6:~aig - richmond, british columbia · once the upgrades to secondary treatment are complete, the...

23
City of Richmond To: Development Permit Panel From: Wayne Craig Director of Development Report to Development Permit Panel Date: October 24, 2018 File: DP 18-820582 Re: Application by Greater Vancouver Sewerage and Drainage District for a Development Permit at 1000 Ferguson Road Staff Recommendation That a Development Permit be issued at 1000 Ferguson Road in order to allow construction of temporary dewatering facilities on a site designated an Environmentally Sensitive Area. Director of WC:je Att. 8 5973337

Upload: others

Post on 24-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

City of Richmond

To: Development Permit Panel

From: Wayne Craig Director of Development

Report to Development Permit Panel

Date: October 24, 2018

File: DP 18-820582

Re: Application by Greater Vancouver Sewerage and Drainage District for a Development Permit at 1000 Ferguson Road

Staff Recommendation

That a Development Permit be issued at 1000 Ferguson Road in order to allow construction of temporary dewatering facilities on a site designated an Environmentally Sensitive Area.

6:~aig Director of

WC:je Att. 8

5973337

Page 2: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

October 24, 2018 -2- DP 18-820582

Staff Report

Origin

Greater Vancouver Sewerage and Drainage District (GVS&DD) has applied to the City of Richmond for an Environmentally Sensitive Area (ESA) Development Permit (DP) to allow construction of temporary mechanical dewatering facilities at 1000 Ferguson Road (Attachments 1 and 2). As the site is currently designated as an ESA, a Development Permit is required prior to Building Permit approval.

The 48.36 ha (119.45 acre) subject site currently contains the Iona Island Wastewater Treatment Plant (IIWWTP) that provides primary sewage and storm water treatment for the City of Vancouver and the University Endowment Lands, and portions of the Cites of Richmond and Burnaby.

The Province has mandated that the IIWWTP be upgraded to secondary treatment by 2030. In preparation for the upgrades, the site's existing sludge lagoons and stockpiles, which currently serve as the dewatering facilities, must be decommissioned to create space for the expansion. As a result, temporary dewatering facilities are proposed as an interim measure to replace the lagoons and stockpiles until all of the secondary treatment upgrades have been completed.

The proposed project footprint for the temporary facilities is 13,666 m2, and would include a

dewatering building, storage tanks, a truck loading building for removing the biosolids to off-site locations, and an odour control facility. Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The applicant has committed to undertaking a new ESA DP in advance of decommissioning the facility to guide rehabilitation of the project footprint. A master plan for the upgrades to secondary treatment is planned for 2019; once details are known, staffwill work with GVS&DD to dete1mine the necessary permits and approvals.

In compensation for disturbing ESA to develop the temporary facilities, GVS&DD has committed to undetiaking invasive species removal and enhancement of an equal amount (13,666 m2

) oflow­value natural area within the adjacent regional park (at a ratio of 1:1 to the project footprint). Additionally, the applicant will provide a total of 1,245 m2 oflandscape restoration within and immediately adjacent to the project footprint.

An ESA DP was adopted in 2015 to allow the GVS&DD to expand the IIWWTP with a 550m2

screening and degrit building, a 20 m diameter thickener, a 25 m2 thickener pump station and four 36m2 digester mixing pump buildings within the ESA at 1000 Ferguson Road (DP14-676361). The project committed to 3,300 m2 oflandscape restoration (a ratio of0.5:1 to the project footprint). The as-built information submitted by GVS&DD shows that 3,791 m2 has been restored as a result of the project.

Development Information

Please refer to the attached Development Application Data Sheet (Attachment 3) for a comparison of the proposed development data with the relevant Bylaw requirements.

5973337

Page 3: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

October 24, 2018 - 3 - DP 18-820582

Background

The area surrounding the site consists of: • To the nmih, the North Aim of the Fraser River;

• To the east, is the Iona Beach Regional Park (Canfor Point), managed by Metro Vancouver;

• To the south, the Iona Island causeway; and,

• To the west, Iona Beach, Iona Jetty and the North Aim Jetty. The Nmih Arm Jetty is under Port of Vancouver jurisdiction.

With the exception of the Iona and North Arm Jetties, Iona Island is entirely designated as "Conservation" in Richmond's Official Community Plan, and zoned "School & Institutional Use (SI)" under Zoning Bylaw 8500.

Staff Comments

The proposed scheme attached to this report has satisfactorily addressed the significant Environmentally Sensitive Area (ESA) issues and other staff comments identified as pmi of the review of the subject Development Permit application. In addition, it complies with the intent of the applicable sections of the Official Community Plan and is generally in compliance with the School and Institutional (SI) zone. No variances are being sought through this ESA Development Permit application.

Advisory Design Panel

As the scope of this Development Permit does not involve any building design components, the application has not been reviewed by the Advisory Design Panel.

Analysis

Site Planning GVS&DD advises that the project is for a temporary mechanical dewatering facility adjacent to the existing IIWWTP. The IIWWTP cunently provides primary sewage treatment, which involves the removal of primary sludge and anaerobic digestion prior to storage in sludge lagoons. The treated effluent is discharged to the Strait of Georgia, while the treated biosolids are stockpiled onsite following lagoon stabilization. GVS&DD is working towards upgrading the facility to provide secondary waste treatment by 2030.

To create space for the upcoming IIWWTP upgrades, the biosolids stockpiles and storage lagoons must be decommissioned. Temporary dewatering facilities are required in lieu of the sludge piles and lagoons until the longer term IIWWTP upgrades are complete. Once the secondary treatment is in place, the temporary dewatering facilities would no longer be required and would be decommissioned. Decommissioning would occur within a year of completing the secondary treatment facility and the area would be rehabilitated under a future ESA DP.

5973337

Page 4: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

October 24,2018 -4- DP 18-820582

The project footprint is proposed to be 13,666 m2 (Attachment 4) and includes various temporary structures and paved areas for vehicle circulation. The facility will include a dewatering building, storage tanks, a truck loading building for removing the biosolids to off-site locations, and an odour control facility. After site clearing and grubbing, three areas within the project footprint and immediately adjacent the project footprint (totalling 1,275 m2

) would be re-landscaped with native vegetation selected to attract pollinator species. Final design of the temporary dewatering facility, vehicle circulation and landscaping will be determined through a design-build process that will include applications for a Building Permit, which is to be completed following adoption of the Development Permit.

To accommodate the proposed temporary dewatering facility, the entire project footprint will be cleared of existing vegetation, and developed or re-landscaped with native vegetation. While the entire project footprint is within the ESA, the area was selected by GVS&DD because of its proximity to the existing IIWWTP and because it has been previously disturbed. A detailed Environmental Assessment completed by AECOM notes that, of the 13,666 m2 ESA required for the project footprint, only 5,097 m2 is vegetated. Of that total, 4,078 m2 is vegetated with exotic or invasive species and 1,019 m2 is vegetated with native species. The remaining 8,569 m2 consists of previously disturbed gravel piles and un-vegetated biosolids stockpiles.

ESA Environmental Inventory The area proposed for the temporary dewatering facility is designated as "Freshwater Wetland" ESA, and is contiguous with "Shoreline" ESA, "Intertidal" ESA and non-ESA natural areas within the Iona Island Regional Park. The total contiguous ESA measures approximately182.4 ha (450.5 acre) and is designated as a hub in the Ecological Network Management Plan.

The biophysical inventory submitted by AECOM (completed in January and August 2018), found no wet areas, rare plants or species at risk. AECOM describes the project area as an anthropogenic ecosystem that is generally flat, dominated by grasses, partially forested with pioneer young tree and shrub species, and several exotic and invasive plant species. Soils were found to be sandy with no standing water. The area offers habitat for foraging, nesting and rearing. During the inventory, three species of song bird (song sparrow, spotted towhee, and golden-crowed sparrow) were observed and two raptor species (peregrine falcon and bald eagle) were noted flying over the site or perching on the cellular towers.

