abb kårstø projects summary rev 3
TRANSCRIPT
Statoil Kårstø SAS Upgrade ProjectsEng. Manager Andrew McConnell, ABB AS Process Automation Division
ABB Scope Overview
© ABB GroupMay 2, 2023 | Slide 2
Process and Stakeholders
Kårstø is a Gas Processing Plant located in Western Norway. This is the largest export harbour for LPG in Europe, and the 3rd largest in the world.The first part of the plant was put into operation in 1985.
Export Capacities:Salesgas / Dry gas:• Statpipe 28”: Capacity approx. 20MSm3/day• Europipe II, 42”: Capacity approx. 72 MSm3/day
NGL and Condensate:• Ethan: 112 tons/hour• Propane: 385 tons/hour• i-butan: 76 tons/hour• n-butane: 145 tons/hour• nafta: 106 tons/hour• condensate: 351 tons/hour
Introduction to Kårstø Gas Processing Plant
© ABB GroupMay 2, 2023 | Slide 3
Process and Stakeholders
Gassco established in 2001, 100% owned by Norwegian Government.Neutral service provider to all North Sea Gas ProducersKårstø is operated by Statoil as Technical Service Provider
https://en.wikipedia.org/wiki/Gassco
InfrastructureOwnersGassled
Regulatory BodiesOD, Ptil, MD,DSB, etc
OperatorGassco
Technical Service ProviderStatoil
Gas Owners(consortium)
© ABB GroupMay 2, 2023 | Slide 4
Project value, from customer perspective
The SAS Systems at Kårstø continually evolved since 1985. There are several distinct system architectures in use. The KEP2010 Project saw a major upgrade of the control systems,
approx 12,000 hardwired IO replaced. The KEP2010 Project also saw an entirely new PSD system split out. The existing (3rd party) ESD systems were replaced. The oldest parts of the F&G system was completely replaced Standard library and custom libraries were produced.
Hardware migration achieved signal-by-signal. Non-critical loops – Changeover during live operation Sub-Critical loops – live operation with compensatory measures Critical – Changeover during shutdown
Target was for maximum percentage of signals to be changed over pre-shutdown to minimise the risk of overrun.
KEP2010 SAS Upgrade - Some requirements and challenges
© ABB GroupMay 2, 2023 | Slide 5
ABB project organisation
ABB O&G Bergen Engineering and supply of PCDA System Engineering and supply 800xA HMI Engineering and supply PSD System Engineering and supply of Network system extensions
ABB O&G Oslo Engineering and supply Fire & Gas System Engineering and supply of Simulator(s)
ABB O&G, Stord Develop 3rd party interfaces to 800xA (sub-supply to ABB Bergen). Engineering and supply of SAS upgrade for the NGL Project
ABB Engineering Center Bangalore, India: Sub- supplier to ABB Oslo and Bergen for HMI display development. Application programming for parts of Fire & Gas Application programming for parts of PCDA Supply of Engineering resources (STA) to Bergen, Oslo and Kårstø.
ABB RFF Trutnov, Czech Manufacturing of Cabinets for PCDA, PSD, and Fire & Gas
ABB Sweden 800xA Software and Hardware S800, AC800MHi, Support
ABB Minden, Germany Melody Hardware and Software, Composer, Support
PASYS Minden, Germany; Melody System Cabinets and power supplies
ABB locations involved in KEP2010 SAS Upgrade
© ABB GroupMay 2, 2023 | Slide 6
Project value, from customer perspective
In total 14 LER’s were affected by the Migration. Hardware deliveries:
95 Marshalling Cabinets refurbishments, consisting of S800 Remote I/O and terminals. Mounted, prewired and tested on frames ready for installation in existing cabinets.
12 Power Cabinets for field I/O. 10 S900 Remote I/O cabinets (for installation in Hazardous areas). 16 system cabinets with PM875 controllers, power and
communication modules. Software:
Develop and test a completely new function library according to NORSOK standard I-005.
Reconfigure all application software to comply with NORSOK standard I-005, based on new SCDs. Hence this is not a 1:1 conversion of application software.
Re-establish / Reconfigure all links to 3rd party systems. - typical CCC antisurge control and motor control centres.
Develop and test high speed antisurge algorithm for implementation of antisurge control in PCDA
KEP2010 PCDA Scope of Supply
© ABB GroupMay 2, 2023 | Slide 7
Project value, from customer perspective
2012 – 2013 Control Room Upgrade (EPC Scope) 2014 – 2016 HMI Upgrade (FEED Study => EPC Scope).
