9–1 chapter 9 reducing project duration. 9–2 where we are now
TRANSCRIPT
![Page 1: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/1.jpg)
9–1
Chapter 9Chapter 9Chapter 9Chapter 9
•Reducing Project Duration
![Page 2: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/2.jpg)
9–2
Where We Are NowWhere We Are NowWhere We Are NowWhere We Are Now
![Page 3: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/3.jpg)
9–3
Rationale for Reducing Project DurationRationale for Reducing Project DurationRationale for Reducing Project DurationRationale for Reducing Project Duration
• Time Is Money: Cost-Time Tradeoffs–Reducing the time of a critical activity usually incurs
additional direct costs.•Cost-time solutions focus on reducing (crashing)
activities on the critical path to shorten overall duration of the project.
–Reasons for imposed project duration dates:•Time-to-market pressures
•Unforeseen delays
• Incentive contracts (bonuses for early completion)
• Imposed deadlines and contract commitments
•Overhead and public goodwill costs
•Pressure to move resources to other projects
![Page 4: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/4.jpg)
9–4
Options for Accelerating Project CompletionOptions for Accelerating Project CompletionOptions for Accelerating Project CompletionOptions for Accelerating Project Completion
• Resources Not Constrained–Adding resources
–Outsourcing project work
–Scheduling overtime
–Establishing a core project team
–Do it twice—fast and then correctly
• Resources Constrained–Fast-tracking
–Critical-chain
–Reducing project scope
–Compromise quality
![Page 5: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/5.jpg)
9–5
Explanation of Project CostsExplanation of Project CostsExplanation of Project CostsExplanation of Project Costs
• Project Indirect Costs–Costs that cannot be associated with any particular
work package or project activity.•Supervision, administration, consultants, and
interest
–Costs that vary (increase) with time.•Reducing project time directly reduces indirect
costs.
• Project Direct Costs–Normal costs that can be assigned directly to
a specific work package or project activity.•Labor, materials, equipment, and subcontractors
–Crashing activities increases direct costs.
![Page 6: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/6.jpg)
9–6
Reducing Project Duration Reducing Project Duration to Reduce Project Costto Reduce Project Cost
Reducing Project Duration Reducing Project Duration to Reduce Project Costto Reduce Project Cost
Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.
Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.
Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.
Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.
Identifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project time
Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.
Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.
![Page 7: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/7.jpg)
9–7
Project CostProject Cost–Duration Graph–Duration GraphProject CostProject Cost–Duration Graph–Duration Graph
FIGURE 9.1
![Page 8: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/8.jpg)
9–8
![Page 9: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/9.jpg)
9–9
Constructing a Project CostConstructing a Project Cost–Duration Graph–Duration Graph Constructing a Project CostConstructing a Project Cost–Duration Graph–Duration Graph
• Find total direct costs for selected project durations.
• Find total indirect costs for selected project durations.
• Sum direct and indirect costs for these selected project durations.
• Compare additional cost alternatives for benefits.
![Page 10: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/10.jpg)
9–10
Constructing a Project CostConstructing a Project Cost––Duration Graph Duration Graph Constructing a Project CostConstructing a Project Cost––Duration Graph Duration Graph
• Determining Activities to Shorten
–Shorten the activities with the smallest increase in cost per unit of time.
–Assumptions:
•The cost relationship is linear.
•Normal time assumes low-cost, efficient methods to complete the activity.
•Crash time represents a limit—the greatest time reduction possible under realistic conditions.
•Slope represents a constant cost per unit of time.
•All accelerations must occur within the normal and crash times.
![Page 11: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/11.jpg)
9–11
Activity GraphActivity GraphActivity GraphActivity Graph
FIGURE 9.2
![Page 12: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/12.jpg)
9–12
CostCost–Duration Trade-off Example–Duration Trade-off ExampleCostCost–Duration Trade-off Example–Duration Trade-off Example
FIGURE 9.3
![Page 13: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/13.jpg)
9–13
CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)
FIGURE 9.3 (cont’d)
![Page 14: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/14.jpg)
9–14
CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)
FIGURE 9.4
![Page 15: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/15.jpg)
9–15
CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)CostCost–Duration Trade-off Example (cont’d)–Duration Trade-off Example (cont’d)
FIGURE 9.4 (cont’d)
![Page 16: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/16.jpg)
9–16
Summary Costs by DurationSummary Costs by DurationSummary Costs by DurationSummary Costs by Duration
FIGURE 9.5
![Page 17: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/17.jpg)
9–17
Project CostProject Cost–Duration Graph–Duration GraphProject CostProject Cost–Duration Graph–Duration Graph
FIGURE 9.6
![Page 18: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/18.jpg)
9–18
Practical ConsiderationsPractical ConsiderationsPractical ConsiderationsPractical Considerations
• Using the Project Cost–Duration Graph
• Crash Times
• Linearity Assumption
• Choice of Activities to Crash Revisited
• Time Reduction Decisions and Sensitivity
![Page 19: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/19.jpg)
9–19
What if Cost, Not Time Is the Issue?What if Cost, Not Time Is the Issue?What if Cost, Not Time Is the Issue?What if Cost, Not Time Is the Issue?
• Commonly Used Options for Cutting Costs
–Reduce project scope
–Have owner take on more responsibility
–Outsourcing project activities or even the entire project
–Brainstorming cost savings options
![Page 20: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/20.jpg)
9–20
Key TermsKey TermsKey TermsKey Terms
Crashing
Crash point
Crash time
Direct costs
Fast-tracking
Indirect costs
Outsourcing
Project cost–duration graph
![Page 21: 9–1 Chapter 9 Reducing Project Duration. 9–2 Where We Are Now](https://reader035.vdocuments.net/reader035/viewer/2022062308/56649d2f5503460f94a07dec/html5/thumbnails/21.jpg)
9–21
Project Priority Matrix: Whitbread ProjectProject Priority Matrix: Whitbread ProjectProject Priority Matrix: Whitbread ProjectProject Priority Matrix: Whitbread Project
FIGURE 9.6