A Block P Block Level 7B Block P Block L9 GlasshouseC Block P Block L9 Cooling TowersD Block P Block - Level 10E Block Q Block Main RoofF Block Q Block Upper RoofG Block R BlockG-H Link S Block - Level 6H Block S Block - Level 13J Block U BlockM Block V BlockM-O Link W BlockN Block Y BlockO Block Z Block - Level 7O Podium Z Block - Level 9O (M Block Side) Z Block - Level 11O Block Walk Way Roof Z Block - Level 12O Block Annex Z Block - Level 13P Block Level 5 - Garden
last date reviewed 13/06/2018
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: A BlockDescribe access arrangements: Access is via the plant room on Level 3, use walkway in ceiling. Roof access key required.
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
Yes
Refer to the latest 'EME Guide for Site Safety' for information relating to exclusions zones and EME safe work procedures for this roof.
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - Cooling Tower enclosure
only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof
7. Other(s):
Roof Safety Zone identifiedYes - Cooling
Tower enclosure only
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard assessment:Campus: Gardens PointBuilding: B BlockDescribe access arrangements: Access is via stairs to plant room. Access via cooling tower enclosure.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof?
No - air cooled unit enclosure only
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - air cooled unit enclosure only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes - air cooled unit enclosure only
Roof hazard assessment:Campus: Gardens PointBuilding: C BlockDescribe access arrangements: Access via fire stairs to air cooled chiller enclosure.
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
N.B. Sky lights installed on roof.
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: D BlockDescribe access arrangements: Access via fire stairs to door which opens to roof space.
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume hood riser.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: E BlockDescribe access arrangements: Access via plant room access hatch.
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: F BlockDescribe access arrangements: Access via manhole in level 2 hallway.
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: G BlockDescribe access arrangements: Access via kitchen drop down ladder on Level 4
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
Pressure relief hydrogen and acetylene - 3 metre exclusion zone or isolate cylinders prior to hot work
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - air handling unit access only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes - air handling unit access only
Roof hazard assessment:Campus: Gardens PointBuilding: G-H LinkDescribe access arrangements: Access via fire stairs from G-H link
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
Pressure relief hydrogen and acetylene - 3 metre exclusion zone or isolate cylinders prior to hot work
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: H BlockDescribe access arrangements: Access via G-H Link stairs
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
Spray booth isolation may need to be consideredElectrical exclusion zones may apply.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No - see note
N.B. Skylights installed on roof
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: J BlockDescribe access arrangements: Access via hatch in plantroom on Mezzanine Level 2
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume hood risers.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: M Block Describe access arrangements: Access via external fixed ladder on Level 6
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: M-O Link Describe access arrangements: Access via Level 5, M Block
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? See note
Glass sky light installed on roof
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s): See note
Multi level access to roof spaces
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: N Block (Old Government House)Describe access arrangements: Access via internal ladder from roof space
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
Yes - see note
Solar panels installed on roof
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes - cooling tower
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: O Block Describe access arrangements: Access is via fire stairs behind lifts on Level 7
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume hood risers.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: O Podium Describe access arrangements: Access via dataroom (Room 503) on Level 5
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: O Block (M Block Side) Describe access arrangements: Access via hatch in Room 502
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume hood risers.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? Yes - see note
Polycarbonate and glass sections of roof.
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: O Block (Walk Way Level) RoofDescribe access arrangements: Access via window in Room 412 and ladder brackets
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? Yes - see note
Polycarbonate sections of roof.
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: O Block AnnexDescribe access arrangements: Access via ladder
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: P Block Level 5 - Garden Describe access arrangements: Access via locked gate on level 5 balcony
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: P Block Level 7 Describe access arrangements: Access via ladder bracket
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
Yes
3x solar trees installed on roof space
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: P Block Level 9 (Glasshouse) Describe access arrangements: Access via Level 9 Plant Room
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: P Block Level 9 (Cooling Towers) Describe access arrangements: Access via Level 9 Plant Room
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
To be verified via inspection
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
Yes - see note
Solar panels installed on roof
4. Is there any known brittle roof sections or voids on this roof? No - see note
Sky lights installed on roof
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof?
Yes - recessed cooling towers on
L9
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: P Block - Level 10 Describe access arrangements: Access via staircase from Level 9 Plant Room
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
Mechanical extraction vents
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: Q Block Main RoofDescribe access arrangements: Access via ladder hatch on level 10
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume stack riser.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - cooling tower platform only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes - cooling tower platform only
Roof hazard assessment:Campus: Gardens PointBuilding: Q Block Upper RoofDescribe access arrangements: Access via door located on Level 12
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume stack riser.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - cooling tower area only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes - cooling tower area only
Roof hazard assessment:Campus: Gardens PointBuilding: R Block Describe access arrangements: Access via ceiling hatch in fire stairs on Level 4 (Link) or Access via ladder in mezzanine roof space
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
NOTE: Half face P1 or P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - North RoofNo - South Roof
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes - North Roof only
Roof hazard assessment:Campus: Gardens PointBuilding: S Block Level 6 (North and South) Describe access arrangements: Level 6 North - Access via narrow door in hallway on level 6 Level 6 South - Access via firestairs on level 6
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
NOTE: Half face P1 or P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: S Block Level 13 Describe access arrangements: Access via firestairs
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: U Block Describe access arrangements: Access via hatch in ceiling space from Level 3
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
Yes
Refer to the latest 'EME Guide for Site Safety' for information relating to exclusions zones and EME safe work procedures for this roof.
