a management plan for the dredging and...
TRANSCRIPT
A MANAGEMENT PLAN FOR THE DREDGING AND DISPOSAL OF
MATERIAL FOR THE PROPOSED TASSAL SPRING BAY JETTY, TASMANIA
An Appendix To
Marine Environmental Impact Assessment for a Proposed Jetty Including Dredging at
Spring Bay, Triabunna, March 2017
www.marinesolutions.net.au
Tassal/SBSF Jetty DMP 2
© Marine Solutions 2017. This document should only be used for the specific project and
purposes for which it was commissioned. 1
Version Author Date reviewed Reviewed by
1 of 2 Coco Cullen-Knox 24/3/16 Sam Ibbott
2 of 2 Coco Cullen-Knox 22/03/2017 Laura Smith
Note: Location maps throughout this report are representative only; for precise GPS coordinates, see the appendices. All satellite imagery used throughout is sourced from The Land Information System Tasmania (LIST) unless otherwise indicated.
1 Cover photo, Paddy’s Point, Spring Bay (photo by Marine Solutions, 2015).
Tassal/SBSF Jetty DMP 3
TABLE OF CONTENTS
Table of Contents .......................................................................................................................................... 3
Table of Figures ............................................................................................................................................. 4
1 Executive Summary ............................................................................................................................... 5
2 Introduction .......................................................................................................................................... 8
2.1 Purpose ......................................................................................................................................... 8
2.2 Legislation ..................................................................................................................................... 8
2.3 Overview of the dredge site .......................................................................................................... 8
3 Management Plan ............................................................................................................................... 11
3.1 Odour .......................................................................................................................................... 11
3.2 Dredging methodology ............................................................................................................... 11
3.2.1 Barge-based excavation dredging ....................................................................................... 11
3.2.2 Dewatering .......................................................................................................................... 11
3.3 Disposal of the material .............................................................................................................. 13
3.4 Water quality .............................................................................................................................. 13
3.5 Toxic Dinoflagellate Cysts ........................................................................................................... 16
3.6 Waste and Spill Management ..................................................................................................... 16
3.7 Release of toxic contaminants from sediment ........................................................................... 16
3.8 Acid Sulphate Soils (ASS) ............................................................................................................. 17
3.9 Noise Disturbance ....................................................................................................................... 17
3.10 Dredge Operator Commitments ................................................................................................. 18
4 References .......................................................................................................................................... 19
Tassal/SBSF Jetty DMP 4
TABLE OF FIGURES
Figure 1 The location of the proposed dredge works at Paddy’s Point, Spring Bay, Tasmania. ................... 9
Figure 2 Proposed design of the jetty (most recent update as of March 2017; source: Burbury
Consulting). ................................................................................................................................................. 10
Figure 3 approximate location of settlement pond proposed as the site for dewatering and dredge
disposal and dredging site .......................................................................................................................... 13
Figure 4 Suggested water quality sampling sites. ....................................................................................... 15
Tassal/SBSF Jetty DMP 5
1 EXECUTIVE SUMMARY
This document outlines the proposed dredge process for removal of sediment around the proposed
jetty at Paddy’s Point, Spring Bay, Tasmania and highlights the commitments to be undertaken during
the works phase to minimise environmental risk.
Spring Bay Seafood’s and Tassal’s plans to dredge by excavation and commits to the following
environmental mitigation actions when doing so:
Commitment #1. Notify the EPA one week before the commencement of first dredging and provide
EPA with an outline of the proposed dredging program.
Commitment #2. Dredge spoil is to be deposited and dewatered in a depression (pond) onsite. Spoil
will be transported by truck to the disposal/dewatering site.
Commitment #3. Dredge operators will comply with the directions of Spring Bay Seafood and Tassal
personnel regarding deposition of dredge spoil.
Commitment #4. Water sampling will be undertaken at four locations during dredging practices.
Commitment #5. If at the time of excavation material becomes odorous it will be capped with non-
odorous material as soon as practicable within a maximum of 12 hours from the
odorous material becoming exposed.
Commitment #6. Waste management and spill response capability to be on site.
Commitment #7. Dredging is only to occur during daylight hours so as not to cause noise disturbance
to local residents.
