1.5 project execution plan: core sampling mv snowgoose 1_5_project execution plan... ·...
Post on 22-Apr-2018
215 Views
Preview:
TRANSCRIPT
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
NAMIBIAN MARINE PHOSPHATE
VERIFICATION SURVEY
GRAVITY CORING
PROJECT EXECUTION PLAN
Prepared for:
Namibian Marine Phosphate (Pty) Ltd.
Prepared by:
Lwandle Technologies (Pty) Ltd.
Report compiled by Kate Munnik and Robin Carter
November 2013
Job no: 149
LWANDLE TECHNOLOGIES (PTY) LTD
The Old Warehouse, Black River Park, Fir Road, Observatory 7925, South Africa
Directors: C.P. Matthysen, B.J. Spolander
Co Reg. No. 2003/015524/07
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
MARINE SPECIALIST TEAM
Robin Carter – Lwandle Technologies, Cape Town
Kate Munnik – Lwandle Technologies, Cape Town
CONDITIONS OF USE OF THIS REPORT
COPYRIGHT © NAMIBIAN MARINE PHOSPHATE (PTY) LTD 2014
ALL RIGHTS RESERVED
© NMP 2014. All rights to the intellectual property and/or contents of this document remain vested in
Namibian Marine Phosphate (Pty) Ltd. (NMP). This document is issued for the sole purpose for which it is
supplied. All rights reserved. No part of this publication may be reproduced, distributed, or transmitted in any
form or by any means, including photocopying, recording, or other electronic or mechanical methods, without
the prior written permission of Namibian Marine Phosphate (Pty) Ltd, except in the case of brief quotations
embodied in critical reviews and certain other non-commercial uses permitted by copyright law. For permission
requests, write to Namibian Marine Phosphate (Pty) Ltd, addressed “Attention: Administration Manager,” at
the address below.
Email: info@namphos.com
127 Theo-Ben Gurirab Street
Walvis Bay
Namibia
Date Version Revised Reviewed
26/07/13 0.1 J Midgley Kate Munnik
© NMP 2014
November 2014 Page i
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
1 PURPOSE AND SCOPE 1
2 WORK PROCEDURE 7
2.1 SURFICIAL SEDIMENT AND WATER COLUMN FEATURES 7
2.2 MOBILISATION 7
2.3 SAMPLING 7
2.3.1 Sediment Properties 7
2.4 BIOGEOCHEMICAL ANALYSIS 8
3 SAMPLE PRESERVATION AND CURATION 8
4 SAMPLING ANALYSIS 9
5 HEALTH AND SAFETY 9
5.1 PERSONAL PROTECTIVE EQUIPMENT 9
5.2 WORK ON DECK 9
5.3 RISK ANALYSIS 10
5.4 EMERGENCY PROCEDURES AND CONTACT NUMBERS 12
5.5 TOOLBOX MEETING TEMPLATE 13
Figure 1-1: Location of Mining Licence Area (MLA) 170 offshore central Namibia. 2
Figure 1-2: Location of the proposed target dredging sites MLA 170. 3
Figure 1-3 : Gravity coring and Verification sampling sites in target dredge site SP-1. 4
Figure 1-4: The verification sites for SP-2. 5
Figure 1-5: The verification sites in SP-3. 6
Figure 5-1: Risk factor table taken from OGP HS&E guidelines for metocean surveys. 10
© NMP 2014
November 2014 Page ii
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Table 5-1: RA for the mobilisation of equipment and loading of ship 11
Table 5-2: RA for work on vessel deck 11
Table 5-3: RA for the handling and analysis of sediment samples 11
Table 5-4: RA for the deployment and recovery of Rosette and CTD 12
Table 5-5: RA for the packaging and unloading of samples 12
Table 5-6: Emergency contact details: 12
© NMP 2014
November 2014 Page iii
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
1 PURPOSE AND SCOPE
Namibian Marine Phosphate (NMP) is proposing to extract marine pelletal phosphate ore from
deposits on the Namibian continental shelf. The phosphate will be extracted by dredging and the
assessment of the environmental impacts associated with the project is therefore strongly reliant on
a sound understanding of the sediment properties of the dredge area.
The purpose of the gravity coring survey is to confirm the sediment properties of the seafloor (to a
maximum depth of ~ 2 m) within the proposed dredge area. This information will then be used, in
conjunction with previous scientific investigations of the region as well as those from the verification
survey, to further inform the assessment of impacts on the marine environment as a result of the
proposed dredging operations. This will aid in the final assessment of the impacts as detailed in the
EIA / EMPR.
