  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    1/8

    BUSINESS SECTIONPolicy: 4.30.1

    INDIVIDUAL CONSTRUCTION/RENEWAL PROJECT

    Project planning will involve and inform various constituent and interestgroups including parents, school administrative staff, teachers, central

    office staff, neighbors, and the Falls Church community at large.

    For each major capital construction/renewal project an ArchitectSelection and Advisory Committee (also called the ASAC) shall beappointed by the School Board to assist central office staff and advisethe School Board.

    Major Construction/Renewal Projects

    Architect Selection and Advisory Committee Formation andGeneral Charge

    Architect Selection and Advisory Committees work on capitalprojects where the impact of educational program issues is centralto the design of the project. Internal space reorganizations, orlarge projects, such as roof replacement, or installation of

    sprinkler systems, where the specifics of the educational programdo not impact on the design of the project, Architect Selection andAdvisory Committees would not be appointed.

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    2/8

    BUSINESS SECTIONPolicy: 4.30.1

    community use and impact, safety and accessibility provisions,and project implementation schedules. The committee will helpdevelop educational facilities specifications, under Policy 4.30.

    The committee advises the School Board on these same issuesand meet with the School Board prior to approval of the schematicdesign.

    During construction, the committee meets periodically to reviewthe progress on the project. Finally, the committee participates inpost-construction evaluation of the project.

    Membership

    1. The ASAC will be appointed by the School Board based onrecommendations from the Superintendent and PTA/PTSA. TheASAC shall generally be comprised of:

    a. Five staff members to include a principal, classroom andspecial subject teachers, and a member of the maintenance

    staff to be recommended by the superintendent

    b. Four citizens who are parents to include at least oneofficer/designee of the PTA/PTSA These representatives will

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    3/8

    BUSINESS SECTIONPolicy: 4.30.1

    e. The School Board may also appoint other persons, includingmembers of Falls Church City Government Organizations orCommissions to the committee.

    2. When the planned project is a new school, the same selectionprocess shall be followed with the exception that the ASAC willgenerally consist of the following:

    a. A school principal or assistant principal from the same level(i.e., elementary, middle, or high school).

    b. Two classroom teachers and one special subject teacherfrom the grade levels proposed to be included in the newschool.

    c. A member of the maintenance staff recommended by theSuperintendent.

    d. Four citizens, to include at least one officer/designee of the

    PTA/PTSA, who are parents of children who would likelyattend the new school or who have had children recentlyattend the grades which would be served by the school.These representatives will be appointed by the School

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    4/8

    BUSINESS SECTIONPolicy: 4.30.1

    Another member from the neighborhood adjacent to thesite will be appointed once the site is approved.

    f. The Superintendent or designee who will serve as chair.

    g. The School Board may also appoint other persons, includingmembers of Falls Church City Government Organizations orCommissions to the committee.

    Information

    At the first meeting the staff will provide necessary information

    to the ASAC to facilitate and direct its work. Such informationmay include but not be limited to the following:

    A roster of the Architect Selection and AdvisoryCommittee Educational specifications The schools capacity information The current five year student projections and other

    enrollment projections A copy of the request for proposal for architecturaland engineering design work School program summary of existing spaces

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    5/8

    BUSINESS SECTIONPolicy: 4.30.1

    A. Communication

    1. The school principal and other school staff members of the

    ASAC shall keep the school staff informed of the design andprogress of the planning of the project. This should be donethrough staff meetings and other regular communicationsand by posting drawings and other informative material.Comments should be solicited and once received, sharedwith the ASAC for consideration.

    2. The parent/PTA/PTSA members of the ASAC, in cooperation

    with the school principal, shall keep the parents informed ofthe design and progress of the planning of the project. TheASAC should schedule design presentations to theschool/parent community and consider comments received.

    3. The Chair of the ASAC shall assure notification andcoordination of the design and progress of planning throughoutreach to near neighbors of the school. Comments

    should be solicited and once received, shared with theASAC for consideration.

    4 The ASAC in conjunction with the neighborhood members

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    6/8

    BUSINESS SECTIONPolicy: 4.30.1

    Board or comments received directly from communitymembers will be considered by the ASAC.

    Planning Sequence

    The general sequence and responsibilities for activitiesassociated with the design and construction of a schoolconstruction or renewal project are presented on theattached chart. The sequence and activities shall begenerally followed but may vary depending on the specificproject requirements.

    I. Maintenance Projects

    Ad hoc school facility committees may be formed from time totime for coordination of specific projects of a defined scope and/orshort duration (e.g. technology cabling, playgrounds,landscaping). Such committees will be formed by the schoolprincipal at the request of the school administration. Membership

    of the committees should include the school principal or designee,school staff, parents and PTA/PTSA representatives as appropriatefor the project, supported by central office staff as needed.

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    7/8

    1

    BUSINESS SECTION Policy: 4.30.1

    Falls Church City Public Schools Facilities Planning Sequence

    School Board Administration Staff Architect/Engineer Architect Selection andAdvisory Committee

    School Board approves scopeof work as defined inFCCPS/CIP

    Staff recommends ASAC

    Appoints ASAC RecommendsArchitect/Engineer resultingfrom selection process

    Approves contract forappointment of architect

    Assists in the development ofschools program, givesdesign guidance

    Reviews and approvesprogram requirements

    Develops schematic designand any City requiredassessments

    Reviews & makesrecommendations onschematic design plans & cityrequired assessmentsHolds briefing on schematicdesign w/PTA/PTSA, neighborsand community

    Reviews schematic designand assessments

    Presents schematic design toSB

    Reviews schematic designplans and assessments

    Holds worksession/briefing toreview design

    Participates inworksession/briefing with SB

    Adopted: 6/12/02 Revised: 2/25/03

    Falls Church City Public Schools

  • 8/9/2019 4.30.1 - Individual Construction/Renewal Project

    8/8

    2

    BUSINESS SECTION Policy: 4.30.1

    to review designApproves schematic design Prepares site waiver (if

    required)Approves request for sitewaiver if required

    Authorizes architect todevelop final drawings andspecifications

    Develops detailed drawingsand specifications

    Reviews 65% completedrawings

    School Board Administration Staff Architect/Engineer Architect Selection andAdvisory Committee

    Reviews 95% drawings andspecifications

    Reviews final drawings &specifications

    Approves final drawings,specifications and projectbudget

    Submits final drawings forpermit

    Develops bid package

    Approves contractspecifications and awardscontracts

    Provides or procures projectmanagement services

    Provides on-site technicaldirection for the constructionproject

    Receives periodic updatesduring construction

    Receives periodic status andfinancial reports on project

    Provides input to projectdebriefing reportapproximately 90 days afteroccupancy

    Performs post-occupancyevaluation after 1 year

    Receives close out report

    Adopted: 6/12/02 Revised: 2/25/03