New Virtualised Server ParkNew Process SimulatorAsset Optimisation, Integrated Operations
Success factors: Focus on Value for money Precision in problem understanding and solving Knowledge of existing plant systems Early identification of shut down scope Timely execution Maintain safe Operability of the plant Maintain plant Regularity Minimise risk through use of Qualified technology Improved system Capacity and Lifetime
Continuing and increasing responsibility for ABB at Kårstø
© ABB GroupMay 2, 2023 | Slide 8
Functional Design and early involvement
KEP2010 – participated as part of Integrated Team working for overall EPC Contractor
LSD – ABB had EPC Scope, but using existing FEED HMI Upgrade – ABB had full FEED and EPC (Extended Scope)
responsibility for Project execution
Program design standards
Hardware typicals
Cabinet layouts
Power distribution
Application guidelines
Tools and methods
Consistent and qualified project team driving progress
FEED EPC
Commissioning and startup
Installation supervision
SAT Loop check support SIS loop validation
suppor As-built
documentation
Site
Operations support System
maintenance Health checks Spares
management Training Life cycle support Obsolescense
management
O&M
Engineering, procurement, construction
Hardware build Application
configuration Model
development Testing and
acceptance FAT
© ABB GroupMay 2, 2023 | Slide 9
45 Operator & Engineering Clients
45 Servers – All critical servers in redundant configuration
Diverse Locations
KEP2010 New Hardware
Existing
Control
Hardware
PCDA
PSDF&GESD (Hima-Sella)
HIPPS
Interface to existing (Safety) Systems
© ABB GroupMay 2, 2023 | Slide 10
Managing technical interfacesChange Management
© ABB GroupMay 2, 2023 | Slide 11
Migration strategies using existing real estate
• LER’s contain a mix of old and newer generation equipment.
• Suite of new controller cabinets was supplied
• Pre-mounted I/O “racks” are used to replace old IO System
• As an example for this LER:• 2 off controllers for the PCDA
(1 cabinet) and 2 off controllers for the UCP (1 cabinet) shall provide the necessary capacity to replace the 14 existing controller stations, and ensure that the required segregation between separate parts of the process trains should be maintained.
Typical PCDA upgrade of equipment room
Existing Melody
I.S. DORELAYS
20-ZC-100
20-ZC-100-CP0120-ZC-100-CP0220-ZC-100-CP0320-ZC-100-CP0420-ZC-100-CP0520-ZC-100-CP0620-ZC-100-CP0720-ZC-100-CP0820-ZC-100-CP09
Contronic P
HardwiredDevices J.B
800xAConnectivity
servers in93-ZC-100
KA-CSMEL3A/B
IS/NIS
O-Net
New ESD/HIPPS
HardwiredDevices J.B
IS/NISProfibus DP**
HW I/O*
HW I/O*
Field
Profibus DP**
HW I/O*
HW I/O
20-ZC-100-MC0120-ZC-100-MC0220-ZC-100-MC0320-ZC-100-MC0420-ZC-100-MC0520-ZC-100-MC0620-ZC-100-MC5120-ZC-100-MC5220-ZC-100-MC5320-ZC-100-MC54
20-ZC-100-DM0220-ZC-100-DM04
(incl. Bentley Nevada)
20-ZC-100-DM05
Local UCP
Electrical Room
HW I/O
HW I/O*
HW I/O*
HW I/O**
20-ZC-100-CP11
NOTE 3**
* To be deleted ** New Installation1.) Expand existing network switches for O-net2.) Existing Modbus links to Melody are not shown3.) New S800 I/O clusters for PCDA.4.) New Wago high speed I/O modules for antisurge5.) The H2O analyser will remain in 20-ZC-100-TC016.) Existing Melody controllers to be moved from KISL02 to KISL037.) Existing I.S. DO relays are mounted in ESD cabinets.