Commitment #8. Sediment transport is to be minimised, via physical barriers/filters (e.g. bunding,
baffles, geotextile cloth), and controlling the rate of dredge material being
deposited ashore.
Commitment #9. Abort dredge if a plume is observed from the dewatering drain.
Commitment #10. Periodic visual and pH monitoring to ensure ASS is not posing environmental threat,
or cap spoil with clean fill at the completion of dredging.
Commitment #11. Dredging operations are to occur during winter months, to reduce the likelihood of
causing a toxic algal bloom.
Tassal/SBSF Jetty DMP 6
The document entitled “Marine Environmental Impact Assessment for a Proposed Jetty Including
Dredging at Spring Bay, Triabunna” (Marine Solutions, 2017) supplements this document. It provides
details of the site assessments undertaken, the results of which have provided the basis for many of the
recommendations made throughout this management plan. Open discussions with relevant
government authorities including DPIPWE and the EPA have helped to frame this DMP.
Table 1 below summarises the potential issues and associated mitigations that form the management
plan strategies.
Tassal/SBSF Jetty DMP 7
Table 1 Potential issues associated with excavation dredging at Paddy’s Point, associated recommended mitigations and commitments of dredging
Impact Recommended Mitigation Priority* Refer to section:
Unnecessary mobilization of sediment plume from disturbance of seabed
Dredge using a barge-based excavator. Constructing a sediment fence during dredge operations will reduce the sediment plume.
1 3.2
Mobilisation of toxic dinoflagellate cysts causing at toxic algal bloom. Contamination of Spring Bay Seafood hatchery’s water intake.
Dredging operations are to occur during winter months to reduce the likelihood of causing a toxic algae bloom. Water intake is to be shut off during dredging activities and/or moved. 1 3.5
Mobilisation of contaminants impacting water quality
Water sampling will be undertaken at four locations while dredging operations are underway. (NATA lab, qualified samplers, data retention for 3 years). Preliminary works indicates this is low risk.
5 3.4
Release of unpleasant odour during dredge
Odours to be managed by submerging odorous material, or by capping odorous material with non-odorous material.
1 3.1
Potential contaminant spill from dredge operations
Waste management and spill response capability to be on site 1 3.6
Noise disturbance The proposed development site is in a rural setting with no residence in the near vicinity and therefore noise disturbance does not pose a high risk.
3 3.9
Release of toxic contaminants from sediments
Minimisation of sediment transport from the disposal/dewatering site, via
- physical barriers/filters (e.g. bunding, baffles, geotextile cloth)
- controlling the rate of dredge material being deposited ashore
Abort dredging if a significant plume is observed.
3 3.7
Release of acid from dredge material
Intermittent lime dosing or other equivalent solution to neutralize potential acidity. Periodic visual and pH monitoring to ensure ASS is not posing environmental threat, or cap spoil with clean fill at the completion of dredging.
5 3.8
* Based on perceived risk. Rated on a scale of 1 (highest priority) to 5 (lowest priority).
Tassal/SBSF Jetty DMP 8
2 INTRODUCTION
2.1 PURPOSE
This document outlines the proposed methods for dredging a section of seabed at the proposed jetty at
Paddy’s Point, Spring Bay, Tasmania. Dredging is required to allow vessel access and reduce the risk of
damage to infrastructure and vessels.
This document also outlines the management methods of the excavated marine sediments, and
provides a table of commitments (mitigations) for the dredge operator.
These activities will be conducted in accordance with the National Assessment Guidelines for Dredging
(DEWHA 2009).
2.2 LEGISLATION
All planning of development within Tasmania is governed by Tasmania’s Resource Management and
Planning System (RMPS). There are 5 main statutes that lend legislative effect to the RMPS (DEP 2009).
These are:
- Land Use Planning and Approvals Act (1993) (LUPAA)
- The Environmental Management and Pollution Control Act (1994) (EMPCA)
- State Policies and Projects Act (1993)
- Resource Planning and Development Commission Act (1997)
- Resource Management and Planning Appeal Tribunal Act (1993)
2.3 OVERVIEW OF THE DREDGE SITE
The site of the proposed jetty site is to the southeast of Paddy’s Point approximately perpendicular to
the shoreline (Figure 1). The proposed jetty may be up to 200 m in length and run from the shore in a
southerly direction, and is required to provide in excess of 4m Chart Datum depth for vessels berthing
alongside. The jetty will be used to support current and proposed aquaculture activities in the area.
