Daniel S. Vacanti
ActionableAgileTM
@danvacanti
Actionable Agile
for
Metrics
Predictability
![Page 2: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/2.jpg)
“When will it be done?”
@danvacanti – https://www.actionableagile.com
![Page 3: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/3.jpg)
“When will it be done?”
Date (number of days)
Elapsed Time
@danvacanti – https://www.actionableagile.com
![Page 4: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/4.jpg)
“When will it be done?”
Date (number of days)
Story Points / Velocity
@danvacanti – https://www.actionableagile.com
![Page 5: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/5.jpg)
Stop me if you’ve heard this
one before…
@danvacanti – https://www.actionableagile.com
![Page 6: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/6.jpg)
“Relative Complexity is the best
predictor of how long it takes
an item to complete”
@danvacanti – https://www.actionableagile.com
![Page 7: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/7.jpg)
![Page 8: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/8.jpg)
I’m going to suggest
something radical…
@danvacanti – https://www.actionableagile.com
![Page 9: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/9.jpg)
As an example:
How long does it take you to get to
work in the morning?
@danvacanti – https://www.actionableagile.com
![Page 10: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/10.jpg)
“It depends…”
@danvacanti – https://www.actionableagile.com
![Page 11: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/11.jpg)
Here’s a spot!!
![Page 12: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/12.jpg)
4 4 2
Active Done
Testing DoneDoneActive
DevelopmentReady Analysis
3
Here’s a spot!!
![Page 13: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/13.jpg)
Try an experiment for
me…
@danvacanti – https://www.actionableagile.com
![Page 14: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/14.jpg)
Calendar Days
Elapsed Time
![Page 15: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/15.jpg)
![Page 16: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/16.jpg)
![Page 17: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/17.jpg)
![Page 18: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/18.jpg)
![Page 19: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/19.jpg)
Try the same thing for
your process
@danvacanti – https://www.actionableagile.com
![Page 20: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/20.jpg)
Backlog Analysis Develop Test Deployed
Start Timer Stop Timer
![Page 21: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/21.jpg)
This chart is called a (Cycle Time) Scatterplot
![Page 22: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/22.jpg)
If you track nothing else*,
track the date that an item starts and
the date that an item completes
(for all work items)
@danvacanti – https://www.actionableagile.com
![Page 23: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/23.jpg)
That will give you a
measure of the flow
metric of
Cycle Time
@danvacanti – https://www.actionableagile.com
![Page 24: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/24.jpg)
Cycle Time
is the amount of
elapsed time
it takes for a given work
item to complete
@danvacanti – https://www.actionableagile.com
![Page 25: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/25.jpg)
“When will it be done?”
(for a single item)
is best answered by
Cycle Time
@danvacanti – https://www.actionableagile.com
![Page 26: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/26.jpg)
“Huh?”
@danvacanti – https://www.actionableagile.com
![Page 27: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/27.jpg)
How does generating a chart like this help us
answer “When will it be done”?
![Page 28: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/28.jpg)
How do we make sense of this randomness?
![Page 29: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/29.jpg)
Your process is random.
Therefore, you can’t think
deterministically.
You need to think
probabilistically.
@danvacanti – https://www.actionableagile.com
![Page 30: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/30.jpg)
What does it mean to
think probabilistically?
@danvacanti – https://www.actionableagile.com
![Page 31: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/31.jpg)
Let’s try another experiment…
@danvacanti – https://www.actionableagile.com
![Page 32: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/32.jpg)
Thinking probabilistically means
acknowledging that there is
more than one
possible
future outcome
@danvacanti – https://www.actionableagile.com
![Page 33: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/33.jpg)
How many people can we “expect” to
be standing after 3 flips?
12.5%
Does that mean 12.5% was the only
possible outcome?@danvacanti – https://www.actionableagile.com
![Page 34: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/34.jpg)
Backlog Analysis Develop Test Deployed
2
Start Timer Stop Timer
![Page 35: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/35.jpg)
Backlog Design Develop Test Deployed
2
Exactly
this dot?
Exactly
this dot?
Or Exactly
this dot?
Will Item #3
end up as…
![Page 36: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/36.jpg)
Backlog Design Develop Test Deployed
2
There is more than one possible outcome
for Item #3 while it is sitting in the backlog
![Page 37: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/37.jpg)
What are the possible
outcomes?
@danvacanti – https://www.actionableagile.com
![Page 38: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/38.jpg)
38
How do we make sense of this
“randomness”?
![Page 39: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/39.jpg)
39
50th Percentile = 6 days or less
![Page 40: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/40.jpg)
40
85th Percentile = 15 days or less
![Page 41: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/41.jpg)
41
95th Percentile = 22 days or less
![Page 42: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/42.jpg)
42
50th Percentile = 6 days or less
95th Percentile = 22 days or less
85th Percentile = 15 days or less
Scatterplot Percentiles (making a forecast)
![Page 43: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/43.jpg)
The answer to “When will it
be done?” is a percentile and
its associated range.
@danvacanti – https://www.actionableagile.com
![Page 44: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/44.jpg)
![Page 45: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/45.jpg)
85th Percentile = 33 days or less
![Page 46: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/46.jpg)
85th Percentile = 13 days or less
![Page 47: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/47.jpg)
![Page 48: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/48.jpg)
![Page 49: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/49.jpg)
All of these dots are “done”.
![Page 50: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/50.jpg)
The most important chart you’ve
never heard of
@danvacanti – https://www.actionableagile.com
![Page 51: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/51.jpg)
![Page 52: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/52.jpg)
To sum up…
@danvacanti – https://www.actionableagile.com
![Page 53: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/53.jpg)
Customers care about
elapsed time
@danvacanti – https://www.actionableagile.com
![Page 54: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/54.jpg)
If you track nothing else, track
the date that an item starts
and the date that an item
completes
(for all work items)
@danvacanti – https://www.actionableagile.com
![Page 55: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/55.jpg)
Calculate Cycle Time
from start and end
date data
@danvacanti – https://www.actionableagile.com
![Page 56: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/56.jpg)
Use a
Cycle Time Scatterplot
to get a sense of
possible outcomes
@danvacanti – https://www.actionableagile.com
![Page 57: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/57.jpg)
Use percentile lines on a
Scatterplot to help answer
“When Will It Be Done?”
@danvacanti – https://www.actionableagile.com
![Page 58: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/58.jpg)
Use a WIP Aging chart to
be proactive in managing
Cycle Time for greater
predictability
@danvacanti – https://www.actionableagile.com
![Page 59: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/59.jpg)
What does a 19th century
Yorkshire cotton industrialist
have to do with the
Manhattan Project?
For next time…
@danvacanti – https://www.actionableagile.com
![Page 60: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/60.jpg)
“Actionable Agile
Metrics for
Predictability”
https://leanpub.com/actionableagilemetrics
![Page 61: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/61.jpg)
“When Will It Be
Done?”
https://leanpub.com/whenwillitbedone
Coming Soon….
![Page 63: Actionable Agile Metrics for - Agile SoCal€¦ · Daniel S. Vacanti ActionableAgileTM daniel@actionableagile.com @danvacanti Actionable Agile for Metrics Predictability](https://reader030.vdocuments.net/reader030/viewer/2022033118/5ecdaff5c36c81086508e43b/html5/thumbnails/63.jpg)
All charts created by:
Thank-you!