8th stakeholder group meeting of the gas regional initiative north-west (gri nw)
DESCRIPTION
8th Stakeholder Group Meeting of the Gas Regional Initiative North-West (GRI NW). Brussels, 26 November 2010. Mark Hobbelink Wiekens, GTS. Agenda. a new cross border service What is Link4Hubs? How does it work? Preliminary conclusions. What is Link4Hubs?. - PowerPoint PPT PresentationTRANSCRIPT
26 November 2010
8th Stakeholder Group Meeting of the Gas Regional Initiative North-West (GRI NW)
Brussels, 26 November 2010
Mark Hobbelink Wiekens, GTS
Agenda
a new cross border service
– What is Link4Hubs?– How does it work?– Preliminary conclusions
GUDGTS
ENDK
What is Link4Hubs?
Short term capacity assessment makes a new firm Day Ahead product possible
Service enables the transfer of gas between the 3 grids
A One-click service
Capacity booking and nomination combined
Enhance possibilities for day ahead cross-border gas trade and price arbitrage
Link4Hubs – how does it work?
•One Click:
Transfer of gas from
portfolio in one
country to portfolio
in another country
The TSOs arrange the underlying physical transportation
The offered service is firm (we start by offering a small amount)
Shipper
TSO Contracts
TSO actions
One click received
TSO A prepares exit-contract from country A
TSO B prepares entry-contract and exit-contract through country B
TSO C prepares entry-contract into country C
All TSOs nominate to these contracts
Shipper only sees new cross-border service contracts
GUDGTS
ENDK
Some preliminary conclusions
Results Challenges
• Common focus on market facilitation
• Successful inter TSO cooperation
• Co-operation agreement established
• Implemented very fast and within budget and deadlines!
• Positive customer feedback
• Common focus on market facilitation
• Successful inter TSO cooperation
• Co-operation agreement established
• Implemented very fast and within budget and deadlines!
• Positive customer feedback
• Three parties
• New international inter-TSO project organization
• Different contract and tax rules
• Differences in TSO IT-systems and internal procedures
• Cultural differences
• Three parties
• New international inter-TSO project organization
• Different contract and tax rules
• Differences in TSO IT-systems and internal procedures
• Cultural differences
Registration started 1 June 2010 Operational since 1 July 2010
– Opening hours – business days between 9-11
Capacity available at the GTS side of Link4Hubs starts with a cap of 60 MWh/h
More information on www.link4hubs.com
“in a nutshell”