SAUDI COMMITTEE FOR UNITED NATIONS
PALESTINIAN RELEIF DEVELOPMENT PROGRAMM
CONSTRUCTION OF 300 RESIDENTIAL
UNITS IN RAFAH
Construction of Infrastructure works
Bill of Quantity
SAUDI COMMITTEE FOR UNITED NATIONS
PALESTINIAN RELEIF DEVELOPMENT PROGRAMM
CONSTRUCTION OF 300 RESIDENTIAL
UNITS IN RAFAH
Construction of Infrastructure works
Bill of Quantity
-
8/2/2019 boq300resunits infras
2/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
Bill No (1)
1. Mobilization & Demobilization
in Numbers In Letters
All works according to particular specifications, and
supervisor engineer instructions.
1/1
Preparation works including:1- Supply Site office, shed, equipments, and furniture for
both supervision and contractor.
2- Access road to and through the site.
3- Transportation & Communication.for the supervisor
engineers
4- Cleaning the existing site outside the buildings, the
work includes removing all debris around buildings and
transmitting to approved dumping site.
5-Determination the Road axis ,coordinates by Total
Stationand allignment of the sewage , water and
electrical networks.
LS 1
1/2Dismantle and remove all facilities, services, furniture,shed and any equipment related to the project supervisor
and contractor office.As per the engineer instructon.
LS 1
Total
Total (US$)ITEM DESCRIPTION UNIT QTYRATE (US$)
Contractor Signature
-
8/2/2019 boq300resunits infras
3/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
in Numbers In Letters
2 Water Supply Works1- All works must be coordinated with the water department at the
Municipality &CMWU.
2- The price includes the cost of excavation to depth indicated in
drawings not less than 1m using retaining shuttering, shoring
according to instructions of Engineer, bedding of 20 cm clean
sand under around and above the pipe with compaction,
backfilling of the trench up to design level with sand in layers 25
cm thick for each with compaction 98% MDD and all required
tests.
3- The work includes removal of the surplus materials outside the
site to places as instructed by the Engineer.
4- The work includes supply and installation of metallic warning
tap, and other accessories and thrust blocks according to details.
5- The covers of manholes are made of cast iron with diameter 60
cm engraved by the word " Water " in English and Arabic. the ring
is from cast iron square shaped with 70*70 cm dimensions. the
concrete which used around the ring is B350 and should have a
Basalts layer of 2 cm above the concrete and around the cover
rings. according to drawings, specifications and Engineers
instruction.
6-Cleaning ,disinfection and testing all the installed pipes
according to technical specification, Engineers instructions and
coordinating with water department in the municipality & CMWU.
7-All works are performed according to the drawings,
specifications and Engineers instruction
8-All Manholes items to be painted with hot bituminous 70/25
paint in addition to primer coat as directed by the supervision
Engineers & the manufacture instructions.
9-The price include reinstate repairing any damage resulted from
the works, all according to specification & as per engineer
instructions
10-The contractor must be submit detailed shop drawings of the
coming items for the approval by the Engineer before starting the
work.
11-The price includs supply and lay warning tape over the pipeline
with text indicating the exiatance of Water Pipeline.
12-All gate valves should be 16 bar working pressure Hakohav,
Raphael made or equivalent13- All ball valves should be 16 bar working pressure Zagiv made
or equivalent
14- Air release valves should be 16 bar working pressure A.R.I
made or equivalent
2.1 Supply, and install 110mm diameter PVC-U water pipes PN 10including excavation, backfilling, elbows, angles, Tees, flanges,
end caps, joints and accessories .The pipe should be bedded
and covered with at les t 20 cm of clean sand around, at the top
and bottom of the pipe . The used sand for backfilling of the
trench will be in layers not exceeding 25cm, with compaction not
less than 98 % , up to the design leveling of the road all according
to the engineer's instruction, drawings and technical specifications
L.M 800
2.2 Ditto but 63 mm diameter MDPE (Polyethylene) water pipes . L.M 3500
BILL NO. 2 WATER SUPPLY WORKS
ITEM DESCRIPTION UNIT QTYRATE (US$)
Total (US$)
Contractor signature
-
8/2/2019 boq300resunits infras
4/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
in Numbers In Letters
BILL NO. 2 WATER SUPPLY WORKS
ITEM DESCRIPTION UNIT QTYRATE (US$)
Total (US$)
Supply and install 80 cm internal diameter precast circular
reinforced concrete water manhole for air release valve,
complete with B300 cast in place reinforced concrete base,
cast iron cover (25ton Capacity) with frame. The supplied
concrete rings should be provided with cast iron steps @
30cm maximum. The work includes excavation in any type
of soil to any depth , backfilling with clean sand and
compaction 98% MDD up to the design leveling of theroads. The manhole base should be provided with
drainage opening with aggregate bed.
