schematic design review and approval lawshe museum

5
10/11/2021 1 Schematic Design Review and Approval Lawshe Museum Renovation Project Mike Wiese, Sr. Project Manager - CPM Parks, Facilities, and Fleet Department Physical Development Division Dakota County Physical Development Committee Meeting 12 October 2021 Background Schematic Design Project Schedule Requested Action Questions Overview 1 2

Upload: others

Post on 11-Feb-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

10/11/2021

1

Schematic Design Review and Approval Lawshe Museum Renovation Project

Mike Wiese, Sr. Project Manager - CPMParks, Facilities, and Fleet Department

Physical Development Division

Dakota County Physical Development Committee Meeting12 October 2021

• Background

• Schematic Design

• Project Schedule

• Requested Action

• Questions

Overview

1

2

10/11/2021

2

• Q1-21: Directed to pursue $1.2M for mostly accessibility renovations.

• Q2 & Q3: Awarded design to CDG and refined design shared today.

Background

• Accessibility Upgrades:o Elevator, Stairs & Restrooms

o Regrading for Accessibility at Parking Lot

o Reception Desk & Adjacent Gallery on Level 1

o Kitchenette & Adjacent Offices on Level 2

Schematic Design

3

4

10/11/2021

3

Schematic Design – Level 1

Schematic Design – Level 2

5

6

10/11/2021

4

• Level 1: Provide Museum Display Wall System

• Level 1: Relocate Workshop & Gallery Storage

• Level 2: Provide New Research Room 204

Schematic Design – Alternates

Balance of Design 5 months

Bid and Award 3 months

Construction 5 months

TOTAL 13 months

• Return to Board at Contractor Awards – Dec. 2021 & April 2022.

Project Schedule

7

8

10/11/2021

5

• Approval of Schematic Design as presented.

Requested Action

Questions?

9

10