Within the vicinity of the project area, a provincially blue-listed wetland exists to the west and is home to a Provincially red-listed population of western painted turtle. The project area is situated in an area mapped as estuarine marsh by the Metro Vancouver Sensitive Ecosystem Inventory, and is contiguous with estuarine marsh, wetland swamp and freshwater pond.

Tree Inventory There were no bylaw sized trees found on-site during the inventory, but 100 undersized poplar trees were counted. All trees are proposed to be removed as part of the project works.

Mitigation The project was intentionally sited in an area with limited sensitive habitat value, between the existing IIWWTP and wastewater sludge piles.

5973337

Page 5: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

October 24,2018 - 5- DP 18-820582

Increased impermeable surfaces from construction and paving is not expected to impact runoff or infiltration as existing soils are sandy and support only vertical infiltration, not horizontal movement of groundwater. Surface run-off will be directed to the site's stormwater system, which is processed through the IIWWTP.

Proposed Compensation and Landscape Restoration To compensate for impacts to 13,666 m2 ofESA within the project footprint, GVS&DD proposes to restore to natural condition an equal area within Iona Island Park on Canfor Point (a compensation ratio of 1:1 ). Proposed compensation would include invasive species removal and enhancement of 13,666 m2 of existing ESA within the park, resulting in an overall net gain in ESA function (Attachment 5).

The proposed compensation area is divided into two distinct but contiguous planting areas, A and B, which are detailed below. Both compensation areas have well-drained, sandy soils, and are dominated by invasive plant species, including three species identified as priority species in the City's Invasive Species Action Plan (scotch broom, Himalayan blackbeny and reed canarygrass). Restoration of each area will include removal invasive plant species and enhancement with native plant species.

Specific enhancement plans for each area are differentiated according to existing topography, location, and hydrology:

• Area A (670m2): Enhancement is proposed to create a small tree and shrub ecosystem free

of invasive species that helps to provide ecosystem connectivity within the regional park. Plant species include a mix of 260 native trees and shrubs, including:

o black cottonwood (60 trees), o chokecheny ( 40 trees), o red elderberry (60 small trees/shrubs), o crabapple ( 40 trees), and o willow (60 small trees).

The selected plant species provide fruits and benies as food sources for wildlife, as well as structural diversity for roosting, nesting and denning.

• Area B (12,996 m2): located on the south side of the compensation area, Area B is slightly

below Area A in elevation. The intent is to create an open shrub/dune grass ecosystem that provides wildlife habitat, including food sources, nesting, borrowing, foraging and dispersal habitat, and helps to provide connectivity to habitats within the regional park. Species were selected for these objectives and to provide structural diversity include:

o red elderberry (203 small trees/shrubs), o tall Oregon grape (203 plants), o coastal strawberry (2000 plants), and o dune grass (11,000 plants).

The proposed compensation plan includes 200 trees at a 4:1 replacement ratio to trees removed for the temporary dewatering facilities, to a total of 13,666 native plants. Plant density would be 1 plant/m2

.

5973337

Page 6: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

October 24, 2018 - 6- DP 18-820582

While the compensation area is not designated as ESA, the ecosystem services resulting from the proposed compensation plan will be protected through Metro Vancouver's long term objectives for Iona Beach Regional Parle

In addition to the compensation area proposed within Canfor Point, the applicant commits to restoring andre-vegetating a minimum landscape area of 1,245 m2 with native plant species, within and immediately adjacent the project footprint. Landscaping restoration is proposed in three distinct areas: Areas I (360m2

), Area II (210m2) and Area III (675m2

) (Attachment 6). Landscape restoration in each area would include:

• removal of invasive species while preserving existing native plant species, if possible; • restoring soils with growing medium and topsoil; • re-planting with native trees, shrubs and other plant species selected to attract pollinators

and wildlife; and, • providing wood mulch around the planting areas to maintain soil moisture and control re­

growth of invasive species.

Planting within each of the three planting areas includes an evenly-distributed mix of small trees, shrubs and plants:

• vine maple ( 6 trees), • tall Oregon grape (35 shrubs), • red-flowering cmmnt (55 shrubs), • red elderberry (55 small trees/shrubs), • baldhip rose (145 shrubs), • common snowberry (130 shrubs), • red huckleberry (165 shrubs), • salal (265 plants), • dwarf Oregon grape (155 plants), and • sword fern (240 plants).

If approved, the project would result in: • the development of 13,666 nl oflow value ESA on-site; • landscaping using native plant species for 1,245 m2 on-site; and • the restoration of 13,666 m2 oflow value habitat area off-site.

The result would be a total of 14,911 m2 of enhanced natural area and ESA within Iona Island, which represents a net gain in habitat function and ecosystem services by improving:

• the density and diversity of native plant species; • the quality of wildlife habitat through focusing on ben·y and fi:uit producing vegetation; • tree canopy cover through planting 200 trees (a ratio of2:1 for non-bylaw sized trees); and, • connectivity with the contiguous ESA, the Ecological Network and Metro Vancouver's

regional park as a result of removing invasive species and enhancing the function of contiguous natural areas.

For details on the proposed compensation and landscape restoration, refer to Development Petmit Plans #1- 5.

5973337

Page 7: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

October 24, 2018 - 7 - DP 18-820582

Monitoring and Maintenance To ensure that the proposed enhancements have the best chance of survival and that invasive species are controlled, monitoring and annual reporting by a Qualified Environmental Professional (QEP) will occur for five years following completion of the landscape restoration plan. Reports will be provided to the City.

The applicant has submitted a letter committing to implementing the works described above by 2021, and to complete monitoring and maintenance of the compensation area following completion (Attachment 6). Receipt of the commitment letter is included as a Development Permit Considerations (Attachment 7).

Engineering Comments

A Servicing Agreement will not be required for this development. Utility connections and frontage improvements will be addressed at the time of Building Pe1mit.

Financial Impacts

The application results in an insignificant Operational Budget Impact (OBI) for off-site City infrastructure (such as road works, waterworks, stmm sewers, sanitary sewers, street lights, street trees and traffic signals).

Conclusions The applicant proposes to develop a total of 13,666 m2 within an area designated as Enviromnentally Sensitive Area (ESA) as part of upgrades to the IIWWTP. Compensation is proposed through a combination of invasive species removal, off-site restoration of 13,666 m2

within the adjacent Metro Vancouver regional park, and landscaping with native species for at least 1,245 m2 within the project footprint adjacent to the IIWWTP. As the proposed, compensation plan would result in a net gain in ESA function; staff recommend that the Development Permit be endorsed, and issuance by Council be recommended.

9~~ Jeanette Elmore Planner 2

JE:cas

Attachments: Attachment 1: Location Map Attachment 2: Context Map Attachment 3: Data Sheet Attachment 4: Site Landscape Plan Attachment 5: Off-site Compensation Plan Attachment 6: Landscape Restoration Detail Attachment 7: Committement Letter from Metro Vancouver Attachment 8: Development Pe1mit Considerations

5973337

Page 8: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

City of Richmond

DP 18-820582

ATTACHMENT 1

Original Date: 04/26/18

Revision Date:

Note: Dimensions are in METRES

Page 9: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

Context Plan

Environmentally

Sensitive Areas

(ESA)

60 11 058

ATTACHMENT 2

Compensation

Areas A & B

Page 10: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

City of Richmond

Development Application Data Sheet Development Applications Department

DP 18-820582 Attachment 3

Address: 1000 Ferguson Road Greater Vancouver Sewerage and Drainage Greater Vancouver Sewerage and

Applicant: _D_is_tr--=ic-'-t __________________ Owner: Drainage District

Planning Area(s): Sea Island ~~~~~----------------------------------

Floor Area Gross: N/A Floor Area Net: N/A ~~------------------ ~~---------------------

I Existing I Proposed Site Area: 48.36 Ha No change

Land Uses: Waste water treatment facility No change

OCP Designation: Conservation No change

Zoning: School and Institutional Use (SI) No change

Number of Units: 0 No change

I Bylaw Requirement I Proposed I Variance

Floor Area Ratio: No maximum Consistent with zone none permitted

Lot Coverage: No maximum Consistent with zone none

Setback- Front Yard: Min. 6.0 m Consistent with zone none

Setback- Side Yard (one side): Min. 3.0 m Consistent with zone none

Setback- Rear Yard: Min. 3.0 m Consistent with zone none

Max. 12 m within 10 m of Height (m): a residential zone, Consistent with zone none

otherwise no minimum

Lot Size: No minimum Consistent with zone none

Total off-street Spaces: None 79 existing none

5973337

Page 11: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

) A: -c

oM

4th

FLO

OR

, 32

92 P

RO

DU

CT

ION

WA

Y,

BU

RN

AB

Y,

B.C

.,

V!i

A4R

4

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

li,.

