 1L CT & 2 CT FOR FEEDER--1 & 1 & 3 CT, 3L CT & 2 CT FOR FEEDER3 CT, 3L CT & 2 CT FOR FEEDER--2)2)

    TEEDTEED--2 PROTECTION (LOW Z)2 PROTECTION (LOW Z)(1 CT, 1L CT & 2 CT FOR FEEDER(1 CT, 1L CT & 2 CT FOR FEEDER--1 &1 &3 CT, 3L CT & 2 CT FOR FEEDER3 CT, 3L CT & 2 CT FOR FEEDER--2)2)

    STUBSTUB--1 PROTECTION1 PROTECTION( MAIN( MAIN--1 DISTANCE SCHEME IS CONVERTED 1 DISTANCE SCHEME IS CONVERTED TO STUBTO STUB--1 WHEN LINE ISOLATOR OPENS) 1 WHEN LINE ISOLATOR OPENS)

    STUBSTUB--2 PROTECTION2 PROTECTION( MAIN( MAIN--2 DISTANCE SCHEME IS CONVERTED 2 DISTANCE SCHEME IS CONVERTED TO STUBTO STUB--2 WHEN LINE ISOLATOR OPENS)2 WHEN LINE ISOLATOR OPENS)

    OTHER INFORMATION

    TEED PROTECTIONTEED PROTECTION( THE 3NOs CTs ARE CONEECTED IN TEE SHAPE ( THE 3NOs CTs ARE CONEECTED IN TEE SHAPE AND CONNECTED TO DIFFERENTIAL RELAY SO AND CONNECTED TO DIFFERENTIAL RELAY SO IT IS CALLED TEED PROTECTION). IT IS CALLED TEED PROTECTION). TEEDTEED--11 IS CONNECTED ON SUMMATION OF 3 TEE IS CONNECTED ON SUMMATION OF 3 TEE SHAPED CTs & CONNECTED TO 3SHAPED CTs & CONNECTED TO 3--PH HIGH PH HIGH IMPEDENCE DIFFERENTIAL RELAY . IMPEDENCE DIFFERENTIAL RELAY . TEEDTEED--22 IS CONNECTED TO 3 WINDING LOW IS CONNECTED TO 3 WINDING LOW IMPEDENCE BIASED DIFFERENTIAL RELAY OF IMPEDENCE BIASED DIFFERENTIAL RELAY OF 3 TEE SHAPED CTs. 3 TEE SHAPED CTs. ( TEED PROTECTION WILL BE USED TO COVER ( TEED PROTECTION WILL BE USED TO COVER BLIND AREA BETWEEN TEE SHAPED CTs BLIND AREA BETWEEN TEE SHAPED CTs CONNECTED IN DIFF PROTECTION)CONNECTED IN DIFF PROTECTION)

    STUB PROTECTIONSTUB PROTECTION( THERE IS NO UNCOVERED BLIND ZONE ) (WHEN ( THERE IS NO UNCOVERED BLIND ZONE ) (WHEN

    EVER LINE ISOLATOR OPENS MAINEVER LINE ISOLATOR OPENS MAIN--1 & MAIN1 & MAIN--2 2 WILL BE CONVERTED TO STUB/ BUS OVER LOAD WILL BE CONVERTED TO STUB/ BUS OVER LOAD

    RELAYS. STUB MEANS DEAD END) RELAYS. STUB MEANS DEAD END) ( STUB IS INBUILT FEATURE IN ADVANCED ( STUB IS INBUILT FEATURE IN ADVANCED NUMERICAL DISTANCE SCHEME RELAYS)NUMERICAL DISTANCE SCHEME RELAYS)

  • INFORMATION REGARDING INFORMATION REGARDING 6CT METHOD 6CT METHOD

    THE LOCATION OF THE CTs ON BOTH SIDES OF THE CIRCUIT BREAKERS IS TYPICAL FOR SUBSTATIONS WITH DEAD-TANK CIRCUIT BREAKERS or GIS CIRCUIT BREAKERS.

    LIVE-TANK CIRCUIT BREAKERS MAY HAVE CTs ONLY ON ONE SIDE TO REDUCE COST.

    A FAULT BETWEEN CIRCUIT BREAKERS AND CT(END FAULT) MAY THEN STILL BE FED FROM ONE SIDE EVEN WHEN THE BREAKER HAS BEEN OPENED.

    CONSEQUENTLY, FINAL FAULT CLEARING BY CASCADED TRIPPING HAS TO BE ACCEPTED IN THIS CASE.

    STUB PROTECTION RELAY PROVIDED IN CASE OF LINE ISOLATOR OPENS.

    1B-CT FOR BUSBAR-1 AND 3B-CT FOR BUSBAR-2 FOR BUSBAR PROTECTION & BUSBAR CHECKUP PROTECTION.

    1A-CT & 2B-CT SECONDARIES ARE PARALLED AND CONNECTED TO MAIN-1 PROTECTION, MAIN-2 PROTECTION AFTER LBB/BFR AND METERING.

  • ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEMEONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME

  • TYPICAL ONE & HALF BREAKER TYPICAL ONE & HALF BREAKER SYSTEM ADOPTED IN GISSYSTEM ADOPTED IN GIS

    DS : DISCONNECTOR SWITCH, GS: GROUNDING SWITCH, CT: CURRENT TRANSFORMER, VD: VOLTAGE DIVIDER

  • 400KV C.T. INFORMATION400KV C.T. INFORMATION

    33U

    3U

    3

    U3

    1S11S21S3

    2S12S22S3

    3S13S23S33S4

    5S15S25S35S44S14S24S34S4

    P1 P2

    P1 P2

    31S11S21S3

    32S12S22S3

    3

    U

    3S13S23S33S4

    3U 5S15S25S

    35S

    4

    3U 4S14S24S34S4

    EYE BOLT EYE BOLT DESIGNDESIGN

    HAIRHAIRPIN / PIN /

    U SHAPE U SHAPE DESIGNDESIGN

    DEAD TANK DESIGNDEAD TANK DESIGN

    PRIMARY CONNECTIONS : P1 PRIMARY CONNECTIONS : P1 P2P2CURRENT RATING : 2000 AMPSCURRENT RATING : 2000 AMPS

    SECONDARY CONNECTIONSSECONDARY CONNECTIONSCURRENT RATING : 1ACURRENT RATING : 1ACORESCORES CLASSCLASS PURPOSEPURPOSE

    2000/ 1A2000/ 1A 1000/ 1A1000/ 1A 500/ 1A500/ 1A

    CORECORE--11 PSPS BUSBAR BUSBAR PROTECTIONPROTECTION 1S1 1S1 1S31S31S2 1S2 1S3 1S3 1S1 1S1 1S21S2

    ____

    CORECORE--22 PSPSBUSBAR BUSBAR CHECKUP CHECKUP

    PROTECTIONPROTECTION2S1 2S1 2S32S3 2S2 2S2 2S3 2S3 2S1 2S1 2S22S2 ____

    CORECORE--33 0.5 / 0.20.5 / 0.2 METERINGMETERING 3S1 3S1 3S43S4 3S2 3S2 3S43S43S1 3S1 3S23S23S3 3S3 3S43S43S2 3S2 3S33S3

    CORECORE--44 PSPS MAINMAIN--2 2 PROTECTIONPROTECTION 4S1 4S1 4S44S44S2 4S2 4S44S44S1 4S1 4S24S2

    4S3 4S3 4S44S44S2 4S2 4S34S3

    CORECORE--55 PSPS MAINMAIN--1 1 PROTECTIONPROTECTION 5S1 5S1 5S45S45S2 5S2 5S45S45S1 5S1 5S25S2

    5S3 5S3 5S45S45S2 5S2 5S35S3

  • CT LOAD FLOW DIAGRAMS WHEN CT LOAD FLOW DIAGRAMS WHEN 11--52 CB OPEN52 CB OPEN

    1-52CB 3-52CB3

    2-52CBP1P2

    0A

    S2 S40A

    2000-1000-500/1A

    3

    P2P11000A

    S4 S21.0A

    2000-1000-500/1A

    3

    P1P21000A

    S3 S42.0A

    2000-1000-500/1A

    3

    P2P11500A

    S4 S33.0A

    2000-1000-500/1A1-CT 2-ACT 2-BCT 3-CT

    LINE AT/F1000A 500A

    MAINMAIN--1/ 1/ MAINMAIN--2/ 2/ METERMETER

    FORFORLINELINE

    MAINMAIN--1/ 1/ MAINMAIN--2/ 2/ METERMETER

    FORFORAT/FAT/F

    0A

    0A

    1.0A1.0A

    3.0A

    3.0A

    2.0A

    2.0A 2.0A

    1.0A 1.0A

    1.0A

    1.0A

  • CT LOAD FLOW DIAGRAMS WHENCT LOAD FLOW DIAGRAMS WHEN22--52 CB OPEN52 CB OPEN

    1-52CB 3-52CB3

    2-52CBP1P2

    1000A

    S2 S41.0A

    2000-1000-500/1A

    3

    P2P10A

    S4 S20A

    2000-1000-500/1A

    3

    P1P20A

    S3 S40A

    2000-1000-500/1A

    3

    P2P1500A

    S4 S31.0A

    2000-1000-500/1A1-CT 2-ACT 2-BCT 3-CT

    LINE AT/F1000A 500A

    MAINMAIN--1/ 1/ MAINMAIN--2/ 2/ METERMETER

    FORFORLINELINE

    MAINMAIN--1/ 1/ MAINMAIN--2/ 2/ METERMETER

    FORFORAT/FAT/F

    1.0A

    1.0A

    1.0A1.0A

    1.0A

    1.0A

    0A

    0A 0A

    0A 0A

    0A

    0A

  • CT LOAD FLOW DIAGRAMS WHEN CT LOAD FLOW DIAGRAMS WHEN 33--52 CB OPEN52 CB OPEN

    1-52CB 3-52CB3

    2-52CBP1P2

    1500A

    S2 S41.5A

    2000-1000-500/1A

    3

    P2P1500A

    S4 S20.5A

    2000-1000-500/1A

    3

    P1P2500A

    S3 S41.0A

    2000-1000-500/1A

    3

    P2P10A

    S4 S30A

    2000-1000-500/1A1-CT 2-ACT 2-BCT 3-CT

    LINE AT/F1000A 500A

    MAINMAIN--1/ 1/ MAINMAIN--2/ 2/ METERMETER

    FORFORLINELINE

    MAINMAIN--1/ 1/ MAINMAIN--2/ 2/ METERMETER

    FORFORAT/FAT/F

    1.5A

    1.5A

    1.0A1.0A

    0A

    0A

    1.0A

    1.0A 1.0A

    0.5A 0.5A

    0.5A

    0.5A

  • MAINMAIN--1, MAIN1, MAIN--22PROTECTION &PROTECTION &

    METERINGMETERINGFOR LINE FOR LINE

    ADOPTED IN ADOPTED IN ONE AND HALFONE AND HALF

    CIRCUIT BREAKER CIRCUIT BREAKER SCHEMESCHEME PREPARED BYGOPALA KRISHNA PALEPU

    ADE/MRT(PROTECTION)

  • NORMS OF PROTECTION FOLLOWED IN APTRANSCO NORMS OF PROTECTION FOLLOWED IN APTRANSCO FOR TRANSMISIION LINES & DISTRIBUTION LINES ( FEEDER / LINE PROTFOR TRANSMISIION LINES & DISTRIBUTION LINES ( FEEDER / LINE PROTECTION )ECTION )

