what were gri nw investment objectives?

13
GRI NW Investment - Update on project ommon effort on making regional investment happen 21 September 2010

Upload: anka

Post on 18-Jan-2016

38 views

Category:

Documents


0 download

DESCRIPTION

What were GRI NW Investment objectives?. By end of 2009 “an agreed framework for (all) new cross border investments and pilot projects underway” By end of 2009 establish and implement across region these coordinated incentives - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: What were GRI NW Investment objectives?

GRI NW Investment-

Update on project

Common effort on making regional investment happen

21 September 2010

Page 2: What were GRI NW Investment objectives?

2

By end of 2009 “an agreed framework for (all) new cross border investments and pilot projects underway”

By end of 2009 establish and implement across region these coordinated incentives

By end of 2008 “TSOs should understand how they will be incentivized to make new (additional to immediate demand) regulated capacity available efficiently

During q2 2010 – 2011 roll-out of Action Plan in order to implement the agreed in Policy paper framework for (all) new cross border investments in the region

Subject to update Roadmap Combine implementation with pro-active following of EU-

developments

What were GRI NW Investment objectives?

Page 3: What were GRI NW Investment objectives?

3

We continue to focus on implementing policy advice in 2010, while pro-actively

working towards 3rd package discussion:

- Progress of regional projects monitored for ad-hoc action RCC (all rec)

- Regulators address stranded asset risk discussion via documenting solutions in

exchange of letters between PB and NRAs (rec 1) => pending, by November

2010 (Joint Statement, subject to comments).

- TSO’s clarify investment prerequisites via website publications (rec 4) => by

21.09 IG presentation of end-results.

- Share Regulatory best practices on re-numeration in general via input to FGL

tarification (rec 2 and pro-active) => paper submitted by 12 August 2010 to

ERGEG.

- Regulators clarify GRI NW view on scope of regional plan => paper welcomed

with Gasplatform (discussion continued 09 Nov 2010)

Where do we stand with implementation? First results by 21.09.2010

Page 4: What were GRI NW Investment objectives?

4

FGL Tarification See

http://www.energy-regulators.eu/portal/page/portal/EER_HOME/EER_INITIATIVES/GRI/North_West/Priorities%2020102011/Projects/Investment - Key elements walk through:

Stranded assets mechanism should be clear to TSO Limiting ex-post refusal of investment (and keeping some risk on TSO) Minimum investment criteria (hurdle) specified Accompanying tariff arrangements – which can be reset - specify:

the manner in which investment costs will be calculated the period over which the investment cost is recovered

(also known as the period of depreciation) the rate of return and the extent of User Commitment (UC) required to signal

investment

Regional plans

Pro-active work results in (partial) recording of lessons learned in 3rd package instruments

Page 5: What were GRI NW Investment objectives?

5

Question for discussion: So is the work finished and goal achieved?

5

The path to secure and integrated market from Roadmap GRI NW:

“The (path to) investment climate should be such that investments in capacity are sufficient and (efficient and therefore) timely and persistent physical congestion is avoided. (…) Investments should facilitate gas supplies from diverse sources to meet the need for secure gas supplies”.

Page 6: What were GRI NW Investment objectives?

6

Key questions for today: Comments on Joint Statement?

Stop or continu potential work of GRI Investment after finalization of implementation of Policy Advice?- Subject to pending information on Regional Initiatives paper EU

Commission, Infrastructure package content, definitive ERGEG/ACER workplan 2011+, GRI workplan 2011+, Open Seasons and Regional plan work.

Thank you for your attention and time.

Further questions can be emailed to: [email protected] and [email protected]

Page 7: What were GRI NW Investment objectives?

7

ANNEXDetailed Policy advice (=the key result) implementation slides

Page 8: What were GRI NW Investment objectives?

8

For original text of the Policy advice of GRI Investment, February 2010, with the 7 recommendations please consult weblink at http://www.energy-regulators.eu/portal/page/portal/EER_HOME/EER_INITIATIVES/GRI/North_West/Priorities1/Investment

In this annex we provide walk through the Policy advice implementation….

The key result – Policy advice of February 2010.What is the Policy advice, that is being implemented?

Page 9: What were GRI NW Investment objectives?

9

Recommendations – walk though

Recommendation 1: “Roll in (partially, and with exemption of exempt interconnectors) the new investment in the existing asset base and/or allow shorter depreciation periods and/or increase the WACC to bear the risk, in proportion to TSO risk burden..” (of stranded assets

- Joint Statement approach

9

Page 10: What were GRI NW Investment objectives?

10

Recommendation 2: encourage to agree national regulator and TSOs on the parameters for remuneration of future investments and stimulate this debate on a regional level by sharing good regulatory practices.

The pilot for encouraging (national) agreement is clearly implementation of Recommendation 1 (adressing stranded asset risk). Pilot for sharing regulatory practices on remuneration in 2010 is input to FG Tarification.

Implementation actions in 2010 are therefore addressed via work on Recommendation 1 and input to FG Tarification debate.

As concerning future regional debate, there is a clear need for future “anchoring” regional investment discussions in RCC or e.g. during future Regional Plan discussions. We need to ensure that once GRI Investment is finalized, we DON’T need in 2 years again a Virtual Test II.

10

Implementation actions worked out per recommendation

Page 11: What were GRI NW Investment objectives?

11

Recommendation 3: Make tariffs or methodology to calculate them transparent.

This is “arranged” as of 3.3. 2011 with approval of Ro. 715/2009. Therefore no implementation action shall be taken by GRI NW unless repeated signals are to be received from market parties.

Recommendation 4: Make elements transparent that help achieve the investment prerequisites (e.g. communicate the minimum level of commitment you need from shippers)

As 1st implementation action, the TSOs are to publish by end of 2010 the required for investment decisions elements on their websites. The progress with implementation is reported by Operators in IG of 21September 2010. This will allow time for implementation during September – December 2010.

2nd implementation 2010 action on this topic in the context of “2010+” is discussion by TSOs, Regulators and Shippers on Regional Plan theme. The output of this discussion should provide a further step on Recommendation 4 .

11

Implementation actions worked out per recommendation

Page 12: What were GRI NW Investment objectives?

12

Recommendation 5Recommendation 5:: Close co-operation between (adjacent) TSOs and NRAs in the organisation and timing of allocation processes.

No specific implementation action is required at the time. The need for action is being monitored by continuous presentations in workshops and other meetings by TSOs/NRAs on the pending projects (see Rec. 6).

12

Implementation actions worked out per recommendation

Page 13: What were GRI NW Investment objectives?

13

Recommendation 6: Organise regular ‘3-lateral’ regional co-operation meetings on cross-border investments.

Workshop on 4 June 2010. More workshops follow if needed.

Informal meetings and telco’s advisory core group.

Recommendation 7: Ex-post review of cross-border investment projects at regional level every 2 years.

In 2011, subject to GRI-developments. To be addressed in projectplan update in q3- q4 2010, if relevant.

13

Implementation actions worked out per recommendation