I-75 Express Overview
From NW 170 Street (Miami-Dade County) to I-595 (Broward County)
Project Limits
Scope of Work
• Constructing Express Lanes in the existing I-75 median
• Constructing ingress and egress points throughout the corridor
• Constructing direct connections to 595 Express, Palmetto Express and
Homestead Extension of Florida’s Turnpike (HEFT)
• Reconstructing the interchanges along the corridor
• Constructing sound barrier walls at various locations
• Installing additional traffic cameras, dynamic message signs and toll
gantries
• Adding new signals, signage, lighting and landscaping
Corridor wide
75 Express LanesEntrance and Exit ramps
Please visit our webpage to download the Entrance and Exit ramps guide
Segments A&BConstruction update
Current activities• Constructing Express Lanes bridges over the Snake Creek
canal and Florida’s Turnpike• Continuing bridge construction on the I-75 Express Lanes
direct connect to southbound Florida’s Turnpike• Building Express Lanes within the existing median• Clearing vegetation and constructing sound barrier walls
along several communitiesFuture activities• Complete sound barrier wall installation• Continue Express Lanes bridges and ramps• Continue building Express lanes in the existing median
Proposed I-75/HEFT Interchange
Northbound Turnpike to Northbound I-75Southbound I-75 to Southbound TurnpikeSouthbound I-75 Express to Southbound TurnpikeSouthbound I-75 to Northbound TurnpikeSouthbound Turnpike to Southbound I-75 & Miami Gardens DriveSouthbound Turnpike to Northbound I-75Southbound Turnpike to Northbound I-75 ExpressNorthbound I-75 to Northbound TurnpikeMiami Gardens Drive to Northbound TurnpikeNorthbound Turnpike to Northbound I-75 Express
Existing Movement to RemainNew MovementExisting Movement to RemainNew Movement
N
Segment CConstruction update
Current activities• Continuing new Pembroke Road bridge construction• Continuing Miramar Parkway Bridge phase 2 construction• Excavating ponds at Miramar Parkway and Pines Blvd• Building future Express Lanes within the existing median• Constructing swale areasFuture activities• Miramar Parkway Bridge phase 3 construction• Continue new Pembroke Road bridge construction• Anticipated bridges completion by late 2016• C-4 Canal crossing construction within the existing median
Segment DConstruction update
Current activities• Sheridan Street Interchange Phase 1 construction• Excavating ponds• Constructing new toll plaza• Installing sign structures throughout segment
Future activities• Drainage activities along segment• Continue building Express lanes in existing median• Continue Sheridan Street Interchange Phase 2 construction
Segment EConstruction update
Current activities• Building future Express Lanes in the existing median• Excavating ponds for future drainage• Building new bridge to connect 75 Express to 595 Express• Installing drilled shafts for sign structures
Future activities• Complete and paint sound walls• Continue new bridge construction • Build Express Lanes in the existing median
Upcoming Closures
Segment E
Monday, September 21 from 9:00 p.m. to 5:30 a.m.
• All lanes of northbound Sawgrass Expressway at the I-595 interchange will be closed. Motorists will be detoured to eastbound I-595 (Exit 19), exit Flamingo Road, make a U-turn at Flamingo Road, then continue westbound on SR 84 to re-enter westbound I-595 and take the exit to northbound Sawgrass Expressway (Exit 19).
• All lanes of eastbound I-595 will be closed. Motorists will be detoured to take the exit ramp at Glades Parkway (Exit 22), continue eastbound on SR 84 to Flamingo Road to re-enter I-595 eastbound.
• The entrance ramp from Weston Road to eastbound I-595 will be closed. Motorists will continue on eastbound SR 84 to enter eastbound I-595, just east of Flamingo Road.
• One lane of EB SR 84 at SW 148 Avenue will be closed.
Upcoming Closures
Segment E
Tuesday, September 22 and Wednesday, Sept 23• The entrance ramp from Weston Road to eastbound I-595 will be
closed from 10:30 p.m. to 5:30 a.m. Motorists will continue on eastbound SR 84 to enter eastbound I-595, just east of Flamingo Road.
• One lane of EB SR 84 at SW 148 Avenue will be closed.
Thursday, September 24 and Monday, September 28• All lanes of eastbound SR 84 will be closed 10:30 p.m. to 5:30 a.m.
Motorist will be detoured to enter I-595 eastbound, then exit at Flamingo Road (Exit 2) to continue on eastbound SR 84.
*This schedule may change due to inclement weather or other unexpected conditions.