    Sr.NoSr.No VOLTAGE VOLTAGE MAINMAIN-- 1 PROTECTION1 PROTECTION MAINMAIN--2 PROTECTION/ BACKUP PROTECTION2 PROTECTION/ BACKUP PROTECTION1.1. 11 KV LINES11 KV LINES 2 O/L + E/F ( 51 + 51N )2 O/L + E/F ( 51 + 51N ) --2.2. 33 KV LINES33 KV LINES 3 O/L + E/F ( 51 + 51N )3 O/L + E/F ( 51 + 51N ) --3.3. 66 KV LINES66 KV LINES4.4. 132 KV LINES132 KV LINES

    SWITCHED DISTANCE SCHEME SWITCHED DISTANCE SCHEME ORORNUMERICAL DISTANCE SCHEME (21P+ 21N)NUMERICAL DISTANCE SCHEME (21P+ 21N)

    3 O/L + E/F 3 O/L + E/F ( 50 + 50N + 51 + 51N + 67 + 67N )( 50 + 50N + 51 + 51N + 67 + 67N )

    5.5. 220 KV LINES220 KV LINES NON SWITCHED DISTANCE SCHEME NON SWITCHED DISTANCE SCHEME ORORNUMERICAL DISTANCE SCHEME (21P + 21N)NUMERICAL DISTANCE SCHEME (21P + 21N)SWITCHED DISTANCE SCHEME SWITCHED DISTANCE SCHEME OROR

    NUMERICAL DISTANCE SCHEME (21P+ 21N)NUMERICAL DISTANCE SCHEME (21P+ 21N)

    6.6. 400 KV LINES400 KV LINES NON SWITCHED DISTANCE SCHEME NON SWITCHED DISTANCE SCHEME ORORNUMERICAL DISTANCE SCHEME (21P + 21N)NUMERICAL DISTANCE SCHEME (21P + 21N)NON SWITCHED DISTANCE SCHEME NON SWITCHED DISTANCE SCHEME OROR

    NUMERICAL DISTANCE SCHEME (21P + 21N)NUMERICAL DISTANCE SCHEME (21P + 21N)IF MAINIF MAIN--1 & MAIN1 & MAIN--2 ARE NUMERICAL RELAYS BOTH SHOULD BE SEPARATE 2 ARE NUMERICAL RELAYS BOTH SHOULD BE SEPARATE CHARECTERESTICS, MODELS AND ALGORITHAMS (SHOULD NOT BE DUPLICATECHARECTERESTICS, MODELS AND ALGORITHAMS (SHOULD NOT BE DUPLICATED) AND D) AND ALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYSALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYS SHOULD SHOULD BE 100% REDENDENCY IN ALL ASPECTS.BE 100% REDENDENCY IN ALL ASPECTS.ZONEZONE--1: 80% OF MAIN LINE1: 80% OF MAIN LINEZONEZONE--2: 100% OF MAIN LINE + 50% OF SHORTEST LINE AT OTHER END2: 100% OF MAIN LINE + 50% OF SHORTEST LINE AT OTHER ENDZONEZONE--3: 100% OF MAIN LINE + 100% OF SHORTEST LINE AT OTHER END3: 100% OF MAIN LINE + 100% OF SHORTEST LINE AT OTHER ENDZONEZONE--4: 100% OF MAIN LINE + (100% OF SHORTEST LINE + 20% OF LONGEST L4: 100% OF MAIN LINE + (100% OF SHORTEST LINE + 20% OF LONGEST LINE)INE)

    AT OTHER END.AT OTHER END.

  • MAINMAIN--1 PROTECTION FOR LINE1 PROTECTION FOR LINE(4CT METHOD)(4CT METHOD)

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REL 521REL 5213 3 3

    3 3 3

    IR5 / A511IY5 / A531IB5 / A551

    IN5 / A571

    1-CT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    2-BCT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    5S4 5S4 5S4

    5S25S2 5S2

    P2P2P2 CT MB

    CT MB

    P2P2P2

    5S4 5S4 5S4

    5S25S2 5S2

    VR11 / E111VY11 / E131VB11 / E151VN11 / E171

    1-CVT

    CORE 1

    200VA

    CLASS: 3P

  • MAINMAIN--1 PROTECTION FOR LINE1 PROTECTION FOR LINE(4CT METHOD) (NEW DEVELOPMENT)(4CT METHOD) (NEW DEVELOPMENT)

    3 3 3

    3 3 3IR5 / A511IY5 / A531IB5 / A551

    IN5 / A571

    1-CT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    2-BCT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    5S4 5S4 5S4

    5S25S2 5S2

    P2P2P2 CT MB

    CT MB

    P2P2P2

    5S4 5S4 5S4

    5S25S2 5S2

    VR11 / E111VY11 / E131VB11 / E151VN11 / E171

    1-CVT

    CORE 1

    200VA

    CLASS: 3P

    IA =250.10 AIB =250.10 A IC =250.10 AVAB =400.0 KVVBC =400.0 KVVCA =400.0 KV

    ESC ENT

    ENABLEDTRIP TARGET RESET

    INSTTIMECOMMSOTFZONE1ZONE2ZONE3ZONE4

    PH-APH-BPH-CGND505179 RESET79 LOCKOUT

    SEL- 421PROTECTIONAUTOMATIONCONTROL

    SELIR5 / A511IY5 / A531IB5 / A551

    IN5 / A571

  • MAINMAIN--1 PROTECTION FOR LINE1 PROTECTION FOR LINE(5CT METHOD)(5CT METHOD)

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REL 521REL 5213 3 3

    IR5 / A511IY5 / A531IB5 / A551

    IN5 / A571

    1-LCT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    5S4 5S4 5S4

    5S25S2 5S2

    P2P2P2 CT MBVR11 / E111VY11 / E131VB11 / E151VN11 / E171

    1-CVT

    CORE 1

    200VA

    CLASS: 3P

  • MAINMAIN--2 PROTECTION FOR LINE2 PROTECTION FOR LINE(4CT METHOD)(4CT METHOD)

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REL 316REL 3163 3 3

    3 3 3IR4 / C411IY4 / C431IB4 / C451

    IN4 / C471

    1-CT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    2-BCT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    4S4 4S4 4S4

    4S24S2 4S2

    P2P2P2 CT MB

    CT MB

    P2P2P2

    4S4 4S4 4S4

    4S24S2 4S2

    VR21 / E211VY21 / E231VB21 / E251VN21 / E271

    1-CVT

    CORE 2

    200VA

    CLASS: 3P

    LBB / BFR

    RAICA

    LBB / BFR

    RAICA

    50ZT

    50Z

  • MAINMAIN--2 PROTECTION FOR LINE2 PROTECTION FOR LINE(4CT METHOD) ( NEW DEVELOPMENT)(4CT METHOD) ( NEW DEVELOPMENT)

    3 3 3

    3 3 3IR4 / C411IY4 / C431IB4 / C451

    IN4 / C471

    1-CT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    2-BCT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    4S4 4S4 4S4

    4S24S2 4S2

    P2P2P2 CT MB

    CT MB

    P2P2P2

    4S4 4S4 4S4

    4S24S2 4S2

    VR21 / E211VY21 / E231VB21 / E251VN21 / E271

    1-CVT

    CORE 2

    200VA

    CLASS: 3P

    IR4 / C411IY4 / C431IB4 / C451

    IN4 / C471

  • MULTI FUNCTION NUMERICAL RELAY FOR MULTI FUNCTION NUMERICAL RELAY FOR MULTI BREAKER, MULTI CT & CVT/PT APPLICATION MULTI BREAKER, MULTI CT & CVT/PT APPLICATION

    (NEW APPLICATION) (ONE & HALF BREAKER SYSTEM or RING BUS SYSTEM)(NEW APPLICATION) (ONE & HALF BREAKER SYSTEM or RING BUS SYSTEM)

    1-52 CB 2-52 CB 3-52 CB3 3

    LINE

    1-52,2-52: MAIN & TIE CIRCUIT BREAKER21P: PHASE DISTANCE PROTECTION21G: GROUND DISTANCE PROTECTION27: UNDER VOLTAGE RELAY67: DIRECTIONAL RELAY50: INST OVER CURRENT RELAY51: TIME OVER CURRENT RELAY59: OVER VOLTAGE RELAY64: EARTH FAULT RELAY50BF-1: LBB/BFR OF MAIN CB50BF-2: LBB/BFR OF TIE CB79-1,2: AUTO RECLOSURE RELAY OF

    MAIN & TIE CB25-1,2: CHECK SYNCHRONISAM RELAYFOR MAIN & TIE CB

    67 50 BF-1 50 BF-2

    21G 79-1 79-2

    21P 25-1 25-2

    50 51 27 59

    3

    3

    3

    33

    3

    BUS-1 PT BUS-2 PT

    LINE CVT

  • MAINMAIN--2 PROTECTION FOR LINE2 PROTECTION FOR LINE(5CT METHOD)(5CT METHOD)

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REL 316REL 3163 3 3

    IR4 / C411IY4 / C431IB4 / C451

    IN4 / C471

    1-LCT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    4S4 4S4 4S4

    4S24S2 4S2

    P2P2P2 CT MBVR21 / E211VY21 / E231VB21 / E251VN21 / E271

    1-CVT

    CORE 2

    200VA

    CLASS: 3P

  • MULTI FUNCTION PANEL METERING & ENERGY METERMULTI FUNCTION PANEL METERING & ENERGY METER(4CT METHOD)(4CT METHOD)

    3 3 3

    3 3 3IR3 / D311IY3 / D331IB3 / D351

    IN3 / D371

    1-CT

    CORE-3CTR: 2000-1000-500/1A

    CLASS: 0.5

    2-BCT

    CORE-3CTR: 2000-1000-500/1A

    CLASS: 0.5

    3S4 3S4 3S4

    3S23S2 3S2

    P2P2P2 CT MB

    CT MB

    3S4 3S4 3S4

    3S23S2 3S2

    VR31 / E311VY31 / E331VB31 / E351

    VN31 / E371

    1-CVT

    CORE 3

    100VA

    CLASS: 0.5P2P2P2

    LD/G MVAR

    + MWATTS

    KVOLTS

    AMPS

    PANEL METER

  • 3 3 3

    IR3 / D311IY3 / D331IB3 / D351

    IN3 / D371

    1-LCT

    CORE-3CTR: 2000-1000-500/1A

    CLASS: 0.5/0.2

    3S4 3S4 3S4

    3S23S2 3S2

    P2P2P2 CT MB

    VR31 / E311VY31 / E331VB31 / E351

    VN31 / E371

    1-CVT

    CORE 3

    100VA

    CLASS: 0.5/0.2

    LD/G MVAR

    + MWATTS

    KVOLTS

    AMPS

    PANEL METER

    MULTI FUNCTION PANEL METERING & ENERGY METERMULTI FUNCTION PANEL METERING & ENERGY METER(5CT METHOD)(5CT METHOD)

  • BUSBARBUSBARPROTECTIONPROTECTION

    SCHEMES SCHEMES ADOPTED INADOPTED IN

    ONE AND HALFONE AND HALFCIRCUIT BREAKER CIRCUIT BREAKER

    SCHEMESCHEMEPREPARED BY

    GOPALA KRISHNA PALEPUADE/MRT(PROTECTION)

  • BASICS OF BUSBAR PROTECTIONBASICS OF BUSBAR PROTECTIONNEED FOR BUSBAR PROTECTIONNEED FOR BUSBAR PROTECTION

    IN ITS ABSENCE FAULT CLEARING TAKES PLACE IN ZONE-2 OF DISTANCE RELAY BY REMOTE END TRIPPING.