ITf;

O .,

L3n

<k<

...,P

iann

ing

Arr

htt.

<:t

u"'

Bu!

ldin

1 E

eolc

gy

Prc

joet

Mon

ao•m

onl

6Hl5

Elm

Sin

lat,

Van

coo.

,.r.B

C,C

anad

u,V

&N

1B2

?11.:{8~)261·6100

flll

C(6

04)2

e1-6

103

Em~~il:urtnmootulloo'>@lctus.,.,t

Wot

>olto

· ww

•owi

'OI!

IIll

oM•O

fl~I

Jit:

\1 c

a

BID

Sau

DS

1

0A

O/N

GP

Prolc~~ionai S

eol

PA

VE

D

WM

.KW

AY

$ {&

SE

RV

ICE

AC

CE

SS)

TO

PS

OIL

&G

RA

SS

H'It

!RQ

SE

ED

(R

Efr

RlO

NO

TE

S)

NO

TE

S -

ton

do

cop

e R

""tc

rotl

cn

Ar<

>os

For

Lo:md~~ap& R

nto

rcl!

cn

Ar

ea~

!, II,

C

!'ld I

ll:

l.DigcutandremoY~~<>IIlnvaolvel'llll'llipee)ea.

2R

otc

ln

en

d proto~\

ell

rom

cln

lng

n

ou

..,

pi(

mh

.

:5.S

up

ply

cnd

ln

otol

l ap

prov

ed

grow

ing

med

ium

I<>

m

ou

nd

ec~h

'Rut

arC

itlo<

! A

r8c"

\o 1

.2M

ma

Klm

um

h

elg

hto

thig

hp

cln

l-to

op

prc

vo

l.

4.P

ion

tln

g o

rao

• to

ne

va 4

50

rr"n

m

inim

um

d

ep

th

of

<>pp

rov"

d gr

owin

g m

odlu

m.

S.C

cver

entl

re'R

o•t

orc

llo

nA

rco

"wll

ho

pr>

rov

ed

flrj

h.,m

lock

woo

d m

ulch

100

mm

do.

,p.

CO

NT

AC

T,K

E11

HR

OS

SR

EC

lST

ER

EO

lAN

DS

CA

PE

A.R

CH

i1E

CT

D

IREC

T LI

NE

: 6

04

-41

8-9

91

7

For

Grc

,Aro

cn·

l.P

rep

crcs

ub

gro

deo

nd

lln

l:;h

qrc

dln

glo

app

rov

ol.

2

.Su

pp

ly O

!'ld

Inst

all

op

p't

lwd

gro

win

g m

ed

ium

2

00

Mm

df

>&P.

J.S

oo

d b

y h

yd

rnu

Uc-a

ud

lng

me

tho

d u

sin

g t

ho

fo

llt>w

lng

'to

ast

cl M;~·gra•s

'".nl

mld

uro

:

26JI

:Per

enni

o1 R

)'l'

~~to

n 9J

I:W

hlte

Clo

v..r

2'1l

':: C

reep

ing

Red

fc

Ge

uc

8T.

Tim

othy

14JI

:Ain

lkeC

io""

r '!

)';C

on

cdaB

iuo

qro

n

1JJ

I::H

crd

fose

uo

V

:Red

Tcp

S...

.din

g ra

to-

75

K9

/Ho

elcr

e

)>

~

~

)>

(")

::I: s m

z ~

~

Page 12: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

Off-Site Compensation Area

NATIVE SPECIES PI ANTING - SITE A:

NA Tnf: PLANT 'Sl'£0£5 (~~tifll ri-vib. I bl:f(t/~¥)

.~c:p.:Ji~:; bm'somilera ~:S,P. tf"l'c.M!:O'"()f1

5C'('!jb!JCiJ!I roc!'mr::te 1/0.~. r:rt>t:~res.:~.-•5 "

6011097

COMMO."J JIAUE

Pr:cl~'c Crab ~PP•'~

{iYr:-:k Cc:ri~rur:u:d

Cl>t~YI'·(:/•,<•TJ'

J-lcoJ-'!'r'!; lt'!.'ion

RM f.'d~ri~t.¥

S'Z£

2 ~~

5 .,.. 2 !:1>(11

2~·

2 .,, TGTI-L

orr PL,4NTN<JG ,i?A7TC5 (;., Sh!' A)

<J!J ~ !:1.1:

6'!) 2J~

"'0 l!i~

t'!.} 2.n

f') 2.J'!t

- 260 PLliNTS

ATTACHMENT 5

NATIVE SPECIES PLANTING - SITE B: .fLAT, SQ!}TH Srrt:. Al~'EA = 72,936 S(), M£T£P.S

f/~1HE' Fi.ANT Sff:C,'£5 (~witf! fwil"s / herrllflf)

fiiY'Ib:JC\.1!1 .riX!!!T'Ii:iS"' Kl'", arb~J't:-sceo!1 ,

CCV,)MO.\' !iAV£

Cr:;o!'tm' ..S'!ratr!le«J'

o,.,. c ...... .:~s::::

j:CJ(I 0rf<'(}'Jr.. (.<tl,f!!l

(.:C~J J:.,•d,rverry

S•'Z::

J.s•

f"UQ:J

7 ~\·~

1 go!

TUTAL-

Q{r' f'I..ANTlN() RA 7TG$ r.·rr S:Us ii)

~·c.too ~5;t

tr,oo.::· 8211

;o:~ t!i:f

:.::tYJ tS;t

i.~,lif,}{l PLA>ITS

Page 13: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

rgwl

"'f"

'l"'

rl~

IU.N

TU

ST

-TA

LL

SHR

UB

S

rgwl"'f"l"'rl~

Toi

iO"#

li""

Cru

t>•

Rl:

>l•

••""

gu

m..

..,.

J

RIK

I-II

oW«O

igC

tllr<

wll

SZE

/NO

TC

S

,Sp

ol;

t5

Uh

l,

muJ/1-~-

d.m

>p

SZ£/

NO

TC

S

llO!IERSArn;>AC~WSCC~ANO

HU

IJU

ING

BIR

OS;

8£R

RI€5

Arn

;>A

CT

SBIR

OS

.55

:HJ

5 :J

O

So-

S<w>obu<U~ l't

1t:

.mn

• ll

Cil

iER

S A

T1R

AC

TS WSCC~ A

NO

.,;brp.P<JI>~~/-,

art>

oru.

:..,.

xw

::;::M

's/!JJ

f'€5

rgwl

"'r"

l"~f

"l"'

:i"

-#J"'

Mr=

Jt'

PO

Sym

ph

arl

coq

>u

•dl>

<lll

C

M'I

tiiM

Stlo

oob_

.ry

15

Jro

oJ

ll>

l'au

llllu

mp

cr>

ifo

//u

m

RH

IIu

ckf"

".-r

y

rgwl

"'f"

'l""

"rl~

Szr

;'NO

TfS

12P

"t:

sp

od

->g

fllll<

>c.

pp

ot'

Jp

oci>

gfl

/1/<

>.c

.

f2p

ot'

sp

<'d

>g

0/U

<>.

c.

