airport quaraterly update feb.14 2012

13
Fort Lauderdale Hollywood International Airport Quarterly Update February 14, 2012

Upload: city-of-dania-beach

Post on 17-Jan-2015

828 views

Category:

Business


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

February 14, 2012

Page 2: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

South Runway Expansion

Accomplishments – Nov. 2011- Jan. 2012

• Groundbreaking Ceremony held

• Construction on US1/FEC Structures (Design/Build) Project

commenced

• Quality Assurance Materials Testing selection and final ranking of

selected firm approved by the Board

• Site Preparation (Earthwork) Project advertised

• Lancaster Steel Building demolished

• Port Everglades ID office vacated and ready for demolition

Page 3: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

South Runway Expansion

Scheduled Activities – Feb. through April 2012

• Perimeter Road closure scheduled for mid-March

• Broward County Aviation Department (BCAD) staff to move to new

offices and portion of BCAD trailers to be occupied by D/B

Contractor in mid-March

• South Runway to close mid-April

• Site Preparation (Earthwork) and Quality Assurance Materials

Testing contracts to be awarded in late April

• 10th Street Extension construction under US1/FEC Structures

Project continues

Page 4: Airport Quaraterly update feb.14 2012

South Runway

9R-27L

Fort Lauderdale – Hollywood International Airport

Quarterly Update

BCAD Offices

Site Preparation Project

10th Street Extension Project

FEC Structures

Port ID Office &

Lancaster Steel

Page 5: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Noise Mitigation

Accomplishments –Nov. 2011- Jan. 2012

Voluntary Residential Sound Insulation Program

• 80 Homeowners volunteered to be part of the Program

• BCAD met with Homeowners in late January

Noise Mitigation Plan

• Plan submitted to the Federal Aviation Administration (FAA)

• Aviation Director and City of Dania Beach met with FAA in Atlanta

Page 6: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Noise Mitigation

Scheduled Activities – Feb. through April 2012

Voluntary Residential Sound Insulation Program

• Assessments for 80 Homeowners to occur in mid-February

• Review of design concept packets with Homeowners in April

Noise Mitigation Plan

• FAA approval of Plan anticipated in mid-February

• Negotiations with The Urban Group for the 5 year Program to begin in

March

Page 7: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Terminal 4 Gate Replacement

Accomplishments –Nov. 2011- Jan. 2012

Western Expansion

• 100% Construction Documents for the Foundations and Security

Screening Checkpoint Packages completed

• Hydrant Fueling 90% Design completed

• Apron - West Conceptual Design 30% completed

• Construction Project Manager negotiations completed

Eastern Expansion

• Majority in Interest (MII) ballot presented to Airlines for approval of

Eastern portion expansion

Page 8: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Terminal 4 Gate Replacement

Scheduled Activities – Feb. through April 2012 Western Expansion

• Construction Project Manager contract to be awarded in February

• Detailed 60% design of the Apron - West to commence in February

• Negotiations with Contractor for the construction of Foundations and

Security Screening Checkpoint Packages to be completed in April

• Hydrant Fueling 100% design to be completed in late April

Eastern Expansion

• MII ballot for Eastern portion to be approved by Airlines in late February

• Negotiations with PGAL/Zyscovich for the Design of the Eastern portion

expansion to commence in April

Page 9: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Hydrant Fueling Project

T-4 Western Expansion Project

T-4 Western Expansion Apron

Detailed Design

Page 10: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Small Business Participation

through January 2012 Contract Title and

Prime Vendor

Amount paid to

date to Prime

Vendor

Amount paid to

date to sub-

vendors

Participation

attained to date

Program

Management

Services

DMJM Aviation

$15,543,086.51 $3,853,946.26 24.80% DBE

Design for South

Runway Expansion

ATKINS

$10,143,909.44

$3,067,060.55 30.24% DBE

CPM for South

Runway

Expansion/Parsons

Transportation

Group, Inc.

$283,765.66 (Initial Payment

Application)

N/A

25% Committed

CBE

Page 11: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Small Business Participation continued

through January 2012

Contract Title and

Prime Vendor

Amount paid to

date to Prime

Vendor

Amount paid to

date to sub-

vendors

Participation

attained to date

Design-Build for

Structures/Tutor

Perini

$5,537,700.00 (Initial Payment

Application)

N/A

23.02% Committed

DBE

Design for Terminal

4 Gate

PGAL /Zyscovich

$12,742,956.28 $3,451,378.00 27.08% M/WBE

CMR for Terminal 4

Cummings-Balfour

Beatty

$261,344.32 (Step 2 not yet

awarded)

$4,320.00

1.65% CBE (28% Committed CBE

on overall project)

Page 12: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Terminal Modernizations • Short term projects started in 2011 to improve Terminal 3

include:

Carpeting replacement

Installation of terrazzo floors

Additional restrooms

Replacement of ceiling tile

Upgrade of lighting fixtures

• Design contract for improvements to Terminals 1, 2 and 3

awarded in late January 2012 to include the following:

Enhancement of Concessions

Improvement of passenger flow

Reconfiguration of Security Checkpoints

Additional restrooms

Page 13: Airport Quaraterly update feb.14 2012

Fort Lauderdale – Hollywood International Airport

Quarterly Update

Next Steps

• Ongoing updates to the Board on a Quarterly basis

• Upcoming Board actions: Award of Quality Assurance and Materials Testing

Consultant contract

Award of Site Preparation Construction contract

Award of Terminal 4 Eastern Expansion Consultant

amendment