accelerated bridge construction university transportation

20
1/21/2021 Blackhall Road at Rum Creek Bridge Project • GDOT Project PI 0011691 Modular Decked Beams made with Bulb‐Tee Girders Accelerated Bridge Construction University Transportation Center January 21, 2021 2 Commitment to ABC Culture of Innovation and Collaboration Solving project time constraints and user cost Utilizing Accelerated Bridge Construction 1 2

Upload: others

Post on 05-Dec-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Accelerated Bridge Construction University Transportation

1/21/2021

Blackhall Road at Rum Creek Bridge Project  • GDOT Project PI 0011691

Modular Decked Beams made with Bulb‐Tee Girders

Accelerated Bridge ConstructionUniversity Transportation Center

January 21, 2021

2

Commitment to ABC

• Culture of Innovation and Collaboration

• Solving project time constraints and user cost

• Utilizing Accelerated Bridge Construction

1

2

Page 2: Accelerated Bridge Construction University Transportation

1/21/2021

3

GDOT Projects utilizing ABC: SR 211 over Beech Creek

• PI 0007159 Barrow County

• 148’‐0” Single span Bulb Tee 72 beams

• Precast Deck Panels with UHPC closure pours

4

GDOT Projects utilizing ABC: SR 299 over I‐24

• PI 0011682 Dade County

• 201’‐7” two spans Type III Mod beams

• Prefabricated bridge elements and SPMT

• Construction of proposed substructure underneath existing bridge

3

4

Page 3: Accelerated Bridge Construction University Transportation

1/21/2021

5

GDOT Projects utilizing ABC: CR 131 (Elliot Rd) over Walnut Creek

• PI 0011690 Henry County

• 145’‐0” Single span Bulb Tee 72 beams

• Precast Deck Panels with UHPC closure pours

6

GDOT Projects utilizing ABC: SR 3 over Peachtree Creek

• PI 0007174 Fulton County

• Two 110’‐2” spans, continuous plate girder unit

• Precast Deck Panels with UHPC closure pours

5

6

Page 4: Accelerated Bridge Construction University Transportation

1/21/2021

7

Project Description

Atlanta

Project Site

• Replacement of a load posted bridge

• Correct substandard roadway geometry• improve sight distances• raise vertical profile  • shoulder widths

• Preliminary Design ‐ Conventional construction  

• Roadway closure and offsite detour

8

Blackhall Road

Existing Bridge

Lake Spivey

Dam

Spillway/Rum Creek

Blackhall RoadADT = 6550

7

8

Page 5: Accelerated Bridge Construction University Transportation

1/21/2021

9

Preferred Alternative

Offsite detour with a 9 to 12‐month closure

10

Plan and Elevation

9

10

Page 6: Accelerated Bridge Construction University Transportation

1/21/2021

11

Other Alternatives Considered

Permanent roadway realignment

Maintain existing roadway alignment using onsite detour

12

ABC Considerations and Alternatives

• Stakeholder Meetingo Home Owner’s Associations and elected officials request for significantly 

shortened roadway closure duration

• GDOT Office of Bridge and Structures o recent completion of single‐span ABC replacement project

o seeking multi‐span ABC candidates 

o requested project alternatives to achieve maximum 4‐month road closure 

• Alternatives Analysis

11

12

Page 7: Accelerated Bridge Construction University Transportation

1/21/2021

13

Deck Bulb‐tee beams shipped from the fabricator• Deck is integral, only closure pour required • Placement immediately upon shipping• Can be opened to traffic after closure pours and barriers placed

• Local availability; shipping requiring special permitting• Cost• Complications with profile and cross slope

NEXT D & F beams• Placement immediately upon shipping• Stability during shipping and placement• NEXT D beams use to set main span• F‐Beams require deck to be poured• Heavy to ship, pick and set

Contractor Built Modular Decked Bulb‐tee Beams • Availability and shipping  • No special equipment or subcontractors

• Requires onsite staging area to pre‐assemble bridge• Final beam is heavy to pick  and set

ABC Alternatives Analysis

PROs

CONs

PROs

CONs

PROs

CONs

14

Modular Decked Beam Units (DBU)

54”Bulb Tee Beams 

Conventional deck cast onsite at laydown yards

Steel DiaphragmsDeck cast with final cross slope

13

14

Page 8: Accelerated Bridge Construction University Transportation

1/21/2021

15

Letting and Construction… 

• Laydown yards and “false bents”

• Superstructure: pre‐cast decked beam units

• Delivery Method:  Design, Bid, Build

• 60‐day road closure per special provision

• $4182/day liquidated damages for failure to reopen road

• A+B Bidding

• A = Construction Costs

• B = Total # Calendar Days x LD of $4182/day

AcceleratedBridge Construction

16

Project Details

• Two bidders

• Letting in August 2018

• CW Matthews ‐ $5,003,000 bid• Bridge cost = $2,037,000 ($253/sf)• 407‐day schedule 

