advanced earned value management presented by · pdf fileadvanced earned value management...
TRANSCRIPT
Powered by POeT Solvers Limited
Advanced
Earned Value Management
Presented by
Dipo Tepede, PMP, SSBB, MBA
This presentation is copyright © 2009 by POeT Solvers Limited. All rights reserved.
This presentation is protected by the Nigerian Copyright law and may not be reproduced,
distributed, transmitted, displayed, published or broadcast without the prior written permission
of POeT Solvers Limited. You may not alter or remove any trademark, copyright or other
notices. PMP®, CAPM®, PMI®, PMBOK® Guide are
registered marks of Project Management Institute, Inc.
Powered by POeT Solvers Limited
• Be able to know the formulas for:
– Cost and Schedule Performance Index
– Estimate at Completion – To complete Performance Index
• Be able to explain Estimate to Complete
Powered by POeT Solvers Limited
At the end of this training, our goal is for you to:
• EVM – Earned Value Management
• EVT – Earned Value Technique
• AC – Actual Cost • PV – Planned Value
• EV – Earned Value
• Cost Variance: CV = EV – AC
• Schedule Variance: SV = EV – PV
• Variance: Subtract/Index: Divide Powered by POeT Solvers Limited
Review
• Cost Performance Index
• Measure of cost efficiency on a project
• Ratio of earned value to actual costs • CPI = EV/AC
– CPI: Cost Performance Index
– EV: Earned Value
– AC: Actual Cost
Powered by POeT Solvers Limited
CPI Overview and Formula
• Schedule Performance Index
• Measure of schedule efficiency on a project
• Ratio of earned value to planned value
• SPI = EV/PV – SPI: Schedule Performance Index
– EV: Earned Value
– PV: Planned Value Powered by POeT Solvers Limited
SPI Overview and Formula
Powered by POeT Solvers Limited
Things to Know
• Positive is good • Negative is bad
• < 1 is bad • =1 is good • > 1 is good
CV and SV
CPI and SPI
Powered by POeT Solvers Limited
Earned Value Terms
Estimate to Complete
Estimate at Completion
• Estimate for the cost of all the remaining work in the project
• Forecasted estimate for the total cost of the project
Powered by POeT Solvers Limited
Bottom-up ETC Estimate work left and multiply by the hourly
rate
Accurate estimate to complete
Re-estimating everything
EAC = AC + Bottom-Up ETC
• Takes time
• Time spent in re-estimating is lost and cannot be regained
• Re-estimation is costly
Powered by POeT Solvers Limited
Problems
Powered by POeT Solvers Limited
EAC Questions to Ask
• Project Progress so far?
• Will progress rate be same in future?
Powered by POeT Solvers Limited
Conclusions Drawn
Original estimate was right and the current project performance is wrong
Original estimate was wrong and the current project performance is correct
Might also have to consolidate both cost and schedule while calculating EAC
• EAC = AC + BAC – EV
• Abbreviations:
– EAC = Estimate at Collection – AC = Actual Costs
– BAC = Budget at Completion
– EV = Earned Value
Powered by POeT Solvers Limited
EAC at Budgeted Rate
• EAC = BAC/CPI
• Abbreviations:
– EAC = Estimate at Completion – BAC = Budget at Completion
– CPI = Cost Performance Indexe
Powered by POeT Solvers Limited
EAC at Present CPI Rate
Powered by POeT Solvers Limited
EAC With CPI & SPI Factored in
EAC = AC + ((BAC - EV)/(CPI*SPI))
• EAC at budgeted rate
– EAC = AC + BAC – EV
• EAC at present CPI rate – EAC = BAC/CPI
– EAC = AC + ((BAC - EV)/CPI)
• EAC with CPI & SPI factored in
– EAC = AC + ((BAC - EV)/CPI*SPI)
Powered by POeT Solvers Limited
EAC Review
• Situational questions
• Identity EVM situations
• Decide which formula to use • All formulas must be on your cheat sheet
• There is only one way to learn them:
– Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice, Practice,
Powered by POeT Solvers Limited
Know the Reasoning
560 km at 80km/h = 7hours
Leaving at 8am / Arrive at 3pm
At 1pm, you have driven 300km
Powered by POeT Solvers Limited
TCPI Example
• Using your original arrival time:
• You have 2 hours left
• There are 250 km to go • That means that you must drive 250km/2h
= 125km/h to reach your target
• So your TCPI based on your original arrival estimate = 125
Powered by POeT Solvers Limited
TCPI based on original BAC
• Using new arrival time:
• 4’o clock: you have 3 hours left
• There are 250km to go • You must drive 250km/3h = 83km/h to
reach the target
• TCPI based on new arrival estimate = 83
Powered by POeT Solvers Limited
TCPI based on New EAC
• Your Target is BAC:
• TCPI = (BAC - EV) / (BAC - AC)
• Your Target is EAC: • TCPI = (BAC - EV) / (EAC - AC)
Powered by POeT Solvers Limited
TCPI Formulas
Powered by POeT Solvers Limited
Two More Formulas
Variance at Completion
Calculation of the Percent
Spent
• VAC = BAC - EAC
• % Spent = AC/BAC
• Earned Value Techniques concern with:
– Earned value Mgt.
– Forecasting – To-Complete Performance Index
• Terms and abbreviations that you need to know are: – AC – Actual Cost
– PV – Planned Value
– EV – Earned Value Powered by POeT Solvers Limited
Review
• CV & CPI – Cost Variance and Cost Performance Index
• SV & SPI – Schedule Variance and Schedule Performance Index
• EAC – Estimate at Completion
• ETC – Estimate to Complete
• BAC – Budget at Completion • TCPI – To Complete Performance Index
• VAC – Variance at Completion Powered by POeT Solvers Limited
Review
Powered by POeT Solvers Limited
Review
Positive Variances Negative
Variances
Good
Index = 1
Index > 1
Bad
Index < 1