Ganda ERP Project |
Current Progress and Achievements
2
• CG and SAG ERP go live on 01-Jan-2014 including Purchasing, Inventory, sales, Distribution & FG Warehouse, Production and Finance & Accounting.
• CG ERP Jan-2014 accounting period still in Month-End closing process, most of sub-ledger (AP, AR, NM, FA) and GL Accounts are balanced, now is doing Cost Related Voucher adjustment and final checking.
• SAG ERP Jan-2014 accounting period still in Month-End closing process, most of sub-ledger (AP, AR, NM, FA) and GL Accounts are balanced, now is doing cost value check and fine tune.
• All of CFC ERP Customization requirement have been collected and now is under Customization Spec Development and Programming
• All of MFG Modules customization spec have been confirmed and near 60% customization program (Total around 2200 Hrs, Finished around 1200 Hrs)have been complete and under internal testing.
• All of MFG Reports Requirement have been confirmed on Feb-2014 and those customization specs will be finished before 16-Mar-2014.
• All of FIN customization have been collected and confirmed, except Dual currency solution.
Ganda ERP Project |
ERP Implementation Schedule for Whole Group
3
2013 2014
Oct Nov Dec Jan Feb Mar April May June July
CG, SAG, GAMA
CFC
SIN
MM
ANP
Preparation For Go-Live
Preparation For Go-Live
Go-Live
Parallel Run Go-Live
Go-LivePreparation For Go-LiveTraining
Training
Training Customize
Customize
Preparation For Go-Live
Preparation For Go-Live
Prepare PUR & FIN Go-Live
Prepare PUR & FIN Go-Live
Customize
Ganda ERP Project |
Nov-2013 Dec-2013 Jan-2014 Feb-2014 Mar-2014 Apr-2014 May-2014 June-2014 July-2014 Aug-2014
Purchasing
Inventory
Sales
Distribution / FG Warehouse
Production
Maintenance
Finance & Accounting
Human Resouce
Customization Basic Data upload Test / Simulation End User Training Parallel Test Run
GO - LIVE
ERP Go Live
The Schedule to Go-Live for CFC
ERP Go Live
Sim
ulation Testing 10%
(15-Apr)
Sim
ulation Testing 50%
(12-May)
Ganda ERP Project |
Current Status of CFC ERP Implementation
Module Customization Basic Data Status Comment
Purchasing 1.PRProposalPOGR have been completed , except Proposal and related reports. 2. Purchasing Proposal have been confirmed by C.G on 03-Mar, and plan to delivery on Mar-2014.3. Proposal Customization spec have need developed but still wait CFC & CG final confirm4. GR weight-scale & belt-scale Integration will be put on Phase-I (Plan to delivery on May-2014)5. Purchasing Reports will be delivery on May-2014
1. Under Progress (Total :12 items , Complete : 9 items)2. Should be put into ERP before Mid of Mar-2014
p.s. please reference “CFC Basic Data List- Non Finance
Module.xls”
1. Middle Risk 2. Purchase Proposal
Customization. Will be release to programming on this week.
3. GR Weight-Scale and Belt-Scale will be set lower priority in this Phase.
Inventory 1. Almost the same with CG ERP go live Inventory function, just need to add some additional column for memo purpose.2. All of the customization have been completed.3. CFC need application for new Item No (using TIPTOP standard function to fulfilled ; program id : aimi150)
1.Under Process (Total : 5 items , Complete : 4 items)2.Should be put into
ERP before Mid of Mar-2014
p.s. please reference “CFC Basic Data List- Non Finance Module.xls
1. Low Risk
Ganda ERP Project |
Current Status of CFC ERP Implementation
Module Customization Basic Data Status Comment
Sales 1. B2B Web SO and Delivery Schedule have been completed and under internal testing, those function will be delivery before 07-Mar. ( MIS check )2. Quotation Contract SO DO operation functions almost same with CG, and related customization have been completed.3. Delivery Target Setting Requirements are not include in project scope, so will not be delivery in this Phase. (we plan to have discussed about those extend requirements in the Mid of Mar-2014)
1. Under Progress (Total :13 items , Complete : 9 items)2. Should be put into
ERP before Mid of Mar-2014
p.s. please reference “CFC Basic Data List- Non Finance Module.xls
1. Low Risk 2. All of the function
will be trained and tested when Consultant fly-in
on Mar-2014.3. Related Cust report will be delivery on May-2014.4. CFC want sales
target in phase-I, so need to discuss.
Distribution& F/G Warehouse
1. Main flow is same with CG, and most of customization have been completed. (> 90%) (DODSLNLCDN all complete)
2. Delivery Note need to add internal Invoice and Commercial Invoice function will be delivery on 16-Mar.
1.Under Process (Total :8 items , Complete : 6 items)
2. Should be put into ERP before Mid of Mar-2014
1. Low Risk2. Digiwin already put
high-priority for Delivery Note Cust. Requirement.