Slzr

;'N

PT

CS

~~A!

l/:~

rsV:

tffi

rrs:

ll

O!I

£JlS

AT

WA

C1S

INS£

CT

S;

F'R

UIT

Arn

;>A

CT

SI'I

tDU

FC

n:Sa

"~~g

,'=f

srs:

~COIOFORitr.DIJF

IJ£R

RI£

SAT

1RA

CT

BIR

OS;

ll

OI!

fR5

AT

1R

AC

TIN

SC

CT

S

ISS

5

0

IJ£R

R/£

SAT

1RA

CT

BIR

OS;

CO

NT

AC

T:K

EIT

HR

OS

SR

EG

IST

ER

ED

LAN

DS

CA

PE

AR

CH

ITE

CT

D

IRE

CT

UN

E: 6~-•118-9917

~COI£HfORIIItDL/Fr

£1

£R

CR

£rN

CO

I£H

fOR

IIIt

DL

IFr

5 se

>.u. ~m

V

ER

P

LAN

TIN

G

DE

TA

IL

-•=

TY

P.

GR

OU

ND

C

O

0 TY

P.

PLA

NT

ING

D

ET

AIL

®

8 P

LAN

TIN

G

PLA

N

-A

RE

A

I /

~···~

/ 0

PLA

NT

ING

P

LAN

-

AR

EA

II

/

~~·~

/

0 P

LAN

TIN

G

PLA

N

-A

RE

A

Ill

~~·»

A: -c

oM

4th

FLO

OR

. 3

29

2 P

RO

DU

CT

ION

WA

Y,

:~~ 4~

~.io

g C

, V

SA

4R

4

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

L

IMIT

ED

--L

.and

,..,.e

Pil

lnnl

ng Ar<:~lllPCW"'

Sull

din;

~E<:

olcg

v P

roj•

ctM

on

•ll"

"'""

l 61

89 S

m Strua~

Var

n:tn

lvor

, B

C. Canoa~. V

eN

1B

Z

Ph.

:(60

4)2S

I..l

l106

F"

-'"'{

604)

261>

{/10

3 E

mllL

~rbllnooUWm;@leM,l1(1\

Web

.;ito

:ww

wur

tlans

oluU

onsa

rch.

c;o

PrDf

essio

noiS

eol

)>

-1

-1

)>

('") :::c s m

z -1

en

Page 14: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

~'4 metrovancouver ~ SERVICES AND SOLUTIONS FOR A LIVABLE REGION

August 28, 2018

Mr. Wayne Craig, Director of Development The City of Richmond Development Applications Division 6911 No. 3 Road Richmond, BC V6Y 2C1

Dear Mr. Craig:

ATTACHMENT 7

Liquid Waste Services Project Delivery Division

Tel: 604 451 6011 Fax: 604 436 6714

File: SE-02-01-16006/50

RE: DP 18-820582 - Letter of Commitment, lana Island Wastewater Treatment Plant Biosolids Dewatering Facility- Environmental Considerations

The Greater Vancouver Sewerage & Drainage District (GVS&DD) is proposing to construct a new Biosolids Dewatering Facility at its existing lona Island Wastewater Treatment Plant at 1000 Ferguson Road. To support this work, the GVS&DD has made an application to the City of Richmond for a Development Permit. The Development Permit is for an area of approximately of 13,666 m2 on the east side of the wastewater treatment plant, and will include a Dewatering Building, a Truck Loading area, an area for odour control equipment, and a temporary haul road.

The location of the proposed works is zoned by the City of Richmond as an Environmentally Sensitive Area. An Environmental Assessment has been conducted for the project area and a Compensation Plan has been developed which describes compensation measures used to offset project effects that cannot be mitigated through other means.

Based on the above, and to support the Development Permit process, the GVS&DD is committing to the following actions:

Implement the site restoration, invasive species management and compensation measures outlined in the final Environmental Assessment Report by December 2021 (within 1 year of completion of the Dewatering Facility);

Undertake and maintain the landscape installations outlined in the final Landscape Compensation Plan by December 2021; and

Submit to the City of Richmond for information only, annual monitoring and maintenance reports for 5 years following installation of compensation plantings.

Should you have any questions with respect to this letter, please do not hesitate to contact me.

26611449 4730 l<ingsway, Burnaby, BC, Canada VSH OC6 I 604-432-6200 I metrovancouvewrg

Metro Vancouver Regional District 1 Greater Vancouver Water Dist rict 1 Greater Vancouver Sewerage and Drainage District I Metro Vancouver Housing Corporation

Page 15: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

Letter to City of Richmond RE: lona Island Wastewater Treatment Plant Biosolids Dewatering Facility- Environmental Considerations

Page 2 of 2

Daniel Wee, P. Eng.

Lead Senior Engineer

DW/KKH/ js

cc: Kate Ho, MV, LWS Project Delivery

Rick Bitcon, AECOM Donald Yen, Urban Solutions Architecture Ltd.

Page 16: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

City of Richmond

Address:1000 Ferguson Road

ATTACHMENT 8

Development Permit Considerations Development Applications Department

6911 No.3 Road, Richmond, BC V6Y 2C1

File No.: DP 18-820582

Prior to approval of the Development Permit, the developer is required to complete the following: 1. Ministry of Environment (MOE) Cetiificate of Compliance or alternative approval to proceed granted from MOE

regarding potential site contamination issues. This approval is required prior to dedication of land or road to the City if applicable.

2. Receipt of a Letter of Commitment from the Greater Vancouver Sewerage and Drainage District to undetiake the landscape restoration works as described in the Iona Island Wastewater Treatment Plant Biosolids Dewatering Facility Expansion Environmental Assessment, dated August 2018.

*Prior to Building Permit Issuance, the developer must complete the following requirements: 1. Submission of a Construction Parking and Traffic Management Plan to the Transpmiation Department. Management

Plan shall include location for parking for services, deliveries, workers, loading, application for any lane closures, and proper construction traffic controls as per Traffic Control Manual for works on Roadways (by Ministry of Transportation) and MMCD Traffic Regulation Section 01570.

2. If applicable, payment of latecomer agreement charges associated with eligible latecomer works.

3. Obtain a Building Permit (BP) for any construction hoarding. If construction hoarding is required to temporarily occupy a public street, the air space above a public street, or any part thereof, additional City approvals and associated fees may be required as pati of the Building Permit. For additional information, contact the Building Approvals Depatiment at 604-276-4285. · ·

Note:

* ' This requires a separate application.

• Where the Director of Development deems appropriate, the preceding agreements are to be drawn not only as personal covenants of the property owner but also as covenants pursuant to Section 219 of the Land Title Act.

All agreements to be registered in the Land Title Office shall have priority over all such liens, charges and encumbrances as is considered advisable by the Director of Development. All agreements to be registered in the Land Title Office shall, unless the Director of Development determines otherwise, be fully registered in the Land Title Office prior to enactment of the appropriate bylaw.

The preceding agreements shall provide security to the City including indemnities, warranties, equitable/rent charges, letters of credit and withholding permits, as deemed necessary or advisable by the Director of Development. All agreements shall be in a form and content satisfactory to the Director of Development.

• Additional legal agreements, as determined via the subject development's Servicing Agreement(s) and/or Development Permit(s), and/or Building Permit(s) to the satisfaction of the Director of Engineering may be required including, but not limited to, site investigation, testing, monitoring, site preparation, de-watering, drilling, underpinning, anchoring, shoring, piling, pre-loading, ground densification or other activities that may result in settlement, displacement, subsidence, damage or nuisance to City and private utility infrastructure.