The gravity coring survey will include the collection of seafloor sediments using a drop or gravity
corer from aboard the MV Snowgoose. The collected sediment samples will be frozen on board the
vessel and then transported in a frozen state back to South Africa for various analyses.
The focused survey area is defined as mine area SP-1, which is within MLA 170 (Figure 1-1), and is
situated south west of Walvis Bay, directly offshore of Conception Bay and Meob Bay. The Sandpiper
Phosphate licence area (MLA 170) includes mine target areas; SP-1, SP-2 and SP-3 (Figure 1-2). SP-1,
where the verification survey will take place, is the primary dredging target area of the project (a 20-
year mine plan is established for this site), while the dredging of SP-2 and SP-3 will take place
subsequently. The gravity coring sites will match those to be sampled during the verification survey
which will take place between 24 July and 8 August.
© NMP 2014
November 2014 Page 1
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Figure 1-1: Location of Mining Licence Area (MLA) 170 offshore central Namibia.
MLA 170 is a consolidation of EPLs 3414 and portions of EPLs 3323 & 3415.
© NMP 2014
November 2014 Page 2
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Figure 1-2: Location of the proposed target dredging sites MLA 170.
SP-1 (20 year mine plan established), SP-2 and SP-3 within the three resource areas of the Sandpiper Phosphate
licence area.
© NMP 2014
November 2014 Page 3
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
A grid of sampling sites will be placed across SP-1 such that the broad distributions of sediment
properties across the entire mine site can be determined. Figure 1-3 shows the sampling station
layout (large black open squares).
Figure 1-3 : Gravity coring and verification sampling sites in target dredge site SP-1.
Note that the gravity coring/verification survey sites are represented by black open squares. Green squares
represent sites identified for benthos verification sampling (Steffani); additional sampling sites for the macro
benthos, meiofauna and sediment properties monitoring programme are shown in yellow (impact) and blue
(reference). The blue square shows the provisional moored instrumentation site. Only the gravity
coring/verification sites will be sampled during this survey.
© NMP 2014
November 2014 Page 4
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Figure 1-4: The verification sites for SP-2.
© NMP 2014
November 2014 Page 5
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Figure 1-5: The verification sites in SP-3.
© NMP 2014
November 2014 Page 6
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
2 WORK PROCEDURE
2.1 SURFICIAL SEDIMENT AND WATER COLUMN FEATURES
Equipment and personnel will be mobilised to the port of embarkation (Walvis Bay). Following
loading of the survey vessel, equipment will be carefully unpacked and assembled. Electronic
equipment will be powered up and tested to determine whether any breakages have occurred during
transit. Repairs or replacements will be made if and where necessary.
2.2 MOBILISATION
It is assumed that all coring equipment will be provided on board the MV Snowgoose and that this
will be deployed by the ship’s crew. The MV Snowgoose will mobilise out of Lüderitz, Namibia, for
this survey.
2.3 SAMPLING
The ship’s crew will conduct a test run of the sampling equipment before the vessel leaves the port
area. This will allow the repair or modification of any equipment or deployment and recovery
techniques before the cruise gets underway.
Once the testing has been completed; the vessel will progress to the relevant sampling locations and
carry out the following procedures:
2.3.1 Sediment Properties
A gravity core is required to determine the subsurface particle size and texture distribution to a depth
of ~3 m into the seabed, optimally terminating into footwall clay. Gravity core samples will be
collected in similar locations to where box core samples are to be collected during the verification
survey in the target dredge area SP-1.
All procedures are to be conducted by the officers and crew of the Snowgoose; there will be no
Lwandle company representative on board during the survey.
There may be instances where the gravity core is unable to penetrate the surface of the seafloor, or
where the core does not close correctly as a result of shelly bottom and/or debris becoming trapped
in the sealing device. In such a case, the core attempt will be repeated a maximum of three times. In
the event of no successful core being completed in any of the three attempts, the sampling site will
be abandoned.
Following retrieval of the gravity core to deck the inner plastic liner (inner core tube) will be capped
(top and bottom), cut in half and re capped at the open ends. The core reference number and
sampling data are to be written on the subsample and these data logged on the data sheets. Each
capped core section is to be directly placed in a chest freezer operating at -18 °C or lower. The core
samples are to remain in the freezer until reaching CSIR Stellenbosch, where the analyses will take
place.
