aace® internationalaace® international chinook-calgary section commercial bid evaluation the...
TRANSCRIPT
AACE® InternationalChinook-Calgary Section
Commercial Bid EvaluationThe Inside Track
September 25, 2019
James Smith, PMP
James Smith
2Commercial Bid Evaluation
rhi’s Operations Manager, Canada
15 years industry experience & with rhi since 2011
$10s of millions saved for clients
Education / Designations / Other
• BSc (Hons) Quantity Surveying
• PMP
• RICS Associate
• COAA Contracting Committee Member
rhi at a Glance
3Commercial Bid Evaluation
Estimating Benchmarking Risk analysisCost management/
quantity surveyingContracts Project controls Planning
Services
skilled
resources
years
experiencecountries regional offices
client base –
local, regional,
international
Track
record
Sectors
Active major
projects
Experience
130+ 15+50+ 6 Multiple
Oil & Gas Energy Infrastructure Mining
FPSOs & FPUs LNG & FLNG topsides downstream and
infrastructure
20+ 20+20+ 30+ 20+
Overview
Bid Evaluation from a consultant’s view
• Scene Setting
• Bid Evaluation Plan 9-box
• Recap
• Questions
4Commercial Bid Evaluation
Contract Strategy
Scene Setting - Key Contracting Activities
4 RFP Preparation Client determines the
contract form
Engineering input
Engineering Analysis
Compensation
5 RFP Issue Request For Proposal
Preambles
Schedule of Rates
Bill of Quantities
6 Clarification Bidder queries resolved
7 Bid Submittal Bidder submits
proposal
8 Bid Evaluation Bids compared using
the tendered SOR
Sensitivity analysis on
quantities and rates
9
Client selects
contractor based on
commercial and other
evaluation criteria
Contract Selection
Contract
Award
Identify
Need
3 Prequal Capability
Capacity
Test compensation
method
1 Market Analysis Current best practices
Service providers
License to operate
2
Determine key elements
of risk distribution
Compensation Principles
(productivity,
mob/demob, scaffolding)
5Commercial Bid Evaluation
Scene Setting – Compensation Models
Compensation has many gradients
Trade-off between Owner control/risk
and information available
In a mainly Unit Rate contract
• Contractor takes productivity and
pricing risk
• Owner takes scope & quantity risk
Source: Procurement Strategy (CEM, 2012)
6Commercial Bid EvaluationA
vailab
le in
form
ati
on
at
con
tract
aw
ard
Info
rmati
on
req
uir
ed
for
con
tro
l
Control effort required
client flexibility
Owner control
Owner risk
Prior to Bid Opening
Objective: Select ‘Best Value’ Service Provider
Lowest Proposal ≠ Best Value
Bid Evaluation Plan-on-a-page
Rank as-bid proposals
Review clarifications &
exceptions
Normalize & Condition proposals
Rank normalized & conditioned
proposalsNegotiate
Award recommendation
Bid Evaluation Plan
Bid Check Estimate
Communication & Clarifications
7Commercial Bid Evaluation
Bid Evaluation Plan 9-Box
AS-BID
PROPOSALS
NORMALIZE
CONDITION
CLARIFICATIONS
& EXCEPTIONS
BID CHECK
ESTIMATE
SENSITIVITES
RISKS &
OPPORTUNITIES
NEGOTIATE AWARD
RECOMMENDATION
Quantitative
Amounts for unpriced
items, clarifications, and
exceptions
Qualitative / “soft money”
Execution concerns
Review of Commercial &
Technical
Day 0 Risks
Bid Risk Register
Change Orders
8Commercial Bid Evaluation
What is a Bid Check Estimate?
• Buyer-side estimate of what the work should cost
• A negotiation & comparison tool with a known build-up
• A proxy for market pricing (under sole source)
• Resilient to challenge
Box 1: Bid Check Estimate
9Commercial Bid Evaluation
Why prepare a Bid Check Estimate?