    THIS MEANS SLOW AND UNSELECTIVE TRIPPING AND WIDE SPREAD BLACKOUT.EFFECT OF DELAYED CLEARENCEEFFECT OF DELAYED CLEARENCE

    GREATER DAMAGE AT FAULT POINT.INDIRECT SHOCK TO CONNECTED EQUIPMENT LIKE SHAFTS OF

    GENERATOR AND WINDINGS OF TRANSFORMER.BASIC THEORYBASIC THEORY

    KIRCHOFFs CURRENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING AT THAT NODE.BUS BAR PROTECTION SYSTEMSBUS BAR PROTECTION SYSTEMSLOW IMPEDENCE DIFFERENTIAL PROTECTION

    THE MOST SUITABLE PROTECTION SCHEME FOR DOUBLE AND MULTIPLE BUSBAR SYSTEMS (WITH OR WITHOUT TRANSFER BUS) WITH FEEDERS BEINGSWITCHED BETWEEN SECTIONS OF BUSBAR, WHICH OPERATES WITH FULL SELECTIVITY FOR ALL POSSIBLE BUSBAR CONFIGUARATIONS.HIGH IMPEDENCE DIFFERENCIAL PROTECTION

    THE HIGH IMPEDENCE PROTECTION SCHEME, ON THE OTHER HAND, IS A GOOD SOLUTION FOR SINGLE BUSBAR ARRANGEMENTS , ONE & HALF BREAKER SYSTEMS OR RING BUSBARS, PROVIDING THAT APPROPRIATE DEDICATED CTCORES ARE AVAILABLE FOR THIS USE ALONE.

  • HIGH IMPEDENCE DIFFERENCIAL PROTECTIONSENSTIVE, STABLE & FAST PROTECTION FOR SINGLE BUSBAR

    ARRANGEMENTS AND ONE & HALF BREAKER SYSTEMS. THE SYSTEM HAS LIMITS WHEN USED IN COMPLEX BUSBAR CONFIGUARATIONS.

    HOWEVER, SPECIAL CT REQUIREMENTS, ADDITIONAL HIGH VOLTAGE DEVICE PROTECTION, DEMANDING MAINTANENCE ETC PUT RESTRICTIONS IN ITS APPLICATIONS.LIMITATIONS OF CONVENTIONAL HIGH IMPEDENCE DIFFERENTIAL RELAYPUTS STRINGENT REQUIREMENTS ON CTs.NEED FOR DEDICATED CT CORES.IDENTICAL CT RATIO, MAGNETISING IMPEDENCE.AUX CTs RATIO CORRECTIONS UNACCEPTABLE.IN ABILITY TO COPE WITH INCREASING FAULT CURRENT.SLOW RESPONSE.BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 20ms.

    THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIP COMMAND IS ONLY GIVEN WHEN BOTH A DISCRIMINATING & CHECK ZONE SYSTEM OPERATES.LOW IMPEDENCE DIFFERENTIAL PROTECTION

    LOW IMPEDENCE PROTECTION(PERCENTAGE BIASED BUS DIFFERENTIAL RELAY) IS PREFARABLE FOR THE PROTECTION OF DOUBLE AND MULTIPLE BUSBAR SYSTEMS.ADVANTAGES

    FREE OF ANY NEED FOR MATCHED CT CHARACTERESTICS OR RATIOs, LOW LEAKAGE REACTANCE OR RESISTANCE.

    OTHER PROTECTIVE RELAYS CAN BE INCLUDED IN THE SAME CIRCUIT.STABLE FOR INFINITE FAULT LEVELS. INSENSITIVE TO CT SATURATION.DETECTS FAULTS WITHIN 1 2ms & INITIATES TRIPPING WITHIN 5 7ms.

  • BASICS OF BUS BAR PROTECTIONBASICS OF BUS BAR PROTECTIONBASIC THEORY

    EXTERNAL FAULT

    KIRCHOFFs CURENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING THAT NODE

    I6

    I4

    I2

    I5

    I3

    I1

    IF

    IF= I6= I1+I2+I3+I4+I5

    INTERNAL FAULT

    I6

    I4

    I2

    I5

    I3

    I1IF

    IF= I1+I2+I3+I4+I5+I6

  • DIFFERENCE BETWEEN BUSBAR SCHEMESDIFFERENCE BETWEEN BUSBAR SCHEMESDETAILSDETAILS HIGH IMPEDENCE BUSBAR HIGH IMPEDENCE BUSBAR

    PROTECTIONPROTECTIONPERCENTAGE BIASED LOW PERCENTAGE BIASED LOW

    IMPEDENCE BUS BAR IMPEDENCE BUS BAR PROTECTIONPROTECTION

    PRINCIPLE THE CURRENTS ENTERING AND LEAVING THE BUSBAR ARE COMPARED CONTINUOSLY. IT INVOLVES CHOOSING OF IMPEDENCE HIGH ENOUGH STABLISE THE RELAY FOR HEAVY EXTERNAL FAULTS

    IT HAS DIFFERENTIAL AND BIAS SETTING. THE RESULTANT BIAS IS PROPOTIONAL TO ARITHMATIC SUM OF ALL CURRENTS, WHEREAS THE OPERATING CURRENT IS VECTOR SUM OF ALL CIRCUIT CURRENTS.

    CTs IT REQUIRES ALL IDENTICAL CT RATIOs & TURNS RATIO. LOW RESISTANCE OF SECONDARY WINDINGMINIMUM KNEE POINT VOLTAGE OF 300-500V.LOW MAGNETISING CURRENT(FEW MILLIAMPS).

    IT CAN WORK WITH CTs OF UNEQUAL RATIOS ALSO. FREE OF ANY NEED OF MATCHED CT CHARACTERESTIC OR RATIOs LOW LEAKAGE REACTANCE OR RESISTANCE. OTHER PROTECTIVE RELAYS CAN BE INCLUDED IN THE SAME CIRCUIT.

    BURDEN IMPOSES COMPARATIVELY HIGH BURDEN ON CTs. AUXILIARY CTs REDUCE THE PERFORMANCE OF THE SCHEME

    IMPOSES LESS BURDEN ON CTs. AUXILIARY CTs HAVE NO EFFECT ON PERFORMANCE OF SCHEME.

    CT SATURATION OPERATION OF SCHEME EVEN WHEN CTs GET SATURATED DURING INTERNAL FAULTS.OPERATION OF SCHEME EVEN WHEN CTs GET SATURATED DURING INTERNAL FAULTS. INSENSITIVE TO CT SATURATION.

    UTILISATION IT IS GOOD SOLUTION FOR SINGLE BUSBAR ARRANGEMENTS, ONE & HALF BREAKER SYSTEMS OR RING BUSBAR SYSTEMS.

    MOST SUITABLE FOR DOUBLE AND MULTIPLE BUSBAR SYSTEMS ( WITH OR WITHOUT TRANSFER BUS).

    OPERATING TIME

    BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 20 Ms.

    DETECTS FAULTS WITH IN 1 2 Ms AND INITIATES TRIPPING WITH IN 5-7mS.

    STABILITY INABILITY TO COPE WITH INCREASING FAULT CURRENTSTABLE FOR INFINITE FAULT LEVEL.

    PERFORMANCE HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELY STABLE FOR EXTERNAL FAULTS.HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELY STABLE FOR EXTERNAL FAULTS.

    ADDITIONAL PROTECTION

    THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIP COMMAND IS ONLY GIVEN WHEN BOTH A DISCRIMINATING & CHECK ZONE SYSTEM OPERATES.

    THIS RELAY HAS IN BUILT CHECK ZONE FEATURE (NO SEPARATE CHECKZONE FEATURE) i.e OVER CURRENT STARTING RELAY PROVIDED.

  • BUS BAR PROTECTIONBUS BAR PROTECTION(4CT & 5CT METHOD)(4CT & 5CT METHOD)

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REB 521REB 521

    3 3 3

    3 3 3

    IR1 / B111IY1 / B131IB1 / B151

    IN1 / B1711-CT

    CORE-1CTR: 2000-1000/1A

    CLASS: PS

    3-CT

    CORE-1CTR: 2000-1000/1A

    CLASS: PS

    1S3 1S3 1S3

    1S11S1 1S1

    P2P2P2 CT MB

    CT MB

    P2P2P2

    1S3 1S3 1S3

    1S11S1 1S1

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REB 316REB 316

    BUS BAR PROTECTION

    FOR BUS-1

    BUS BAR PROTECTION

    FOR BUS-2

    IR1 / B111IY1 / B131IB1 / B151

    IN1 / B171

  • BUS BAR PROTECTIONBUS BAR PROTECTIONABB RADSS BUS BARABB RADSS BUS BAR--2 PROTECTION2 PROTECTION

    ABB RADSS BUS BARABB RADSS BUS BAR--1 PROTECTION1 PROTECTIONBUS-1

    BUS-2

    3

    31CT1-52CB

    2-52CB

    3-52CB

    3CT 3

    34CT4-52CB

    5-52CB

    6-52CB

    6CT 3

    37CT7-52CB

    8-52CB

    9-52CB

    9CT 3

    310CT10-52CB

    11-52CB

    12-52CB

    12CT 3

    313CT13-52CB

    14-52CB

    15-52CB

    15CT 3

    316CT16-52CB

    17-52CB

    18-52CB

    18CT

  • BUSBARBUSBAR--1 PROTECTION TRIPPING SCHEME1 PROTECTION TRIPPING SCHEME

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REB 521REB 521

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 11--52 CB52 CB

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    11--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    44--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    77--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    1010--52CB PANEL52CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    1313--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    1616--52 CB PANEL52 CB PANEL

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 44--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 77--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 1010--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 1313--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 1616--52 CB52 CB

    11--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    44--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    77--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    1010--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    1313--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    1616--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    +VE BUSBAR PANEL

  • BUSBARBUSBAR--2 PROTECTION TRIPPING SCHEME2 PROTECTION TRIPPING SCHEME

    C

    E

    DISPLAY

    ACTIVE START TRIP

    REB 316REB 316

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 33--52 CB52 CB

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    33--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    66--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    99--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    1212--52CB PANEL52CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    1515--52 CB PANEL52 CB PANEL

    TO CLOSE CKT INTERLOCKTO BLOCK A/RTO TRIP COIL-1TO TRIP COIL-2DIRECT TRIP SEND CH-1DIRECT TRIP SEND CH-2TO DISTURBENCE RECORDER

    1818--52 CB PANEL52 CB PANEL

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 66--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 99--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 1212--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 1515--52 CB52 CB

    HIGH SPEEDHIGH SPEEDTRIP RELAYTRIP RELAY

    FOR FOR 1818--52 CB52 CB

    33--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    66--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    99--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    1212--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    1515--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    1818--52 CB PANEL52 CB PANELTRIP FROM 50 LBB

    TO START 50 LBB

    +VE BUSBAR PANEL

  • MISCELENEOUSMISCELENEOUSRELAYS & PROTECTIONSRELAYS & PROTECTIONS

    ADOPTED FOR LINE INADOPTED FOR LINE INONE AND HALF ONE AND HALF

    CIRCUIT BREAKERCIRCUIT BREAKERSCHEME SCHEME

    (STUB, TEED, LBB/BFR AND AUTO (STUB, TEED, LBB/BFR AND AUTO RECLOSURE FUNCTIONS)RECLOSURE FUNCTIONS)

    PREPARED BYGOPALA KRISHNA PALEPU

    ADE/MRT(PROTECTION)

  • STUBSTUB--1/ STUB1/ STUB--2 PROTECTION2 PROTECTION1-52CB 2-52CB 3-52CBBUS-1 BUS-23 3

    33

    LINE-1 AT/F-1

    STUB-1&2(BAY 1&2)