The price shall include Tee 110x110x50mm, ball valve 2"
diameter Sagiv or equivalent, air release valve 2" diameter
double action ARI or equivalent, Nipples, f ittings and all
needed tests to finish work according to drawing,
specification and engineer's instructions.
2.4 Ditto but Manhole 100 cm diameter for washout valve. Theprice includes supply and install gate valve 3", flanged
dresser 3", Tee 63x63x50mm , Nipples, Jack supports,
male connector for firefighting hose, fire fighting hose 2"
with length 15 m and all fittings according to drawing,
specification and engineer instructions
No. 1
2.5 Ditto but Manhole 80 cm diameter for Gate Valve 4" on thepipe 110 mm (MH1). The price includes Flanges, dressers,socket flange, gate valve 4" diameter, Jack supports, and
all fittings according to drawings, specification and
engineer's instructions
No. 1
2.6 Ditto but Manhole 80 cm diameter for Gate Valve 3" on thepipe 63 mm (MH2, MH3). The price includes Flanges,
dressers, socket flange, gate valve 3" diameter, Jack
supports and all fittings according to drawings,
specification and engineer's instructions
No. 2
2.7 Ditto but Manhole 80 cm diameter for Gate Valve 4" on thepipe 110 mm (MH4,MH5,MH6,MH7)). The price includes
Flanges, dressers, socket flange, reducer 4"/3", gate
valve 4" diameter, Jack supports, and all fittings according
to drawings, specification and engineer's instructions
No. 4
2.8 Ditto but Manhole 80 cm diameter for the fire hydrant. Theprice includes Flanges, dressers, socket flange, gate
valve 4" diameter, Jack supports,3" & 4" galvanized steel
pipes, galv. steel reducer 4"/3"galvanized elbow 3", f ire
hyrant valve 3" 16 bar and all flanges and fittings. The
galv. pipes should be painted and supprted by concrete
thrust block ,all works as specification drawings and
engineer's instruction.
No. 2
2.9 Cutting the existing 200mm UPVC pipe and connecting thenew UPVC pipe 110mm including T200X200X110mm,
Dressers, flanges and all needed fittings and accessories.
The work includes excavation and backfil ling with clean
compacted sand all as specification drawings and
engineer's instruction.
No. 1
2.10 Cutting the existing 160mm UPVC pipe and connecting thenew UPVC pipe 110mm including T160X160X110mm,
Dressers, flanges and all needed fittings and accessories.
The work includes excavation and backfil ling with clean
compacted sand all as specification drawings and
engineer's instruction.
No. 1
2.11 Excavation , backf illing with clean sand on layers not toexceed 25 cm each , Supply and install house connection
32". The price includes approved Saddle 110/32mm ,
thrust block ,MDPE pipe 32 mm diameter to be connected
to the existing 1" steel pipe and all needed fittings
according to drawings, specification and engineer's
instructions.
No. 20
2.12 Ditto, but saddle 63/32 mm No. 80
Total ($)
2.3 No. 2
Contractor signature
-
8/2/2019 boq300resunits infras
5/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB2012-099
BILL NO.3
SEWAGE WORKS
Numbe In Letters
3 Sewage works
_The contractor has to submit detailed shop drawings of
the coming items for the approval by the Rafah
municipality and CMWU before starting the work.
_The Contractor has to visit the site for inspection.
