aledo trail traffic control december 19, 2013 p hase 1 switch to phase 2
TRANSCRIPT
Aledo Trail Traffic Control
December 19, 2013
PHASE 1 SWITCH TO PHASE 2
Aledo Trail Update• Contractor’s schedule shows 3 months for Phase 2 construction and project completed by May
2014.• Phase 1 to Phase 2: Contractor has stated that traffic switch will occur from 9:00 AM to 3:00
PM on one day in mid to late January 2014. • Electronic Message Boards will post date of traffic switch 2 weeks prior to exact date of traffic
switch• Contractor anticipates traffic switch to take approximately 5 hours• Traffic to transition from west side to east side of FM 1187 at Oak Street Intersection.• S. Front Street access closed off of FM 1187 and maintained via Crockett Street• N. Front Street will be closed and Elm Street will remain open for the first portion of Phase 2.
Once N. Front Street improvements are completed N. Front Street will be opened and Elm Street will be closed until Elm Street improvements are completed.
• RR crossing at Chestnut Street will be closed once Phase 1 is completed.• All driveways will have access to public ROW during this process. Contractor and FNI staff will
coordinate with adjacent property/business owners throughout construction for access while driveways are being constructed.
Aledo TrailPhase 1/Phase 2 – RR Crossings
• Chestnut RR crossing to be closed to general public traffic once relocation of existing gates to southbound Aledo Trail RR crossing begins.
• Chestnut RR crossing to remain available to emergency vehicles only while relocation work takes place.
N. FRONT ST
ELM
ST
S. FRONT ST
OLD ANNETTA RD
UNDERWOOD RD
W. OAK ST
CRO
CKET
T D
R
CHESTN
UT ST
PHASE 2 CONSTRUCTION
FM 1187
FM 1187
Aledo TrailTraffic Control Plan - Phase 2• New Aledo Trail becomes
one way southbound
• Existing FM 1187 becomes one way northbound
• Westbound Turnaround to be open begin with Phase 2
• N. Front Street to be closed for initial construction of Phase 2
• Elm Street to remain open until N. Front Street improvements are completed
N. FRONT ST
ELM
ST
S. FRONT ST
OLD ANNETTA RD
UNDERWOOD RD
W. OAK ST
CRO
CKET
T D
R
ELM ST. TO INITIALLY REMAIN OPEN UNTIL FRONT STREET IMPROVEMENTS ARE COMPLETED
CHESTNUT STREET RR CROSSING
Westbound Turnaround
PHASE 2 CONSTRUCTION
TRAFFIC FLOW
FM 1187
FM 1187
Aledo TrailS. Front Street Detour• Access off of FM 1187 to be
closed throughout Phase 2
• Contractor’s schedule allows for 3 months of construction for Phase 2
• S. Front Street access off of FM 1187 to be available at the beginning of Phase 3
N. FRONT ST
ELM
ST
S. FRONT ST
OLD ANNETTA RD
UNDERWOOD RD
W. OAK ST
CRO
CKET
T D
R
PHASE 2 CONSTRUCTION
DETOUR ROUTE
FM 1187
TCP at Aledo Trail & FM 1187 Project Limits • Transition traffic from east side of FM 1187 to west side of FM
1187 at Oak Street Intersection.• Transition likely to occur approximately one month after Phase
2 begins. Contractor is currently constructing the west side of FM 1187 at the Oak Street intersection.
FM 1187 Traffic Control Plan
QUESTIONS?