© NMP 2014
November 2014 Page 7
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
2.4 BIOGEOCHEMICAL ANALYSIS
Analyses will be conducted under subcontract by CSIR, Stellenbosch. Variables will include AVS, POM,
POC and PON, and particle size distributions.
Refer to: Gravity core analysis requirements (Appendix 1.6).
3 SAMPLE PRESERVATION AND CURATION
The preservation and curation of all samples collected while on board the vessel will be the
responsibility of the ship’s crew. It is very important that the samples are preserved and stored
correctly to avoid any loss of data while the vessel is underway, or during transportation back to
South Africa.
All permissions, authorisations and permits required for transporting the chemical/biological samples
and any associated sampling equipment back into South Africa will need to be organized by NMP.
On board:
• All sample containers to be clearly labelled with the relevant station number, date etc. This
information is to match that in the sample record data sheets.
• Check sample conditions in freezer daily. Ensure power connection to all fridges / freezers
containing samples remains stable.
• Check integrity of biological samples daily (i.e. no leaks/drying etc.).
During transport back to South Africa:
• Ensure sufficiently inert packing material to safeguard samples and increase insulation.
• Add an operating temperature logging device (TidBit) to each of the freezers.
• Ensure the freezers are secured correctly and are not able to be opened.
• Ensure there is a continuous power source to the freezers so that the internal temperature
remains below 18 °C.
• Clearly label the freezers with number and type of samples and destination.
• These samples must be transported back to South Africa overland via Swift Air or other courier
to be arranged by the client.
© NMP 2014
November 2014 Page 8
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
4 SAMPLING ANALYSIS
Sediment samples will then be analysed back in Cape Town, the following analyses will be carried
out:
• Organic content, POC and PON concentrations;
• Heavy metal concentrations;
• AVS and SEM;
• ORP.
5 HEALTH AND SAFETY
Mr Jeremy Midgley (NMP’s representative) will be responsible for the overseeing of health and safety
aspects for the duration of the trip.
5.1 PERSONAL PROTECTIVE EQUIPMENT
Personal protective equipment (PPE) must be worn on the vessel as directed by the vessel master.
The following general offshore PPE should be provided to personnel on board the MV Snowgoose:
• Bright Coveralls or at least long working pants with a reflective vest
• Safety footwear
• Safety helmet (as required during lift operations)
• Gloves
• Masks, safety glasses and nitrile gloves for working with formalin
• Self-inflatable life jackets
• Safety harnesses
5.2 WORK ON DECK
Particular care is required when handling any over-side equipment, each member of the field team is
to ensure that the correct and safe procedures are understood and implemented for all work taking
place on the deck of the vessel. The field team should ensure their safety harnesses are properly
secured for any work undertaken near the gunwale of the vessel.
If the weather conditions begin to deteriorate, the field team should continually assess the situation
and stop work whenever necessary. This is especially true in conditions where equipment becomes
unstable, or instrumentation begins swaying excessively on the winch.
All the members on the field team will have the full authority to issue a “Stop work” command if
anyone perceives a hazard during work operations. Most technical/manual activities are to be
undertaken by trained boat crew.
A toolbox meeting should be held prior to any new tasks and or beginning of every shift being
undertaken, and a refresher meeting should occur whenever necessary.
© NMP 2014
November 2014 Page 9
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
5.3 RISK ANALYSIS
A number of risk assessments have been carried out in alignment with the tasks that the field team
will be carrying out. The risk assessments have been prepared on the basis of the risk factor table
presented in Figure 5-1. The risk assessment tables should be read in conjunction with the associated
deployment and recovery procedures.
Figure 5-1: Risk factor table taken from OGP HS&E Guidelines for Metocean Surveys1..
1 International Association of Oil and Gas Producers. http://www.ogp.org.uk/pubs/348.pdf
© NMP 2014
November 2014 Page 10
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Table 5-1: RA for the mobilisation of equipment and loading of ship
Risk H R Mitigation H R
Theft/loss of valuables/
equipment/ personnel
4 3 12 • Keep all valuables out of sight
while travelling.
• Ensure equipment is securely
packaged before
transportation.
• Be vigilant when travelling.