Ganda ERP Project |
Current Status of CFC ERP Implementation
Module Customization Basic Data Status Comment
Production 1. Most of production requirements are the same with CG except Packing ,and all of the programs have been complete. 2. Packing Program for CFC current is under programming and the expected delivery date will be 15-Mar
CFC need to know the gaps and solution between Packing shift report & F/G real time report (Please reference Appendix I ) Can setting some Warehouse to allow negative Inventory to solve.
1.Complete (Total : 4 items Complete : 4 items)
1. Low Risk 2. Digiwin already put
high-priority for CFC Packing Process Cust. Requirement.3. Related Cust. report willl be delivery on May-2014.
Maintain 1. New Development Module for Ganda ERP Project, all of programs for this module have been complete on 27-Feb.2. MFG Consultant need to introduce Maintain Module functions to CFC user and do some fine tuning.3. Plan to training on Apr-2014 and align between delivered function with CFC requirement.
1. Wait Maintain Module Training
1. Middle Risk2. New Module will be
delivery on 30-Mar.3. Due to this module
is not on the Major Operation Flow, We suggest to put this module into simulation test on May-2014.
Ganda ERP Project |
Current Status of CFC ERP Implementation
Module Customization Basic Data Status Comment
Electric Power
1. New Module for CFC and Spec have been confirmed on End of Jan-2014.2. All of customization of spec already been released, and under programming now. (around 100 hours)3. The expected delivery date will be 30-Mar-2014.
p.s. Electric Power Report will related to Cost Calculation so need on phase-I.
1. No Need 1. Low Risk 2. Independent module3. Due to this module is
not on the Major Operation Flow, We suggest to put this module into simulation test on May-2014.
QC Report 1. New Module for CFC and Spec have been confirmed on End of Jan-2014.2. All of customization of spec already been released, and under programming now. (around 150 hours)3. The expected delivery date will be 30-Mar-2014.
p.s. QC Report will related IQC, PQC so need on phase-I.
1. No Need 1. Low Risk2. Independent module3. Due to this module is
not on the Major Operation Flow, We suggest to put this module into simulation test on May-2014.
Ganda ERP Project |
Current Status of CFC ERP Implementation
Module Customization Basic Data Status Comment
Financial & Accounting
1. All of Customization Requirement have been collected & confirmed on Feb-2014 except dual currency solution.2. Most of CG Financial & Accounting function can fulfill CFC requirement or just need a little bit adjustment.3. Ms. Iris have provide final suggestion to CFC about dual currency solution on 26-Feb and waiting CFC’s reply.4. All of customization spec will be released before 05-Mar, and expected delivery date on 21-Mar, except dual currency and VAT output format.
1.Under Progress (currently only provide COA data, total have 56 items)2. Should be put
into ERP before Mid of Mar-2014
p.s. please reference “CFC-Financial data
check list V2.xls”
1. Middle Risk 2. Need decision
support on dual currency solution
3. If dual currency solution can’t be delivery before 30-Mar-2014, we will suggest to use one currency to do simulation testing on Apr-2014 first.
4. If not yet finished the dual currency customization, CFC can not do the test.
Need to discuss
Cost Accounting
1. How to solve the problem for the dual currency and separate the cost for 2 production line
Please Reference Appendix II
1. Under Progress 1.Middle Risk2. Will related with dual currency solution
Ganda ERP Project |
Current Status of CFC ERP ImplementationModule Customization Basic Data Status Comment
SMS 1. Digiwin already release PO to buy SMS Modem and related software license. (MIS trace )
2. The SMS Platform is under developing and plan to complete before 10-Mar.
3. We plan to do the fist SMS message test on 17-Mar-2014. (check point)4. Each SMS Message Program will take 3 days to development. And all of the SMS functions will be delivery on 30-
Mar.
1. No Need 1.Low Risk 2.We will delivery SMS
Module to CFC on end of Mar-2014.
3. Supplier still not confirm when can delivery SMS modem to Digiwin.
Customization Reports(50 reports)
1. CFC site review all the first priority reports on 3/3/2014 and already reduce the reports from 61 to 52. 2. MFG Consultants will provide those RPT specs for CFC confirm on Mar-20143. Digiwin will select 2 confirmed shift- related reports to develop and delivery before 30-Mar-2014, to ensure the shift-related report can be process well.4. All of 50 Customization Reports will be delivery before 30-May-2014.
1. Under Progress 1.Middle Risk2. Customization RPTs
will be partially delivery from Apr-2014 to May-2014.