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? Yes
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - cooling tower enclosure area only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes - cooling tower enclosure area only
Roof hazard assessment:Campus: Gardens PointBuilding: V Block Describe access arrangements: Access via Level 8 plant room
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
0.5m exclusion zone around head of fume stack riser.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: W Block Describe access arrangements: Access via hatch from mezzanine plant room (Level 4)
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof?
Roof #7 - Yes (smoke fans)
Smoke fans installed on Roof #7
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
Roof #8 - YESRoof #15 - YES
Refer to the latest 'EME Guide for Site Safety' for information relating to exclusions zones and EME safe work procedures for this roof.
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Roof #3 - Yes Banner installation area only
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
Roof Safety Zone identified
Roof #3 - YES (Banner installation
area)
Roof #1,2, 4 to 17 - NO
Roof hazard assessment:Campus: Gardens PointBuilding: X Block Describe access arrangements: Roof #1 - Access via plant room in Theatre Foyer. Ladder access point. Roof #2 - Access via plant room in Theatre Foyer (N.B. no ladder access point). Roof #3 - Access via plant room in Theatre FoyerRoof #4 - Access via plant room in Theatre Foyer (N.B. no ladder access point) Roof #5 - Access via plant room in Theatre Foyer (N.B. no ladder access point) Roof #6 - Access via plant room in Theatre Foyer (N.B. no ladder access point). Roof #7 - Access via Theatre stage tower via roof 8. Roof #8 - Access via Theatre stage towerRoof #9 - Access via plant room doors on Level 4 (provides access to Roof #11). Via ladders from Roofs 11 to 9Roof #10 - Access via plant room doors on Level 4 (provides access to Roof #11). Via ladders from Roofs 11 to 10Roof #11 - Access via plant room doors on Level 4 (provides access to Roof #11). Roof #12 - Access via Roof 14 (N.B. rope access only to Roof #12). Roof #13 - Access via Roof 14 (N.B. rope access only to Roof #13)Roof #14 - Access via building stairwell. Roof #15 - Access via Roof #14 (N.B. Ladder access required to Roof #15)Roof #16 - Access via Roof #14 (N.B. Ladder access required to Roof #16). Roof #17 - Access via Roof #14 (N.B. rope access required to Roof #17)
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
Mechanical exhaust vents from retail tenants located on roof space.
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
Yes
Solar panels installed on roof space
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified Yes
Roof hazard assessment:Campus: Gardens PointBuilding: Y Block Describe access arrangements: Access via firestairs from Level 9 and Level 10
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? Yes
Mechanical extraction vents
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
Yes
Refer to the latest 'EME Guide for Site Safety' for information relating to exclusions zones and EME safe work procedures for this roof.
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: Z Block - Level 7 Describe access arrangements: Access via window in room 700A
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
Yes
Solar panels installed on roof space
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: Z Block - Level 9 Describe access arrangements: Access via window in room 937
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
Yes
Refer to the latest 'EME Guide for Site Safety' for information relating to exclusions zones and EME safe work procedures for this roof.
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
No
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified No
Roof hazard assessment:Campus: Gardens PointBuilding: Z Block - Level 11 Describe access arrangements: Access via window in foyer 1100
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
Yes
Refer to the latest 'EME Guide for Site Safety' for information relating to exclusions zones and EME safe work procedures for this roof.
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
Yes
Solar panels installed on main concrete roof and colorbond roof
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof? No
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - main concrete roof
No - colorbond roof area
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified
Yes - main concrete roof
No - colorbond roof area
Roof hazard assessment:Campus: Gardens PointBuilding: Z Block - Level 12 Describe access arrangements: Access to main concrete roof via firestairs; Access to colorbond roof over baulastrade from main concrete roof
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
Roof hazard identification Y/N Special safety precautions
1. Is there any known fume stacks or vents located on this roof? No
2. Is there any known radio communication equipment producing electromagnetic energy (EME) located on this roof?
No
3. Is there any known overhead electrical power line, high voltage equipment, or solar PV panels located on this roof?
No
4. Is there any known brittle roof sections or voids on this roof? No
5. Is there any known rooftop cooling tower or evaporative condenser equipment located on this roof?
Yes - cooling towers
NOTE: Half face P2 particulate respiratory protection is the minimum PPE required when working near cooling towers. If working on or in cooling tower, please refer to AS 3666.2 and SDS for hazardous substances in use.
6. Is routine maintenance of fixed plant and equipment located on this roof able to be conducted within an area which is protected by a full height edge protection system?
Yes - concrete roof section
No - colorbond roof area
A work at heights / roof access permit must be issued for any work conducted within 3 metres of an unprotected edge.
Refer to the KG or GP Height Safety Inspection reports for information relating to installed height safety systems on each roof.
7. Other(s):
Roof Safety Zone identified
Yes - concrete roof section
No - colorbond roof area
Roof hazard assessment:Campus: Gardens PointBuilding: Z Block - Level 13 Describe access arrangements: Access via fixed ladder from Level 12
Guides and Reports
YES - Roof access permit exemption for authorised QUT staff and Facilities Management contractors performing essential maintenance activities or approved research activities located within the identifed roof safety zone/s. Note - this does not remove the requirement of the QUT Contract / FM Manager to verify the contractor or QUT staff member has a safe system of work for their nominated task/s which identifies the hazard and risk control measures taking into consideration the roof hazard assessment outlined above. All workers must have completed the QUT FM induction prior to access.
NO - Roof access permit required prior to all access.
top related