• Quickly uncover areas of negotiation
• Detect risk premiums and unbalancing
• Identify inconsistencies and gaps in RFP documents
• High ROI / high leverage activity
Box 1: Bid Check Estimate (cont’d)
10Commercial Bid Evaluation
Final Thoughts
• Negotiation first
• Avoid the shell game
• Finalize Bid Check Estimate before you open the proposals
Box 1: Bid Check Estimate (cont’d)
No. Description Status
1 Read RFP
2 Review Historical Data
3 Normalize Historical Data
Compensation Method
Pricing Structure
Timing
Volume / Type of Work
Market Conditions
Indirects
4 Apply pricing to RFP quantities
5 Adjudicate estimate
6 Basis of Estimate
Bid Check Estimate Checklist
11Commercial Bid Evaluation
Initial ranking within 30 minutes
Structured per Contract Price build-up
Box 2: As-Bid Proposal
Bidder
1
Bidder
2
Bidder
3
Check
Estimate
DIRECT COSTS
1) Civil Work
2) Piping Work
3) Electrical Work
4) Instrument Work
5) Painting Work
6) Insulation Work
TOTAL DIRECT COSTS
INDIRECT COSTS
1) Mobilisation
2) Project Site Establishment
3) Construction Management Personnel
4) Demobilisation
TOTAL INDIRECT COSTS
OVERHEAD AND PROFIT
TOTAL PROPOSAL AMOUNT
ADJUSTMENTS
1) Normalization
2) Conditioning
3) Sensitivities
TOTAL ADJUSTMENTS
TOTAL EVALUATED PRICE
Item
Evaluation Summary
12Commercial Bid Evaluation
Heat Maps
Extract positioning at-a-glance
Unit Rates & Time Rates
Completed initially on As-Bid data
Box 2: As-Bid Proposal (cont’d)
Sch
No.
Schedule DescBidder 1 Bidder 2 Bidder 3
021 EXCAVATION AND BACKFILLING $10,048,763 $4,623,217 $11,807,505
028 SUPPLY AND INSTALL CAST-IN-SITU CONCRETE AND SUNDRIES $18,660,784 $8,518,008 $8,088,716
060 FABRICATE AND ERECT FRAMING MEMBERS $5,644,182 $4,227,231 $4,832,570
150 FABRICATE AND ERECT PIPEWORK COMPLETE N.E. 1.5" DIAMETER (AG) $1,402,763 $437,369 $1,628,195
155 FABRICATE AND ERECT PIPEWORK GREATER THAN 1.5" DIAMETER (AG) $36,679,831 $7,582,299 $29,582,653
160 BUTT & BRANCH WELD JOINT OR THE LIKE $0 $5,629,683 $6,736,191
180 SOCKET WELD JOINT OR THE LIKE $0 $845,840 $1,022,386
210 INSTALL PIPEWORK SPECIAL ITEMS $0 $54,781 $86,926
216 INSTALL VALVES (ALL TYPES) $671,554 $1,135,947 $1,102,915
245 MAKE BOLTED JOINTS $0 $323,681 $120,866
290 TESTING, FLUSHING, AND CLEANING OF PIPEWORK $0 $1,524,018 $1,763,812
295 INSTALL MECHANICAL EQUIPMENT $1,289,721 $742,836 $600,873
455 INSTALL INSTRUMENT TUBING $441,452 $555,704 $820,698
350 INSTALL LADDER RACK AND CABLE TRAY $1,352,610 $668,172 $1,404,780
385 INSTALL CONTROL STATIONS $113,486 $94,598 $77,856
390 INSTALL JUNCTION BOXES $79,267 $11,267 $16,749
450 INSTALL INSTRUMENTS $171,556 $193,445 $810,368
355 INSTALL CABLING ONLY (A/G) (CORES) $1,695,313 $1,358,376 $2,159,987
360 INSTALL CABLING ONLY (A/G) (PAIRS, TRIPLES AND QUADS) $439,264 $441,762 $587,008
365 GLAND AND TERMINATE (CORES) $899,453 $475,546 $447,014
370 GLAND AND TERMINATE (PAIRS, TRIPLES AND QUADS) $178,750 $295,561 $103,864
TOTAL $79,768,751 $39,739,340 $73,801,932
Heat Map
13Commercial Bid Evaluation
Box 3: Clarifications & Exceptions
Batch work using FiTR method
Find: Read the proposal, identify concerns
Triage: Rank concerns by importance/urgency
Resolve: Quantify impacts, issue clarifications, discuss with bidders
No. Value No. Value No. Value
High 3 $3,000,000 1 $150,000 0 $0
Medium 8 $2,000,000 15 $1,500,000 30 $2,000,000
Low 120 $200,000 175 $500,000 100 $100,000
Total 131 $5,200,000 191 $2,150,000 130 $2,100,000