    WHEN A LINE IS SUPPLIED VIA TWO CIRCUIT BREAKERS IN A ONE & HALFWHEN A LINE IS SUPPLIED VIA TWO CIRCUIT BREAKERS IN A ONE & HALF CIRCUIT CIRCUIT BREAKER ARRANGEMENT, THE LINE PROTECTION INCLUDES THE AREA BETWEBREAKER ARRANGEMENT, THE LINE PROTECTION INCLUDES THE AREA BETWEEN THE TWO EN THE TWO CTs. HOWEVER, WHEN THE LINE ISOLATOR IS OPEN THE LINE CVTs FCTs. HOWEVER, WHEN THE LINE ISOLATOR IS OPEN THE LINE CVTs FOR THE DISTANCE OR THE DISTANCE PROTECTION ARE CONNECTED TO THE LINE AND CANNOT PROVIDE THE CORPROTECTION ARE CONNECTED TO THE LINE AND CANNOT PROVIDE THE CORRECT RECT VOLTAGE FOR THE STUB END.(i.e THE AREA BETWEEN THE LINE ISOLATOVOLTAGE FOR THE STUB END.(i.e THE AREA BETWEEN THE LINE ISOLATOR AND CTs) R AND CTs) (STUB = DEAD END)(STUB = DEAD END)

    TO PROVIDE PROTECTION FOR A FAULT IN THIS AREA, REL 521/ REL 316TO PROVIDE PROTECTION FOR A FAULT IN THIS AREA, REL 521/ REL 316 IS IS PROVIDED WITH A STUB PROTECTION WHICH GIVES AN BUS OVER CURRENT PROVIDED WITH A STUB PROTECTION WHICH GIVES AN BUS OVER CURRENT TRIP IF THE TRIP IF THE LINE ISOLATOR IS OPEN AND THE CURRENT EXCEEDS THE SET VALUE IN LINE ISOLATOR IS OPEN AND THE CURRENT EXCEEDS THE SET VALUE IN ANY PHASE.ANY PHASE.

    STUBSTUB--1 (BAY 1&2) 1 (BAY 1&2) OPERATESOPERATES

    IT OPERATES THE 3PH TRIP GRIT OPERATES THE 3PH TRIP GR--A MAIN CB (1A MAIN CB (1--52CB) 52CB) AND 3PH TRIP GRAND 3PH TRIP GR--A TIE CB (2A TIE CB (2--52CB)52CB)

    STUBSTUB--2 (BAY 1&2) 2 (BAY 1&2) OPERATESOPERATES

    IT OPERATES THE 3PH TRIP GRIT OPERATES THE 3PH TRIP GR--B MAIN CB (1B MAIN CB (1--52CB) 52CB) AND 3PH TRIP GRAND 3PH TRIP GR--B TIE CB (2B TIE CB (2--52CB)52CB)

    1-89L

    REL 521REL 521

    REL 316REL 316

    DISTANCE RELAYS CONVERTED TODISTANCE RELAYS CONVERTED TOSTUB/BUS OVER LOAD RELAYSSTUB/BUS OVER LOAD RELAYSWHEN LINE ISOLATOR OPENSWHEN LINE ISOLATOR OPENS

  • STUB PROTECTION TRIP SCHEMESTUB PROTECTION TRIP SCHEME

    BUS-1 BUS-2

    1-52CB 2-52CB

    8686--AAMTR/MTR/HSTRHSTR

    ABBABBREL521REL521MAINMAIN--11

    8686--BBMTR/MTR/HSTRHSTR

    8686--BBMTR/MTR/HSTRHSTR

    8686--AAMTR/MTR/HSTRHSTR

    ABBABBREL521REL521STUBSTUB--11

    ABBABBREL316REL316STUBSTUB--22

    TRIP COIL-1 TRIP COIL-1

    TRIP COIL-2 TRIP COIL-2

    8686--A : GROUPA : GROUP--A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 8686--B : GROUPB : GROUP--B MASTER TRIP RELAY / HIGH SPEED TRIP RELAYB MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

    LINE ISOLATOR OPENS THIS INTERLINE ISOLATOR OPENS THIS INTERLOCK WILL INITIATE MAINLOCK WILL INITIATE MAIN--1 REL 521 1 REL 521 & CONVERTED STUB& CONVERTED STUB--1 PROTECTION1 PROTECTION

    LINE ISOLATOR OPENS THIS INTERLINE ISOLATOR OPENS THIS INTERLOCK WILL INITIATE MAINLOCK WILL INITIATE MAIN--2 REL 316 2 REL 316 & CONVERTED STUB& CONVERTED STUB--2 PROTECTION2 PROTECTION

  • TEEDTEED--1 PROTECTION1 PROTECTION{BAY1&2}(5CT METHOD){BAY1&2}(5CT METHOD)

    C

    E

    DISPLAY

    ACTIVE START TRIP

    RADHARADHA

    3 3 3

    3 3 31-CT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    1-LCT

    CORE-1CTR: 2000-1000/1A

    CLASS: PS

    P2P2P2

    P1P1P1

    3 3 32-CT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    P1P1P1P2P2P2

    P1P1P1

    P2P2P2

    5S4 5S4 5S4

    5S25S2 5S2

    5S4 5S4 5S4

    5S25S2 5S2

    1S4 1S4 1S4

    1S11S1 1S1TEED-1 PROTECTION FOR BAY 2&3 IS ALSO SAME AS ABOVE AND THE FOLLOWING CTs & CORES ARE USED3-CT(CORE-5), 2-CT(CORE-1) & 3-TCT(CORE-1) ARE STARRED AND CONNECTED TO TEED-1 PROTECTION

    IR5IY5IB5

    IN5

    IR5IY5IB5

    IN5

    IR1IY1IB1

    IN1

  • TEEDTEED--2 PROTECTION2 PROTECTION{BAY1&2}(5CT METHOD){BAY1&2}(5CT METHOD)

    3 3 3

    3 3 3

    1-CT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    1-LCT

    CORE-2CTR: 2000-1000/1A

    CLASS: PS

    4S4 4S4 4S4

    4S24S2 4S2

    P2P2P2 CT MB

    CT MBP2P2P2

    2S2 2S2 2S2

    2S32S3 2S3

    3 3 3

    2-CT

    CORE-4CTR: 2000-1000-500/1A

    CLASS: PS

    4S2 4S2 4S2

    4S44S4 4S4

    P2P2P2CT MB

    C

    E

    DISPLAY

    ACTIVE START TRIP

    RADSBRADSB

    R

    A

    I

    C

    A

    L

    B

    B

    /

    B

    F

    R

    R

    A

    I

    C

    A

    L

    B

    B

    /

    B

    F

    R

    TEED-2 PROTECTION FOR BAY 2&3 IS ALSO SAME AS ABOVE AND THE FOLLOWING CTs & CORES ARE USED

    3-CT(CORE-4), 2-CT(CORE-2) &

    3-TCT(CORE-2) ARE CONNECTED TO

    TEED-2 PROTECTION

  • TEEDTEED--1/ TEED1/ TEED--2 PROTECTION2 PROTECTION1-52CB 2-52CB 3-52CBBUS-1 BUS-2

    3

    3 3

    3

    3

    LINE-1 AT/F-1

    TEED-1&2(BAY 1&2)

    TEED-1&2(BAY 2&3)

    TEED PROTECTION IS BASED ON KIRCHOFFS CURRENT LAW. THREE SETS OTEED PROTECTION IS BASED ON KIRCHOFFS CURRENT LAW. THREE SETS OF CTSF CTSARE CONNECTED IN STAR FASHION. SOME OF THE CURRENTS MUST BE ZERARE CONNECTED IN STAR FASHION. SOME OF THE CURRENTS MUST BE ZERO. IF ANY O. IF ANY UNBALANCE CURRENTS ARE NOTICED THEN IMMEDIATELY TEED PROTECTION UNBALANCE CURRENTS ARE NOTICED THEN IMMEDIATELY TEED PROTECTION OPERATES. IF TEED PROTECTION BAY 1&2 OPERATED THEN IT TRIPS 1OPERATES. IF TEED PROTECTION BAY 1&2 OPERATED THEN IT TRIPS 1--52CB & 252CB & 2--52CB. 52CB. SIMILARLY IF TEED PROTECTION BAY 2&3 OPERATED THEN IT TRIPS 2SIMILARLY IF TEED PROTECTION BAY 2&3 OPERATED THEN IT TRIPS 2--52CB & 352CB & 3--52CB.52CB.

    TEEDTEED--11PROTECTIONPROTECTION

    SUMMATION OF INDIVIDUAL PHASES OF T-SHAPED 3 CTs BEFORE REACHING TO RELAY. THE CURRENT

    FLOWING THROUGH IN 3-PHASES AFTER SUMMATION IS ZERO DURING BALANCED CONDITION.

    HIGH IMPENDENCE THREE PHASE DIFFERENTIAL HIGH IMPENDENCE THREE PHASE DIFFERENTIAL RELAY IS USED AS TEEDRELAY IS USED AS TEED--1 PROTECTION.1 PROTECTION.

    TEEDTEED--22PROTECTIONPROTECTION

    T- SHAPED 3 CTs ARE CONNECTED TO RELAY. THE RELAY HAVING OPERATING COIL & RESTAIRING

    COIL. BASED ON THE DIFFERENTIAL CURRENT FLOWING THROUGH THE OPERATING COIL THE

    RELAY OPERATES.LOW IMPEDENCE PERCENTAGE BIASED THREE LOW IMPEDENCE PERCENTAGE BIASED THREE

    TERMINAL THREE PHASE DIFFERENTIAL RELAY IS TERMINAL THREE PHASE DIFFERENTIAL RELAY IS USED AS TEEDUSED AS TEED--2 PROTECTION.2 PROTECTION.

  • TEED PROTECTION TRIP SCHEMETEED PROTECTION TRIP SCHEME

    BUS-1 BUS-2

    1-52CB 3-52CB2-52CB

    8686--AAMTR/MTR/HSTRHSTR

    ABBABBREL521REL521MAINMAIN--11

    8686--BBMTR/MTR/HSTRHSTR

    8686--BBMTR/MTR/HSTRHSTR

    8686--AAMTR/MTR/HSTRHSTR

    8686--BBMTR/MTR/HSTRHSTR

    8686--AAMTR/MTR/HSTRHSTR

    ABBABBRADHARADHATEEDTEED--11

    ABBABBRADSBRADSBTEEDTEED--22

    ABBABBRADHARADHATEEDTEED--11

    ABBABBRADSBRADSBTEEDTEED--22

    TRIP COIL-1 TRIP COIL-1 TRIP COIL-1

    TRIP COIL-2 TRIP COIL-2 TRIP COIL-2

    8686--A : GROUPA : GROUP--A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 8686--B : GROUPB : GROUP--B MASTER TRIP RELAY / HIGH SPEED TRIP RELAYB MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

  • BASICS OF LBB/BFR PROTECTIONBASICS OF LBB/BFR PROTECTIONLOCAL BREAKER BACKUP PROTECTIONLOCAL BREAKER BACKUP PROTECTION

    A PROTECTION WHICH IS DESIGNED TO CLEAR A SYSTEM FAULTY BY INITIATING TRIPPING OTHER CIRCUIT BREAKER(S) IN THE CASE OF FAILURE TO TRIP OF THE APPROPRIATE CIRCUIT BREAKER.