2 3 6
Scratches from securing
equipment/moving/carrying
boxes
2 3 6 • Use of PPE.
• Ensure all boxes/crates are
properly secured.
• Ensure vessel crew is
responsible for hoisting.
1 2 2
Injury to personnel and / or
damage to equipment from
uncontrolled lifting/dropping
of boxes/equipment
4 3 12 • Use of PPE
• Lift carefully, bend knees and
not back.
1 2 2
Table 5-2: RA for work on vessel deck
Risk H R Mitigation H R
Personal injury due to
Slips/trips/falls
4 3 12 • Use of PPE, especially safety
shoes when on deck
• Ensure deck is cleared of
potential trip hazards
1 2 2
Personal injury due to falling
over gunwale
5 3 15 • Use of PPE, especially life
jackets and safety harnesses
when working near the gunnel.
• Work close to the gunnel only
when it is safe to do so, if
weather conditions are not
favourable –Stop work.
3 2 6
Table 5-3: RA for the handling and analysis of sediment samples
Risk H R Mitigation H R
Injury to
personnel/equipment from
mishandling samples/grabs
4 3 12 • Use of PPE
• Be vigilant when handling
equipment and samples
• Ensure no one puts their
fingers close to the jaws of
either grab.
1 2 2
Personal injury due to
exposure to formalin
4 2 8 • Use of PPE
• Use supplied gas mask
• Only use formalin in well
ventilated areas
• Wash hands after work with
formalin
3 1 3
© NMP 2014
November 2014 Page 11
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
Table 5-4: RA for the deployment and recovery of Rosette and CTD
Risk H R Mitigation H R
Personal
(hands/head/feet)injury or
damage to equipment due to
mishandling of rosette
3 3 9 • Use of PPE, especially
hardhats, safety boots
• Ensure care is taken when
setting up Niskin bottles, keep
fingers away from the
tops/bottoms of open bottles
• Ensure care is taken when
hoisting/lowering rosette unit.
3 2 6
Table 5-5: RA for the packaging and unloading of samples
Risk H R Mitigation H R
As per table 5-1 0 0 0 0 0 0
5.4 EMERGENCY PROCEDURES AND CONTACT NUMBERS
In the case of any emergency the following numbers are to be called either from a satellite phone,
local sim card, or on board telephone (Table 5-6). Please ensure that this list of numbers is placed in
an area visible to all field staff during work on board the vessel and while travelling.
Table 5-6: Emergency contact details:
Name Position Email Phone number
Jeremy Midgley NMP
representative
mwjmidg@mweb.co.za
+ 27 21 7886212
+27 832649484
Bill Ludick NMP
representative
bludick@mweb.co.za
0814822386
(Namibian number)
Mike
Woodborne
NMP land project
coordinator
mike.woodborne@uclresources.com.au
mike.woodborne@gmail.com
+61 410307205 /
+37281054658
Hospital Walvis Bay
Medipark T/a
Welwitchia
Hospital
Street Address:
Gertrude Rikumba Kandanga Hilukilwa Street,
Walvis Bay
+26 464 21 8911
Police Station Walvis Bay Police
Station
Walvis Bay, Namibia +264 64 21 9048 /
64 202 055 / 10111/
Sea Rescue Namibian Sea
Rescue
208 2221 or 081 129
6295
While on board, the vessel staff will be required to follow and adhere to all health and safety
requirements/instructions given to them by the vessel captain.
© NMP 2014
November 2014 Page 12
ENVIRONMENTAL VERIFICATION REPORT
Dredging of Marine Phosphate ML 170
SECTION D, APPENDIX 1 - WATER COLUMN AND SEDIMENTARY ENVIRONMENT
1.5 Project Execution Plan: Core Sampling MV Snowgoose
5.5 TOOLBOX MEETING TEMPLATE
Toolbox Meetings
A toolbox meeting will be held prior to each operation, inclusive of Client rep, Party chief, technicians
and divers discussing the following:
• Anticipated operations to be undertaken
• Any hazards that have not been actioned
• Individual concerns of employees
The toolbox meeting will be documented according in the following format:
Date & time of
meeting
Date & time of
report
Location Vessel
List of attendees
Present
weather
conditions
Matters for discussion
Scope of work
summary
Comments
Review and
acceptance of
JSA
Signed
Signatures
Party Chief Dive
Master
Client Rep
© NMP 2014
November 2014 Page 13
top related