  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    1/28

    CATERPILLAR TUNNELING CANADA

    LARGE DIAMETER PIPE JACKING

    MWRD Revive Wacker Drive By-PassTunnel Project, Chicago, IL, USA

    Walter R. Trisi Area Sales Manager

    Wojciech Sawicki Sales Advisor

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    2/28

    CATERPILLAR TUNNELING CANADA

    PROJECT INFORMATION

    Name: Revive Wacker Drive, Part 2, By-Pass Tunnels

    Location: Chicago, IL, USA

    Owner: Metropolitan Water Reclamation District (MWRD)

    of Greater ChicagoContractor: F.H. Paschen / SN Nielsen / Cabo Joint Venture

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    3/28

    CATERPILLAR TUNNELING CANADA

    PROJECT INFORMATION

    Machine: Caterpillar RME170PJ EPB-Pipe Jacking-TBM

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    4/28

    CATERPILLAR TUNNELING CANADA

    PROJECT INFORMATION

    Lining: Reinforced Concrete Jacking Pipe

    ID: 3.6m (12 ft), OD: 4.2m (14ft), L: 2.4m (8ft)

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    5/28

    CATERPILLAR TUNNELING CANADA

    PROJECT INFORMATION

    Drives: 1 x 163m (536 ft) + 1 x 56 m (184 ft)

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    6/28

    CATERPILLAR TUNNELING CANADA

    PROJECT INFORMATION

    Alignment: Under the Congress Expressway and narrowlypassing over a Chicago Transit Subway tunnel

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    7/28

    CATERPILLAR TUNNELING CANADA

    PROJECT INFORMATION

    Geology: Mixed ground conditions, Clay, Sand, silt,boulders, fill material (granite pavers),

    and wood pile foundations.

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    8/28

    CATERPILLAR TUNNELING CANADA

    TBM SPECIFICATIONS

    Type: Earth Pressure Balance Pipe Jacking

    Cuttinghead: Mixed ground, interchangeable Rippers & Discs

    CH Torque: 2,345 kN.m (max)

    CH Speed: 6 rpm (max)

    CH Power: 900 kW (1200 hp)

    Propulsion: 12 x 180 tonne cylinders

    Max Thrust: 2160 tonne @ 340 bar

    Articulation: 12 x 115 tonne cylinders

    Art. Angle: 0 to 2 degrees

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    9/28

    CATERPILLAR TUNNELING CANADA

    TBM CUTTING TOOLS

    Caterpillar Ripper TeethFully Armored with:

    Tungsten Carbide Bullets

    Chromium Carbide PlateCHT 100 base metal

    Backloaded Design

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    10/28

    CATERPILLAR TUNNELING CANADA

    TBM SPECIFICATIONS

    Screw: 610 mm diameterSpeed: 20 rpm (max)

    Belt: 610 mm wideSpeed: 0 100m / min

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    11/28

    CATERPILLAR TUNNELING CANADA

    MAIN JACKING STATION

    Type: Single stage jacking cylinders, stroke: 10 ftCylinders: 10 x 115 tonne

    Total Thrust: 1150 tonne @ 340 bar

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    12/28

    CATERPILLAR TUNNELING CANADA

    JOBSITE LAYOUT

    LAUNCH SHAFT

    JXN BOX 4

    TURNING SHAFT

    JXN BOX 3

    RETRIEVAL SHAFT

    JXN BOX 1

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    13/28

    CATERPILLAR TUNNELING CANADA

    TUNNELLING INFORMATION

    TBM started to arrived on site in late January 2011, in

    the middle of one of the worst winters on record for

    the Chicago area.

    TBM and Main Jacking Station were assembled and

    ready to launch in less than one month.

    First Drive (163m) started March 9th and was

    completed in 7 days, on March 16

    th

    .

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    14/28

    CATERPILLAR TUNNELING CANADA

    TBM LAUNCH SEQUENCE (1)

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    15/28

    CATERPILLAR TUNNELING CANADA

    TBM & Jacking Station Assembly in Shaft

    TBM Cutt inghead

    Jacking Station

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    16/28

    CATERPILLAR TUNNELING CANADA

    BURYING THE TBM

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    17/28

    CATERPILLAR TUNNELING CANADA

    TBM LAUNCH SEQUENCE (2)

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    18/28

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    19/28

    CATERPILLAR TUNNELING CANADA

    MUCKING OUT THE SCREW CONVEYOR

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    20/28

    CATERPILLAR TUNNELING CANADA

    WAITING FOR TAIL CAN & LEADING CAN

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    21/28

    CATERPILLAR TUNNELING CANADA

    TBM LAUNCH SEQUENCE (3)

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    22/28

    CATERPILLAR TUNNELING CANADA

    PARTIAL ASSEMBLY ARCH RINGS INSTALLED

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    23/28

    CATERPILLAR TUNNELING CANADA

    TBM COMPLETELY ASSEMBLED

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    24/28

    CATERPILLAR TUNNELING CANADA

    COMPLETED FIRST TUNNEL DRIVE

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    25/28

    CATERPILLAR TUNNELING CANADA

    REPOSITIONING TBM AFTER 1ST DRIVE

    AFTER COMPLETION OF

    FIRST DRIVE THE TBM

    HAD TO BE TURNED 90DEGREES AND

    ADVANCED INTO TUNNEL

    EYE SEAL FOR SECOND

    DRIVE (MAJORITY OFGANTRY WAS LEFT IN

    FIRST TUNNEL AND

    UMBILICAL CABLES

    WERE RUN TO THE TBM)

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    26/28

    CATERPILLAR TUNNELING CANADA

    TUNNELLING INFORMATION

    TBM and Main Jacking station were repositioned andre-launched in approximately 10 days.

    Second Drive (56m) was completed by April 1st; 5

    days.

    Best shift production was 5 pipes, 12m (40ft).

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    27/28

    CATERPILLAR TUNNELING CANADA

    COMPLETION OF SECOND DRIVE

    BREAK THROUGH !

  • 8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA

    28/28

    CATERPILLAR TUNNELING CANADA

    CONCLUSION

    First time mechanized tunnel project for contractorTunnels completed on time and ahead of schedule

    No settlement under Congress Expressway

    No damage to active Subway systemTBM operator supplied by Manufacturer (CAT)

    No loss time injuries

    Best shift production was 5 pipes, 12m (40ft)

    Happy customer, happy owner, successful project!