_The price includes the cost of excavation to depth
indicated in drawings and using retaining shuttering,
shoring according to the instructions of Engineer,
bedding of 15 cm clean sand under ,around and above
the pipe with compaction, backfilling of the trench up to
design level in layers 25cm thick for each with
compaction 98% MDD and all required tests.
_The work includes removal of the surplus materials
outside the site to places as instructed by the Engineer.
_The work includes connection of the manholes to the
existing sewage line after cleaning and adjusting the
level and orientation of the existing pipes if needed
according to engineer instructions.
_ The holes of the manholes have to be done using
core machine.
_ All the manholes have to be coated by one coat
primer and external hot bitumen coating 75/25.
_ Measurement of pipes and manholes depth is from
the invert level of pipes to the design asphalt level.
the price include erecteing Flexible Joints for manholes
at the main line of sewage
_Cleaning and testing all the installed pipes according
to technical specification, Engineers instructions and
coordinating with water department in the municipality
_All tests costs to be included in the unit rate items,
without any extra paid money.
_The price include reinstate repairing any damage
resulted from the work, all according to specification &
as per engineer instructions
_Covers of manholes are made of cast iron with
diameter 60 cm for all manholes sizes 25 ton capacity,
and engraved by the word " Sewage " in English and
Arabic. the r ing is from cast iron square shaped with
70*70 cm dimensions. The concrete used around the
ring is B300 for at least 30cm width and depth, Basalt
layer of 2 cm thick above the concrete and around the
cover to fix the ring should be supplied and installed, all
according to drawings, specifications and Engineers
instruction.
_All the above mentioned instructions are
considered part of the next items
UNIT QTYRATE (US$)
Total (US$)ITEM DESCRIPTION
Contractor Signature
-
8/2/2019 boq300resunits infras
6/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB2012-099
BILL NO.3
SEWAGE WORKS
Numbe In LettersUNIT QTY
RATE (US$)Total (US$)ITEM DESCRIPTION
3-1 UPVC Pipes:-
Supply, install and join, UPVC pipes SN8 250 mm
outside diameter. for the sewer networks with watertight
and flexible joints sealed with approved gasket rubber
ring including excavation in any ground for the depth
indicated in the drawings, shoring, shuttering, safety
measures, testing, sand beds all according to the
drawings, specifications and Engineers instruction.
L.M 150
3-2
200 mm outside diameter UPVC PipesL.M
120
3-3160 mm outside diameter UPVC Pipes L.M
1200
3-4 Manholes: -
Supply, install precast circular reinforced concreteB300
kg/cm2 Sewage manholes 1.25m internal diameter and
wall thicness 15 cm with reinforced base, cast iron
steps @30cm spacing, cast iron manhole cover,(25 ton
capacity), outlet pipes for future connection with end
cap where shown or necessary. The price including twoexternal bitumen coating, shuttering, excavation in any
ground to the depth indicated in the drawings, shoring,
safety measures, formwork, backfilling with sand,
removing the surplus soil to the tip ..etc. The price
includes also supply and install 10cm plain concrete
B200 under the base of the manhole and for benching.
The price includes also erecteing Flexible Joint 80-50
cm at connection btween pipe and manhole . All are as
per drawings , specifications and the engineer
instructions.
No 3
3-5
Ditto but Manholes with internal dia. 1. 0 m wall thicness
14 cm and 25 ton capacityNo 68
3-6
Ditto but Manholes with internal dia. 0.80 m wall
thicness 12.5 cm and 25 ton capacity No 62
3-6
Ditto but Manholes with internal dia. 0.60 m wall
thicness 7.5 cm and 40 cm opening with 8 ton capacity
cover
No 66
total
Contractor Signature
-
8/2/2019 boq300resunits infras
7/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
BILL NO.4
COMMUNICATION WORKS
Numbe In Letters
4 Communication Works
_The contractor has to submit detailed shop drawings of
the coming items for the approval by the PalTel
Company before starting the work.
_The Contractor has to visit the site for inspection.
