agricultural routine data system (ards) asdp m&e thematic working group 14 march, 2012

31
Agricultural Routine Data System (ARDS) ASDP M&E Thematic Working Group 14 March, 2012

Upload: kenneth-freeman

Post on 01-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Agricultural Routine Data System (ARDS)

ASDP M&E Thematic Working Group

14 March, 2012

Contents of presentationBackground (ASDP, ASDP M&E TWG &

ARDS)why improve ARDSRationaleStepsGuiding principlesChallengesFuture Plan

2

Background The Agricultural Sector Development Programme

(ASDP), started to be implemented in 2006, is a program to revive the Tanzanian agriculture through the transformation from subsistence to commercial agriculture.

In order to implement the ASDP efficiently and effectively, seven thematic working groups (TWGs) were formed.

One of the TWGs is the ASDP Monitoring and Evaluation (M&E) Thematic Working Group.

3

Background…cont. The primary task of the M&E TWG was to develop

and operationalize the ASDP M&E framework and consequently improve the Agricultural Routine Data System (ARDS)

The Framework was developed in 2007, ever since the M&E TWG has been working hard to improve the ARDS which envisaged to plays an important role in tracking the progress of the ASDP.

4

BUT what is ARDS? …what is improve ARDS ARDS is a system whereby agricultural performance information are collected and transmitted from LGAs to the Agricultural Sector Lead Ministries (ASLMs) through regions.

….improving the ARDS involve a series

of activities:-Scrutinising the current ARDS from villages to national level,

…what is improve ARDS…cont. Streamlining the common reporting formats of

the provisional model of the ARDS by coordinating ASLM’s routine data systems,

Development of Standardized Reporting Formats, Development of Software for Data Delivery from

LGAs to ASLMs, Providing training in operating the provisional

model of the ARDS for officials in ASLMs, RSs and districts (including ward and village agricultural extension officers).

6

…why improve ARDS It has been difficult for Agricultural Sector

Lead Ministries (ASLMs) to receive technical agricultural reports / information from LGAs.

To obtain data, ASLMs have had to send a number questionnaires to LGAs or visited them.

For Regions, it has been difficult to receive technical agricultural reports / information from LGAs regularly.

7

…why improve ARDS… cont.For LGAs, they receive a

number of questionnaire from ASLMs and other national institutes. Responding to each questionnaire has been a lot of work.

8

•LGAs’ response rates have been low.• Sometimes questions are overlapping.

…why improve ARDS… cont. Within LGAs, extension officers

submit village / ward monthly reports to districts, but…No standard form Difficult to aggregate them into

district level figures.Keeping agricultural data in

order at district has also been a challenge.9

Rationale for ARDS improvement There was a need to improve the ARDS in

which:LGAs find it easy to keep key agricultural

information in order for their own uses.LGAs’ workload to fill in the questionnaire

from ASLMs / Regions is reduced.

10

Rationale for ARDS improvement…cont. There was a need to improve the ARDS in

which:Regions receive agricultural reports

regularly from LGAs for effective monitoring and supervision.

ASLMs receive agricultural reports regularly from LGAs through regions for effective planning and policy making.

11

Steps in ARDS improvement

1. MAFC started consolidating data needs of each department (2007).

2. With the establishment of the ASDP M&E Thematic Working Group, it took over the task and it became a sectoral effort (2008).

3. JICA started a Technical Cooperation to support ARDS improvement (2008).

12

Steps in ARDS improvement…cont.

4. Integrated the data needs of ASLMs (2008).

5. Selected pilot regions/districts (2008) Morogoro: Morogoro Rural and Kilosa. Dodoma: Kondoa and Mpwapwa.

6. By harmonizing the data needs of ASLMs with those of regions/LGA, developed a draft Integrated Data Collection Format (2008 - 09).

13

Steps in ARDS improvement…cont.

7. Developed a draft VAEO/WAEO format to be used at village / ward level (2009). It feeds data into the Integrated Data Collection Format.

8. The two formats were piloted in the four districts (2009 – 10).

14

Steps in ARDS improvement…cont.9. The two formats were also

shared with all regions/LGAs, and their comments were incorporated (2009 - 10).

15

10.Developed a web-based computer software (LGMD2 ) to transmit data in the Integrated Data Collection Format from districts to ASLMs via region (2009 – 10)

Steps in ARDS improvement…cont. PMO-RALG DMIS (DCIT) approved

LGMD2 development in November 2008.

Bitz’ study (2009) conducted jointly by PMO-RALG and DPs recommended that they should promote the use of Local Government Performance Monitoring System (a.k.a LGMD2) as the M&E solution for sectors not undertaking harmonization activities.

LGMD2 developed in 2009, ever since has undergone a series of tests and now it is complete

16

…LGMD2 cont…

LGMD2 operates at any of three levels: District Level Regional Level National Level

17

…LGMD2 major function at each Level

18

District District officers enter data into LGMD2 in the form of the Integrated Data Collection Format

Region Data in LGMD2 become available upon synchronization. Approve or comment on the data and synchrnonize again.

National LGMD2 data become available for ASLMs officers upon synchronization

Agricultural Routine Data System

19

Steps in ARDS improvement…cont.

11. Developed training guide for each format (2010).

20

Steps in ARDS improvement…cont.12. The pilot implementation was

completed and the two formats were finalized (Nov. 2010).

14. Roll-out for remaining LGAs in Morogoro and Dodoma done in March 2011.

15. Roll-out for 5 regions in Lake zone done in September 2011

21

Impact of the improved ARDSin the pilot districts

In the pilot districts, relevant data can be easily retrieved from LGMD2; officers do not have to rush to field to collect data, when requested.

Previously, district officers were required and submit a number of agricultural reports. However, the improved ARDS has reduced the number of reports.

Data collected are used for DADPs planning and other interventions in agricultural sector.

22

23Source: Morogoro DC, 2010

The rate of report submission by VAEO/WAEO has been improved.

In Kondoa DC, quality of data submitted has been improved because the district officers (SMS)provide feedback to extension officers regularly.

In Morogoro DC, motivation of extension officers has been enhanced because the district officer prepares feedback report and distributes to all officers.

24

Impact of the improved ARDSin the pilot districts cont…

Guiding Principles

Participatory approachASLMs, regions, LGAs

Consistent with GoT reporting flows (LGA – regions – ASLMs)

Start small and simple Review regularly and improve as need

arises.25

Key Challenges for ARDS

Number of extension officers and their transportation facilities.

Use of computers (e.g., computer virus) and access to internet at LGAs.

Office equipment and electricity at each administrative level.

26

Key Challenges for ARDS…cont.

Tight budget at LGA. Regular change of LGA officials

participating on ARDS LGAs relocate to other uses the

equipment meant for ARDS

27

Responsibilities for District

Regular train newly posted WAEO/VAEO. Budget for duplicating monthly WAEO/VAEO

formats and distribute to extension officers at Village and Ward.

Ensure equipments (computer, motocycle, modern etc.) are used for ARDS purposes.

28

Future Plan Currently, ARDS has already been

rolled out in all districts of Morogoro, Dodoma, Mwanza, Mara, Shinyanga, Kigoma and Kagera.

In fy 2011/12 the ARDS will be rolled in Iringa, Mbeya, Ruvuma and Rukwa.

Roll out in the remained 10 regions will be done in fy 2012/13.

29

30

Now let’s see how LGMD2 works!

mwisho

Ahsanteni Sana

31