nasa ames update to restoration advisory board

Post on 22-Jan-2018

3.782 Views

Category:

Education

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

NASA AMES RESEARCH CENTER

NOVEMBER 2015

KIMBERLY FINCHNASA AMES PROJECT MANAGER

1

• FY16 Site Management Plan (SMP)– Draft Final SMP under review; Final SMP: December 2015

• Community Involvement Plan (CIP): Sept. 2015

• AOI 6 Former Storm Drain Ditch– Multiple soil removal actions conducted from 1990-2001

(lead and PCBs)

– Draft Remedial Action Completion Report (Oct 2015) under review

• NASA VI area of responsibility – 7 buildings– Draft Tier Response Evaluation Report (July 2015) under

review; Tiers 3B/3A (long-term monitoring)

NASA AMES UPDATENOVEMBER 2015 RAB

2

Upcoming activities

• Land Use Control Implementation and Monitoring Plan (FY16)

• VI monitoring NASA buildings

• AOI 14 Action Memorandum and Removal Action

NASA AMES UPDATENOVEMBER 2015 RAB

3

Information: https://environment.arc.nasa.gov

NASA AMES UPDATENOVEMBER 2015 RAB

4

AREA OF INVESTIGATION 14REMOVAL ACTION

OVERVIEW

NOVEMBER 2015

KEVIN BRICKNELL, PE

5

Site Background

Engineering Evaluation/ Cost Analysis

OVERVIEW

6

Action Memorandum

Cleanup (removal action)

AOI 14 SITE BACKGROUND.

7

● Over 400 soil samples collected from AOI 14 during various investigations conducted from 1992 to 2014

● N217 and N217A Areas: 

● 5.5 acres, native and fill material

● Areas do not pose unacceptable risk to human and ecological receptors

● Former Soil Fill Area:  

● 8 acres, fill material placed on existing surface of stormwaterretention pond 

● Area poses potential current and future risk to human and ecological receptors

• Fill material placed at the Former Soil Fill Area (FSFA) is – contaminated with PCBs, DDT, and Lead– potential source of contamination to surrounding stormwater pond (Navy

Installation Restoration (IR) Site 25)

REASON FOR REMOVAL ACTION AT AOI 14

8

• NASA, with EPA and Water Board concurrence, is conducting a non-time critical removal action (NTCRA) to prevent erosion of contaminated soil from AOI 14 to adjacent Navy IR Site 25

REASON FOR REMOVAL ACTION AT AOI 14

9

– Currently, silt fence in place to prevent soil erosion

• NTCRA intended to:– Evaluate and address all

potential human and ecological risks

– Serve as the final action at AOI 14

• Engineering Evaluation/Cost Analysis (Final September 2015)– Summarizes contaminants, potential risks, and exposure pathways– Evaluates cleanup options for effectiveness, implementability, and cost– 30-day Public Comment Period completed October 5, 2015

• Action Memorandum (Ongoing)– Documents the cleanup decision process and identifies the selected cleanup option

• Removal Action (Targeted for September 2016 to March 2017)– Removal Action Work Plan—design document– Implements the cleanup action

AOI 14 TIMELINE

10

Objectives:• Prevent erosion of contaminated soil to protect wetland receptors

• Prevent terrestrial ecological receptor exposure to contaminated surface and subsurface soil

• Prevent industrial worker exposure to contaminated surface and subsurface soil

Cleanup Goals:• Consistent with Site 25 cleanup goals for DDT, PCBs, Lead

REMOVAL ACTION OBJECTIVES AND CLEANUP GOALS

11

• AOI 14 Engineering Evaluation/Cost Analysis evaluated and compared three cleanup alternatives:– Alternative 1: No Action– Alternative 2: Soil Cover and institutional controls– Alternative 3: Excavation and Off-site Disposal

EE/CA ALTERNATIVES EVALUATION

12

Alternative 3: Excavation and Off-site Disposal

• Excavation of all fill material in the northern portion of the FSFA where contaminant concentrations exceed cleanup goals

• Transportation of contaminated soil off site to an appropriate disposal facility

• Grading of disturbed areas for stormwater drainage, revegetation, and habitat mitigation

NASA’S SELECTED ALTERNATIVE FOR AOI 14

13

14

Clean SoilDirty Soil

Excavate

Regrade

Native Soil

AOI 14 EXCAVATION

Implementation of Alternative 3 will:

• Allow complete onsite habitat mitigation and habitat improvement

RESULTS OF AOI 14 REMOVAL ACTION

15

• Allow for unrestricted site use

• Require no long-term O&M

• Serve as the final action for AOI 14

• Finalize the Action Memorandum (April 2016)

• Removal Action Work Plan (August 2016)

• Implementation (September 2016 to March 2017)

• Removal Action Completion Report (October 2017)

NEXT STEPS

16

QUESTIONS?

17

top related