The requirements of the dredge zone include:
• A declared depth of -5.0 m Australian Height Datum (AHD);
Tassal/SBSF Jetty DMP 9
• Nominal dredge footprint area of 5, 500 square metres; and
• Nominal bulk volume of 4, 700m
Figure 1 The location of the proposed dredge works at Paddy’s Point, Spring Bay, Tasmania.
Sediments at the site are characterised by spatially heterogeneous thick mud with areas of course sand
and shell grit throughout. Some trend of stratification was evident with a thin layer of mud overlaying a
layer course sand/mud and shell grit followed by thick black mud from a depth of ~50cm onward. A mild
odour was present at some sites during sediment sampling, however it is not foreseen to pose a
problem while dredging.
The proposed berthing jetty (Figure 2) is proposed to run through the proposed dredge area (hereafter
referred to as "the jetty"), dividing it into an east section (approximately two thirds of the total dredge
area) and a west section (approximately one third of the total dredge area). Located within to the
proposed dredging site is the Spring Bay Seafood’s water intake pipe.
Tassal/SBSF Jetty DMP 10
Figure 2 Proposed design of the jetty (most recent update as of March 2017; source: Burbury Consulting).
Tassal/SBSF Jetty DMP 11
3 MANAGEMENT PLAN
3.1 ODOUR
Field studies indicated that there was some mild odour from some core samples taken throughout the
dredge site, however it is not expected pose a problem during the dredging and dewatering phase.
If odour does pose a problem during dredging operations control may be undertaken by ensuring the
material remains submerged or is quickly capped, thus preventing the release of odours. At the
completion of the dredge works any non-submerged odorous material should be immediately covered
by non-odorous material. To facilitate this, a ready and adequate supply of non-odorous material
should be identified, and potentially present as a stockpile on site. For more detail regarding odour
control, refer to Dredging Methodology in Section 3.2 below.
3.2 DREDGING METHODOLOGY
A seafloor area of approximately dredge footprint area of 5, 500 square metres will be dredged to
provide 1m additional depth of water. This equates to a total volume of dredge material of
approximately 4,700m3.
Shore based, or barge based excavation dredging is deemed an appropriate methodology for this site.
This option is individually described in further detail below (section 3.2.1). Agitation or injection
dredging techniques is not appropriate for the initial dredge at this site, as the spoil would be disturbed,
but not removed from site, however it may be appropriate for any maintenance works.
3.2.1 Barge-based excavation dredging
Dredging will be conducted via mobilisation of a barge with excavator. The barge will contain baffle
walls for containment of the dredge material. This material will be transferred by mooring at causeway
and onto trucks. Disposal will occur on the sediment storage zone.
3.2.2 Dewatering
A dewatering process is proposed whereby dredge spoil will be deposited from the site into the
settlement pond (Figure 3). While it is unlikely, if odour presents as an issue, priority should be given
to moving the material into the settlement pond and quickly capping with non-odorous material.
Tassal/SBSF Jetty DMP 12
Spoil may wholly or partially dewater at the intermediate zone, where run-off would return back to
the dredge-site or to the settlement pond.
A barrier within the settlement pond may also be constructed, to divide the pond into two “sub-
ponds” and allow for a two-stage dewatering process, whereby spoil is deposited into the first sub-
pond, and the second sub-pond will receive any overflow from the first. At both sub-ponds (both
stages), settlement of sediment will occur.
The settlement pond will be lined with geotextile fabric to minimise the return of fines to the bay
during the dewatering process, thus minimizing any increases in turbidity.
Adequate control measures will be implemented to slow the surface runoff of water, thus minimise
sediment transport from the dewatering site back into the port via the dewatering drain. These may
include but not be limited to;
• Bunding of the site,
• Baffles within the site to cause the dredged material to travel slowly and allow adequate time
for sediment to settle out,
• Silt curtains located across the dewatering drain prior to water re-entering the port
• Hay bale ‘filters’ placed in the drain water course
• Control of the rate of dredged material being deposited ashore
A combination of these measures is intended to enable effective dewatering, and thus avoid an
observable plume being present at the point of water draining from the spoil and re-entering the port.