Bidder 2 Bidder 3
Exceptions Summary
ImportanceBidder 1
14Commercial Bid Evaluation
Box 4: Normalize
Level the playing field
Quantitative adjustments
Exclusions cannot make proposal more attractive
15Commercial Bid Evaluation
Cost Normalization Adjustments Bidder 1 Bidder 2 Bidder 3Bid Check
Estimate
Exceptions & Clarifications $5,200,000 $2,150,000 $2,100,000 $0
Zero Rates / Unpriced Items
Provisional Items
Other Clarification Adjustments
Normalization Total $5,200,000 $2,150,000 $2,100,000 $0
Normalization Summary
Box 5: Condition
Level the playing field
Qualitative adjustments
‘Soft money’ analysis
16Commercial Bid Evaluation
Cost Conditioning Adjustments Bidder 1 Bidder 2 Bidder 3Bid Check
Estimate
Schedule Impacts
Additional Owner/PMT Oversight
Other Adjustments
Conditioning Total $0 $0 $0 $0
Conditioning Summary
Box 6: Sensitivities
Discipline
• Relative position is constant
• Magnifies existing differences
Basket
• Relative position can change
• Reveals different weighting on work
activities
17Commercial Bid Evaluation
Box 6: Sensitivities (cont’d)
Scenario Sensitivity Adjustments%
Change
Bidder
1
Bidder
2
Bidder
3
Check
Estimate
A Large bore piping (> 6") including pipe erection, welding, valve
installation, testing, painting, and insulation5%
B Small bore piping (<= 2") including pipe erection, welding,
painting, and insulation10%
C Electrical cabling including cable tray, cable laying, glanding &
terminating, junction boxes15%
D Instrument cabling including cable tray, cable laying, glanding &
terminating, instruments, junction boxes15%
E Tertiary and miscellaneous steel fabrication and erection 10%
F Labour Rates - 5,000 hour multi-discipline Change Order n/a
G Equipment Rates - Additional equipment use of crane, trucks, and
forkliftsn/a
Sensitivity Total $0 $0 $0 $0
Sensitivity Adjustment Summary
18Commercial Bid Evaluation
Focus on high impact & high probability
The agreement will not be perfect
Find “Day 0 vulnerabilities”
Turnover Package to include a risk & opportunity memo
Box 7: Risks & Opportunities
Low Medium High
High
Medium
Low
Imp
act
Probability
19Commercial Bid Evaluation
Agree strategic objective e.g. $10 mil reduction
Support the objective
My model:
Box 8: Negotiation
No. Type Applicability Example
1 Incorrect Wide CPP amounts
2 Incorrect Narrow Scaffolding in rates instead of Lump Sum
3 Inadequate Wide E&I rates 30% above references
4 Inadequate Narrow 3C #4 cable rate is 10% above references
20Commercial Bid Evaluation
You need a story
Explain complexity simply
Be a salesman
Box 9: Award Recommendation
No. Description Status
1 Contracting Strategy
2 Bid Evaluation Plan (incl. deviations)
3 Term Sheet (summarize exceptions)
Terms & Conditions
Compensation
Scope of Work
Risk distribution principles
4 Key Data
Key Milestones
Contract Schedule
Interfaces
Payments Schedule
Award Recommendation Checklist
21Commercial Bid Evaluation
Bid Evaluation Plan 9-Box Recap
AS-BID
PROPOSALS
NORMALIZE
CONDITION
CLARIFICATIONS
& EXCEPTIONS
BID CHECK
ESTIMATE
SENSITIVITES
RISKS &
OPPORTUNITIES
NEGOTIATE AWARD
RECOMMENDATION
Quantitative
Amounts for unpriced
items, clarifications, and
exceptions
Qualitative / “soft money”
Execution concerns
Read the proposal
FiTR
Prioritize
Bid Risk Register
Fit-for-purpose
Best Value > Lowest Proposal
Be a salesman
Initial ranking quickly
Heat Maps
22Commercial Bid Evaluation