Notes:
20-ZC-100-DM0120-ZC-100-DM03
Local Panels
Note2&6
T100/200 CP-Bus *
I/O
I/O
MaestroUX
ContronicP and existing Melody
**
*
Profibus DP**
NOTE 4**
20-ZC-100-TC01
HW I/O*ESD
Planar4
Profibus DP
C-Net(C)
20-ZC-100-CP12
C051 & C052
20-ZC-100-CP13
C053 & C054
*
Existing Melody (F&G)
20-ZC-100-CP10
KISL03
KISL03
KISL03
Profibus DP
KISL03Note1&6
20-ZC-100-PC02
P01
New PSD
Note7
Note5
© ABB GroupMay 2, 2023 | Slide 12
Migration strategies using existing real estate
• Mounting frames are Rittal sections. • 300 new knife terminals, (IS or Non-IS signal)• S800 remote I/O modules mounted on DIN rail • All cross wiring in the MC panels shall be marked
with to/from details on both sides of each wire.• Temporarily mount the assembled mounting frame
in the Marshalling cabinet.
• Field Cable Wiring input data from SPI• S800 IO allocation (with segregation)• Cross wiring info generated for Manufacture & Test• IO Info used for channel allocation (programing)• Data re-imported to SPI for as-built
Marshalling Cabinet mounting frame with S800
© ABB GroupMay 2, 2023 | Slide 13
PSD System
The System cabinets contains the following main components: Redundant CPU-unitsI/O Cluster containing signal interface cards for hardwired signals including termination units.Exi barriersPower Supply and power distribution/fuse panel.Cables for connection between the PSD node cabinet and the existing field termination cabinet (MC). All components are labeled with a position and a equipment number. I.e. the cluster modem unit in the cabinet can be labeled +B1-T100. +B1 is the position in the cabinet and T100 is the equipment number.
PSD System Cabinet
© ABB GroupMay 2, 2023 | Slide 14
Hardware Migration – Concept NEW PCDA Controller Cabinet
NEW PSD controller and S800 IO
New IS
Frame
in MC
New NIS
Frame
in MC
PCDA I/O
Profibus Links
PSD IO was hardwired to new PSD Cabinets
Mig
rate
IO w
ire b
y w
ireM
igra
te IO
wire
by
wire
Migration of HMI via ”Parallel Operation”, F&GMaestro Unix GraphicsLEVEL 2 Overview
800xA GraphicsLEVEL 2 Overview
Existing Melody Group Logic(eg 74UA101)
New Melody Logic Eg: Fire Area 2R400(Based on 74UA101)
New AC800 HW & Logic for (eg)Fire Area 2R400
Typical Åsgard Fire Area Hardware
Melody Detector Logic
Step 1:DetectorLogic clean-up(Naming rules)
Step 2: Copy Group Logic
Single Gas (DO)
MelodyConnect
SIL Relay
Single Fire (DO)SIL Relay
MAC (DO)SIL Relay
Single Gas (AI/DI)
Single Fire (AI/DI)
MAC (AI/DI)
Step 3: Rebuild Group Logicaccording to
KEP2010 CAP requirements
(seperate MAC)(Delete CP links)
Group signals to HMI:•Single Gas•Single Fire•Fault•Block
Gas/Fire/MACper Fire Area to CAP via AC800M
HW signals
Output DevicesBlue/Red lightsSounderCCR Alarm
Critical Action Panel
Transfer Outputsto new Group Logic
BL/TL/ISC (AI/DI) BL/TL/ISC (DO)SIL Relay
Escalation Area LogicFrom CAP via AC800M
© ABB GroupMay 2, 2023 | Slide 16
Control Room UpgradeCCR was upgraded with new Furniture and 4 x Large Screen Displays
comprising a total of 42 x 60" Large Screen Cubes .
© ABB GroupMay 2, 2023 | Slide 17
Current Project
Renewal of servers with virtualised system Significant reduction in number of servers and footprint Upgrade of 1875 Graphics and trends displays to PG2. New Process Simulator (entire plant is covered) Process Model updated and interfaced to emulator of all
plant control hardware. Simulator covers Process control, PSD, ESD, F&G Improved Asset Management Integrated Operations, Blocklog, PNSM, SEPTIC (Statoil
proprietary loop tuning software)3rd Party Metering Interfaces.
Cybersecurity to latest standards, whitelisting.
HMI Upgrade
© ABB GroupMay 2, 2023 | Slide 18
Technical Highlights & Lessons Learned
Importance of defining job well in early stages Get maximum information from existing config data. Be wary of as-built information Understanding of Plant and any restrictions inherent in
systems - Find the limits. Cooperation between all parties leads to successful
execution Identify problems – bring out into open – solve at earliest
possible stage Try to use standard solutions to give best support and
avoid later costs.