    IN MODERN NETWORKS THE CRITICAL FAULT CLEARING TIME MAY BE LESS THAN 200ms. HENCE, IF THE FAULT IS NOT CLEARED DUE TO FAILURE OF THE PRIMARY PROTECTIVE RELAYS OR THEIR ASSOCIATED CIRCUIT BREAKER, A FAST ACTING BACK-UP PROTECTIVE RELAY MUST CLEAR THE FAULT.THERE ARE TWO BASIC FORMS.REMOTE BACK-UP.LOCAL BACK-UP.

    REMOTE BACKREMOTE BACK--UPUPPROVIDES BACK-UP PROTECTION FOR THE BOTH THE RELAYS

    (MAIN-1 & MAIN-2) AND BREAKERS AT REMOTE SUBSTATION.

    LOCALLOCAL BACKBACK--UPUPLOCAL BACK-UP PROTECTION CAN BE DEVIDED INTO TWO CATAGORIES.RELAY BACK-UPBREAKER BACK-UP

  • RELAY BACKRELAY BACK--UPUPz DUPLICATE PRIMARY PROTECTION. i.e ONE IS NON SWITCHED

    DISTANCE PROTECTION AND ANOTHER IS SWITCHED DISTANCE SCHEME OR OTHER WISE BOTH SCHEMES CHARECTERSTICS ARE DIFFERENT (QUADRALATERAL, MHO CIRCULAR, TAMOTO & OPTICAL ) OR DIFFERENT MANUFACTURERS(ABB, ALSTOM, SIEMENS, EASUN REYROLL, SEL, GE, NXT PHASE OR BASLER) OR DIFFERENT METHODS (i.eELECTROMECHANICAL, STATIC, NUMERICAL{MICROPROCESSOR &DSP}).

    IF MAIN-1 & MAIN-2 ARE NUMERICAL RELAYS BOTH SHOULD BE SEPARATE CHARECTERESTICS AND SEPARATE MODELS AND ALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYS SHOULD BE 100% REDENDENCY IN ALL ASPECTS

    TO INCREASE THE SECURITY, THE CIRCUIT BREAKER HAS TWO TRIP COILS, ONE IS CONNECTED TO MAIN-1 PROTECTION AND ANOTHER IS CONNECTED TO MAIN-2 PROTECTION.

    BREAKER BACKBREAKER BACK--UPUPBECAUSE OF THE HIGH COST OF HIGH VOLTAGE CIRCUIT

    BREAKERS, IT IS NOT FEASIBLE TO DUPLICATE THEM.IN CASE OF A BREAKER FAILURE THE OTHER CIRCUIT BREAKERS

    CONNECTED TO THE SAME BUS AS THE FAULTED BREAKER MUST THERE FORE BE TRIPPED.

  • LBB/BFR FLOW CHARTLBB/BFR FLOW CHART

    MAIN PROTECTIONOPERATED

    YES

    YES

    TRIP MAIN

    BREAKER

    INITIATEBFR

    WAIT FOR FAULT

    CLEARENCEAND

    FAULT CLEARED

    YES

    NO

    RESETBREAKER FAILURE SCHEME

    TRIPBACK-UP

    BREAKERS

  • LBB/BFR TIME COLBB/BFR TIME CO--ORDINATION CHARTORDINATION CHARTFAULT OCCURS

    NORMAL CLEARING

    INOPERATIVEBREAKER

    BREAKER INTURUPTING TIME

    PROTECTIVE RELAYFOR EX: DISTANCE RELAY

    NORMAL CLEARING TIME

    BREAKER FAILURE RELAY START

    MARGIN

    RESETTING TIME OF THE CURRENT MEASURING UNITS

    SET TIME OF THE TIME MEASURING UNIT TRIPPING RELAYTIME

    BACK-UP BREAKERINTERUPTING TIME

    TOTAL CLEARING TIME OF THE BREAKER FAILURE RELAY

    MARGIN

    MAXIMUM FAULT CLEARING TIME BEFORE SYSTEM INSTABILITY

    ~30ms ~60ms

  • LBB/BFR LOGICLBB/BFR LOGICPHASE L1

    PHASE L2/E

    PHASE L3

    CURRENT INPUTS

    ~

    |||

    A/DCONVERTER

    &I > ISET

    I > ISET

    PHASE CURRENT SET POINT

    EARTH CURRENT SET POINT

    &

    CIRCUIT BREAKER FAILURE INITIATE

    BINARY INPUT

    OUT PUT OF DISTANCE RELAY ORSHORT CIRCUIT CURRENT RELAY

    > 1

    TIMING/OUTPUT STAGE

    0 1

    0 1

    TIME STAGE T1

    TIME STAGE T2

    TIME STAGE T2SWITCHED OFF

    &

    &

    &

    O

    > 1

    LEDCB FAILURE

    INITIATE

    LED

    TRIP T2RELAY

    ALARM T1 RELAY

    LED

    TRIP T1 RELAY

    LED(PHASE START)

    LED(EARTH START)

    ALARM RELAY(PHASE START)

    ALARM RELAY(EARTH START)

  • LBB/BFR PROTECTIONLBB/BFR PROTECTION

    1-52CB 2-52CB 3-52CBBUS-1 BUS-2

    LINE1 AT/F-1

    LBB / BFR

    RAICA

    50ZT

    LBB / BFR

    RAICA

    50ZLBB / BFR

    RAICA

    50Z LBB/BFR IS LOCAL BREAKER BACKUP PROTECTION/ BREAKER FAILURE RELALBB/BFR IS LOCAL BREAKER BACKUP PROTECTION/ BREAKER FAILURE RELAY.Y. 1No RELAY IS PROVIDED FOR EACH BREAKER.1No RELAY IS PROVIDED FOR EACH BREAKER. THIS IS CURRENT OPERATED RELAY.THIS IS CURRENT OPERATED RELAY. THIS RELAY IS ENERGISED WHEN MASTER TRIP RELAY(86THIS RELAY IS ENERGISED WHEN MASTER TRIP RELAY(86--A & 86A & 86--B) OPERATES B) OPERATES

    AND GIVEN SIGNAL TO BREAKER FOR TRIP. AND GIVEN SIGNAL TO BREAKER FOR TRIP. IN THIS RELAY TIME DELAY IS PROVIDED.IN THIS RELAY TIME DELAY IS PROVIDED. THIS RELAY OPERATES WHEN THE BREAKER IS UNDER TROUBLE/ FAILS TO THIS RELAY OPERATES WHEN THE BREAKER IS UNDER TROUBLE/ FAILS TO

    OPERATE. OPERATE. AFTER ENERGISED THE RELAY AND TIME DELAY COMPLETES, EVEN CURRENTAFTER ENERGISED THE RELAY AND TIME DELAY COMPLETES, EVEN CURRENT

    IS THERE THIS THINKS BREAKER FAIL TO OPERATE AND GIVEN SIGNAL ASIS THERE THIS THINKS BREAKER FAIL TO OPERATE AND GIVEN SIGNAL AS PER PER SCHEME DESCRIBED NEXT PRESENTATION.SCHEME DESCRIBED NEXT PRESENTATION.

  • 11--52 CB LBB/BFR OPERATION52 CB LBB/BFR OPERATION

    BUS-1 BUS-2

    1-52CB 3-52CB2-52CB

    8

    6

    8

    6

    -

    -

    A

    A

    8

    6

    8

    6

    -

    -

    B

    B

    ABBABBREL521REL521MAINMAIN--11

    ABBABBREL316REL316MAINMAIN--22

    INITIALISATION

    LBB/BFRLBB/BFRTIMETIME

    DELAYDELAY

    8

    6

    8

    6

    -

    -

    A

    A

    8

    6

    8

    6

    -

    -

    B

    B

    TC-1 TC-2

    BUSBAR-1 PROTECTION OPTD

    AND BUSBAR-1 ISOLATED

    DIRECT TRIP 1&2VIA CARRIER TO

    OTHER END

    TC-1TC-2

  • 22--52 CB LBB/BFR OPERATION52 CB LBB/BFR OPERATION

    BUS-1 BUS-2

    1-52CB 3-52CB2-52CB

    ABBABBREL521REL521MAINMAIN--11

    ABBABBREL316REL316MAINMAIN--22

    INITIALISATION

    LBB/BFRLBB/BFRTIMETIME

    DELAYDELAY8

    6

    8

    6

    -

    -

    A

    A

    8

    6

    8

    6

    -

    -

    B

    B

    TC-1 TC-2

    ABBABBRET521RET521MAINMAIN--11

    ABBABBRET316RET316MAINMAIN--22

    TO 86-B TRIP RELAYOF LINE CB(1-52CB)

    DIRECT TRIP 1&2VIA CARRIER

    TO OTHER END

    TO 86-B TRIP RELAYOF AT/F(ICT) CB

    (3-52CB)

    INTER TRIP TOLVCB & TBCCB

  • 33--52 CB LBB/BFR OPERATION52 CB LBB/BFR OPERATION

    BUS-1 BUS-2

    1-52CB 3-52CB2-52CB

    8

    6

    8

    6

    -

    -

    A

    A

    8

    6

    8

    6

    -

    -

    B

    B

    ABBABBRET521RET521MAINMAIN--11

    ABBABBRET316RET316MAINMAIN--22

    INITIALISATION

    LBB/BFRLBB/BFRTIMETIME

    DELAYDELAY

    8

    6

    8

    6

    -

    -

    A

    A

    8

    6

    8

    6

    -

    -

    B

    B

    TC-1 TC-2 TC-1TC-2

    BUSBAR-2PROTECTION OPTD

    AND BUSBAR-2 ISOLATED

    INTER TRIP TO LV CB & TBC CB

  • AUTO RECLOSURE BASICSAUTO RECLOSURE BASICS FAULTS ARE THREE TYPES

    1. TRANSIENT FAULT: These are cleared by the immediate tripping of Circuit Breakers and do not reoccur when the line is re-energized.2. SEMI-PERMANENT FAULTS: These require a time interval to disappear before a line is charged again.3. PERMANENT FAULTS: These are to be located and repaired before the line is re-energized.

    About 80-90% of the faults occurring are transient in nature. Hence the Automatic Reclosure of breaker (after tripping on Fault) will result in the line being successfully re-energized.

    ADVANTAGES:A. Decreasing outage time.B. Improving Reliability.C. Improving system stability.D. Reduce fault damage and Maintenance Time.

    DEAD TIME: The time between the Auto-reclosing Scheme being energized and the operation of the contacts which energize the Circuit Breaker closing circuit.

    RECLAIM TIME: The Time Following a successful closing operation measured from the instant the Auto-Reclosing relay closing contacts make which must elapse before the Auto-Reclosing relay initiates another reclosing attempt. In other words, it may be said to be the time between 1st and 2ndAuto-Reclosure.

  • TYPES OF AUTO-RECLOSING SCHEMES:1. BASED ON PHASE

    A. THREE PHASE AUTO-RECLOSING: This type of Auto-Reclosing causes an immediate drift part of the two systems and hence no interchange of synchronizing power can take place during the dead time. B. SINGLE PHASE AUTO-RECLOSING: In this, only the faulty phase(only SLG Faults) is reclosed without causing interruption in interchange synchronizing power between two systems through other two healthy phases.

    2. BASED ON ATTEMPTS OF RECLOSUREA. SINGLE SHOT AUTO-RECLOSING: In this scheme, Breaker is reclosed only once on a given fault before lockout of Circuit Breaker Occurs. High-Speed Auto-Reclosing for EHT System is invariably Single Shot.B. MULTI-SHOT AUTO-RECLOSING: In this scheme, more than one reclosing attempts made for a given fault before lockout of Circuit Breaker occurs.B.I. DISADVANTAGES: Repeated closure attempts has with high fault level would seriously affect the Circuit Breaker, Equipment and System Stability.B.ii. CIRCUIT BREAKER LIMITATIONS: Ability of Circuit Breaker to Perform several Trip Close operations in quick succession. B. iii. SYSTEM CONDITIONS: In the percentage of the semi-Permanent faults (which could be burnt out) is moderate, For example on the lines through the forest, multi shot Auto-Reclosing is followed.

