CONSTRUCTION WORK QUÉBEC/JEAN-LESAGE INTERNATIONAL AIRPORT (CYQB)
SUMMER 2017 (Replaces AIP Supplement 8/17)
Three (3) major projects from April to December 2017
Major construction work will be done on the airport airside at Québec/Jean-Lesage International Airport (CYQB) resulting in important changes in the use of the runways, their access, and movement on the taxiways and ramps.
24 April to 24 November 2017 – Construction of aircraft parking 33-37 Apron I
• Gates 33 to 37 will be closed for the duration of the construction period
• Apron I, south of Taxiway Delta, will be closed from 22 May to 09 August 2017
• Entrances D1, D2 and D3 to Apron I will be closed from 22 May to 09 August 2017 due to a temporary construction fence
22 May to 09 August 2017 – Construction of aircraft parking 32 Apron I
• Gates 32 will be closed for the duration of the construction period
• Temporary construction fence will be east of Gate 31
• Entrances D1, D2, and D3 to Apron I will be closed from 22 May to 09 August 2017 due to a temporary construction fence
22 May to 09 August 2017 – Repaving and electrical work Runway 06-24
• Work 24 hours a day
• Runway 06-24 will be closed
• Taxiway Alpha will be closed from 26 June to 09 August 2017
• Taxiways Echo will be closed for the duration of work period
• Taxiway Golf will be closed from 22 May to 15 June 2017
• Taxiway Hotel will be closed from 22 May to 15 June 2017
• Northern field will be closed to helicopter training
• No touch-and-go will be allowed on Runway 11-29 between the hours of 0900Z to 1300Z and 2100Z to 0000Z daily during this period
• Runway 06: will be unavailable for CAT I precision approach
• Runway 24: will be unavailable for RNAV approach
• The work being conducted over the next few weeks will affect instrument approach procedures to Runways 06-24. Please review the NOTAMs in effect before proceeding to this airport.
25 MAY 17
Page 2 of 3 AIP CANADA (ICAO) SUPPLEMENT 18/17
For further information, contact
Aéroport de Québec Inc. 505, rue Principale Québec QC G2G 0J4 Attention: Simon Boucher, Manager Operations
Tel.: 418-640-2600 extension 2663 Fax: 418-640-2656
James Ferrier Manager, Aeronautical Information Management
25 MAY 17
AIP CANADA (ICAO) SUPPLEMENT 18/17 Page 3 of 3