• Applicants for all City Permits are required to comply at all times with the conditions of the Provincial Wildlife Act and Federal Migratory Birds Convention Act, which contains prohibitions on the removal or disturbance of both birds and their nests. Issuance of Municipal permits does not give an individual authority to contravene these legislations. The City of Richmond recommends that where significant trees or vegetation exists on site, the services of a Qualified Environmental Professional (QEP) be secured to perform a survey and ensure that development activities are in compliance with all relevant legislation.

Signed Date

6006792

Page 17: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

City of Richmond Development Permit

No. DP 18-820582

To the Holder: Great Vancouver Sewerage and Drainage District

Property Address: 1 000 Ferguson Road

Address: c/o Donald Yen Urban Solutions Architecture Ltd. 6189 Elm Street, Vancouver, BC V6N 182

1. This Development Permit is issued subject to compliance with all of the Bylaws of the City applicable thereto, except as specifically varied or supplemented by this Permit.

2. This Development Permit applies to and only to those lands shown in cross hatch on the attached Schedule "A" and any and all buildings, structures and other development thereon.

3. Subject to Section 692 of the Local Government Act, R.S.B.C.: buildings and structures; off-street parking and loading facilities; roads and parking areas; and landscaping and screening shall be constructed generally in accordance with Plans #1 to #5 attached hereto.

4. Sanitary sewers, water, drainage, highways, street lighting, underground wiring, and sidewalks, shall be provided as required.

5. As a condition of the issuance of this Permit, the applicant will install the works shown on the Landscape Compensation Plan before 2021, and once in place, the applicant will provide landscape monitoring and maintenance for the compensation for 5 years following completion.

6. If the Holder does not commence the construction permitted by this Permit within 36 months of the date of this Permit, this Permit shall lapse and the security shall be returned in full.

7. The land described herein shall be developed generally in accordance with the te1ms and conditions and provisions of this Permit and any plans and specifications attached to this Permit which shall form a part hereof.

This Permit is not a Building Permit.

AUTHORIZING RESOLUTION NO. OF

DELIVERED THIS DAY OF

MAYOR

6007042

ISSUED BY THE COUNCIL THE DAY

Page 18: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

City of Richmond

DP 18-820582 SCHEDULE "A"

Original Date: 04/26/18

Revision Date:

Note: Dimensions are in METRES

Page 19: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

LOC

ATI

ON

P

LAN

N

.T.S

PR

EP

AR

ED

BY

:

A: C

OM

4t

h F

LO

OR

, 3

29

2 P

RO

DU

CT

ION

WA

Y,

BU

RN

AB

Y,

B.C

.,

VS

A 4

R4

6

04

-44

4-6

40

0

' \

' \ ' ' \ ' \ W

ATER

C

ON

TRO

L B

UIL

DIN

G

---~

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

L

IMIT

E 0

, La

nd-u

se P

lan

nin

g

Arc

hite

ctu

re

Bu

ildin

g E

colo

gy

Pro

ject

Man

agem

ent

61

89

Elm

Str

eet,

Va

nco

uve

r, B

C,

Can

ada,

V6N

18

2

Ph.:

(604

) 26

1-61

06

Fax:

(60

4) 2

61-6

103

Em

ail:

urba

nsol

utlo

ns@

telu

s.ne

t W

ebsi

te:

ww

w.u

rba

nso

lutio

nsa

rch

.ca

Pr

ofes

siona

l Se

al

[X/S

TIN

G

SE:O

IME:

NTA

TIO

N

TAN

KS

NOV

1 4

rr--..

-.. -

.. r··-·

--:-

11 ~

•~-··

------~-"'

I

MA

IN

PRO

JE:C

T S

ITE

BO

UN

DA

RY

:

AD

ulnO

NA

L P

RO

JE:C

T W

OR

K S

ITE

S:

TOTA

L PR

OJE

:CT

SIT

E

ARE:

A:

10

55

5m

'

13

66

6m

'

Plot

\ I

\ \ \ ' \ \ \

PLA

N ' \ \ \ \ \ \ \ \ \ ' \ \ \

#1A

GR

EATE

R VA

NCOU

VER

SEW

AGE

AND

DRAI

NAGE

DIS

TRIC

T f---+

--+

-+

-+

---1

--+

--------------------j

Desig

n: _D

Y~~

1--+

--+

-+

-+

---1

--+

---------------------l Dr

own:

~

Chec

ked:

_DY~~

f-cc_+S~EP:_c.I~B'-}~DY'--j~M~RM~.".DY'--J--'T~J -J-R~E:::-I;::SS;::U:=_E_:_fO":.Rc.cD~E~VE=LO"'-P~M'O.EN~T_:_P~ER~M~IT~~~~~-~~-1 A

ppro

ved

APR.

IB

DY

MRM

DY

TJ

ISSU

E FO

R DE

VELO

PMEN

T PE

RMIT

Issu

e Do

te

Desn

Dr

'n Ch

kd

Appd

De

scrip

tion

0 20

-Ba

r is

20m

m O

n O

rigina

l Dr

awing

. 1f

Not

On T

his S

heet

, Ad

just

Sco

les A

ccor

ding

ly.

ION

A

ISLA

ND

W

WTP

B

IOS

OLI

DS

D

EW

ATE

RIN

G

FAC

ILIT

Y

SIT

E

PLA

N

SCAL

E:

AS

S

HO

WN

DIST

RICT

FILE

Page 20: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

PR

EP

AR

ED

BY

:

0 0

0 0

0

EX

IST

ING

S

CR

EE

N

AN

D

DE

GR

imN

G

BU

ILD

ING

A: C

OM

4t

h F

LOO

R,

3292

PR

OD

UC

TIO

N W

AY

, B

UR

NA

BY

, B

.C.,

VS

A 4

R4

604-

444-

6400

/ /

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

L

IM !

TE

D ,

Land

-use

Pla

nnin

g A

rch

itect

ure

B

uild

ing

Eco

log

y P

roje

ct M

anag

emen

t 61

89 E

lm S

treet

, V

anco

uver

, B

C,

Can

ada,

V6N

182

Ph

.: (6

04)

261-

6106

Fa

x: (

604)

261

-610

3 E

mai

l: ur

bans

olut

ions

@te

lus.

net

Web

site

: w

ww

.urb

anso

tutio

nsar

ch.c

a

I M

AIN

P

RO

JEC

T

• S

ITE

BOUNDARY~ I

/

SEP.

I8

DY

MRM

DY

TJ

RE-IS

SUE

FOR

DEVE

LOPM

ENT

PERM

IT

APR.

18

DY

MRM

DY

TJ

ISSU

E FO

R DE

VELO

PMEN

T PE

RMIT

Issue

Do

te

DeSn

Dr

'n Ch

kd

ApPd

De

scrip

tion

Prof

essio

nal

Seal

~o

Bar

is 20

mm

On

Orig

inal

Draw

ing.

lf N

ot O

n Th

is Sh

eet,

Adju

st S

cales

Acc

ordi

ngly.

Desig

n:

Draw

n:

Chec

ked:

App

rove

d

Man

a er

EX

IST

ING

DE

BR

IS

(TO

BE

RE

MO

VE

D)

• I M

AIN

PR

OJE

CT

SIT

E BOUNDARY~

PLA

N

#1

8

GREA

TER

VANC

OUVE

R SE

WAG

E AN

D DR

AINA

GE D

ISTR

ICT

_DY _

_

ION

A

ISLA

ND

W

WTP

SC

ALE:

~

BIO

SO

LID

S

DE

WA

TER

ING

FA

CIL

ITY

AS

SH

OW

N

_DY _

_

DIST

RICT

FILE

SIT

E

PLA

N

DOCU

MENT

COD

E

~ g g

Page 21: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

PR

EP

AR

ED

BY

:

WAT

ER

CO

NTR

OL

BU

ILD

ING

A: C

OM

4t

h F

LOO

R,

3292

PR

OD

UC

TIO

N W

AY

, B

UR

NA

BY

, B

.C.,

V5

A4

R4

60

4-44

4-64

00

EXIS

77N

G

SC

RE

EN

A

ND

D

EG

R!T

nNG

B

UIL

DIN

G

MA

IN P

RO

JEC

T

SIT

F B

OU

ND

AR

Y

I I I I I I •

I

_W

/

-------'

-.