_The price includes the cost of excavation to depth
indicated in drawings and using retaining shuttering,
shoring according to the instructions of Engineer,
bedding of 15 cm clean sand under ,around and above
the pipe with compaction, backfilling of the trench up to
design level in layers 25cm thick for each with
compaction 98% MDD and all required tests.
_The work includes removal of the surplus materials
outside the site to places as instructed by the Engineer.
_The work includes connection of the manholes to the
existing PalTel line after cleaning and adjusting the level
and orientation of the existing pipes if needed according
to engineer instructions.
_ The holes of the manholes have to be done using
core machine.
_ All the manholes have to be coated by one coat
primer and external hot bitumen coating 75/25.
_ Measurement of pipes and manholes depth is from
the invert level of pipes to the design asphalt level.
_Cleaning and testing all the installed pipes according
to technical specification, Engineers instructions and
coordinating with PalTel.
_All tests costs to be included in the unit rate items,
without any extra paid money.
The price includs supply and lay warning tape over the
pipe with text indicating the exiatance of PalTel line.
_The price includes installation of pulling ropes inside
the the PVC pipes
_The price includes reinstate repairing any damage
resulted from the work, all according to specification &
as per engineer instructions
_Covers of manholes are made of cast iron with
diameter 70 cm for all manholes sizes 25 ton capacity,
and engraved by the word " PalTel " in English and
Arabic. the r ing is from cast iron square shaped with
80*80 cm dimensions. The concrete used around the
ring is B350 for at least 30cm width and depth, Basalt
layer of 2 cm thick above the concrete and around the
cover to fix the ring should be supplied and installed, all
according to drawings, specifications and Engineers
instruction.
_All the above mentioned instructions are
considered part of the next items
ITEM DESCRIPTION UNIT QTYRATE (US$)
Total (US$)
Contractor signature
-
8/2/2019 boq300resunits infras
8/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
BILL NO.4
COMMUNICATION WORKS
Numbe In LettersITEM DESCRIPTION UNIT QTY
RATE (US$)Total (US$)
4-1 PVC Pipes:-
Supply, install and join single line of PVC pipes 4"
diameter V1. for the PalTel network with approved
gasket rubber ring including excavation in any ground
for min. 1.5m depth, shoring, shuttering, safety
measures, testing, sand beds all according to the
drawings, specifications and Engineers instruction.
L.M 800
4-2
Ditto but double lines of PVC pipes 4" V2L.M
620
4-3
Ditto but trible lines of PVC pipes 4" V3L.M
150
4-4Ditto but four lines of PVC pipes 4" V4 L.M
850
4-5
Supply, install and join single line of flexible PVC pipes
3" diameter for the PalTel house connection including
excavation in any ground for min. 1.5m depth, shoring,
shutter ing, safety measures, testing, sand beds all
according to the drawings, specifications and
Engineers instruction.
L.M 1000
Manholes: -
4-6 Supply, install precast circular reinforced concrete B300
kg/cm2 manhole 100cm internal diameter and wall
thicness 15 cm with cast iron manhole cover,(25 ton
capacity . The price includes two coats of external hot
bitumen, shuttering, excavation in any ground to the
depth of 1.5-2.0m, shoring, safety measures, formwork,
backfilling with sand, removing the surplus soil to
approved site ..etc. all as per drawings , specifications
and the engineer instructions.
No 31
4-7 Supply and cast in situe reinforced concrete B300
kg/cm2 for the manholes M1 with cast iron manhole
cover,(25 ton capacity . The price includes two coats of
external hot bitumen, shutter ing, excavation in any
ground to the internal height of 2.0 m, shoring, safetymeasures, formwork, backfilling with sand, removing
the surplus soil to approved site ..etc. all as per
drawings , specifications and the engineer instructions.
No 25
total
Contractor signature
-
8/2/2019 boq300resunits infras
9/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
Bill No (5)
Electricity Works
in Numbers In Letters
A- Steel Poles and Bases:
5.1
Supply and Install Lattice Steel Pole L.S.P 70/80 12 m
long. with Steel Base ,Arms &brackets , B200 Concrete
Foundation, Lattice Pole Suspension Side Arm, K7972,1.5m, 1.st Phase. Auxiliary Steel Arm K160/3.
