ac switchboard checksheet

Upload: warwick-audet

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 AC Switchboard Checksheet

    1/3

    AC SWITCHBOARD TESTRESULTS DOCUMENT NUMBER

    Project Check Sheet

    Client Location

    Created on 15/10/2013PAGE: 1 OF 3

    Standard: AS:3000 Fed From:

    Manufacturer: Serial number:

    NOTE: Where automated relay test equipment is used, the test results obtained may take priority over or supplement theinformation recorded on this check sheet. In this case, a reference will be made to an attached result sheet.

    ABIDE BY SAFETY AND ISOLATION PROCEDURES IN SWMS6

    1 VERIFY INSTALLATION

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify board installation method

    Verify board design and labelling as per schematic notes

    Verify clearances, terminal shrouding/pole blanks are installed and labelled

    Verify operation of all handles/locks N/A

    Verify door seals N/A

    Ensure all penetrations are filled/blanked N/A

    2 VERIFY CIRCUIT BREAKER/FUSE/LINK/RELAY TYPES AND RATINGS

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify circuit breaker/fuse and link type and ratings

    Verify relay types and ratings

    3 VERIFY EARTHING

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify M.E.N. is installed with correct rating and clearly stamped

    Verify earthing to each cubicle section/gland plate/escutcheon plate/door

    Verify R.C.D. earthing (same numbered terminal as C/B pole)

    Verify cable screen earthing

    Verify spare cores are earthed

    Test earth resistance to earth grid/stakeSwitchboard Earth bar to grid/stake

    Acceptance 0.5

    Test MEN resistance to earth gridMEN bar to grid connection

    Acceptance 20

    Test MEN resistance to switchboard

    MEN bar to switchboardconnection Acceptance 20

  • 7/27/2019 AC Switchboard Checksheet

    2/3

    AC SWITCHBOARD TESTRESULTS DOCUMENT NUMBER

    Project Check Sheet

    Client Location

    Created on 15/10/2013PAGE: 2 OF 3

    4 VERIFY CABLE INSTALLATION

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify cable types as per schematics

    Verify cable glanding N/A

    Ensure single core cables do not penetrate continuous ferrous material N/A

    Verify cable bending radius(12x diameter for multi-core, 15x diameter for single-core)

    N/A

    Verify segregation N/A

    Verify ducting/cable ties

    Verify internal and external labelling

    Verify ferruling as per schematicsVerify termination lugs for correct size/type N/A

    Verify terminal tightness N/A

    5 TEST INSULATION RESISTANCE

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify switchboard insulation resistance N/A

    Test at 1kV for 1 MinuteA B+C+N+E B A+C+N+E C A+B+N+E N A+B+C+E Acceptance

    100M (New), 1M (Aged)M M M M

    6 TEST INCOMMING SUPPLIES

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify incoming supply polarity and phasing N/A

    Verify -N continuity. Confirm similar between phases(Max 10% tolerance)

    N/A

    7 RECORD VOLTAGES

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation

    (Pass/Fail)

    AcceptedBy

    (signature)

    Record switchboard voltages N/A

    A-B A-C B-C A-N B-N C-N A-E B-E C-E

    8 TEST RCDs

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify operation of RCDs with test trip button N/A

    Test each RCD and fill out logbook N/A

  • 7/27/2019 AC Switchboard Checksheet

    3/3

    AC SWITCHBOARD TESTRESULTS DOCUMENT NUMBER

    Project Check Sheet

    Client Location

    Created on 15/10/2013PAGE: 3 OF 3

    TEST PHASE ROTATION

    Tests Required (Minimum)Schematics

    Green-lined/Updated

    Operation(Pass/Fail)

    AcceptedBy

    (signature)

    Verify phase rotation of switchboard and attached outlets N/A

    Remarks:

    The associated system has been tested and proved to operate successfully as per the design information provided. Please refer to the DefectReport list and Testing Equipment Details.

    Commissioning Officer: Signed: Date:

    The test results have been reviewed, are within tolerance and are consistent with the design information provided.

    Commissioning Engineer(RPEQ): Signed: Date:

    Test equipment Description Serial Number