CATERPILLAR TUNNELING CANADA
LARGE DIAMETER PIPE JACKING
MWRD Revive Wacker Drive By-PassTunnel Project, Chicago, IL, USA
Walter R. Trisi Area Sales Manager
Wojciech Sawicki Sales Advisor
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
2/28
CATERPILLAR TUNNELING CANADA
PROJECT INFORMATION
Name: Revive Wacker Drive, Part 2, By-Pass Tunnels
Location: Chicago, IL, USA
Owner: Metropolitan Water Reclamation District (MWRD)
of Greater ChicagoContractor: F.H. Paschen / SN Nielsen / Cabo Joint Venture
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
3/28
CATERPILLAR TUNNELING CANADA
PROJECT INFORMATION
Machine: Caterpillar RME170PJ EPB-Pipe Jacking-TBM
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
4/28
CATERPILLAR TUNNELING CANADA
PROJECT INFORMATION
Lining: Reinforced Concrete Jacking Pipe
ID: 3.6m (12 ft), OD: 4.2m (14ft), L: 2.4m (8ft)
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
5/28
CATERPILLAR TUNNELING CANADA
PROJECT INFORMATION
Drives: 1 x 163m (536 ft) + 1 x 56 m (184 ft)
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
6/28
CATERPILLAR TUNNELING CANADA
PROJECT INFORMATION
Alignment: Under the Congress Expressway and narrowlypassing over a Chicago Transit Subway tunnel
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
7/28
CATERPILLAR TUNNELING CANADA
PROJECT INFORMATION
Geology: Mixed ground conditions, Clay, Sand, silt,boulders, fill material (granite pavers),
and wood pile foundations.
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
8/28
CATERPILLAR TUNNELING CANADA
TBM SPECIFICATIONS
Type: Earth Pressure Balance Pipe Jacking
Cuttinghead: Mixed ground, interchangeable Rippers & Discs
CH Torque: 2,345 kN.m (max)
CH Speed: 6 rpm (max)
CH Power: 900 kW (1200 hp)
Propulsion: 12 x 180 tonne cylinders
Max Thrust: 2160 tonne @ 340 bar
Articulation: 12 x 115 tonne cylinders
Art. Angle: 0 to 2 degrees
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
9/28
CATERPILLAR TUNNELING CANADA
TBM CUTTING TOOLS
Caterpillar Ripper TeethFully Armored with:
Tungsten Carbide Bullets
Chromium Carbide PlateCHT 100 base metal
Backloaded Design
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
10/28
CATERPILLAR TUNNELING CANADA
TBM SPECIFICATIONS
Screw: 610 mm diameterSpeed: 20 rpm (max)
Belt: 610 mm wideSpeed: 0 100m / min
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
11/28
CATERPILLAR TUNNELING CANADA
MAIN JACKING STATION
Type: Single stage jacking cylinders, stroke: 10 ftCylinders: 10 x 115 tonne
Total Thrust: 1150 tonne @ 340 bar
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
12/28
CATERPILLAR TUNNELING CANADA
JOBSITE LAYOUT
LAUNCH SHAFT
JXN BOX 4
TURNING SHAFT
JXN BOX 3
RETRIEVAL SHAFT
JXN BOX 1
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
13/28
CATERPILLAR TUNNELING CANADA
TUNNELLING INFORMATION
TBM started to arrived on site in late January 2011, in
the middle of one of the worst winters on record for
the Chicago area.
TBM and Main Jacking Station were assembled and
ready to launch in less than one month.
First Drive (163m) started March 9th and was
completed in 7 days, on March 16
th
.
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
14/28
CATERPILLAR TUNNELING CANADA
TBM LAUNCH SEQUENCE (1)
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
15/28
CATERPILLAR TUNNELING CANADA
TBM & Jacking Station Assembly in Shaft
TBM Cutt inghead
Jacking Station
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
16/28
CATERPILLAR TUNNELING CANADA
BURYING THE TBM
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
17/28
CATERPILLAR TUNNELING CANADA
TBM LAUNCH SEQUENCE (2)
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
18/28
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
19/28
CATERPILLAR TUNNELING CANADA
MUCKING OUT THE SCREW CONVEYOR
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
20/28
CATERPILLAR TUNNELING CANADA
WAITING FOR TAIL CAN & LEADING CAN
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
21/28
CATERPILLAR TUNNELING CANADA
TBM LAUNCH SEQUENCE (3)
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
22/28
CATERPILLAR TUNNELING CANADA
PARTIAL ASSEMBLY ARCH RINGS INSTALLED
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
23/28
CATERPILLAR TUNNELING CANADA
TBM COMPLETELY ASSEMBLED
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
24/28
CATERPILLAR TUNNELING CANADA
COMPLETED FIRST TUNNEL DRIVE
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
25/28
CATERPILLAR TUNNELING CANADA
REPOSITIONING TBM AFTER 1ST DRIVE
AFTER COMPLETION OF
FIRST DRIVE THE TBM
HAD TO BE TURNED 90DEGREES AND
ADVANCED INTO TUNNEL
EYE SEAL FOR SECOND
DRIVE (MAJORITY OFGANTRY WAS LEFT IN
FIRST TUNNEL AND
UMBILICAL CABLES
WERE RUN TO THE TBM)
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
26/28
CATERPILLAR TUNNELING CANADA
TUNNELLING INFORMATION
TBM and Main Jacking station were repositioned andre-launched in approximately 10 days.
Second Drive (56m) was completed by April 1st; 5
days.
Best shift production was 5 pipes, 12m (40ft).
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
27/28
CATERPILLAR TUNNELING CANADA
COMPLETION OF SECOND DRIVE
BREAK THROUGH !
-
8/10/2019 9-2 Large Diameter Pipe Jacking for the MWRD by-Pass Tunnel Project in Chicago USA
28/28
CATERPILLAR TUNNELING CANADA
CONCLUSION
First time mechanized tunnel project for contractorTunnels completed on time and ahead of schedule
No settlement under Congress Expressway
No damage to active Subway systemTBM operator supplied by Manufacturer (CAT)
No loss time injuries
Best shift production was 5 pipes, 12m (40ft)
Happy customer, happy owner, successful project!