If an obvious plume is observed at the point water is draining from the shore back into the port, then
the dredging is to be aborted until measures to quell the plume are in place. The dewatering discharge
point will be visually monitored while the dredging works are underway.
Tassal/SBSF Jetty DMP 13
Figure 3 approximate location of settlement pond proposed as the site for dewatering and dredge disposal and dredging site
3.3 DISPOSAL OF THE MATERIAL
The dredge spoil will be retained within a 8,000m2 pen just north of the dredging site, to be used as fill
and capped. Therefore, assuming minimal post-dredge bulking, the entire amount of won material could
be accommodated within the settling pond if filled to a depth of ~0.75m.
3.4 WATER QUALITY
It is anticipated that water quality at the dewatering discharge will be satisfactory to re-enter the port
via the dewatering drain. A series of sediment tests indicate that the sediments at this site are not likely
to be acid producing when dredged, and they have low levels of contaminants, including metals.
~Proposed location for dredge spoil disposal/dewatering
~ Proposed location for dredge site
~ Location of Spring Bay Seafood’s water intake
Tassal/SBSF Jetty DMP 14
Notwithstanding this, a series of water quality monitoring sites will be sampled daily during the first
week of dredging. Integrated samples from each site shown in Figure 4 will be tested for turbidity, pH,
hardness, total suspended solids and total and dissolved metals. These sites correlate with;
• (a) 800m upstream of the dredge site,
• (b) 800m downstream of the dredge site,
• (c) within proximity to recreational use areas on the other side of the bay
• At the dredge site / Immediately in front of the Spring Bay Seafood’s hatchery water intake
Water quality sampling sites shown in
Figure 4 below are intended as a guide only. Following the first week of dredging, a review of the
dredging process and water quality sampling frequencies should be undertaken, in conjunction with the
EPA.
Tassal/SBSF Jetty DMP 15
Figure 4 Suggested water quality sampling sites.
Upstream
Downstream
Close proximity to recreational use
Spring Bay Seafood’s water intake
WQ 1
WQ 2
WQ 3
WQ 4
Tassal/SBSF Jetty DMP 16
3.5 TOXIC DINOFLAGELLATE CYSTS
Toxic algal blooms in eastern Tasmania appear to be increasing. Preliminary surveys indicate resting
stages of toxic dinocysts are present, atop the sediments, which are >2m deep. Areas of limited wave
action and current, such as the jetty development site, are at risk of accumulating toxic microalgal
cysts and a large disturbance can trigger an algal bloom. Minimising sediment disturbance is the
main mitigation strategy against algal blooms as the other important factors to stimulate a bloom
such as sufficient nutrients and light are less able to be manipulated. Dredging activities should
occur during winter months, no later than 21st August, and minimizing sediment disturbance
remains an important mitigation.
Due to the close proximity of Spring Bay Seafood’s water intake a toxic algae bloom would pose
significant threats to the survival of the oyster hatchery for which the water is used. Moving the intake
location could be an appropriate mitigation measure to reduce the threat to the hatchery.
3.6 WASTE AND SPILL MANAGEMENT
Contractors on site should be aware of their environmental obligations and provide facilities for
adequate disposal of waste, which should be removed from site.
Given there is a range of machinery involved in the dredging phase, spill kits, appropriate to
hydrocarbons found in the machinery should be available on site. This may include but is not be limited
to Petrol, Diesel, Hydraulic Fluid and Oils.
3.7 RELEASE OF TOXIC CONTAMINANTS FROM SEDIMENT
Contaminant tests identified no contaminant guidelines (ANZECC) were exceeded in sediments
throughout the site. Therefore the release of contaminants does not pose a threat during dredging
operations. The installation of a silt screen at the dewatering drainage point and around the dredge site
is however recommended to minimize the bulk movement of resuspended sediments.