Transformer Isolator Side Arm , K1558 , 3m, Protection
Arm, K81. Anti-Climbing Steel Arm K113/8, for (L.S.P).
22 kV Pin & Tension type Insulators, Complete Low
Tension Insulator Unit, Wire KHF CU 95 mm2 Stranded
(Hard Drawn).
Line KHF CU 35 mm2 Stranded (Soft drawn). 22 kV
Cable 1*50 mm2 CU, XLPE.
With Steel bolts , Nuts , Washers ,Clamps, Earth Rod
15mm Diameter, 1.5 m. Wire PN CU 70 mm2 PVC
Yellow/Green and Master lock key.and all needed
fittings and accessories to hand over the work in clean
tested and good workmanship and operable Condition.
No. 1
5.2
Supply and Instal 24 kV, 630A Switchgear, and 16 kA
Short Circuit Current Ring Main Unit SF6, 2 incoming
switch Disconnectors, one Transformer Protection fuse
switch combination (CTC) With 22 kV Porcelain Fuses
63 A. Including cables Trench.and chaqar cover
No. 0
5.3
Supply and Install hermetically sealed Type,
1250KVA,22/0.4KV, ,Mineral oil Low losses
Transformer With Bushings and Arms for Fixing the
Cable, Beside the Transformer with cable ladder. The
Works Includes Transformer Concrete base B250 , And
all needed Lugs, Clamps ,Wires and Earthling system
for transformer and chaqar Plate cover for trenchs.
According to
Engineer Instructions and Approval of Gedco
No. 0
5.4
Supply and Install L.V Distribution Board 2000A with
Main CB IZM 2000A (8 Feeder).with Bus Bars 2000A,
NZM Circuit Breakers , KWH Meters , Current and
Voltage Instruments With CTs , wires , Clamps and all
needed Accessorizes Per drawings and Engineer
Instructions .
No. 0
5.5
Supply and Install Underground 22 kV Cable 1*240
mm2
AL, XLPE.The Works including Excavation 150
cm under ground Cable Trench and Backfilling with
Clean sand ,Warning Tape and concrete Slabs
(45x45x5)cm entire the length of trench ,6 inch UPVC
Pipes With compression lugs, Shrink Insulator for Lugs
(Color). PVC& Buckle Clamps with all needed wires
and Accessories as per Drawings .
L.m. 1200
5.6
Supply and Install LV Panel with main Vertical
Disconnect or switch LTL 630/400 Amps and 6 Vertical
Disconnector switch LTL 160/100 A including Earthing ,
civil structure 10 Nos ,4 Inch Pvc sleeves pipes and all
needed to fix and connect the Panel as per drawings.
No. 0
5.7
Supply and Install LV Panel with main Vertical
Disconnect or switch LTL 400//250 Amps With
LTL(3X63/40A) With Bus bars including earthing , civil
structure with 6mm thick chaqar plate cover with hand
held ,10 Nos ,4 Inch sleeves and all needed wires and
PVC Terminals connections to fix and connect
consumers Cables .with Electricity
No. 0
Total (US$)ITEM DESCRIPTION UNIT QTYRATE (US$)
Contractor Signature
-
8/2/2019 boq300resunits infras
10/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
Bill No (5)
Electricity Works
in Numbers In LettersTotal (US$)ITEM DESCRIPTION UNIT QTY
RATE (US$)
5.8
Supply and Install LV Panel with main Vertical
Disconnect or switch LTL 400//200 Amps with
LTL(3x63/40)A With Bus bars including earthing , civil
structure with 6mm thick Chaqar plate cover with hand
held ,8 No S,4 Inch Sleeves and all needed wires andPVC Terminals connections to fix and connect
consumers Cables .with Electricity
No. 0
5.9
Supply and Install LV Panel with main Vertical
Disconnector switch LTL400//160 Amps with
LTL(3x63/40)A and three phases Bus bars including
Neutral and Earthl ing Buses , civil structure with 6mm
thick Chaqar plate cover with hand held ,8 No S,4 Inch
Sleeves and all needed wires and PVC Terminals
connections to fix and connect consumers Cables .with
Electricity
No. 18
5.10Supply, Install and connect 0.6/1KV ,L.V Cable
3*240+120 mm2