    3. DEPENDING ON SPEED:A. HIGH-SPEED AUTO-RECLOSING: This aids in fast restoration of supply but should be done by taking into account the following factors.I. System disturbance time can be tolerated without loss of system stability.ii. Characteristics of Protection Schemes and Circuit Breaker. B. LOW SPPED OR DELAYED AUTO RECLOSING: This is suitable for highly interconnected systems where the loss of a single line is unlikely to cause two sections of the system to drift apart and loose synchronism.

  • METHOD OF ADOPTION IN ONE AND HALF BREAKER SYSTEM: The Auto-Reclosure Functions used for the Bus Breakers 1-52CB & 3-52CB are set as Masters and one for the Center Breaker 2-52CB(TIE) as Follower. Co-ordination is required between the Auto-Reclosure Functions. A Synchrocheck function is also loaded in each Relay to permit 3 pole Auto-Reclosing.Each Line Protection relays starts both MAIN & TIE Circuit Breakers to trip for the Concerned line. After a Successful reclosure of the Main Breaker, The Tie Breaker will be reclosed after a supplementary time delay. Should the Main CB Auto-Reclosure relay not be successful in its reclosing attempts, the Tie CB Auto-Reclosure is blocked. If the Main CB is Open or its Auto-Reclosure Relay is not ready or Out of service, The TIE CB Auto-Reclosure will reclose The TIE Breaker after its own dead time without any supplementary time delay.

    CHOICES OF EHV SYSTEM:1. CHOICE OF DEAD TIME: A. Lower limit is decided by deionising of Circuit Breaker.B. Upper Limit is decided by Transient Stability and Synchronism.C. Longer Transmission Lines Require Longer dead Time.D. The dead time for High Speed Auto-Reclosing scheme with EHV System is 0.3 to 1.2 sec.2. CHOICE OF RECLAIM TIME:This should not be set to such a low value that the operating cycle of Breaker is exceeded when two faults incident occurs close together. The reclaim time will be in the range of 10 to 30 sec., depending the breaker opening and closing mechanisms.3. CHOICE OF ZONE:This should normally kept in Zone-1. It is a Zone-1 fault and SLG fault only auto-reclosure is comes in to picture. In other zones the auto reclosure is blocked.

  • AUTOAUTO--RECLOSURE FOR RECLOSURE FOR ONE & HALF BREAKER SCHEMEONE & HALF BREAKER SCHEME

    1-52CB 2-52CB 3-52CB

    21 L121 L1MAINMAIN--1 1 REL 521REL 521

    21 L221 L2MAINMAIN--2 2 REL 316REL 316

    21 L121 L1MAINMAIN--1 1 REL 521REL 521

    21 L221 L2MAINMAIN--2 2 REL 316REL 316

    LINE-1 LINE-2

    79 (A/R)+79 (A/R)+25(SYNC) 25(SYNC) RAAAMRAAAMRASCRASC

    79 (A/R)+79 (A/R)+25(SYNC) 25(SYNC) RAAAMRAAAMRASCRASC

    79 (A/R)+79 (A/R)+25(SYNC) 25(SYNC) RAAAMRAAAMRASCRASC

    TRIP COMMANDSAUTO RECLOSURE

    COMMANDS

  • AUTO RECLOSING TIMING CHARTAUTO RECLOSING TIMING CHART

    TIME

    AUTO RECLOSERELAY

    INSTANT OF FAULT

    PROTECTION

    CIRCUIT BREAKERT

    R

    A

    N

    S

    I

    E

    N

    T

    F

    A

    U

    L

    T

    P

    E

    R

    M

    A

    N

    E

    N

    T

    F

    A

    U

    L

    T

    PROTECTION

    CIRCUIT BREAKER

    OPERATING TIME

    OPERATING TIME

    OPERATES

    OPERATES

    TRIP COILENERGISED

    CONTACTSSEPARATE

    ARCEXTINGUISHED

    CONTACTS FULLY OPEN

    RESETS

    TRIP COILENERGISED

    CONTACTSSEPARATE

    ARCEXTINGUISHED

    CONTACTS FULLY OPEN

    RESETS

    OPENING TIME

    ARCING TIME

    OPERATING TIME

    OPENING TIME

    ARCING TIME

    OPERATING TIME

    CLOSING COILENERGISED

    CONTACTS MAKE

    CONTACTSFULLY CLOSED

    CLOSINGTIME

    DEAD TIME

    CLOSING COILENERGISED

    CONTACTS MAKE

    CONTACTSFULLY CLOSED

    CLOSINGTIME

    DEAD TIME

    RECLOSE ON TO FAULT

    OPERATES

    TRIP COILENERGISED

    CONTACTSSEPARATE

    ARCEXTINGUISHED

    CONTACTS FULLY OPEN

    RESETS

    SYSTEM DISTURBANCE TIMERECLOSE INITIATED

    BY PROTECTION

    DEAD TIME CLOSING PULSE TIMERECLAIM TIME

    RELAY READY TO RESPONDTO FURTHER FAULT INCIDENTS(AFTER SUCEESFUL RECLOSRE)

  • CARRIER CARRIER INTERTRIPPING INTERTRIPPING

    SCHEMESSCHEMESADOPTED IN ADOPTED IN

    ONE AND HALFONE AND HALFCIRCUIT BREAKER CIRCUIT BREAKER

    SCHEME SCHEME PREPARED BY

    GOPALA KRISHNA PALEPUADE/MRT(PROTECTION)

  • PROTECTION COUPLER PANELPROTECTION COUPLER PANEL

    C

    E

    DISPLAY

    ACTIVE START TRIP

    NSD 50/ NSD 50/ NSD 70NSD 70

    G4AC TB: V9LC

    11--

    2+2+

    55--

    6+6+

    99--

    10+

    1313--

    14+14+

    TXTXTRIP TRIP A(C)A(C)

    RXRXTRIPTRIPA(C)A(C)

    TXTXTRIPTRIPB(D)B(D)

    RXRXTRIPTRIPB(D)B(D)

    CS

    CS

    CR

    CR

    GA4D TB:V9LC

    11--

    2+2+

    55--

    6+6+

    99--

    10+10+

    13-

    14+14+

    TXTXTRIP TRIP C(A)C(A)

    RXRXTRIPTRIPC(A)C(A)

    TXTXTRIPTRIPD(B)D(B)

    RXRXTRIPTRIPD(B)D(B)

    CS

    CS

    CR

    CR

    G4AA TB: V9LB

    A

    L

    A

    R

    M

    A

    L

    A

    R

    M

    -

    -

    1

    1

    2

    5

    0

    V

    D

    C

    2

    5

    0

    V

    D

    C

    A

    L

    A

    R

    M

    A

    L

    A

    R

    M

    -

    -

    2

    2

    2

    5

    0

    V

    D

    C

    2

    5

    0

    V

    D

    C

    55

    66

    77

    88

  • PROTECTION COUPLERS FOR 400KV LINEPROTECTION COUPLERS FOR 400KV LINE FOR EACH LINE 2Nos PROTECTION COUPLER PANELS PROVIDED.FOR EACH LINE 2Nos PROTECTION COUPLER PANELS PROVIDED. FOR EACH LINE 1NO CARRIER SPEECH PANEL PROVIDED.FOR EACH LINE 1NO CARRIER SPEECH PANEL PROVIDED. SO, 1 LINE REQUIRES TOTAL 3 PANELS.SO, 1 LINE REQUIRES TOTAL 3 PANELS. CARRIER SPEECH PANEL PURELY FOR VOICE COMMUNICATION BETWEEN CARRIER SPEECH PANEL PURELY FOR VOICE COMMUNICATION BETWEEN

    TWO SUBSTATIONS, i.e THE LINE CONNECTED SUBSTATIONS.TWO SUBSTATIONS, i.e THE LINE CONNECTED SUBSTATIONS. THE VOICE COMMUNICATION ARE TWO METHODS PROVIDED.THE VOICE COMMUNICATION ARE TWO METHODS PROVIDED. ONE IS HOTLINE COMMUNICATION/DEDICATED/ LIFT&TALK METHOD.ONE IS HOTLINE COMMUNICATION/DEDICATED/ LIFT&TALK METHOD. ANOTHER IS DIAL METHOD.ANOTHER IS DIAL METHOD. IN PROTECTION COUPLER PANELIN PROTECTION COUPLER PANEL--1 TOTAL 3 CARDS ARE IMPORTANT FOR 1 TOTAL 3 CARDS ARE IMPORTANT FOR

    SENDING & RECEIVING TRIP SIGNALS.SENDING & RECEIVING TRIP SIGNALS. ONE CARD FOR ALARM i.e G4AA. ONE CARD FOR PERMISSIVE/PROTECTION ONE CARD FOR ALARM i.e G4AA. ONE CARD FOR PERMISSIVE/PROTECTION

    TRIP i.e G4AC & ANOTHER CARD FOR DIRECT TRIPS i.e G4AD.TRIP i.e G4AC & ANOTHER CARD FOR DIRECT TRIPS i.e G4AD. IN PROTECTION COUPLERIN PROTECTION COUPLER--2 PANEL ALSO 3 CARDS ARE PROVIDED SIMILAR TO 2 PANEL ALSO 3 CARDS ARE PROVIDED SIMILAR TO

    PROTECTION COUPLERPROTECTION COUPLER--1 PANEL.1 PANEL. THE PROTECTION COUPLER PANEL DRAWING IS SHOWN IN PREVIOUS MENU.THE PROTECTION COUPLER PANEL DRAWING IS SHOWN IN PREVIOUS MENU. 1SET TX & RX FOR PERMISSIVE/ PROTECTION TRIP(G4AC)1SET TX & RX FOR PERMISSIVE/ PROTECTION TRIP(G4AC) 1SET TX & RX FOR BACKUP FOR PERMISSIVE/ PROTECTION IN ANOTHER 1SET TX & RX FOR BACKUP FOR PERMISSIVE/ PROTECTION IN ANOTHER

    PANEL(G4AC).PANEL(G4AC). 1SET TX & RX FOR DIRECT TRIP CHANNEL1SET TX & RX FOR DIRECT TRIP CHANNEL--1( G4AD).1( G4AD). 1SET TX & RX FOR SPARE UNDER EMERGENCY(G4AD).1SET TX & RX FOR SPARE UNDER EMERGENCY(G4AD). THE ABOVE ARRANGEMENT SIMILAR FOR PROTECTION COUPLER PANELTHE ABOVE ARRANGEMENT SIMILAR FOR PROTECTION COUPLER PANEL--2.2. G4AA CARD FOR ALARM.G4AA CARD FOR ALARM.

