COST CENTER ACCOUNTING
SAPTOPJOBS Page 1 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
CKMLCP - Actual Costing Run Functionality Actual costing run performs single level and multi level actual costing by plant. The differences are allocated to the issues (single level) and then the differences are passed on to the next level (multi level).The recalculated prices can then be used for future valuation. Scenario This transaction code is to calculate actual cost at the month end. The executing of actual costing run in a material ledger activated plant is compulsory for every month end. Requirements The material ledger is active. The price determination indicator in the material master is set to ‘3’. The price control indicator in the material master is set to ‘S’.
Menu Path Accounting → Controlling → Product Cost Controlling → Actual Costing/Material Ledger → Actual Costing → CKMLCP - Edit Costing Run
Transaction Code CKMLCP
1. Double Click on CKMLCP - Edit Costing Run
COST CENTER ACCOUNTING
SAPTOPJOBS Page 2 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
2. Update the following fields:
Field Name Field Description Values
Costing run Number of the Costing run. 5200_06A
Costing run Description of the Costing run should include information about the plant.
Costing Run plant 5200
Period Number identifying a fiscal month
06
Period Number identifying a fiscal month
2002
3. Click the Enter button.
4. Click Create .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 3 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Create Costing Run
5. Click the Enter button.
Costing Cockpit: Actual Costing - Change / Execute
6. Click 5200 .
7. Click Column left Button .
8. Click the Save button.
Note: It is advisable to prepare separate costing runs for each plant due to performance issues.
9. Select Goto→Switch Screen Formatting.
10. Click <tab button> Process .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 4 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
11. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 5 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Maintain Variant: Report SAPRCKMLMV_RUN_BASIC_LIST, Variant 0000000000
12. Click Background processing .
13. Click Back .
14. Click the Yes Button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 6 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
15. Click the Execute Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 7 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Actual Costing: Select Materials
16. Click Back .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 8 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
17. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 9 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Choose Log
18. Click the Display button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 10 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Choose Log
19. Click Button .
20. Click Back .
21. Click Cancel button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 11 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
22. Click <tab button> Costing results .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 12 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
No material for multi-level price determination was chosen.
23. Click <tab button> Process .
Costing Cockpit: Actual Costing - Change / Execute
COST CENTER ACCOUNTING
SAPTOPJOBS Page 13 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
24. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 14 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Maintain Variant: Report SAPRCKMLMV_RUN_CREATE_STEPS, Variant 00000000
25. Click Background processing .
26. Click Back .
27. Click the Yes Button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 15 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
COST CENTER ACCOUNTING
SAPTOPJOBS Page 16 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Actual Costing: Determine Costing Sequence
28. Click Back .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 17 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
COST CENTER ACCOUNTING
SAPTOPJOBS Page 18 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
29. Click Single-level pr. determination Button .
30. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 19 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Maintain Variant: Report SAPRCKMA_RUN_SETTLE, Variant 000000000001
31. Click <radio button> Process again .
32. Click <radio button> Check against the standard price in the period .
33. Click <checkbox> Background processing .
34. Click Back .
35. Click Yes Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 20 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
36. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 21 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Single-Level Price Determination for Costing Run
37. Click Back .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 22 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
38. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 23 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Maintain Variant: Report SAPRCKMLMV_RUN_MLEVEL_SETTLE, Variant 0000000
39. Click <radio button> Check against the standard price in the period .
40. Click <checkbox> Background processing .
41. Click Back .
42. Click the Yes Button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 24 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
43. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 25 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
COST CENTER ACCOUNTING
SAPTOPJOBS Page 26 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
44. Click Post closing Button .
45. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 27 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Maintain Variant: Report SAPRCKMA_RUN_CLOSE, Variant 000000000001
46. Click <checkbox> Background processing .
47. Click <checkbox> Test run .
48. Click Back .
49. Click the Yes Button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 28 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
50. Click Button .
Tip: In this step you are able to proceed ‘Post closing’ only for the whole plant, to process particular materials you should use transaction CKMI.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 29 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Post closing for costing run
COST CENTER ACCOUNTING
SAPTOPJOBS Page 30 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
COST CENTER ACCOUNTING
SAPTOPJOBS Page 31 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
COST CENTER ACCOUNTING
SAPTOPJOBS Page 32 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
51. Click <tab button> Process .
52. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 33 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Maintain Variant: Report SAPRCKM_PRMT_RUN_TYPE, Variant 000000000001
53. Update the following fields:
Field Name Description Values
Manual date Enter the date from which price will be marked as a future.
01/07/2002
Button: Beginning of the following period
Switch into to choose the first day of the coming period.
01/07/2002
54. Click Back .
55. Click the Yes Button.
COST CENTER ACCOUNTING
SAPTOPJOBS Page 34 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
56. Click Button .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 35 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
57. Click Back .
COST CENTER ACCOUNTING
SAPTOPJOBS Page 36 of 36
MATERIAL LEDGER END USER TRAINING DOCUMENTS
Costing Cockpit: Actual Costing - Change / Execute
top related