activity based costing examples

Upload: rajveer-patel

Post on 05-Apr-2018

235 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/2/2019 Activity Based Costing Examples

    1/23

    Activity based costing examples

    Example: 1

    A company manufactures two products X and Y.The Product X is a low- volume and its sales are only 5000 units p.a.Produ

    volume, its sales are are 25000 units p.a.Product X takes 6 labor hours to make one unit, but Product Y requires 8 hours

    Details of costs for materials and labor for each product are: Rs

    Particulars product x product y

    Direct materials 200 100

    Direct labor(@Rs.10 per hour) 60 80

    260 180

    The company works 100000 direct labour hours p.a. Total manufacturing overhead costs Rs.1750000p.a.

    You are required to compute per unit cost of each product using:

    (a)Direct labour hour rate method for absorption of overhead costs, and(b) ABC technique for absorption of overhead costs.

  • 8/2/2019 Activity Based Costing Examples

    2/23

    Solution

    (A)Computation of product costing using direct labour hour rate methodOverhead cost per our = Total manufacturing overhead /total direct labuor hour

    =Rs. 1750000/100000 D.L.H Rs. 17.50

    Manufacturing overhead

    Product X =Rs. 17.50xD.L.H. =Rs. 105

    Product Y =Rs 17.50x 8 D.L.H =Rs. 140

    Activity based costing approach

    Step1: ascertain the major activates or events and determine overhead rates for each activity

  • 8/2/2019 Activity Based Costing Examples

    3/23

    Activity total overheads frequency rate per

    (Traceable costs) of activity activity

    Machine setup 450000 10000 45 per setup

    Quality inspection 300000 15000 20 per Inspection

    Production order 180000 600 300 per order

    Machine hours worked 625000 50000 12.5 hour

    Material receipts 195000 1500 130 per receipt

    Total overheads 1750000

    Step:2 Allocate overheads to products on the basis of activity rates

  • 8/2/2019 Activity Based Costing Examples

    4/23

    Product x product y

    Activity frequently rate per activity amount activity frequency amt.

    activity activity frequency (Rs.)

    Machine setup 10000 45 6000 270000 4000 180000Quality inspection 15000 20 10000 200000 5000 100000

    Productive order 600 300 200 60000 400 120000

    Machine hours worked 50000 12.5 12000 150000 38000 475000

    Material receipts 1500 130 300 39000 1200 156000

    Total overhead cost 719000 1031000

    Total number of units produced 5000 25000

    Overhead cost per unit 143.80 41.24

    Computation of Total Cost under Both Methods

    (RS.)

  • 8/2/2019 Activity Based Costing Examples

    5/23

    Particulars ABC technique Traditional method

    Product x product y Product x Product y

    Direct material 20000 100.00 200 100

    Direct labour 60.00 80.00 60 80

    Manufacturing overhead 143.80 41.24 105 140

    Total cost of manufacture 403.80 221.24 365 320

    Example:2

    ABC Ltd. Manufactures two types of machinery equipments Y and Z and applies/absorbs overheads on the basis of direct

    hours. The budgeted overheadsand direct labour hours for the month of December,2009 are Rs. 1242500 and 20000 horespectively.The information about Companys products is as follows:

  • 8/2/2019 Activity Based Costing Examples

    6/23

    Particulars Equipment Y Equipment Z

    Budgeted production volume 2500 units 3125 units

    Direct material cost Rs.300 p.u. Rs.450 p.u.

    Direct labour cost:Y (3 hours @ Rs.150 p.h.) Rs.450 _

    X (4 hours @ Rs.150 p.h.) _ Rs.600

    ABC Ltds overheads of Rs. 1242500 can be identified with three major activities:

    Order processing (Rs. 210000), machine processing (Rs. 875000),and product inspection (Rs.157500).These activities are

    number of orders processed , machine hours worked, and inspection hours,respectively.The data relevant to these activ

    follows:

  • 8/2/2019 Activity Based Costing Examples

    7/23

    Orders processed machine hours worked inspection hours

    Y 350 23000 4000

    Z 250 27000 11000

    Total 600 50000 15000

    Required:

    (i) Assuming use of directlabour hours to absorb/ apply overheads to production,compute the unit manufacturing coequipments Y and Z,if the budgeted manufacturing volume is attained.

    (ii) Assuming use of activity based costing, compute the unit manufacturing costs of the equipments y and , if the budmanufacturing volume is achieved.

    (iii) ABC Ltd.s selling prices are based heavily on cost.By using direct labour hours as an application base,calculate thecost distortion(under-costed or over-costed)for each equipment.

    (iv) Discuss, how an Activity Based costing might benefit ABC ltd.

  • 8/2/2019 Activity Based Costing Examples

    8/23

    Solution:

    (i) Computation of unit manufacturing cost using Direct Labour hours to absorb overheads to productionDirect labour hour rate =Rs.1242500/20000 D.L.H.=Rs.62.125 per D.L.H.