  • MAINMAIN--1 PROTECTION CARRIER INTER TRIPPING1 PROTECTION CARRIER INTER TRIPPING

    ABB REL521ABB REL521CR

    CS

    -VECARRIER RECEIVE

    CARRIER SEND

    ALARM

    IN

    A

    B

    B

    A

    B

    B

    N

    S

    D

    5

    0

    N

    S

    D

    5

    0

    OUT

    PANEL-1

    PANEL-2

    G4AC V9LC 1

    G4AC V9LC 2

    G4AC V9LC 5

    G4AC V9LC 6

    G4AA V9LB 5

    G4AA V9LB 6

    A

    B

    B

    A

    B

    B

    N

    S

    D

    5

    0

    N

    S

    D

    5

    0 G4AC V9LC 10

    G4AC V9LC 14

    G4AC V9LC 9

    G4AC V9LC 13THIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIPTHIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIPAND CONNECTED IN ANOTHER PANELAND CONNECTED IN ANOTHER PANEL

    +VE -VE

  • MAINMAIN--2 PROTECTION CARRIER INTER TRIPPING2 PROTECTION CARRIER INTER TRIPPING

    ABB REL316ABB REL316CR

    CS

    -VECARRIER RECEIVE

    CARRIER SEND

    ALARM

    IN

    A

    B

    B

    A

    B

    B

    N

    S

    D

    5

    0

    N

    S

    D

    5

    0

    OUT

    PANEL-2

    PANEL-1

    G4AC V9LC 1

    G4AC V9LC 2

    G4AC V9LC 5

    G4AC V9LC 6

    G4AA V9LB 5

    G4AA V9LB 6

    A

    B

    B

    A

    B

    B

    N

    S

    D

    5

    0

    N

    S

    D

    5

    0 G4AC V9LC 10

    G4AC V9LC 14

    G4AC V9LC 9

    G4AC V9LC 13THIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIPTHIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIPAND CONNECTED IN ANOTHER PANELAND CONNECTED IN ANOTHER PANEL

    +VE -VE

  • DIRECT TRIP SEND CARRIER CHANNELDIRECT TRIP SEND CARRIER CHANNEL--11

    T N C

    MAIN CB(1-52CB)

    T N C

    TIE CB(2-52CB)

    CONTROL PANEL

    BUSBAR TRIP (ZONE-1)

    BUSBAR TRIP (ZONE-2)

    BUSBAR PROT-1 PANEL

    BUSBAR PROT-2 PANEL

    R Y B

    R Y B

    TIE CB (2-52 CB)

    MAIN CB (1-52 CB)

    50 LBB/BFR FOR MAIN CB

    RAICA

    59L1

    OVER VOLTAGE STAGE-1

    59L2

    OVER VOLTAGE STAGE-2

    50 LBB/BFR FOR TIE CB

    RAICA

    ABBABBNSD 50NSD 50DC +VE

    FROM PANEL

    G4AD V9LC 2

    DC VE FROM PANEL

    G4AD V9LC 1

    PANEL-1

  • DIRECT TRIP SEND CARRIER CHANNELDIRECT TRIP SEND CARRIER CHANNEL--22

    T N C

    MAIN CB(1-52CB)

    T N C

    TIE CB(2-52CB)

    CONTROL PANEL

    BUSBAR TRIP (ZONE-1)

    BUSBAR TRIP (ZONE-2)

    BUSBAR PROT-1 PANEL

    BUSBAR PROT-2 PANEL

    R Y B

    R Y B

    TIE CB (2-52 CB)

    MAIN CB (1-52 CB)

    50 LBB/BFR FOR MAIN CB

    RAICA

    59L1

    OVER VOLTAGE STAGE-1

    59L2

    OVER VOLTAGE STAGE-2

    50 LBB/BFR FOR TIE CB

    RAICA

    ABBABBNSD 50NSD 50DC +VE

    FROM PANEL

    G4AD V9LC 2

    DC VE FROM PANEL

    G4AD V9LC 1

    PANEL-2

  • DIRECT TRIP RECEIVE CHANNELDIRECT TRIP RECEIVE CHANNEL--1&21&2

    ABBABBNSD 50NSD 50

    G4AD V9LC 6

    G4AD V9LC 5

    ABBABBNSD 50NSD 50

    G4AD V9LC 6

    G4AD V9LC 5

    PANEL-1

    PANEL-2

    DC +VE

    DC +VE

    +VE -VE

    TO 86TO 86--A MASTER TRIP RELAY A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR (HIGH SPEED TRIP RELAY) FOR MAIN CB(152CB)MAIN CB(152CB)TO 86TO 86--A MASTER TRIP RELAYA MASTER TRIP RELAY(HIGH SPEED TRIP RELAY) FOR (HIGH SPEED TRIP RELAY) FOR TIE CB(252CB)TIE CB(252CB)

    TO 86TO 86--B MASTER TRIP RELAYB MASTER TRIP RELAY(HIGH SPEED TRIP RELAY) FOR(HIGH SPEED TRIP RELAY) FORMAIN CB(152CB)MAIN CB(152CB)

    TO 86TO 86--B MASTER TRIP RELAY B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR(HIGH SPEED TRIP RELAY) FORTIE CB(252CB)TIE CB(252CB)

    DIRECT TRIP-1CARRIER RECEIVE RELAY

    DIRECT TRIP-2CARRIER RECEIVE RELAY

  • PLCC CARRIER PROTECTION SYSTEMPLCC CARRIER PROTECTION SYSTEM(TELEPROTECTION)(TELEPROTECTION)

    C

    E

    ABB Network Partner AG REL531

    REL 521MAIN-1

    PROTECTION

    C

    E

    1

    2345678

    9

    10111213141516

    ABB Network Partner AG REC 316*4

    C

    E

    1

    2345678

    9

    10111213141516

    ABB Network Partner AG REC 316*4

    C

    E

    ABB Network Partner AG REL531

    REL 316MAIN-2

    PROTECTION

    PLCCPANEL

    PLCCPANEL

    NSD 50PANEL

    NSD 50PANEL

    NSD 50PANEL

    NSD 50PANEL

    ELECTRICAL CONNECTION

    ELECTRICAL CONNECTION

    ELECTRICAL POWER LINE

  • FIBRE OPTIC PROTECTION SYSTEMFIBRE OPTIC PROTECTION SYSTEM(TELEPROTECTION)(TELEPROTECTION)

    C

    E

    ABB Network Partner AG REL531

    REL 521MAIN-1

    PROTECTION

    C

    E

    1

    2345678

    9

    10111213141516

    ABB Network Partner AG REC 316*4

    C

    E

    1

    2345678

    9

    10111213141516

    ABB Network Partner AG REC 316*4

    C

    E

    ABB Network Partner AG REL531

    REL 316MAIN-2

    PROTECTION

    NSD 70PANEL

    NSD 70PANEL

    NSD 70PANEL

    NSD 70PANEL

    ELECTRICAL CONNECTION

    ELECTRICAL CONNECTION

    FOX-UFOX-515

    T

    U

    N

    O

    S

    G

    E

    C

    O

    D

    /

    S

    I

    F

    O

    X FOX-UFOX-515

    T

    U

    N

    O

    S

    G

    E

    C

    O

    D

    /

    S

    I

    F

    O

    X

  • FIBRE OPTIC CARRIER PROTECTION SYSTEMFIBRE OPTIC CARRIER PROTECTION SYSTEM(TELEPROTECTION)(TELEPROTECTION)

    DIGITAL RELAY CONNECTION VIA FIBRE OPTICDIGITAL RELAY CONNECTION VIA FIBRE OPTIC

    FOX-UFOX-515

    T

    U

    N

    O

    S

    O

    T

    E

    R

    M

    FOX-UFOX-515

    T

    U

    N

    O

    S

    O

    T

    E

    R

    M

    C

    E

    ABB Network Partner AG REL531

    REL 521MAIN-1

    PROTECTION

    C

    E

    1

    2345678

    9

    10111213141516

    ABB Network Partner AG REC 316*4

    C

    E

    1

    2345678

    9

    10111213141516

    ABB Network Partner AG REC 316*4

    C

    E

    ABB Network Partner AG REL531

    REL 316MAIN-2

    PROTECTION

  • MAINMAIN--1 & MAIN1 & MAIN--22PROTECTION FORPROTECTION FOR

    AUTO TRANSFORMER AUTO TRANSFORMER ADOPTED IN ADOPTED IN

    ONE AND HALFONE AND HALFCIRCUIT BREAKER CIRCUIT BREAKER

    SCHEMESCHEMEPREPARED BY

    GOPALA KRISHNA PALEPUADE/MRT(PROTECTION)

  • BASICS OF TRANSFORMER PROTECTIONBASICS OF TRANSFORMER PROTECTION1. 1. PURPOSE OF POWER TRANSFORMER PROTECTIONPURPOSE OF POWER TRANSFORMER PROTECTION

    POWER T/F PROTECTION IS USUALLY INSTALLED TO DISCONNECT THE T/F AT:A.A. INTERNAL SHORT CIRCUITS AND EARTH FAULTS IN THE T/F AND ITS CONNECTED CIRCUITS.B.B. EXTERNAL FAULTS ON OTHER CIRCUITS. (BACK-UP PROTECTION)C.C. ABNORMAL SERVICE CONDITIONS SUCH AS OVERLOAD & OVER VOLTAGE.

    2.2. PROTECTION DEVICES INBUILT OR MOUNTED ON POWER T/FPROTECTION DEVICES INBUILT OR MOUNTED ON POWER T/FA.A. OIL IMMERSED POWER T/F USUALLY HAVE A GAS DETECTOR AND OIL SURGE. DETECTOR (BUCHHOLZ ALARAM & TRIP DEVICES), WHICH ARE EXCELLENT FOR DETECTING INTERNAL FAULTS.B.B. LOAD TAPCHANGER COMPARTMENTS MAY HAVE A SIMILAR OVER PRESSURE DEVICE. C.C. TEMPARATURE MONITORS FOR OIL & WINDING PROVIDE GOOD OVER LOAD PROTECTION.D.D. PRESSURE RELIEF DEVICE IS PROVIDED TO SAFE GUARD THE T/F FROM HIGH PRESURES.

    3.3. TRANSFORMER DIFFERENTIAL PROTECTIONTRANSFORMER DIFFERENTIAL PROTECTIONIT IS WIDELY USED AS INSTANTANEOUS PROTECTION FOR SHORT CIRCUIT FAULTS WITH IN THE DIFFERENTIAL ZONE. THIS IS TREATED AS MAIN-1 PROT FOR T/F.THE MOST COMMON TYPE OF PROTECTION IS THE CURRENT RESTRAINT TYPE.SOME TYPE OF DIFFERENTIAL RELAYS REQUIRE INTERPOSING CTs FOR CT RATIO MATCHING AND/OR PHASE SHIFT.HIGH IMPEDENCE DIFFERENTIAL PROTECTION CAN BE USED ON AUTO T/F & REACTORS.IT COVERS ONE GALVANICALLY INTERCONNECTED WINDING (WDG DIFF). BUT NOT A SEPARATE TERTIARY WINDING. IT REQUIRES A THREE PHASE SET OF CTs AT THE NEUTRAL SIDE OF WINDING.

  • 4.4. RESTRICTED EARTH FAULT PROTECTIONRESTRICTED EARTH FAULT PROTECTIONTHIS IS A HIGH IMPEDENCE DIFFERENTIAL EARTH FAULT PROTECTION FOR ONE WINDING OR 1-PH. IT IS SOME TIMES USED IN LOW IMPEDENCE EARTHED SYSTEMS TO GIVE AN INSTANTANEOUS PROTECTION. WHICH IS MORE SENSITIVE THAN THE TRANSFORMER DIFFERENTIAL ONE. TYPICAL SENSITIVITY IS 5%. THERE ARE SOME PARTICULAR CT REQUIREMENTS, e.g. EQUAL TURNS RATIO OF THE CTs. INCASE OF T/F HAVING EARTHED STAR WINDING ONE RELAY SUFFICIENT. T/F HAVING STAR/STAR (BOTH EARTHED) APPLY TWO INDEPENDENT RELAYS.

