chemical injection

Post on 04-Dec-2015

217 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

DESCRIPTION

hasgdfsdfkdghfhgdhjbka

TRANSCRIPT

1. During Commissioning of HP Separator first fill up the HP Separator(V-116001) with water.2. After filling up the HP Separator drain out this water.3. Again fill up the separator with water and pressurized it with nitrogen up to 7 bar(kg-f/cm2).4. Check the functioning, opening & closing of control valves and all instruments properly.5. Do loop check of instruments.