80 m st. case study - woodworks
TRANSCRIPT
![Page 1: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/1.jpg)
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board.
80 M St. Case StudyAdding Complexity - Mass Timber Vertical Expansion
Presented by Sean Fox
![Page 2: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/2.jpg)
SESSION
AGENDA1. Project Details
2. Preconstruction
3. Delegated Design
4. Procurement
5. Project Sequence
6. Lessons Learned and Best Practices
![Page 3: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/3.jpg)
PROJECT STAKEHOLDERS
OwnerColumbia Property Trust CxP
ArchitectHickok Cole
Structural / Fire /
Code EngineerARUP
General ContractorDAVIS Construction
Timber ContractorKaterra
![Page 4: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/4.jpg)
PROJECT DETAILS
First Mass Timber Project in DC
Existing 7-Story Concrete Building
Vertical Expansion of 3 floors,
adding 105k sq ft.
Occupied Building
Upgrading of Existing Structure
Phased Modernization of Existing
Elevators
![Page 5: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/5.jpg)
PRECONSTRUCTION
DAVIS (GC), Hickok
Cole (Architect), and
ARUP (Engineer)
engaged by Columbia to
assist in budgeting a
future repositioning of
80 M
Q1 | 2018
General scope
determined - (vertical
expansion (2.5 timber, vs
3.5 concrete)
Q1 | 2019
APRIL 2019
SD Presentation
DCRA Presentation for
Code Modification
MAY | 2019
Q4 | 2019
Timber contractors
engaged
Katerra hired
Q1 | 2020
April | 2020
Job Mobilized
2018 2019 2020 2022
SCHEDULED TO
DELIVER
Q2 2022
![Page 6: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/6.jpg)
PRECONSTRUCTION
HCA began researching mass timber in 2016
Designed under DCMR 2013 (IBC 2012)
DCRA was willing to look at projects on case-by-case basis
Accepted as a code modification using IBC 2021 type IV-C,
even though over 85’DCRA required addition of normal use sprinklers and redundant fire pump
DAVIS assisted throughout design with concrete cores,
early demolition of L7, and structural construction strategy
![Page 7: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/7.jpg)
PRECONSTRUCTION 2
DC Code AcceptanceIBC 2021 and Type IV-C updates have not been adopted by
the local AHJ, however the design team was able to get the
project accepted as a code modification. IBC 2021 may be
adopted by DCMR by 2023.
Early Design Assist PackagesElevators, Curtainwall, and Mass Timber
Design team provided an early release drawing
package to price and release the delegated
design mass timber scope of work
![Page 8: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/8.jpg)
MASS TIMBER RELEASE PROCESS
+ TIMELINEBID SOLICITATION + INTERVIEW
TIMBER vs STEEL CONCEPTUAL BUDGETING
SCHEMATIC DESIGN
EARLY RELEASE DESIGN PACKAGES
MASS TIMBER BIDDING AS DELEGATED DESIGN
INTERVIEWS
![Page 9: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/9.jpg)
PROCUREMENT PROCESS + TIMELINEDESIGN ASSIST + SUBMITTAL CRITERIA
PROGRESS MEETINGS
ANALYSIS
TESTING
SHOP DRAWINGS
FINAL SHOP DRAWINGS
10Month Overall
Submittal Process
![Page 10: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/10.jpg)
PROCUREMENT – DELEGATED DESIGN
JANUARYKaterra Release /
Beginning of Delegated Design
Effort
MARCHRedesign for
revised vibration
requirements
MAYStructural
optimization and geometry lock complete
JULYConnection
Testing
NOVEMBERFull Shop Drawings Complete with VC
Coordination
2020
![Page 11: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/11.jpg)
PROCUREMENT – FABRICATION AND DELIVERY
NOVEMBERGlulam production begins
FEBRUARYCLT fabrication begins
MARCHMass timber delivered to
site
2020 2021
![Page 12: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/12.jpg)
13Month Overall Procurement After Initial Engagement
PROCUREMENT PROCESS + TIMELINEDESIGN ASSIST + SUBMITTAL CRITERIA
![Page 13: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/13.jpg)
PROCUREMENTPROCESS + TIMELINE
FABRICATION + PROCUREMENT
GLULAM COLUMN BEAMS
CLT DECKING
![Page 14: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/14.jpg)
DESIGN ASSIST, ENGINEERING +
TESTING
Designed as Type IV-C per 2021 IBC, although
DC AHJ has not formally adopted this code
update
Vibration Model / Requirements are the
primary controlling factor in Mass Timber
Design
Core of 80 M Street is steel. Remainder of
floorplate is CLT and Glulam
Glulam and CLT portion of the structure
included a Design Assist Effort
Design Assist Process originally scheduled for
14 weeks; It was extended due to redesign of
footfall and vibration model, totaling almost
30 weeks altogether
Sound Transmission Testing will be conducted
in early 2021 to confirm acoustic properties
of CLT slabs
![Page 15: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/15.jpg)
INSTALLATION SCHEDULE
L9 CLT INSTALLATION DIAGRAM
Delivery + LogisticsDelivery + Logistics are keyed off of this plan
DayEvery Colored Dot equals 1 Day of Installation
![Page 16: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/16.jpg)
INSTALLATION SCHEDULE
L9 CLT INSTALLATION DIAGRAM
TimelineMassTimber installation is scheduled to begin early March 2021
Faster InstallationGlulam + CLT Installation: 10 weeksEquivalent Steel Building: 14-16 weeks
![Page 17: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/17.jpg)
Elevator Phase 1 – Modernization of
first half of existing elevators
Existing Building Structural
Reinforcement
Installation of temporary mechanical
system
Demolition of Existing Roof and
Penthouse
Installation of new 8th Floor Steel
Structure
Installation of new steel core to final
height
Installation of mass timber structure
and CLT
PROJECT SEQUENCE
![Page 18: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/18.jpg)
PROJECT SEQUENCE
![Page 19: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/19.jpg)
OCTOBER 1 , 2020
![Page 20: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/20.jpg)
NOVEMBER 1 , 2020
![Page 21: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/21.jpg)
DECEMBER 1 , 2020
![Page 22: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/22.jpg)
JANUARY 1 , 2021
![Page 23: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/23.jpg)
FEBRUARY 1 , 2021
![Page 24: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/24.jpg)
MARCH 2, 2021
![Page 25: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/25.jpg)
MARCH 12, 2021
![Page 26: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/26.jpg)
MARCH 17, 2021
![Page 27: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/27.jpg)
Current photo
APRIL ## , 2021
![Page 28: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/28.jpg)
LESSONS LEARNED + BEST PRACTICES
Water Mitigation• CLT Spline sealing
• Top of Column Sealing
• Early Unwrapping of Structure
• Perimeter Flashing
Factory vs. Field Sealing
Construction Tolerances• AISC Steel Tolerances
• Concrete Slab Tolerances
Temporary Storm System
![Page 29: 80 M St. Case Study - WoodWorks](https://reader031.vdocuments.net/reader031/viewer/2022012410/616a5ad811a7b741a351975f/html5/thumbnails/29.jpg)
This concludes The American Institute of Architects Continuing Education Systems Course
QUESTIONS?
Sean Fox
James G. Davis Construction Corporation