Ganda ERP Project |
Current Status of CFC ERP Implementation
Module Customization Basic Data Status Comment
Human Resource
1. All of Customization Requirement have been collected & confirmed on Feb-2014.2. HR Consultant will delivery Cust. Spec to CFC for confirm before 07-Mar.3. Digiwin HRM Product Center will modify HRM Product to support CFC Date Format on UI (User Interface), and the new HRM will be released on 10-May.4. Due to some customization should be
based on new HRM released, so the expected delivery date will be 31-May
5. Overtime > Offset and P-Bonus customization solution will be provided before 28-Mar.
6. The other work contents progress, please
reference Appexdix-III
1. Under Progress
1. High Risk2. Due to Date Format
Issue, some customization will be delivery on 31-May.
3. HRM Consultant will discuss with CFC to find out any chance to do simulation test on June-2014.
Ganda ERP Project |
Major Activities of CFC on Mar-2014
12
• Customization Report Spec Confirmation
• Customization Program Training & Testing
• SOP Integration Testing for Major Business Flow
• Basic Data and Simulated Opening Data Preparation
• Operation Simulation Environment Setup
• End User Training
Ganda ERP Project |
Suggestion about CFC Operation Simulation Test
13
• Operation Simulation Test Scope on Apr-2014
• Modules : Purchasing, Inventory, Sales & B2B, Distribution & Warehouse,
Production, Finance & Accounting, SMS
• Locations : TKP plant only (or TKP & HPGP two plants)
• Testing Data Volume : 5% ~ 10% of daily transactions
• Major Target : (1) Ensure ERP Major process can running well and do
some fine turning
(2) Let user have more real practice chance
• Remark & Notes
• Maintain, Elec. Power, QC Report, Customization Reports & HRM modules can be put on 2nd round Operation Simulation Test (May-2014)
• The Other CFC Branch Offices can be include in 2nd round Simulation Test
• Testing Data Volume can be enlarge to 50% ~ 100% of daily operation in 2nd round Simulation Test .
Ganda ERP Project |
Month-end Closing1.Check Up2.Reconciliation & Reporting
Apr May AugJune July OctSep
20/2
Jan Feb Mar
Phase 2 development1. Survey & Diagnosis2. Application Training3. Operation Training 4. S.O.P. Modeling5. Gap Analysis &
Customization6. HRM Application Training
/Gap Analysis
Nov Dec
ERP Project Milestone 2014
RMC & Transport1.Design & Development2.Basic data preparation3.UAT4.Training5.Launch
B I1.Workshop2.Design & Development3.UAT4.Launch
Easy flow 1.Design & Development2.UAT3.Launch
AASTAR1.Application Training2.Basic data preparation3.UAT4.Training5.Launch
HR1.Payroll2.ESS
15/3 10/4 10/5 05/6 05/7 20/8 15/8 05/8
RMC – Motive MuliaKick off 11/3/2014 – Go-Live July 2014
Transport - ANPKick off 01/4/2014 – Go-Live July 2014
AASTARKick off 07/4/2014 – Go-Live July 2014
Business IntelligenceKick off 18/3/2014 – Go-Live July 2014
Easyflow / Online approvalKick off 01/4/2014 – Go-Live July 2014
Payroll Kick off 05/2/2014 – Go-Live April 2014ESS (Employee Self ServiceKick Off 24/3/2014 – Go-Live July 2014
Ganda ERP Project |
18
CFC Shift Report Issue
• All production process already contain shift control column.
• To fulfill CFC Shift Report Issue, some Inventory transaction list below still need adding shift control column but need confirm with CG(Need about 24HR additional customization hour):
• Purchase Stock-in
• Purchase Return
• Sales Return
• WH MISC Material Issue
• WH MISC Material Stock-in
• WH transfer
Ganda ERP Project |
20
CFC Dual Currency Cost Accounting
AR(VND) AP(VND)Expense
Allocation(VND)
GLBook1(VND)
Cost AccountingBook1(VND)Calculation
ARBook2(USD)(Auto Gen.)
AP Book2(USD)(Auto Gen.)
Expense Allocation
Book2(USD)(Auto Gen.)
GLBook2(USD)
Cost Accounting
Book2 (USD)Calculation
TransactionBatch Copy and
Convert to USD Amt(by date EX Rate)
GL Voucher Batch Copy and Convert
to USD Amt(by date EX Rate)
WillNot copy
Cost Accounting
Voucher
Ganda ERP Project |
22
HRM Work Contents Progress
No Items Progress or Reply Remark
01 Recruitment, training, performance : postponed to June or July
1. Only Training module will go live on 1st of the July.
2. Recruitment module, we suggest postponed to phase 2. And after discussion with CFC HR Department, actually they’re still using the formal way to recruit new comers, such as bulletin board or newspapers. So we suggest that we could postponed this module and discuss in the future days.