.c--

c--

--'-

.GR

AS

S\

,

·1·)·1-~.-~.~.1-J·I·I-.1·1·1-I_I_I~I·I-1_1_

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

L

! M

ITE

0

Land

-use

Pla

nn

ing

A

rch

ite

ctu

re

Bu

ildin

g E

colo

gy

Pro

ject

Man

agem

ent

61

89

Elm

Str

ee

l V

anco

uver

, B

C,

Can

ada,

V6

N 1

62

P

h.: (

604)

261

-610

6 Fa

x: (

604)

261-

6103

E

mai

l: ur

bans

olut

ions

@te

!us.

net

Web

site

: w

ww

.urb

anso

!utio

nsar

ch.c

a

NOV

1 4

2018

n .. _

.. _

.. _

.. _

.. _

t ··liiii

iiiiiiiii·

·······lii

iiilili···

·····liiii

iiiiiiiii·

·······iii

iiiiiiiiii

ii········

.!

..

8/0S

OU

DS

LO

ADIN

G ;

.•

Prof

essio

nal

Seal

LAN

DS

CA

PE

SI

TE

PLA

N

LEG

EN

D

PA

VE

D

WA

LKW

AY

S

(& S

ER

VlC

E

AC

CE

SS

)

MA

IN

PR

OJE

CT

__

, S

ITE

BO

UN

DA

RY

_

_ _

....

'\

----

----

JM

TYP.

G

RA

SS

ED

GE

D TO

PS

OIL

&

G

RA

SS

H

YO

RO

SE

ED

(R

EFE

R

TO

NO

TES

)

~ L

AN

DS

CA

PE

R

ES

TO

RA

110N

(RE

FER

TO

N

OTE

S)

NO

TES

-

La

nd

sca

pe

R

est

ora

tio

n

Are

as

For

lan

dsc

ape

Res

tora

tio

n

Are

as !

, 1!,

an

d Ill

:

1.D

ig o

ut

an

d

rem

ove

al

l in

vasi

ve

pla

nt

spe

cie

s.

2.R

etai

n an

d

pro

tect

all

rem

aini

ng

nati

ve

pla

nts

.

3.S

uppl

y an

d

inst

all

app

rov

ed

grow

ing

med

ium

to

m

ound

ea

ch

'Res

tora

tio

n

Are

o"t

o 1

.2M

m

axim

um

he

ight

at

high

po

int

-to

ap

prov

aL

4.P

ion

tin

g

are

as

to

ha

ve

45

0m

m

min

imu

m

de

pth

o

f ap

prov

ed

gro

win

g

me

diu

m.

S.C

over

e

nti

re

"Re

sto

ratio

n

Are

a''w

ith

ap

pro

ved

fi

r /h

em

lock

woo

d m

ulc

h

1 OO

mm

de

ep.

CO

NTA

CT:

K

EIT

H

RO

SS

RE

GIS

TER

ED

LA

ND

SC

AP

E

AR

CH

ITE

CT

DIR

EC

T LI

NE

: 6

04

-41

8-9

91

7

NO

TES

Gra

ss

Are

as

For

Gra

ss

Are

as:

1. P

rep

are

su

b g

rad

e

an

d

finis

h

gra

din

g

to

ap

pro

vaL

2.S

up

ply

and

in

sta

ll a

pp

rove

d

grow

ing

me

diu

m

20

0m

m

deep

.

.3.S

eed

by

hyd

rau

lic-s

ee

din

g

me

tho

d

usi

ng

th

e

follo

win

g "C

oast

al

Mix

" gra

ss

seed

m

ixtu

re:

26

% P

eren

nial

R

yeg

rass

9

%

Whi

te

Clo

ver

24

% C

reep

ing

Red

F

esc

ue

8%

T

imo

thy

14%

A

lsik

e C

love

r

13%

H

ard

Fes

cue

See

ding

ra

te =

75

Kg

/He

cto

re 4

% C

anad

a B

lue

gra

ss

2%

Red

To

p

LAN

#3A

GR

EATE

R VA

NCOU

VER

SEW

AGE

AND

DRAI

NAGE

DIS

TRIC

T 1

---+

--+

--t--1

---t--+

--------------------j

Desig

n: ~

ION

A

ISLA

ND

W

WTP

B

IOS

OLI

DS

D

EW

ATE

RIN

G

FAC

ILIT

Y

SCAL

E:

AS

S

HO

WN

1---+

--+

-+

--1

----t-

-+

--------------------j

Draw

n: ~

Chec

ked:

_DY _

_

SEP.

IB

KRR

MRM

DY

TJ

RE-IS

SUE

FOR

DEVE

LOPM

ENT

PERM

IT

APR.

IS

KRR

MRM

DY

TJ

ISSU

E FO

R DE

VELO

PMEN

T PE

RMIT

1--

"-+

=-=

+=

+"=

t-""

--!.

..:.

::--

t-=

-==

==

==

='-

'-'=

.:_

----

----

-j Ap

prov

ed

Issue

Da

te

OeSn

Dr

'n Ch

kd

Appd

De

scrip

tion

Man

ager

co

LAN

DS

C

0 20

Ba

r is

20m

m O

n O

rigina

l Dr

awing

. If

Not

On T

his S

heet

, Ad

just

Scole

s Ac

cord

ingly.

-SU

PER

SED

ES

PR

INTS

O

F TH

IS

DO

CU

M

DIST

RICT

FILE

Page 22: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

TOTA

L A

RE

A

AR

EA

A

RE

A

KE:

Y Q

TY

I II

Ill

5 2

I 3

AC

TOTA

L A

RE

A

AR

EA

A

RE

A

QTY

I

II If/

K

E:Y

35

2

0

10

Ma

55

2

5

25

R

s

55

2

0

JO

TOTA

L A

RE

A

AR

EA

A

RE

A

KE:

Y Q

TY

I

II

Ill

145

40

3

0

75

R

g

130

40

15

7

5

Sa

155

50

15

10

0 IP

TOTA

L A

RE

A

AR

EA

A

RE

A

KE

Y

QTY

I

II Ill

25

5

55

5

0

150

gs

155

50

4

0

55

24

0

50

4

0

150

pm

PL

AN

T L

IST

-S

MA

LL

TRE

ES

SC

JEN

nFIC

NA

ME

C

OM

MO

N

NA

ME

S

IZE

/NO

TES

E

SA

B

EN

EF

IT

Ace

r clr

cin

otu

m

Wne

M

ap

le

15 p

ot;

1.

5M h

f.