    (Rs.)

    Particulars Y Z

    Direct material p.u. 300.00 450.00

    Direct labour cost p.u. 450.00 600.00

    Prime cost p.u. 750.00 1050.0

    Add:overheads (3hrs.xRs. 62.125);(4 hrs. x Rs. 62.125) 186.38 248.50

    Total cost p.u. 936.38 1298.50

    (ii) Computation of unit manufacturing cost using Activity Based CostingSegregation of budgeted overheads

  • 8/2/2019 Activity Based Costing Examples

    9/23

    (a)Order processing

    Y = (Rs.210000x350/600)/2500 units =Rs. 49 p.u.

    Z =(Rs.210000x250/600)/3125 units =Rs. 28p.u.

    (b)Machine processing

    Y = (Rs. 875000x23000/50000)/2500units =Rs.161p.u.

    Z =((Rs. 875000x27000/50000)3125units =Rs.151.20p.u.

    (c)Product inspection

    Y = (Rs.157500x4000/15000)/2500 units = Rs. 16.80 p.u.

    Z= (Rs.157500x11000/15000)/3125units =Rs. 36.96 p.u.

    (Rs.)

    Particulars Y Z

    Direct material p.u. 300.00 450.00

    Direct labour cost p.u 450.00 600.00

    Prime cost p.u. 750.00 1050.00

  • 8/2/2019 Activity Based Costing Examples

    10/23

    Add:budgeted overheads p.u.

    Order processing 49.00 28.00

    Machine processing 161.00 151.20

    Product inspection 16.80 226.80 36.96 216.16

    Total cost p.u. 976.80 1266.16

    (iii) Statement showing difference in cost p.u.Particulars y z

    Total cost p.u.

    (a)Under Activity based costing method 976.80 1266.16(b)Under direct labour hour rate method 936.38 1298.50

    Over stated /(under stated) (40.42) 32.34

    (iv)The absorption of overheads under activity based costing helps in ascertainment of product cost nearest to the cos

    since the activities that apportionment of overheads relates the activities that bring out the production.There will be

    distortion if ABC method is used instead of blanket absorption rate i.e.direct labour hour rate of overhead absorption

  • 8/2/2019 Activity Based Costing Examples

    11/23

    Example 3:

    XYZ ltd. Produces and sells sophisticated glass itens a and b . in connection with both the products the following inform

    revealed from the cost records for the month February , 2009:

    Product A B

    Output (in units) 60000 15000

    Sales(Rs.)

    Cost structure:

    Direct material (Rs. Per unit) 18.75 45.00

    Direct wages (Rs. Per unit ) 10.00 13.00

    Direct labour hours 30000 hours 9750 hours

  • 8/2/2019 Activity Based Costing Examples

    12/23

    No. of quantity produced per batch 240 50

    Steup time per batch 2 hours 5 hours

    The indirect costs for the month are as under. (Rs)

    Cleaning and maintenance wages 270000

    Designing costs 450000

    Set up costs 300000

    Manufacturing operations costs 637500

    Shipment costs 81000

    Distribution costs 391500

    Factory administration costs 255000

    At present the company adopts the policy to absorb indirect costs applying direct labour hour basis ands enjoying a good

    the market with regard to product B,but facing a stiff price competition with regard to product A. the cost accountant of t

    company, after making a rigours analysis of the data, decided to to shift from the absorption technique based on direct la

    to activity cost driver basis and also to treat cleaning and maintenance wages as direct cost.

  • 8/2/2019 Activity Based Costing Examples

    13/23

    The cost accountant identified Rs.120000 for product A and the balance of cleaning and maintenance wages fopr product

    The data revelant to activites and products are as follows;

    Activity cost driver product A product B

    Designing square feet 30 sq. feet 70 sq. feet

    Manufacturing operations moulding machine hours 9000 hours 3750 hours

    Shipment number of shipment 100 100

    Distribution cubic feet 45000 cu ft. 22500 cu ft.

    Setup of moulding machie setup hours

    Favtory administration direct labour hours

    You are required

    (i) To compute the total manufacturing costs and profits of the products by applying direct labour basis of absorptioassuming cleaning and maintenance costs as indirect,

    (ii) To compute the total manufacturing cost andf profits of both the both products by applying activity based costincleaning and maintenance cost as indirect.

  • 8/2/2019 Activity Based Costing Examples

    14/23

    (iii) To compare the results obtained from (i)and (ii) and give your opnion on th decision cost accountant .Solution

    Total direct labor hours = 30000+9750=39750 hours

    Calculation of total indirect costs (Rs.)

    Cleaning and maintenance wages 2750000

    Designing costs 450000

    Setup costs 300000

    Manufacturing operations costs 637500

    Shipment cost 81000

    Factory administration costs 255000

    Total indirect costs 2385000

    Overhead absoption rate = Rs 2385000/39750hrs.