Tassal/SBSF Jetty DMP 17
3.8 ACID SULPHATE SOILS (ASS)
Acid sulphate soils (ASS) are sediments that occur naturally in waterlogged environments (Thornton
2010). These sediments contain iron sulphides, most commonly in the form of iron pyrite (Thornton
2010). ASS occur in two main forms: potential acid sulphate soils (PASS), where the pyrite is retained in
a reduced state (not oxidised), and actual acid sulphate soils (AASS), where the pyrite is oxidised by
exposure to air. The oxidation of ASS results in the formation of sulphuric acid (Thornton 2010). ASS are
harmless when undisturbed on the seafloor (DEP 2009), however, dredging activities that expose PASS
to air can result in destructive leaching of acid into the environment (DEP 2009; Thornton 2010).
To characterise the ASS-related risk of dredging this site, field pH (pHF) and field pH peroxide (pHFOX) ASS
Screening Tests was conducted at 10sampling sites in February. These tests assist in determining the
likelihood of soils being AASS or PASS and are simple and low-cost. PASS/AASS testing was conducted at
the core that appeared most likely to be PASS or AASS as determined by field-based stratigraphical
examination including a visual/odour assessment of sediments in each core. Refer to Marine Solutions
(2016) for details of testing.
The peroxide field tests pHF and pHFOX indicated a low probability of Potential or Actual Acid Sulphate
Soil (PASS or AASS) material being present, and therefore represents a low risk of acid generation by
dredge material (Marine Solution 2016). The results of laboratory CRS testing supported the conclusions
of the field tests that acid generation is low risk.
However, it is suggested that the proponent commits to visual and pH monitoring periodically to ensure
ASS problems are not occurring, or to covering the spoil with clean fill after the dredging is done.
3.9 NOISE DISTURBANCE
The proposed development site it is in a rural setting with no residence in the near vicinity and therefore
noise disturbance does not pose a high risk.
Tassal/SBSF Jetty DMP 18
3.10 DREDGE OPERATOR COMMITMENTS
The commitment list below is to guide operators in their requirements during the dredging operations
to deepen the Paddy’s Point wharf area. It does not imply that permit conditions, planning approvals or
other requirements from statutory bodies have been superseded, but rather is meant to be a pragmatic
operational summary of tasks to be undertaken during the dredging process.
Spring Bay Seafood’s and Tassal plans to dredge by excavation and commits to the following
environmental mitigation actions when doing so:
Commitment #1. Notify the EPA one week before the commencement of first dredging and provide
EPA with an outline of the proposed dredging program.
Commitment #2. Dredge spoil is to be deposited and dewatered in a depression (pond) onsite. Spoil
will be transported by truck to the disposal/dewatering site.
Commitment #3. Dredge operators will comply with the directions of Spring Bay Seafood and Tassal
personnel regarding deposition of dredge spoil.
Commitment #4. Water sampling will be undertaken at four locations during dredging practices.
Commitment #5. If at the time of excavation material becomes odorous it will be capped with non-
odorous material as soon as practicable within a maximum of 12 hours from the
odorous material becoming exposed.
Commitment #6. Waste management and spill response capability to be on site.
Commitment #7. Dredging is only to occur during daylight hours so as not to cause noise disturbance
to local residents.
Commitment #8. Sediment transport is to be minimised, via physical barriers/filters (e.g. bunding,
baffles, geotextile cloth), and controlling the rate of dredge material being
deposited ashore.
Commitment #9. Abort dredge if any plume is observed from the dewatering drain.
Commitment #10. Periodic visual and pH monitoring to ensure ASS is not posing environmental threat,
or cap spoil with clean fill at the completion of dredging.
Commitment #11. Dredging operations are to occur during winter months, no later than the 21st
August, to reduce the likelihood of causing a toxic algal bloom.
Tassal/SBSF Jetty DMP 19
4 REFERENCES
DEP (2009) Dredging and land reclamation in the Derwent: a guidance document to support Best
Practice Management. Derwent Estuary Program 2009
DEWHA (2009) National Assessment Guidelines for Dredging, Commonwealth of Australia, Canberra
Marine Solutions (2016). Environmental Risk Assessment for Dredging of material at the Site of a
Proposed Jetty at Paddy’s Point, Spring Bay, Tasmania, Report to TASSAL, February 2016.
Thornton L (2010) Acid sulphate soils management plan: Norwood-Mowbray 110kv transmission circuit,
Doc No: T9086-PLN-EMP-002