YA

NG

ED

S

EE

DS

FO

OD

S

OU

RC

E

mu

fti-

ste

m d

um

p

PL

AN

T L

IST

-TA

LL

SH

RU

BS

SC

JEN

nFfC

NA

ME

C

OM

MO

N

NA

ME

S

IZE

/NO

TE

S

ES

A

BE

NE

RT

Mo

ho

nfo

a

qu

ilifo

lium

T

oll

Ore

go

n

Gro

pe

Rib

ies

san

gu

ine

um

R

ed

-flo

we

rin

g

Cu

rra

nt

12 p

ot;

F

LO

KfR

S A

TT

RA

CT

S I

NS

EC

TS

AN

D

min

. sp

aci

ng

ti

l 2

M

o.c

. H

UM

MIN

GB

IRD

S;

BE

RR

IES

A

TT

RA

CT

S B

IRD

S

Sa

mb

ucu

s r

ace

mo

se

su

bsp

.pu

be

ns/v

ar.

a

rbo

resce

ns

Re

d E

lde

rbe

rry

13 p

ot;

F

LO

\.i£

RS

AT

TR

AC

TS

IN

SE

CT

S A

ND

m

in.

spa

cin

g

@ 2

M o

.c

HU

MM

ING

BIR

DS

; B

ER

RIE

S

AT

TR

AC

TS

BIR

DS

PL

AN

T L

IST

-M

ED

IUM

S

HR

UB

S

SC

I£N

nF

fC N

AM

E

CO

MM

ON

NA

ME

S

IZE

/NO

TE

S

ES

A

BE

NE

FIT

Ro

sa g

yn

no

ca

rpo

B

afd

hlp

R

ose

12

po

t;

FL

OW

fRS

AT

TR

AC

TS

IN

SE

CT

S;

spa

cin

g

@

1M

o.c

. F

RU

IT A

TT

RA

CT

S

IMLD

LIF

£

S:;

mp

ho

rico

rpu

s a

/bu

s C

om

mo

n

Sn

aw

be

rry

12 p

ot:

F

LO

'M:R

S A

TT

RA

CT

S I

NS

EC

TS

; sp

aci

ng

0

1M

o.c

. F

RU

IT A

TT

RA

CT

S

IMLD

LIF

E

Va

ccin

ium

p

orv

ifo

lium

R

ed

Hu

ckle

be

rry

12 p

ot;

F

LO!t\

£RS

A

TT

RA

CT

S I

NS

EC

TS

; sp

aci

ng

C

1M

o

.c.

BE

RR

IES

AT

TR

AC

T B

IRD

S

PL

AN

T L

IST

-LO

W S

HR

UB

S

AN

D

GR

OU

ND

CO

VE

RS

sa

mn

Ffc

NA

ME

C

OM

MO

N

NA

ME

S

IZE

/NO

TE

S

ES

A

BE

NE

FIT

Ga

ult

he

ria

sh

ollo

n

Sa

lol

11 p

ot;

E

VE

RG

RE

EN

C

OV

ER

F

OR

IM

LDU

FE

; sp

acl

ng

tJl

TM

o

.c.

BE

RR

IES

AT

TR

AC

T B

IRD

S;

FLO

WE

RS

A

TT

RA

CT

IN

SE

CT

S

Mo

ho

nia

ne

rvo

so

Dw

arf

Ore

go

n

Gra

pe

/1

p

ot;

B

ER

RIE

S A

TT

RA

CT

BIR

DS

; sp

aci

'ng

@

1M

a

.c.

EV

ER

GR

EE

N

CO

VE

R

FOR

'M

LDLI

FE

Po

lystl

ch

um

m

un

itu

m

Sw

ord

Fe

m

12 p

ot:

E

VE

RG

RE

EN

C

OV

ER

FO

R

'MLD

LIF

E

spa

cin

g

@

TM

o.c

.

CO

NTA

CT:

K

EIT

H

RO

SS

R

EG

ISTE

RE

D

LAN

DS

CA

PE

A

RC

HIT

EC

T D

IRE

CT

LIN

E:

6D

4-4

18

-99

17

PR

EP

AR

ED

BY

:

A: C

OM

4t

h F

LOO

R,

3292

PR

OD

UC

TIO

N W

AY

, B

UR

NA

BY

. B

.C.,

VS

A 4

R4

604-

444·

6400

EJO

STIN

G S

UB

RA

CO

I.JPA

C1E

fJ

TO 85~

_,

4 T

YP

. P

LAN

TIN

G

DE

TA

IL

--;}

2 ""

"" ""

-""

" /

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

L

IMIT

ED

w

Land~use P

lan

nin

g

Arc

hite

ctu

re

Bu

ildin

g E

colo

gy

Pro

ject

Man

agem

ent

6189

Elm

Str

eet,

Van

couv

er,

BC

, C

an

ad

a,

V6N

18

2

Ph.:

{604

) 26

1-61

06

Fax:

(60

4) 2

61-6

103

Em

ail:

urb

an

solu

tion

s@te

lus.

ne

t W

ebsi

te: w

ww

.urb

anso

lutio

nsar

ch.c

a Pr

ofes

siona

l Se

al

1 4

2018

f>la~

'f

5

'NG

SU

BR

N:J

E

CO

IJPA

C1E

fJ

TO 8

5X

"""

TY

P.

GR

OU

ND

C

OV

ER

P

LAN

TIN

G

DE

TA

IL

~ ~

%: ~ ~

~

%:

Sr%

: (1

2)'

~

%:

%: ~ ~

%:

%: ~ ~ ~

%:

~ ~

%:

%:

%: ~ ~

~

~ ~

%: %:~

~~

%: ~

%:

%:

%:

%: ~

%:

%:

%: ~

~

%:

%:

%: ~

~

%:

%:

%: ~

~ ~

%: ~ ~

%:

~ ~

%: ~ ~

%:

%: ~ ~ ~ ~

%: ~ ~ ~ ~ ~

%: ~ ~ ~

%: ~ ~ ~

~ ~ ~

3 P

LAN

TIN

G

PLA

N

-A

RE

A

Ill

/ P

AN

#

38

GR

EATE

R VA

NCOU

VER

SEW

AGE

AND

DRAI

NAGE

DIS

TRIC

T f--+

--+

-t-----,f---+

-+

--------------------1

Des

ign: ~

1--+

--+

-+

--1

--+

-+

--------------------1

Drow

n: ~

Chec

ked:

_D

Y __

ION

A

ISLA

ND

W

WTP

B

IOS

OLI

DS

D

EW

AT

ER

ING

F

AC

ILIT

Y

CO

NC

EP

TU

AL

PLA

NT

ING

P

LAN

S

SCAL

E:

AS

S

HO

WN

DIST

RICT

FILE

Page 23: 6:~aig - Richmond, British Columbia · Once the upgrades to secondary treatment are complete, the temporary dewatering facilities would be decommissioned by no later than 2031. The

ES

A

CO

MP

EN

SA

TIO

N

SU

MM

AR

Y

(Re

fer

to

Env

i'ron

men

tal

Ass

ess

me

nt

Rep

ort

-A

EC

OM

20

18

)

Pro

ject

Sit

e A

rea

In

ESA

Co

mp

en

satio

n

Rat

io

@ 1

: 1

Exi

stin

g tr

ee

s to

be

rem

oved

on

Pro

ject

si

te

Re

pla

cem

en

t tr

ees

@

2 :

1 ra

tio

13

,66

6

sq.

met

ers

(1.3

7

ho

)

13,6

66

sq.

me

ters

(1.

37 h

o)

Com

pens

atio

n A

rea

requ

ired

100

tree

s (y

oung

E

ast

ern

C

ott

on

wo

od

s -

less

th

an

20

cm

db

h)

20

0 R

ep

lace

me

nt

Tre

es

requ

ired

Pro

po

sed

C

om

pen

sati

on

S

ites

fo

r h

abit

at

rest

ora

tio

n

I n

ativ

e sp

ecie

s pl

anti

ng at

Con

fer

Poi

nt p

ork

site

in

M

etro

V

anco

uver

lo

ne

Bea

ch

Reg

iona

l P

ark:

Site

A

(ra

ise

d

mo

un

d

shap

e,

no

rth

ern

si

te)

Site

8

(fla

t to

po

gra

ph

y,

sou

the

rn

site

)

TO

TA

L C

OM

PE

N S

A T

ION

A

RE

A

TO

TA

L R

ES

TO

RA

TlO

N

PLA

NT

ING

Tot

o!

nu

mb

er

of

Tre

es

Tot

al

nu

mb

er

of

Shr

ubs,

G

ross

es,

an

d G

roun

dcov

ers

PR

EP

AR

ED

BY

:

A: C

OM

4t

h F

LO

OR

, 32

92 P

RO

DU

CT

ION

WA

Y,

BU

RN

AB

Y,

B.C

.,

VS

A 4

R4

6

04

-44

4-6

40

0

67

0 s

q.

me

ters

(0

.07

h

o)

12,9

66

sq.

me

ters

(1.