    (i) Computation of total manufacturing costy and profits of both the products by applying direct labour basis of abso

  • 8/2/2019 Activity Based Costing Examples

    15/23

    Particulars product A product B Total

    60000 units 15000 units

    Per unit amount per unit amount

    (Rs) (Rs) (Rs) (Rs)

    Direct materials 18.75 1125000 45.00 675000 1800000

    Direct labors 10.00 600000 13.00 195000 795000

    Prime cost 28.75 17525000 58.00 8700000 2595000

    Indirect costs

    (30000 hrs x Rs 60) (9750 hrs x Rs. 60) 30.00 1800000 39.00 585000 2385000

    Total cost 58.75 3525000 97.00 1455000 4980000

    Profit(balancing figure) 4.25 255000 40.00 600000 855000

    sales 63.00 3780000 137.00 2055000 5835000

    .

  • 8/2/2019 Activity Based Costing Examples

    16/23

    (ii)Computation of total manufacturing cost and the profits of both the products applying ABC

    (a)Cleaning and maintenance wages (direct labour hour basis)

    =Rs.270000/39750 DLH =Rs. 6.7925per DLH

    Product A=30000 DLH*Rs. 607925 =Rs. 203775

    Product B=9750 DLH *Rs. 607925 =Rs. 66225

    (b)designing costs (square feet basis)r

    =Rs.450000/100sq.feet =Rs. 4500 per sq. feet

    Product A=30.feet *Rs. 4500 =Rs. 135000

    Product B=70 sq feet *Rs. 4500 =Rs. 315000

    (c)setup costs (setup hours basis)

    =Rs. 300000/2000 hrs. =Rs. 150 per hr.

    Product A=500hrs.*Rs. 150 =Rs. 75000

    Product B=1500 hrs.*Rs. 150 =Rs. 2250000

  • 8/2/2019 Activity Based Costing Examples

    17/23

    (d)Manufacturing Operations Costs(moulding machine hours basis)

    = Rs. 637500/12750hrs. = Rs. 50 per MMH

    Product A = 9000 hrs. x Rs.50 = Rs. 450000

    Product B = 3750 hrs. x Rs.50 =Rs.187500

    (e)Shipment Costs (No. of shipment basis)

    =Rs.81000/200shipments =Rs. 405 per shipment

    Product A = 100 shipment x Rs.405 = Rs. 40500

    Product B = 100 shipment x Rs.405 = Rs. 40500

    (f)Distribution Costs (area in cibic feet basis)

    =Rs. 391500/67500 cubic feet =Rs. 5.80 per cubic feet

    Product A = RS.45000 cubic feet x Rs.5.80 =Rs.261000

    Product B = RS.22500 cubic feet x Rs.5.80 =Rs.130500

  • 8/2/2019 Activity Based Costing Examples

    18/23

    (g) Factory Administration Costs(direct labour hours basis)

    =Rs.255000/39750 DLH =Rs.6.4151 DLH

    Product A = 30000 DLH X Rs.6.4151 =Rs.192453

    Product B= 9750 DLH X Rs.6.4151 =Rs.62547

    Computation of Product Cost and Profit by applying Activity Based Costing (Rs.)

    Particulars Product A product B total

    60000 units 15000 units

    Per unit amount per unit amount

    (Rs) (Rs) (Rs) (Rs)

    Direct materials 18.75 1125000 45.00 675000 1800000

    Direct labour 10.00 600000 13.00 195000 795000

    Cleaning and maintenance

    Expences 2.00 120000 10.00 150000 270000

    prime cost (a) 30.75 1845000 68.00 1020000 2865000

  • 8/2/2019 Activity Based Costing Examples

    19/23

    Indirect Costs:

    Designing costs 2.25 135000 21.00 315000 450000

    Setup Costs 1.25 75000 15.00 225000 300000

    Manufacturing operation cost 7.50 450000 12.50 187500 637500

    Shipment costs 0.68 40500 2.70 40500 81000

    Distribution costs 4.35 261000 8.70 130500 391500

    Factory administration costs 3.21 192453 4.17 62547 255000

    Total indirect costs(b) 19.24 1153953 64.07 961047 2115000

    Total costs(a) + (b) 49.99 2998953 132.07 1981047 4980000

    Profit (balancing figure) 13.01 781047 4.93 73953 855000

    Sales 63.00 3780000 137.00 2055000 5835000

    Note:Cleaning and maintenance expenses have been taken on direct basis as per the Cost Accountants observation.

  • 8/2/2019 Activity Based Costing Examples

    20/23

  • 8/2/2019 Activity Based Costing Examples

    21/23

  • 8/2/2019 Activity Based Costing Examples

    22/23

  • 8/2/2019 Activity Based Costing Examples

    23/23