15

16

Page 9: Accelerated Bridge Construction University Transportation

1/21/2021

17

Construction Sequence

18

Laydown Yards

Roadway open to traffic

South Yard

North Yard

17

18

Page 10: Accelerated Bridge Construction University Transportation

1/21/2021

19

Laydown Yards ‐ South

Buried power at Laydown Yard

20

Laydown Yards ‐ North

DamSpillway

Roadway open to traffic

Roadway open to traffic

Ample room for crane/equipment

19

20

Page 11: Accelerated Bridge Construction University Transportation

1/21/2021

21

Decked Beam Units

Steel H‐Piles

• 54” Bulb‐Tees set on “False Bents”

• Conventional timber formwork & deck construction

22

Decked Beam Units

Bearings and Shim Plates

• Utilize steel diaphragm

• Steel diaphragms used 2x  at laydown yard & permanent bridge

• Likewise, shim plates and elastomeric bearingsare used at both sites 

• Permanent pier caps constructed to match “false bents”

Steel Diaphragms

21

22

Page 12: Accelerated Bridge Construction University Transportation

1/21/2021

23

Forming Deck Joints

1” Skim Pour over top of foam

Polystyrene foam

Uncoated Reinf.  On County Roads

24

Forming Deck Joints

Step 4)Surface preparation

Step 2)Remove concrete between saw cuts

Step 1) Shallow Sawcut on both sides of Joint

Step 3) Strip timber forms & remove polystyrene foam

23

24

Page 13: Accelerated Bridge Construction University Transportation

1/21/2021

25

Pre‐Cast Decked Beam Units

• Block‐out the joints/edge beam/end wall

• ¼” Grinding/wearing thickness

• No overlay

• Deck designed as simple span but constructed to be jointless 

• Road is still open to traffic at this point

6’‐0” Block out for Cast in Place Diaphragm (24 hr conc.)

Longitudinal Joints (UHPC)

3’‐0” Block out for Cast in Place End Diaphragm (24 hr conc.)

26

Construction: Decked Beam Erection 

• Close the road

• Demolish exist. bridge

• Construct substructures

• Move DBU & erect

• 800‐ton crane

• Temp fill at end span

• Center span set in single day

25

26

Page 14: Accelerated Bridge Construction University Transportation

1/21/2021

27

Construction: Decked Beam Erection 

Span 1 Span 1

Span 2

28

UHPC: Casting  

Longitudinal Joints (UHPC)

6’‐0” Block out for Cast in Place Diaphragm (24 hr conc.)

Block out for Lifting Loops 

(UHPC)

27

28

Page 15: Accelerated Bridge Construction University Transportation

1/21/2021

29

UHPC: Casting

• Start at the lowest point

• Finish ¼” above the surface of bridge deck

• UHPC mixed on site

Exposed aggregate surface 1/8” min amplitude

30

UHPC: Casting

Top Forms Installed to prevent UHPC movement downhill

29

30

Page 16: Accelerated Bridge Construction University Transportation

1/21/2021

31

Construction: Approach Paving

32

Construction: COMPLETE – ON TIME! < 60 DAYS

November 2019

31

32

Page 17: Accelerated Bridge Construction University Transportation

1/21/2021

33

Profile Management with Adjacent Beam Bridges 

• Correct roadway profiles vary• flat (level or on a constant grade)• crest vertical curves• sag vertical curves

• Prestressed deck beams are cambered• NEXT beams, Deck Bulb‐tees• the camber does not match the roadway profile

• here are solutions, but it brings complexities

www.pcine.org

34

Recommended Approach for Adjacent Beams

Option 1: vary the thickness of the top flange

33

34

Page 18: Accelerated Bridge Construction University Transportation

1/21/2021

35

Recommended Approach for Adjacent Beams

Option 2: vary the thickness of the overlay (if you have one)

36

Effect of Profile Management on the Beam Design

Designer’s Role:

Each solution will have an affect on the design of the beam• variable dead loads• variable beam section properties (flange thickness)• camber tolerance

o can be accounted for in the design if significant

Beam seat detailing• Elevations of beam seats needs to account for:

o the method of profile management choseno camber tolerances

35

36

Page 19: Accelerated Bridge Construction University Transportation

1/21/2021

37

Benefits of the Blackhall Road Design

The modular decked beams can be built to the exact roadway profile• deck haunch is used to adjust the deck elevations

Best of both worlds• prefabrication• high level of profile accuracy

38

Lessons Learned

• No significant problems encountered

• Steel diaphragms performed well – provided immediate stability at both sites

• Utility coordination critical

• Reinforcement fabrication tolerances – additional length cannot be accommodated by splices

• Joint construction with “skim” pour was a success

37

38

Page 20: Accelerated Bridge Construction University Transportation

1/21/2021

39

Thank you

GDOT, CW Matthews and the CHA team

Responsibly Improving the World We Live In

40

Contact Information

Georgia Department of Transportation:• Donn Digamon – [email protected]• Dexter Whaley – [email protected]

CHA:• Jim Aitken – [email protected]• Kevin Kahle – [email protected]• Mike Culmo – [email protected]

CW Matthews Contracting Co.• Mark Dolan – [email protected]• Juan Velasquez – [email protected]