    5.5. BACK UP PROTECTIONBACK UP PROTECTIONA VARIETY OF RELAYS ARE AVAILABLE.A.A. OVER CURRENT & EARTH FAULT PROTECTION. ( 50, 50N, 51, 51N, 67, 67N - ANY COMBINATION OF THESE)B.B. UNDER IMPEDENCE / DISTANCE ( Z).

    6.6. OTHER TYPES OF RELAYSOTHER TYPES OF RELAYSA.A. OVER VOLTAGE RELAY (U >).B.B. OVER FLUX/ EXCITATION (V/F >)( INVERSE TIME & DIFENITE TIME). FOR 400KV/220KV, 315 MVA & 500MVA TRANSFORMERS BOTH SIDES( i.e HV & LV) OVER FLUX RELAYS ARE PROVIDED BECAUSE BOTH SIDES HAVING GRID.

    NORMALLY ADOPTED POWER TRANSFORMERS CAPACITIES IN NORMALLY ADOPTED POWER TRANSFORMERS CAPACITIES IN 400KV / 220KV400KV / 220KV

    CAPACITY OF CAPACITY OF TRANSFORMERTRANSFORMER

    HV HV VOLTAGEVOLTAGE

    HV HV CURRENTCURRENT

    LV LV VOLTAGEVOLTAGE

    LV LV CURRENTCURRENT

    315 MVA315 MVA 400 KV400 KV 454.68 A454.68 A 220 KV220 KV 0826.68 A0826.68 A500 MVA500 MVA 400 KV400 KV 721.71 A721.71 A 220 KV220 KV 1312.20 A1312.20 A

  • NORMS OF PROTECTION FOLLOWED IN APTRANSCO NORMS OF PROTECTION FOLLOWED IN APTRANSCO FOR POWER TRANSFORMERS & AUTO TRANSFORMERSFOR POWER TRANSFORMERS & AUTO TRANSFORMERS

    BACK UPBACK UPPROTECTIONPROTECTIONS.NoS.No CAPACAPACITYCITY

    VOLTAGE VOLTAGE RATIORATIO

    MAIN MAIN PROTECTIONPROTECTION

    HVHV

    ADDITIONAL ADDITIONAL PROTECTIONPROTECTION

    3 OL + 3 OL + 1 DIR EL1 DIR EL

    BUCHHOLZ, BUCHHOLZ, OLTC OSROLTC OSROIL TEMPOIL TEMP

    WDNG TEMPWDNG TEMP

    BUCHHOLZBUCHHOLZOVER FLUX OVER FLUX OLTC OSROLTC OSRPRV/PRDPRV/PRDOIL TEMPOIL TEMP

    WDNG TEMPWDNG TEMP

    3 OL + 3 OL + 1 DIR EL1 DIR EL

    3 OL + 3 OL + 1 DIR EL1 DIR EL3 OL + 3 OL +

    1 DIR EL1 DIR EL

    SPECIALSPECIALPROTECTIONPROTECTION

    11 7.5 MVA 7.5 MVA 16 MVA16 MVA

    3 DIR OL 3 DIR OL (HIGHSET) + (HIGHSET) +

    1 DIR EL1 DIR EL(HIGHSET)(HIGHSET)

    LVLV

    132KV/11KV132KV/11KV 3 OL +3 OL +1 EL 1 EL

    3 OL +3 OL +1 EL 1 EL

    3 OL +3 OL +1 EL 1 EL

    3 OL +3 OL +1 DIR EL 1 DIR EL 3 DIR OL 3 DIR OL

    (HIGHSET) + (HIGHSET) + 1 DIR EL1 DIR EL

    (HIGHSET) (HIGHSET)

    132KV/33KV132KV/33KV

    220KV/33KV220KV/33KV

    220KV/132KV220KV/132KV

    400KV/220KV400KV/220KV

    DIFFERENTIAL DIFFERENTIAL RELAYRELAY

    2216 MVA16 MVA

    31.5 MVA31.5 MVA50 MVA50 MVA

    NIL NIL

    REF RELAY,REF RELAY,OVER LOAD OVER LOAD

    ALARM ALARM RELAYRELAY

    33 31.5 MVA31.5 MVA50 MVA50 MVA

    44 100 MVA100 MVA

    5 5 315 MVA 315 MVA 500 MVA500 MVA

  • MAINMAIN--1/ DIFFERENTIAL PROTECTION FOR AT/F1/ DIFFERENTIAL PROTECTION FOR AT/F(4 CT METHOD)(4 CT METHOD)

    3 3 3

    3 3 3

    3-CT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    2-ACT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    5S4 5S4 5S4

    5S35S3 5S3

    P2P2P2 CT MB

    CT MB

    P2P2P2

    5S4 5S4 5S4

    5S35S3 5S3

    3 3 3

    LV-CT

    CORE-5CTR: 1200-800/1A

    CLASS: PS

    5S1 5S1 5S1

    5S35S3 5S3

    P2P2P2

    CT MB

    C

    E

    DISPLAY

    ACTIVE START TRIP

    RET 521/ RET 521/ RET 316RET 316RADSBRADSB

    A

    U

    X

    .

    C

    T

    Y

    /

    0

    .

    9

    1

    /

    0

    .

    5

    7

    7

    A

    A

    U

    X

    .

    C

    T

    Y

    /

    0

    .

    9

    1

    /

    0

    .

    5

    7

    7

    A

    A

    U

    X

    .

    C

    T

    Y

    /

    0

    .

    6

    8

    9

    /

    0

    .

    5

    7

    7

    A

    NORMALLY LOW IMPEDENCE BIASED

    DIFFERENTIAL RELAY IS USED FOR

    TRANSFORMER DIFFERENTIAL PROTECTION

  • MAINMAIN--1/ DIFFERENTIAL PROTECTION FOR AT/F1/ DIFFERENTIAL PROTECTION FOR AT/F(5 CT METHOD)(5 CT METHOD)

    3 3 3

    3-TCT

    CORE-5CTR: 2000-1000-500/1A

    CLASS: PS

    5S4 5S4 5S4

    5S35S3 5S3

    P2P2P2 CT MB3 3 3

    LV-CT

    CORE-5CTR: 1200-800/1A

    CLASS: PS

    5S1 5S1 5S1

    5S35S3 5S3

    P2P2P2

    CT MB

    C

    E

    DISPLAY

    ACTIVE START TRIP

    RET 521/ RET 521/ RET 316RET 316RADSBRADSB

    A

    U

    X

    .

    C

    T

    Y

    /

    0

    .

    9

    1

    /

    0

    .

    5

    7

    7

    A

    A

    U

    X

    .

    C

    T

    Y

    /

    0

    .

    6

    8

    9

    /

    0

    .

    5

    7

    7

    A

  • SELECTION OF AUX.CTs FOR DIFFERENTIAL PROTECTIONSELECTION OF AUX.CTs FOR DIFFERENTIAL PROTECTION NORMALLY 400KV/220KV AUTO TRANSFORMERS ARE OF CAPACITY 315MVA.NORMALLY 400KV/220KV AUTO TRANSFORMERS ARE OF CAPACITY 315MVA. FOR MERZ PRICE PROTECTION IF TRANSFORMER IS CONNECTED IN STAR/STFOR MERZ PRICE PROTECTION IF TRANSFORMER IS CONNECTED IN STAR/STARAR

    THEN CT SECONDARIES ARE TO BE CONNECTED IN DELTA/DELTA.THEN CT SECONDARIES ARE TO BE CONNECTED IN DELTA/DELTA. CORRECT RATIO CTs ARE NOT AVAILABLE, THEN AUX.CTs ARE TO BE PROVCORRECT RATIO CTs ARE NOT AVAILABLE, THEN AUX.CTs ARE TO BE PROVIDEDIDED

    FOR ACHEVING SUITABLE CURRENTS.FOR ACHEVING SUITABLE CURRENTS. IF AUX CTs ARE USING THEN MAIN CT SECONDARIES ARE CONNECTED IN SIF AUX CTs ARE USING THEN MAIN CT SECONDARIES ARE CONNECTED IN STAR.TAR. THIS IS BROUGHT TO AUX CTs. AUX CTs PRIMARY IS CONNECTED IN STATHIS IS BROUGHT TO AUX CTs. AUX CTs PRIMARY IS CONNECTED IN STAR & R &

    SECONDARIES ARE CONNECTED IN DELTA.SECONDARIES ARE CONNECTED IN DELTA. NORMALLY THE RELAY RATED CURRRENT IS 1A.NORMALLY THE RELAY RATED CURRRENT IS 1A. AUX.CT s SECONDARIES ARE CONNECTED IN DELTA. FOR ACHIEVING 1A TOAUX.CT s SECONDARIES ARE CONNECTED IN DELTA. FOR ACHIEVING 1A TO

    RELAY, AUX.CT SECONDARY CURRENT IS RELAY, AUX.CT SECONDARY CURRENT IS TO BE TO BE 0.577A.0.577A. THE FULL LOAD PRIMARY CURRENT OF 315MVA AT/F IS 454.7A.THE FULL LOAD PRIMARY CURRENT OF 315MVA AT/F IS 454.7A. BUT THE 400KV CTs RATIOs ARE AVAILABLE : 2000BUT THE 400KV CTs RATIOs ARE AVAILABLE : 2000--10001000--500/1A500/1A NEAREST VALUE TO FULL LOAD CURRENT IS 500/1A. HENCE IT IS ADOPTENEAREST VALUE TO FULL LOAD CURRENT IS 500/1A. HENCE IT IS ADOPTED.D. HENCE AT FULL LOAD HV CURRENT i.e 454.7A, THEN SECONDARY OF CT HENCE AT FULL LOAD HV CURRENT i.e 454.7A, THEN SECONDARY OF CT

    CURRENT WILL BE 0.91A.CURRENT WILL BE 0.91A. SO HV SIDE AUX.CT RATIO IS 0.91/0.577A.SO HV SIDE AUX.CT RATIO IS 0.91/0.577A. THE FULL LOAD SECONDARY CURRENT OF 315MVA AT/F IS 826.7A.THE FULL LOAD SECONDARY CURRENT OF 315MVA AT/F IS 826.7A. BUT THE 220KV CTs RATIOs ARE AVAILABLE: 1200BUT THE 220KV CTs RATIOs ARE AVAILABLE: 1200--800/1A.800/1A. NEAREST VALUE TO FULL LOAD CURRENT IS 1200/1A. HENCE IT IS ADOPTNEAREST VALUE TO FULL LOAD CURRENT IS 1200/1A. HENCE IT IS ADOPTED.ED. HENCE AT FULL LOAD LV CURRENT i.e 826.7A,THEN SECONDARY OF CT CUHENCE AT FULL LOAD LV CURRENT i.e 826.7A,THEN SECONDARY OF CT CURRENT RRENT

    WILL BE 0.689A.WILL BE 0.689A. SO LV SIDE AUX CT RATIO IS 0.689/0.577A.SO LV SIDE AUX CT RATIO IS 0.689/0.577A. SPECIAL INFORMATION:SPECIAL INFORMATION: LATEST NUMERICAL RELAYS NEED NOT REQUIRE AUX LATEST NUMERICAL RELAYS NEED NOT REQUIRE AUX

    CTs. IN THESE RELAYS, CT RATIOS MATCHING CAN BE PROGRAMMED.CTs. IN THESE RELAYS, CT RATIOS MATCHING CAN BE PROGRAMMED.

  • MAINMAIN--2/ BACKUP PROTECTION FOR AT/F HV2/ BACKUP PROTECTION FOR AT/F HV(4 CT METHOD)(4 CT METHOD)