ENGLEWOOD PUBLIC SCHOOLS

THE ENGLEWOOD CAMPUS Englewood High School - Englewood Middle School - Englewood Leadership Academy

CREATE THE FUTURE

Englewood Public Schools

ARC Integrated Program Management

Saunders Construction

MOA ARCHITECTURE

INTRODUCTIONS

PREPARING STUDENTS FOR THE 21ST CENTURY  

 

THE ENGLEWOOD

CAMPUS CREATE THE FUTURE

THE ENGLEWOOD

CAMPUS CREATE THE FUTURE

COMMUNITY  CHARRETTE  

THE ENGLEWOOD

CAMPUS CREATE THE FUTURE

COMMUNITY  CHARRETTE  

CREATE THE FUTURE Group 1

Ø Separate Middle and High School Drop-off Ø Separate Administrative areas near each entrance Ø Place Art in areas with natural light and views Ø 2 story high Commons with Mezzanine

THE ENGLEWOOD

CAMPUS

THE ENGLEWOOD

CAMPUS CREATE THE FUTURE

DESIGN  ADVISORY  GROUP  

Community  Use  Opportuni>es  •  Gymnasiums  and  Athle>cs  •  Library/Media  Center  •  Presenta>on  Venue  •  Health  Clinic  •  Fabrica>on  Lab  •  Outdoor  Gardens  •  Community  Mee>ngs  

•  Computer  Labs  •  Culinary  Arts  Lab  •  Arts  and  Music  •  Black  Box  Theater  •  Auditorium  •  Other  ideas?  

EXISTING  CAMPUS  

PHASE  1  DEMOLITION  July  2012  

EXISTING  SCHOOL  WHICH  WILL  REMAIN  OPEN    DURING  PHASE  1  CONSTRUCTION  

PHASE  1  CONSTRUCTION  Approximately  65%  of  the  Project  July  2012  thru  November  2013  

PHASE  2  DEMOLITION  January  2014  

NEW  SCHOOL  OPERATIONAL  DURING  PHASE  2  CONSTRUCTION  

PHASE  2  CONSTRUCTION  Approximately  35%  of  the  Project  January  2014  thru  December  2014  

PROJECT  SCHEDULE    Phase  1  Construc>on  Start  –  July  2012    Phase  1  Comple>on  –  November  2013    Phase  2  Construc>on  Start  –  January  2014    Phase  2  Comple>on  –  December  2014  

       CONSTRUCTION  LOGISTICS  •  Construc)on  Site  

Separa)on  

•  School  Parking  

•  Contractor  Parking  

•  Contractor  Access  

•  Contractor  Work  Hours  -­‐    7:30  to  4:00  

•  Contractor  Deliveries  9:00  to  3:00  

•  Lehigh  Street  Extension  

     

       CONSTRUCTION  LOGISTICS  •  Site  Safety  

•  Contractor  Security  Process  

•   Student  Safety  

•  Noise  

•  Dust  and  Dirt  Controls  

•  Street  Cleaning  

     

COMMUNICATIONS  

Ques)ons  and  Comments:                      tec_ques>ons@englewood.k12.co.us  303-­‐806-­‐2038  

     

THANK YOU!