CU, XLPE.L.m. 200
5.11Supply, install and connect 0.6/1KV,L.V Cable
3*150+75 mm2
CU, XLPE. L.m. 350
5.12Supply, Install and connect 0.6/1KV,L.V Cable
3*120+60 mm2
CU, XLPEL.m. 300
5.13Supply, Install and connect 0.6/1KV,L.V Cable 3*95+50
mm2
CU, XLPEL.m. 665
5.14Supply, Install and connect 0.6/1KV,L.V Cable 3*70+50
mm2
CU, XLPEL.m. 450
5.15Supply, Install and connect 0.6/1KV,L.V Cable 3*50+25
mm2
CU, XLPEL.m. 800
5.16Supply, Install and connect 0.6/1KV,L.V Cable 3*16+10
mm2
CU, XLPEL.m. 100
5.17
Supply, Install and connect L.V Cable 4*16 mm2
Cu.,
XLPE, including spring pipe 2", Civil works to lay the
cables and all needed to connect the dwelling unitsM.D.Bs with electricity .The work includes Excavation
80cm depth in soil and back filling with clean sand ,
warning tape and 80cm diameter manholes every 25
meter distance as per drawings and Engineer approval
.
L.m. 6000
5.18
Supply and Install materials for future installation of
Hot galvanized octagonal street light pole 8m long
including bolts galvanized steel base and B200
concrete foundations 1*1*1m.
No. 50
5.19Supply and Install 3" spring pipe dumped at 80cm deep
as following (pipe then 30cm soft sand then warning
tape then 50cm sand).as per drawings.L.m. 3500
5.2
Supply and Install N 8-4" UPVC pipe dumped at 80cm
deep as following (pipe then 30cm soft sand then
warning tape then 50cm sand) for low voltage Cables
crossings at The Roads.
L.m. 300
5.21 Supply and Install N2XY cable 3*35+16mm 2. L.m. 200
5.22 Supply and Install N2XY cable 5*16mm 2. L.m. 200
5.23 Supply and Install N2XY cable 5*6mm2. L.m. 500
5.24Supply and Install Cu stranded wire 35mm
2for
Earthing.L.m. 100
5.25
Excavation under ground high voltage cable trench 150
cm from finishing floor level in different soil levels at
road crossing and laying 6 inch pipes covered with 50
cm B200, concrete above the pipes and backfilling with
clean sand and compaction for cables trenches.
including warning tape and concrete slab 45x45x5 cm
entire the length of the trench as Per drawings .
L.m. 200
Contractor Signature
-
8/2/2019 boq300resunits infras
11/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
Bill No (5)
Electricity Works
in Numbers In LettersTotal (US$)ITEM DESCRIPTION UNIT QTY
RATE (US$)
5.26
Supply and Construct transformer room buildings with
two
lighting fixtures (2x36W) ,IP65 With lighting switch and
one socket , The work includes Transformer Base
foundation , High Voltage switchgear and low voltagemain trenches covered with 6 mm galvanized steel
chaqar plate entire the trenches . The room shall be
provided with painted galvanized steel door and
window with louvers, plastered internally and externally,
tiled and internally and externally painted . All the work
should be according to GEDCO Regulations, drawings,
specifications and approval of Engineer .
No. 2
Total
Contractor Signature
-
8/2/2019 boq300resunits infras
12/12
Construction of Infrastructure works
PAL10-49740: Construction of 300 Residential Units in RafahITB 2012-099
Bill No (1)
Bill No (2)
Bill No (3)
Bill No (4)
Bill No (5)
Telephone.
Fax .
Mobile .
Name of the contractor ......
Authorized signature ......
Signature and Sealing.
Title ...
Total in numbers ......................................................................
Total in letters ..............................................................................
Mobilization
Water Works
Sewage Works
Communication Works (PalTel)
Electricity Works
Bill No Description Total
Grand Total (US$) Not including ValueAdded Tax (VAT)
Summary
Contractor Signature