3 h

a)

13,6

66

sq.m

ete

rs

(1.3

7 h

a)

13,6

66 P

lan

ts

20

0

tre

es

@ 3

,0 m

o.

c.

min

imu

m

spac

ing

13

,46

6

pla

nts

@

1

pla

nt

pe

r sq

. m

ete

r

LAN

DS

CA

PE

P

RE

SC

RIP

TIO

N

INV

AS

IVE

S

PE

CIE

S

RE

MO

VA

L:

-Re

mo

ve

all

Inva

sive

p

lan

ts

and

the

ir

roo

tba

lls

by

ma

chin

e

exc

ava

tor

-Re

mo

ve

top

3

0cm

o

f se

ed

-la

de

n

soil

by

ma

chin

e

exc

ava

tor

-In

clu

de

b

inn

ing

a

nd

tr

uck

ing

o

f re

mo

ved

m

ate

ria

ls

off

sit

e t

o

gree

n w

ast

e

faci

lity

-Use

o

f b

est

p

ract

ice

s co

nta

inm

en

t a

nd

d

isp

osa

l te

chn

iqu

es

for

rem

ove

d

ma

teri

als

SIT

E

PR

EP

AR

A T

lON

: -E

xpo

sed

sa

nd

on

no

rth

S

ite

A

to b

e re

gra

de

d

to

ma

inta

in

a m

ou

nd

sha

pe.

-So

uth

S

ite 8

to

rem

ain

as f

lat

top

og

rap

hy.

-S

ha

pe

and

fin

ish

gra

din

g

on

bo

th

site

s to

ap

prov

al

as

coa

sta

l sa

nd

dune

zo

ne,

NA

TlV

E

SP

EC

IES

P

LAN

TlN

G:

-AU

tr

ees,

sh

rubs

, gr

osse

s,

and

gro

un

dco

vers

to

be

na

tive

sp

ecie

s,

-Div

ers

ity

of

na

tive

pla

nti

ng

s in

clu

de

fr

uit

ing

an

d b

err

ies

bear

ing

pla

nts

.

MO

NIT

OR

ING

A

ND

M

AIN

TE

NA

NC

E

5 Y

EA

R

MO

NIT

OR

ING

A

ND

M

AIN

TE

NA

NC

E

PR

OG

RA

M

(QE

P}

-S

ITE

~SITS

BY

Q

EP

A

T

YE

AR

1,

2,

3

AN

D

5 W

ITH

A

NN

UA

L R

EP

OR

T TO

M

V

PA

RK

S

AN

D

CIT

Y O

F R

ICH

MO

ND

-

80%

SUR~ V

AL

RA

TE

AN

NU

AL

WE

ED

ING

O

F IN

VA

SIV

E

SP

EC

IES

A

NN

UA

L R

EP

LAC

EM

EN

T

OF

DE

AO

P

LAN

TS

CO

NT

AC

T:

KE

ITH

R

OS

S

RE

GIS

TER

ED

LA

ND

SC

AP

E

AR

CH

IIT

CT

O

IRE

CT

UN

E:

60

4-4

18

-99

17

U

R

B

A

N

SO

LU

TIO

NS

A

RC

HIT

EC

TU

RE

L1

MIT

E 0

w

La

nd

·use

Pla

nn

ing

A

rch

ite

ctu

re

Bu

ildin

g E

colo

gy

Pro

ject

Man

agem

ent

6189

Elm

Stre

et,

Van

couv

er,

BC

, C

anad

a, V

6N 1

82

Ph.

: (6

04)

261-

6106

Fa

x: (

604)

261

-610

3 E

mai

l: ur

bans

o!ut

ions

@te

tus.

net

Web

site

: w

ww

.urb

anso

lutio

nsar

ch.c

a Pr

ofes

siona

l Se

al

1 4

Pla

nS

2 C

OM

PE

NS

ATI

ON

A

RE

AS

NA

TIV

E

SP

EC

IES

P

LAN

TIN

G

-S

ITE

A

: R

AIS

ED

, N

OR

TH

SIT

E A

RE

A ~

67

0 S

Q.

ME

TER

S

NA

nvt:

PLA

NT

SP

EC

IES

C

OM

MO

N N

AM

E

SIZ

E

OTY

P

LAN

TIN

G R

A n

os

(•w

ith

fr

uit

s /b

err

ies)

(in

Site

A

)

Mal

us

Fusc

o "

Pa

cifi

c C

rab

App

le

2 g

al

40

15:<

Pop

ulus

ba

lsa

mife

ra

Bla

ck C

ott

on

wo

od

5

ga

l 60

23

:<

ssp,

tric

ha

carp

a

Pru

nus

virg

inia

na

" C

hoke

C

he

rry

2 ga

l 40

15

X

Sa

lix h

ao

keri

an

a

Ho

oke

r's

H-11

/ow

2 ga

l 60

23

:<

NA

TIV

E

SP

EC

IES

P

LAN

TIN

G

-S

ITE

8

: FL

AT,

S

OU

TH

S

ITE

AR

EA

NA

nvt:

PLA

NT

SP

EC

IES

("

wit

h fr

uit

s /

be

rrie

s)

Fra

ga

ria

ch

iloen

sls

"

Le

ymu

s m

ol/i

s

Mah

onia

a

qu

ifoliu

m

"

Sam

bucu

s ra

cem

ose

va

r. a

rbo

resc

en

s "

12

,99

6 S

Q.

ME

TER

S

CO

MM

ON

NA

ME

S

IZE

Co

ast

al

Str

aw

be

rry

J.s·

Dun

e G

rass

P

lugs

Tall

Ore

gon

Gro

pe

2 g

al

Red

Eld

erb

err

y 2

ga

l

QTY

P

LAN

nNG

RA

nos

(in

S

ite B

)

20

00

15

:<

11,0

00

82!<

203

1.5%

203

1,5%

Sam

bucu

s ra

cem

ose

va

r. R

ed E

lde

rbe

rry

2 ga

l 60

23

:<

TO

TA

L -

13

,40

6

PL

AN

TS

a

rbo

resc

en

s "

TOTA

L -

26

0

PLA

NT

S

p A

N

#4

GREA

TER

VANC

OUVE

R SE

WAG

E AN

D DR

AINA

GE D

ISTR

ICT

1---1

----1

--t-

--1

--1

-+

-+

--------------------l

De5ig

n: 1

S.I

3R

.__

f--+

---+

--+

---1

--1

-+

-+

--------------------1

Drow

n: M

BM

...__

Ch

ecke

d: _

DY __

f-'-rS

:::.E

Pcc.

I.::.B

+KC:

:R':-R

+':-M

R:::'M

'-t-D:

..:Y:-+

""T J'-

-t-'R

"'-E -..:.I

S;:;Sc.

:UE::..:.

cfO':'Rc

'D:=:EV

E='LO'

:-PM':'E'

:cN--:T

':'PE'::R

:':MI:-T

==

--------1

!ippr

oved

JU

N.IB

KR

R MR

M DY

TJ

UP

DATE

IS

SUE

fOR

DEVE

LOPM

ENT

PERM

IT Iss

ue

Date

De

Sn

Dr'n

Chkd

Ap

p'd

Desc

riptio

n M

anag

er

ION

A

ISLA

ND

W

WTP

B

IOS

OLI

DS

D

EW

ATE

RIN

G

FAC

ILIT

Y

LAN

DS

CA

PE

C

OM

PE

NS

ATI

ON

P

LAN

~o

Bor

is 20

mm

On

Orig

inal

Draw

ing.

If No

t On

This

She

et.

Adju

st S

coles

Acc

ordi

ngly.

SU

PER

SED

ES

PR

INTS

O

F TH

IS

DO

CU

MEN

T C

OD

E W

ITH

SCAL

E:

AS

S

HO

WN

DIST

RICT

FILE