Schematic Design Review and Approval Lawshe Museum Renovation Project

Mike Wiese, Sr. Project Manager - CPMParks, Facilities, and Fleet Department

Physical Development Division

Dakota County Physical Development Committee Meeting12 October 2021

• Background

• Schematic Design

• Project Schedule

• Requested Action

• Questions

Overview

1

2

10/11/2021

2

• Q1-21: Directed to pursue $1.2M for mostly accessibility renovations.

• Q2 & Q3: Awarded design to CDG and refined design shared today.

Background

• Accessibility Upgrades:o Elevator, Stairs & Restrooms

o Regrading for Accessibility at Parking Lot

o Reception Desk & Adjacent Gallery on Level 1

o Kitchenette & Adjacent Offices on Level 2

Schematic Design

3

4

10/11/2021

3

Schematic Design – Level 1

Schematic Design – Level 2

5

6

10/11/2021

4

• Level 1: Provide Museum Display Wall System

• Level 1: Relocate Workshop & Gallery Storage

• Level 2: Provide New Research Room 204

Schematic Design – Alternates

Balance of Design 5 months

Bid and Award 3 months

Construction 5 months

TOTAL 13 months

• Return to Board at Contractor Awards – Dec. 2021 & April 2022.

Project Schedule

7

8

10/11/2021

5

• Approval of Schematic Design as presented.

Requested Action