1

Team AquaForceFaquaTeam Members:

Santos Ortiz (TL)

Christopher Munoz

Vicente Mora

Instructor: Raresh PascaliIndustry Advisor: Garrett HohmannFaculty Advisor:

2

Outline

CompetitionProduct Selection ProcessComponent BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)

3

2014 MATE ROV COMPETITION

Mission Scenario • Location: Northwestern Lake Huron, Thunder Bay.

• More than 50 shipwrecks within the Thunder Bay National Marine Sanctuary (TBNMS).

• Scientist and conservation groups are needed.

Map of the Great Lakes with Thunder Bay

Map of Thunder Bay, highlighting the TBNMS and its shipwrecks

4

Mission Tasks • Explore, document, and identify an unknown shipwreck.

• Collect microbial samples and measure conductivity of the groundwater emerging from a sinkhole.

• Remove trash and debris from the shipwreck and surrounding area.

2014 MATE ROV COMPETITION

Side and top view of ROV scanning shipwreck

Zebra mussels engulf a shipwreck

5

2014 MATE ROV COMPETITION

Mission Props

•Outsourced•Materials list provided•Instructions provided

6

CompetitionProduct Selection ProcessROV Design BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)Risk Matrix

7

Product Selection Process

THRUSTER COMPARISON

Thruster Electrical Req.Thrust

PerformanceDepth

Cost (USD)

SeaBotix 19.1 VDC 6 lbs 500 ft $680-720

Crust Crawler 12 VDC to 50VDC 15 lbs 300 ft $480-520

Seamor 24VDC or 48VDC 10 lbs 1000 ft $3,500

• Cost efficient • Thrust capacity• Compatibility

8

CAMERA COMPARISON

Camera Quality HousingCost

(USD)

Aquabotix 720p Included $600

Webcam 1920p x 1080p Not included $80

• Size• Cost efficient • Customizable

Product Selection Process

9

FRAME MATERIAL COMPARISON

Material Density (English) Size (in)Cost

(USD)

Aluminum .098 3/8”x24x48” $250-275

Acrylic .043 1/4”x24”x96” $180-220

3/ inlb3/ inlb

• Cost efficient• Weight • Machinability• Weld ability

Product Selection Process

10

Product Selection Process

PROCESSOR COMPARISON

Processor Capability (Volts) Digital I/O Communication

Arduino 6-20V 14 USB

Olimex 9-30V 16 Ethernet

Seamate 7-52V 8 USB

• Compatibility• Voltage capacity• Cost efficient

11

CONNECTOR COMPARISON

Connectors Dependability ConnectionCost

(USD)

Seacon Industry Standard Limited to 3 $30-70

Manufactured As needed $5-10

Product Selection Process

• Cost efficient• Modifiable• Competition advantage

12

CompetitionProduct Selection ProcessROV Design BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)Risk Matrix

13

ROV Design Breakdown

14

MISCELLENAOUS MATERIALS

Component Material Reason

Ballast Housing & Piston Acrylic Weight

Arm Assembly Aluminum Strength

End Caps Aluminum Strength

ROV Design Breakdown

15

Ballast Housing

P = 100psi

• Tensile strength of acrylic =10,587 psi

• Actual pressure at pool bottom =14psi

ROV Design Breakdown

)(

222

2

io

o

dd

Pd

dwaterdlmatb VVF '

indi 75.7

16

Arm Assembly• Hydraulic controlled• Mission specific design• Cost effective

ROV Design Breakdown

17

Tether and Connector

ROV Design Breakdown

18

CompetitionProduct Selection ProcessROV Design BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)Risk Matrix

19

Design Intent

• The surface area of plates’ provides us with the need to remove material to satisfy weight standards in needed.

• Side slots allow for cross elements to be easily adjusted.

dwaterdlmatb VVF '

20

Communication Flowchart

Design Intent

21

CompetitionProduct Selection ProcessROV Design BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)Risk Matrix

22

Cost Analysis

Cost Analysis

Item Cost Low USD Cost High USD

Thruster (qty. 2 ) $1200 $7000

Tether $140 $140

Connectors (qty. 6) $30 $180

Misc. Acuators/Sensors $200 $2000

Pressure Housing (qty. 4) $210 $300

LabView - $700

Control Board $90 $700

Camera $75 $600

End Cap Material $55 $750

Arm Material $40 $60

Frame Material $180 $275

Competition Materials/Props $50 $100

Power Source On-hand -

Total: $2,110 $12,110

23

CompetitionProduct Selection ProcessROV Design BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)Risk Matrix

24

Gantt Chart

25

CompetitionProduct Selection ProcessROV Design BreakdownDesign IntentCost Analysis Gantt ChartWork Break-down Structure (WBS)Risk Matrix

26

Work Breakdown Structure

AquaForce’s ROV

43.3%

Phase I90.5%

Research90%

Proposal 100%

Competition 100%

ROV components

100%

Market Research

95%

Competition Rules

100%

Competition Mission

100%

Cost Analysis90%

ROV Component

90%

Software Required

50%

Phase II47%

Mechanical Design

85%

Frame 90%

Select Materials

90%

Circuit20%

LabView Programming

0%

Calculations60%

Material Analysis

85%

Electrical Analysis

0%

Hydraulic Analysis

0%

Phase III0%

Fabrication 0%

Redesign 0%

Material Purchasing

0%

Frame 0%

Tendering 0%

Testing 0%

Buoyance Testing

0%

Leaking Test0%

Thruster Testing

0%

27

Questions???