6th Edition
Stormwater C.3 Guidebook
CCCWP Management CommitteeFebruary 15, 2012
Brief Guidebook History Key Changes from 5th Edition Ongoing Issues Recommended Action
Topics
Edition
Date Major Changes
1st January 2005 Implemented new C.3 requirements with Low Impact Development approach
2nd March 2005 Incorporated design guidance for bioretention, other features and facilities;added O&M guidance
3rd October 2006 Implemented HMP requirementsIntroduced IMP Sizing Calculator
4th October 2008 Organized and Improved LID Design Guidance
January 2009October 2009
Soils, Planting, and Irrigation GuidanceAdded 2 additional IMPs
5th October 2010 Implemented MRP RequirementsAdded IMP Construction Checklist
December 2011 “C.3 Update” to implement amendment
Guidebook History
Special Projects Table 4-14 on Page 60 Narrative Analysis of Feasibility of LID on
Special Projects (Instructions are in Guidebook but need to reference these instructions in template)
Technical Criteria for non-LID Facilities (in preparation; to be posted to website)
6th Edition
Harvesting and Reuse Feasibility Screening Procedure on Page 40-42 Background on Page 17 Underdrain discharge located at top of gravel
layer unless infiltration must be prevented
6th Edition
Soils, Plants, and Irrigation Updated Appendix B Incorporates MRP “Attachment L”
6th Edition
Follows organization and content of guidance in Chapter 3
Annotated with explanations and prompts
Prompts Harvesting and Use Feasibility Calculations
Prompt for feasibility narrative to be added
Supports presentation of sizing calculations in Chapter 4
Substitute for, or check, results of IMP Sizing Calculator
Includes a project data summary to facilitate compilation of reports
Template
Hydrograph Modification Management Report and proposal due April 2013
a. Present model verification monitoring results demonstrating that the IMPs are sufficiently overdesigned and perform to meet the 0.1Q2 low flow design criteria; or
b. Present study results of Contra Costa County streams geology and other factors that support the low flow design criteria of 0.2Q2 as the limiting HMP design low flow; or
c. Propose redesigns of the IMPs to meet the low flow design criteria of 0.1Q2 to be implemented during the next permit term.
Awaiting news on Prop. 84 grant application Data will also be relevant re: infiltration
and evapotranspiration requirements
Ongoing Issues
Feasibility/Infeasibility of Infiltration, Evapotranspiration, and Harvesting/Reuse
Response to Water Board staff comments on BASMAA submittal is pending BASMAA Board approval
Report on implementation experience is due December 1, 2013
Documenting harvesting/reuse projects is important
Ongoing Issues
Approve the Stormwater C.3 Guidebook 6th Edition and direct staff to publish it and the template on the Program website.
Direct staff to prepare and publish a new 2-page “Stormwater C.3 Update” summarizing policy changes
Recommendations
Annual and “Special Projects”
Provision C.3 Reporting
CCCWP Management CommitteeFebruary 15, 2012
Provision C.3 Reporting—Annual and Special Projects
REPORTING REQUIREMENT TEMPLATE
MRP Attachment A (C.3.b.)
Table 3.1 (C.3.e.) Table 1 In Plan
Project Name and Address Project Name and Address
Application Date
Project Description Project Description
Site Total Area, Disturbed Site Total Acreage
New & Replaced Impervious
Pre/Post-Project Impervious
Density (DU/Acre and/or FAR)
Special Project Categories
LID Credits Available
Percent LID and Non-LID
Status of Project
Source Control Measures
Site Design Measures
Treatment Systems/Criteria LID & Non-LID Treatment Used
Feasibility of LID Treatment
O&M Mechanism
Alternative Compliance
Hydromodification Controls
Narrative discussion of onsite LID feasibility Infiltration, evapotranspiration, harvesting/reuse
per Stormwater C.3 Guidebook 6th Edition
Description of site and DMAs
Need for pavement where proposed
Why any landscaped areas can’t be bioretention
Narrative discussion of offsite LID feasibility Owner owns land in same watershed?
In-lieu program exists?
Technical Criteria for Non-LID Facilities Reference an existing certification program, or
Prepare our own minimum design criteria?
Special Projects Reporting