3. Performance module: Mr. Andrew will create a blank field in employee master data to let them upload the performance index over there, so we could give up the performance module.
02 Items in Employee basic data : Blood type, Identification Code
Those items we already maintain in HRM system, by the way, CFC have to provide the identification code of Vietnam
Ganda ERP Project |
23
HRM Work Contents Progress
No Items Progress or Reply Remark
03 Seniority Subsidize (automatically calculated from 1st Jan. each year)
Seniority Subsidize will be calculate in payroll module and I will set up the parameters and formula to let them automatically calculated from 1st of Jan on each year.
04 P&S bonus This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar
05 Tax balance This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar
06 Shift arrangement This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar
07 Overtime, Offset Leave This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar
08 All kinds of Report This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar
Ganda ERP Project |
24
HRM Work Contents Progress
No Items Progress or Reply Remark
09 Annual Budget We have a final decision of annual budget , isn’t it? Your currently process are still using paperwork and in our main system, we don’t have any module of function to record this, so please remain your own process.
10 Annual leave : the new commer can take annual leave after 11 months of service
This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar
11 Fingerprint system, E-card : connect to HR system
Mr. Andrew already set up the format of fingerprint in HRM system. And the E-card system, if you want to use it , It also can be set up in HRM system
12 Date formating : DD-MM-YYYY
Under process, HRM Product will modify to support DD-MM-YYY format when user thru UI view and edit data .
Ganda ERP Project |
25
HRM Work Contents Progress
No Items Progress or Reply Remark
13 Employee no need to pay Social Insurance, Medical Insurance in month; employee can not get P&S bonus in month
This will be set up in payroll module, and I already show you the way if the people they no need to pay social insurance or medical insurance in each month. You have to prepare a list of excel( need to pay is 1; no need to pay is 0), so please prepare this excel file and upload to system, then the system will follow your rule to calculate insurance or p/s bonus .
14 Check the order of the item; use standard English in all system
Work in process
Ganda ERP Project |
Dual Currency Solution Digiwin Proposed
PurchasingSales &
Distribution
Good Receiving
ShippingTransaction
Inventory
Production
AccountPayable(VND)
AccountReceivable
(VND)
Cash & NoteManagement
(VND)
Fixed Asset(VND)
General Ledger(VND)
VN
D
FIN
for M
ajor C
urren
cy S
OB
AccountPayable(USD)
AccountReceivable
(USD)
Cash & NoteManagement
(USD)
Fixed Asset(USD)
General Ledger(USD)
FIN
for S
econ
d C
urren
cy SO
B
MF
G M
od
ules
Transfer into 1st set of Accounting Transactions
Sub-LedgerData Transfer(AP, AR , NM, FA)
Transfer into 2nd set of Accounting Transactions
US
D
(synonmy)
Ganda ERP Project |
Account Payable System StructureAccount Payable System Structure
Receipt
AP
offset
Payment Process
Post Voucherto GL
Foreign Purchase
Foreign PurchaseReceipt
LC Application
Misc. APAdvance Payment
PurchaseReturn
PO
Temporary AP
To-offsetAccount
Cost Apportionment
AP Revaluation
APMonth End
Ganda ERP Project |
Sales Order
Sales Return
Incoming Payment
Notes Receivable
Cash Transactions
DepositConfirmation
Incoming Payment
ARMoth End
AR Balance of Payment
Deposit Misc. AR
Credit Memo
Misc. to-offset
Depositto-offset
Over Receipt
Delivery Note
AccountReceivable
Issue VAT Invoice
LC Management
AR Revaluation
Account Receivable System StructureAccount Receivable System Structure
Ganda ERP Project | 30
Dual Solution ComparisonDual Solution Comparison No Solution Description Advantage Disadvantage Remark
01 All of front-end accounting transaction data maintain screen need to put 3 kind of currency like current CFC system
• Can fulfill current CFC process needs.
• User can view & adjust dual currency data in one screen.
(more efficiency)
• Customization hours are 2,619 hrs. (time & cost)
• Due to Impact current ERP design structure will need longer time for testing and hard to maintain.
CFC prefer one.
02 Base on TIPTOP System Structure and create two Set of Books (two full set of sub-ledger) to fulfill DualCurrency Needs
• Can fulfill ACC and auditing need.
• Base on current ERP structure can leverage most of ERP standard reports and easy maintain.
• Customization cost under original budgets (600 hrs)
• Although most of 2nd accounting data can be auto-create by ERP, but still need ACC Dept. to confirm and do some adjustment if needed.
• Different with current process, user have longer learning curve.